LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint , Inc. January 22, 2014

46
LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint, Inc. January 22, 2014

description

LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint , Inc. January 22, 2014. Today’s Topics. Basic INDOT/LPA Program Key People Utility Coordination Process Submittals Agreements Work in Contract Case Studies Utility Company Comments. INDOT/LPA Program. - PowerPoint PPT Presentation

Transcript of LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint , Inc. January 22, 2014

Page 1: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA – Utility Coordination

Natalie Parks, P.E.American Structurepoint, Inc.

January 22, 2014

Page 2: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Today’s Topics Basic INDOT/LPA Program Key People Utility Coordination Process Submittals Agreements Work in Contract Case Studies Utility Company Comments

Page 3: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

INDOT/LPA Program Mission: To empower Local Public

Agencies (LPA) through excellent education and collaborative relationships, to plan, build and maintain a superior transportation system that promotes economic growth, ensures safety, and complies with all local, state, and federal regulations.

Page 4: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

INDOT/LPA Program INDOT is Involved on an LPA

Project When Federal Dollars are Spent District LPA Project Manager to secure federal

funds. District Utility Coordination when there is a

reimbursable utility relocation. Must follow federal regulations for utilities CFR

645 (http://www.fhwa.dot.gov/programadmin/utility.cfm

Must follow 105 IAC 13 Utility Accommodation Policy (July 2013) INDOT Design Manual LPA Design Guidance Document - Chapter 10

Page 5: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Key people

LPA Employee in Responsible Charge (ERC) LPA Design Project Manager Utility Coordinator Utility Personnel INDOT Project Manager Right-of-Way Manager

Page 6: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Responsibilities of Key People: LPA

ERC Review and approve requests form utility

coordinator for time extensions/adjustments Concur with, approve, and sign reimbursable

and subordination agreements Review and sign Notice of Plan Approval Review and sign Notice to Proceed Approve and pay all invoices

Page 7: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Responsibilities of Key People:

Project Manager/Designer Work with the utility coordinator to identify

critical points Communicate all plan changes to the utility

coordinator Responsible for watching cash flow Signs the work plan as the project manager

Page 8: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Responsibilities of Key People: Utility

Coordinator All of the responsibilities already discussed in

other sessions No Utility Oversight Agent…

Work with Project Manager to establish objectives for utility coordination deliverables

Work with Project Manager to develop the risk report Periodically review project funding with Project

Manager for reimbursables Provide quality assurance review of work plan for

compliance Agreements

Provide guidance on the use of SUE

Page 9: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Responsibilities of Key People:

District Utility Coordinator Provide oversight only when a utility is

reimbursable Submits agreement to Central Office for P.O. Submits agreement to Central Office for FMIS

authorization Does not provide general process oversight Does not sign notice to proceeds, notice of plan

approval, work plans Does not review invoices from utilities for

reimbursement

Page 10: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Ultimately the Utility Coordinator and the

Design PM are both responsible for ensuring 105 IAC 13 is followed.

Business decisions are made between the Design Team and the ERC

Page 11: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Process Process is the same – (105 IAC 13)

Research – 1 to 2 weeks Initial Notice – 1 to 2 months Verification Plans – 2 to 4 months Conflict Analysis – 2 to 4 months Work Plan Development – 1 to 6 months Reimbursable Agreements – 2 to 4

months Notice to Proceed/Construction

Page 12: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Process Follow the 105 IAC 13 rules and allow the

appropriate time for response Copy project owner representative on all

submissions Include INDOT PM Include MPO if funding is coming from that

agency INDOT’s District Utility Coordinator is

involved in a LPA projects Utility Coordination process, only when there are Reimbursable Agreements.

Do NOT use “minor” unless it is a minor project

LPA Utility Coordination Process

Page 13: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Research Phase: Many municipalities do not have a permit

program Rely more on:

Indiana 811 Field visits Field surveys

Use previous project information if available Talk to the LPA utility/engineering dept.

