LP3:The Galaxy Industries Production Problem

download LP3:The Galaxy Industries Production Problem

of 12

Transcript of LP3:The Galaxy Industries Production Problem

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    1/12

    1

    The Galaxy Industries Production Problem

    A Prototype Example

    Galaxy manufactures two toy doll models:

    Space Ray.

    Zapper.

    Resources are limited to

    1000 pounds of special plastic.

    40 hours of production time per week.

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    2/12

    2

    Marketing requirement

    Total production cannot exceed 700 dozens.

    Number of dozens of Space Rays cannot exceed number of

    dozens of Zappers by more than 350.

    Technological input

    Space Rays requires 2 pounds of plastic and

    3 minutes of labor per dozen.

    Zappers requires 1 pound of plastic and

    4 minutes of labor per dozen.

    The Galaxy Industries Production Problem

    A Prototype Example

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    3/12

    3

    The current production plan calls for:

    Producing as much as possible of the more profitable product,Space Ray ($8 profit per dozen).

    Use resources left over to produce Zappers ($5 profit

    per dozen), while remaining within the marketing guidelines.

    The Galaxy Industries Production Problem

    A Prototype Example

    X1 = No of dozens to be produced of Space RayX2 = No of dozens to be produced of Zapper

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    4/12

    4

    Max 8X1+ 5X2 (Weekly profit)

    subject to

    2X1+ 1X21000 (Plastic)

    3X1+ 4X22400 (Production Time)

    X1+ X2

    700 (Total production)X1 - X2 350 (Mix)

    Xj> = 0, j = 1,2 (Nonnegativity)

    The Galaxy Linear Programming Model

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    5/12

    5

    1000

    500

    Feasible

    X2

    Infeasible

    ProductionTime3X1+4X2 2400

    Total production constraint:

    X1+X2700 (redundant)500

    700

    The Plastic constraint

    2X1+X2 1000

    X1

    700

    Graphical Analysisthe Feasible Region

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    6/12

    6

    1000

    500

    Feasible

    X2

    Infeasible

    ProductionTime3X1+4X2 2400

    Total production constraint:

    X1+X2 700 (redundant)500

    700

    Production mixconstraint:

    X1-X2 350

    The Plastic constraint

    2X1+X2 1000

    X1

    700

    Graphical Analysisthe Feasible Region

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    7/12

    7

    The search for an optimal solution

    Profit =$4360

    500

    700

    1000

    500

    X2

    X1

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    8/12

    8

    Summary of the optimal solution

    Space Rays = 320 dozen

    Zappers = 360 dozen

    Profit = $4360

    This solution utilizes all the plastic and all the production hours.

    Total production is only 680 (not 700).

    Zappers production exceeds Space Rays production by 40

    dozens.

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    9/12

    9

    If a linear programming problem has an optimalsolution, an extreme point is optimal.

    Extreme points and optimal solutions

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    10/12

    10

    For multiple optimal solutions to exist, the objectivefunction must be parallel to one of the constraints

    Multiple optimal solutions

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    11/12

    11

    1

    No point, simultaneously,

    lies both above line and

    below lines and

    .

    1

    2 32

    3

    Infeasible Model

  • 8/12/2019 LP3:The Galaxy Industries Production Problem

    12/12

    12

    Unbounded solution