LPA Utility Coordination Process

Page 14: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Initial Notice: Do not need to contact Phil Ivy or Troy Boyd Provide an aerial view of the project area Request information regarding any property

interests Bring utilities to the table around

verification plans to discuss Right-of-Way needs

Establish need for replacement property if the right-of-way acquisition causes the subordination of compensable property rights

LPA Utility Coordination Process

Page 15: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

The biggest difference between LPA and INDOT projects from a scheduling standpoint:

Utility Certification, Work Plans & Relocation

Drawings are due at Stage 3 Submission to

INDOT

LPA Utility Coordination Process

Page 16: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Process RFC – Per Section 10-4.03 LPA Guidance

Document: Submission prior to RFC should include: Utility Work Plan/Relocation Drawings from

each utility or Letter of No Conflict LPA/Utility Reimbursement Agreement for each

reimbursable utility Utility FMIS authorization letter or e-mail Utility Certification Utility Special Provisions

Page 17: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Process Reimbursable Agreements

Use the INDOT LPA Agreements as established by INDOT General Counsel

Should build in approximately 4 months into the schedule when agreements are needed

Should submit to INDOT prior to sending to utilities

Should submit to LPA Counsel prior to sending to utilities

Remind LPA that the agreement is approved by INDOT General Counsel and all revisions must be approved by them

Page 18: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Process Plan Approval

Prepare Notice of Plan Approval and provide to LPA ERC for signature once Project has been clear for letting

Prepare Notice to Proceed once project has been let

NOTE: This is a result of utilities being “gun shy” due to the number of LPA projects that have been delayed

Page 19: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Coordination Process Construction

Still on Point Coordinate utilities with LPA personnel as

needed Suggest the use of an advanced right-of-way

clearing and staking contract Suggest the use of consultant utility relocation

oversight

Page 20: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Escalation Chain

1. Become well educated in ALL state and federal documents

2. Concurrently contact: Supervisor/UAR of Utility Design Project Manger LPA ERC

3. INDOT District LPA project manager

4. INDOT Central Office – Kenny Franklin, Statewide Director

Page 21: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Escalation Chain

DOCUMENT EVERYTHIN

G

Page 22: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Reimbursable Relocations Too often a local public agency will find

out TOO late in a project that there is an sizeable REIMBURSABLE utility that negatively impacts the project

Utility coordinator should provide a list of all confirmed reimbursable utility relocations at the end of Stage 1.

One (1) large reimbursable utility can create a critical cost that may have a severe impact such that a LPA cannot move forward with their project.

Or worse, become a burden afterward

Page 23: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Relocation Agreements When is an LPA/Utility agreement

required? Only when a utility relocation is required due

to being in direct conflict. There are 3 scenarios:

Reimbursable: When a utility has a compensable land right When a municipal utility is located in the right-

of-way of a project owned by same municipality Reimbursable : Work in Contract - The utility

relocation is constructed as part of the road contract.

Non-reimbursable: Work in Contract - The utility agrees to include the utility relocation as part of the road contract. These bid items should be identified as “non participating” and 100% of the successful bid will be paid up front by the utility company.

Page 24: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

LPA Utility Relocation Agreements Municipal Agreements

Reimbursable – LPA will usually push for municipal water & sanitary work to be in contract

Agreement is required if the Utility Board is a separate entity from the Board of Public Works (or the “owner” of the project)

Agreement is NOT required when the two entities are the same

Non-reimbursable – the LPA can opt to have the work done in contract to upgrade, etc., but this will not be reimbursable

Work in-contract Agreement The utility will pay 100% of the cost

Page 25: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in Contract Early on (Stage 1) ask the utility

companies to consider including their relocations in the LPA project. Benefits – Why do we recommend WIC :

Allows better overall construction coordination with the contractor in control of the scheduling

Reduces, and hopefully can eliminate, utility delays Saves on overall construction costs (Mobilization,

pavement cuts, shoring, overall efficiency…) Eliminates claims, contractor responsible for the x, y

and z location Saves on overall construction time “The Contractor knows where everyone went”.

Page 26: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in ContractSECTION 5 – REIMBURSEMENT (WORK IN-CONTRACT)

Example Breakdown in Agreement: “(a) 20 % of the cost to design and prepare construction

plans, specifications and preliminary itemized cost estimate for relocation of the Utility’s facilities shall be borne by the Local Public Agency.

  (b) 20 % of the cost to provide testing and inspection

services for relocation of the Utility’s facilities shall be borne by the Local Public Agency.

  (c) The Local Public Agency shall bear 20 % of the cost

of relocating the Utility’s facilities. (See exhibit “B”). “

Page 27: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in ContractSECTION 5 – REIMBURSEMENT

“The cost of relocation of the Utility’s facilities (provided for in (c)) shall equal the amount paid by INDOT to the contractor (based upon the actual units of work performed at the unit prices set out in the contractor’s itemized proposal or extra work agreement), selected in accordance with the procedure in Section 2.”

NOTE: regardless of whether the utility is reimbursable, the LPA is agreeing to include the utility work in their contract with the Contractor, which is being bid by INDOT. INDOT will invoice the LPA for their portion of the work and the LPA will then invoice the utility for their portion of the work.

Page 28: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in Contract SECTION 5 – REIMBURSEMENT

“The estimated cost of relocation is $_ (See Exhibit “B” for an itemized estimate of all anticipated costs, including but not limited to, materials, labor, and equipment costs.)

 The estimated cost of non-reimbursable relocation work to the utility’s facilities is $ . The Utility has appropriated, duly made and entered of record, the sum of $ _ to apply to the cost of the project. A copy of the Utility’s official record wherein such appropriation was made is attached as Exhibit “C”. If the amount to be contributed by the utility is zero then no Exhibit “C” is attached.”

Page 29: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in Contract SECTION 5 – REIMBURSEMENT

When the utility is 100% reimbursable, then the amount listed is the estimated cost of non-reimbursable work would be $0.00.

When the utility is partially reimbursable, the breakdown of reimbursable to non-reimbursable work must be provided.

When the utility is non-reimbursable, the dollar amount would be equivalent to the total cost of relocation as shown in Exhibit “B”.

Some municipalities may opt to have the utility pay the 20% match. This would be done using an MOA, not this agreement.

Page 30: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in Contract SECTION 5 – REIMBURSEMENT

Highly recommend the use of a summary sheet when doing a Work-in-Contract agreement on a LPA project and included with Exhibit “B”

Summary sheet would include: Breakdown of standard costs per FHWA Total cost of relocation that is shown in the

agreement Breakdown of costs to be borne by INDOT and borne

by LPA If the cost is $100,000 then identify the cost to be

borne by INDOT to be $80,000 and the cost to be borne by LPA to be $20,000

When the utility shall bear a portion of the cost, then separate that as well

Page 31: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in ContractSECTION 5 – REIMBURSEMENT (EXAMPLE SUMMARY)Water & Sewer Relocation $ 1,860,384.00 Total Cost on Public R/W $ 1,860,384.00 Betterment $ 56,134.00 Total Cost to be Borne by LPA* $ 1,804,250.00 Total Cost to be Borne by Utility $ 56,134.00 Summary of expenses: Cost of project to be borne by utility - betterment = $ 56,134.00 Cost of project to be borne by LPA = 1,804,250.00

Note – LPA to use Federal Funds – 80/20 match; 20% match = $360,850.00

Method of cost assignment (Work in INDOT Contract): The utility qualifies for reimbursement by LPA for the cost of the relocation

Page 32: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Work in Contract The reimbursements paid for under SECTION 5:

(a), (b), and (c) shall include the cost sharing that is paid with federal funds. This project shall be split in accordance with the funding established, which is typically paid with 20% LPA funding and 80% Federal funding.

How the payments are made: Prior to the awarding of the contract, the LPA submits

their 20% of the Utility Relocation per the Construction estimates.

Contractor actual cost invoices are reviewed and approved by the project manager and paid for with 20% LPA funds / 80% Federal funds.

Any cost overruns or claims should be approved and paid for at the same percentages as the original contract.

Page 33: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Additional Charges and Invoices Assist the ERC in determining if a scope change to the

existing agreement, or a cost overrun requested by the utility are appropriate.

Make sure that all scope changes and cost overruns have been approved by the ERC prior to the utility company proceeding with work. If not, and the utility does any of this work without prior approval, these charges are not reimbursable. FHWA and INDOT will not reimburse for addition work without prior authorization.

Page 34: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Additional Charges and Invoices Request that invoices be sent to BOTH the LPA ERC and the

utility coordinator UC can ensure the code is being followed Allows the UC to review scope was adhered to Allows the UC to review the total invoice and compare it

to similar projects to verify invoice is reasonable Allows the UC to verify only work that is reimbursable

was invoiced

Assist the ERC in ensuring that the charges are per the agreement and the utility invoices are correct.

If an invoice is incorrect or inappropriate, advise the ERC in resolving the issues with the utility.

Page 35: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Case Study

Page 36: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Project involves: Municipal utility relocation Right-of-way limitations Lift station AND Booster Station

Portions of utility on documented, exclusive easement

Project owner owns the utility Utility requires relocation due to new

roundabout & MSE walls

Case Study

Page 37: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Is the utility reimbursable? If so, by whom?

Does the utility need to secure permanent right-of-way? If so, why? If not, why not?

Case Study

Page 38: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Case StudyCase Study

Case Study

Page 39: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Case Study – Existing Pipeline Company has a 14” diameter gas

pipeline that crosses an existing road that the LPA is proposing to add a lane. Existing pipeline has a casing pipe that extends

5 ft. beyond the existing paved shoulder. New pavement will extend beyond the end of

the casing. Pipeline Profile: The top of the pipeline is 6 ft.

below the proposed pavement. Existing pipe is structurally inadequate for the

loading without a casing pipe.

Page 40: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Pipeline Company requested 100% reimbursement. Claim – Lose the ability to access the end of the

casing pipe, therefore will not be able to slide the pipe out for future maintenance.

They proposed 2 possible options and relocation costs:

Option #1: Bore and install a new pipeline with thicker walls under the new wider pavement.

Option #2: Open cut pavement, remove the existing casing, and provide maintenance to the existing pipeline, and install a no-load slab over pipeline.

Case StudyExercise

Page 41: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

What costs are reimbursable? Option 1: New pipe bored in placeOption 2: Remove Casing

Inspect and provide maintenance to coating under casing.

Install no-load slab

Note: Current Industry Design Standards no longer recommend a casing pipe be used due to cathodic corrosion.

Case Study

Page 42: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

INDOT’s Response: Pipeline is in conflict with the roadway

improvements due to the inadequate structural capacity of the pipe.

Option 1: Only the segment of the pipeline between the existing roadway right-of-ways is within an easement with property interests, and therefore is eligible for reimbursement.

Option 2: Removing the casing and inspecting the pipe’s outer wall coating is a maintenance item, and therefore is not reimbursable.

Neither of these options proposed by the utility company will allow for future maintenance.

Case Study

Page 43: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

INDOT’s Response: Therefore only the no-load slab over the

section of pipeline within the easement is reimbursable.

It is the Utility Company’s decision on either boring and installing a new line, or open cutting and removing casing, and installing the no-load slab.

The Utility Company should coordinate with LPA’s contractor to schedule open cut when road is shutdown.

Case StudyPractical Exercise

Page 44: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Utility Companies Several issues utilities have had with LPA

utility coordination Wide range of experience levels Do not know to follow the 105 IAC 13 when

federal aid projects LPA’s often will claim their projects are Minor

Projects to attempt to hold utility companies to shorter response time

Utility companies receive notification to attend a “Pre-construction” meeting when they had not received a Notice to Proceed

LPA project lettings are often delayed

Page 45: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Subconsultant Utility Coordinator When to use a subconsultant when your

firm is prequalified?

1.) Relatively low experience level

2.) Difficult project

3.) Many reimbursable utility relocations

4.) Accelerated project development schedule

Page 46: LPA – Utility Coordination Natalie Parks, P.E. American  Structurepoint , Inc. January 22, 2014

Questions?