Lower Mill Creek Watershed - Project...

20
MONTHLY PROJECT REPORTS As of September 30, 2015 Lower Mill Creek Watershed

Transcript of Lower Mill Creek Watershed - Project...

Page 1: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

MONTHLY PROJECT REPORTS

As of September 30, 2015

Lower Mill Creek Watershed

Page 2: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Monthly Project Reports Lower Mill Creek Watershed Dashboard

Project Status as of September 30, 2015

Project Name Float to Finish

Milestone

Schedule Health Indicator

Change in Schedule Health Indicator from

Last Month

Current Budgeted Project Cost

Estimated Cost at Completion

Projected (Over-run) or

Under-run

Budget Health Indicator

Change in Budget Health Indicator from

Last Month

CSO 125 Stream Separations 104 days No change $13,567,096

(2017 $) $13,597,990 ($30,894) No change

CSO 127 and 128 Stream Separations (Completed in 2015) Met Met $469,271

(2015 $) $343,997 $125,274 No change

CSO 181 Real Time Control 27 days No change $4,289,061 (2016 $) $4,321,211 ($32,150) No change

CSO 217/483 Source Control - Phase A 314 days No change $14,534,275 (2016$) $14,534,275 --- No change

CSO 217/483 Source Control - Phase B 21 days No change $15,586,723 (2017$) $16,498,523 ($911,800) No change

CSO 217/483 Sewer Separation - Phase C 236 days No change $6,330,440 (2017 $) $6,330,840 --- No change

Harrison Avenue Sewer Separation Phase A (Completed in 2013) Met Met $3,342,403

(2013 $) $2,235,043 $1,107,360 No change

Harrison Avenue Sewer Separation Phase B (Completed in 2015) Met Met $1,772,627

(2014 $) $1,495,053 $277,574 No change

Lick Run Property Demolitions 1,003 days No change $4,155,979 (2014 $) $4,142,431 $13,548 No change

Lick Run Valley Conveyance System 12 days No change $165,261,221 (2016 $) $165,283,153 ($21,932) No change

Page 3: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Monthly Project Reports Lower Mill Creek Watershed Dashboard

Project Status as of September 30, 2015

Project Name Float to Finish Milestone

Schedule Health Indicator

Change in Schedule Health Indicator from

Last Month

Current Budgeted Project Cost

Estimated Cost at Completion

Projected (Over-run) or

Under-run

Budget Health Indicator

Change in Budget Health Indicator from

Last Month

Quebec Heights Sewer Separation 691 days No change $4,824,109

(2015 $) $4,825,576 ($1,467) No change

Quebec Road Sewer Separation 223 days No change $9,310,235

(2016 $) $9,310,235 --- No change

Queen City and Cora Avenue R/W Sewer Separation 584 days No change $4,681,591

(2015 $) $4,094,405 $587,186 No change

Queen City Avenue Sewer Separation Phase 1 (Completed in 2015) Met Met $8,558,943

(2013 $) $8,131,376 $427,567 No change

Queen City Avenue Sewer Separation Phase 2 16 days No change $12,478,573 (2016 $) $12,345,151 $133,422 No change

Rapid Run Park Source Control (Completed in 2014) Met Met $2,177,403

(2013 $) $1,852,847 $324,556 No change

Sunset Avenue, Sunset Lane, and Rapid Run Area Sewer Separation 805 days No change $8,542,666

(2014 $) $8,313,216 $229,450 No change

White Street Sewer Separation 748 days No change $4,993,318

2015$) $4,135,933 $857,385 No change

Wyoming and Minion Avenues Sewer Separation 578 days No change $3,472,535 (2015 $) $3,481,214 ($8,679) No change

Asset Management Projects N/A No change $8,741,706 $8,592,908 N/A

N/A N/A

NOTE: The cumulative total cost for all Lower Mill Creek Partial Remedy projects (not including the Asset Management Projects) is less than the $244.3 million (2006$) cap authorized on January 14, 2013 by the Board of County Commissioners.

Page 4: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Monthly Project Reports Lower Mill Creek Watershed Dashboard

Project Status as of September 30, 2015

Schedule The available float each project milestone is in excess of 180 calendar days.

The available float to any project milestone is between 180 and 90 calendar days.

The available float to any project milestone is less than 90 calendar days and there is more than 45 calendar days of scheduled work remaining.

Budget The estimated project costs at completion are 110% or less of the current estimated project cost.

The estimated project costs at completion are between 110% and 120% of the current estimated project cost.

The estimated project costs at completion are in excess of 120% of the current estimated project cost.

Page 5: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

CSO 125 Stream Separations Project Status as of September 30, 2015

Project IDs 10240018

Municipality Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments This project was reviewed in conjunction with the West Fork Sustainable project as reviewed through the LMCPR study. As recommended by the LMCPR study, the discharge pipe was proposed to be upsized from 36-inch, as shown in the 60% drawings, to 48-inch to increase CSO reduction. However, the West Fork watershed model is being updated to confirm the design sizing of the basin outfall pipe. The model update is anticipated to be completed in 2015.

The design task order has been updated to include special authorization for the basin outfall pipe. The design task order and program contingency request to complete the design beyond 30% is being reviewed by the County for approval. Look Ahead Design will proceed concurrently with the West Fork model update. When results of the West Fork model determine the discharge pipe size, confirmation and the 60% revised submittal will be completed.

Acquisition for 16 easements and portions of 10 parcels required to build 2 stormwater basins and install a stormwater pipe will commence when the revised 60% design is received. The 48-inch basin outfall pipe will require additional easements. Construction funds for MSD’s project will be requested from the Board of County Commissioners in 2017.

Issues and Risks Resolution of the West Fork model calibration may impact design schedule.

Planner Leslie Schehl

Project Manager Andrew Spurgeon

Planning Consultant CDM Smith

Design Consultant CDM Smith

Construction Manager Len Bauer

Contractor TBD

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated May 2017 (Construction)

100% Planning June 2010 June 7, 2010

100% Design August 2016 Ongoing

Permitting (PTI Submittal) April 2016

ROW Acquisition June 2017

Bidding & Construction

Bidding July 2017

Start Construction September 2017

Complete Construction September 2018

Current Estimated Project Cost $13,597,990

Legislated Project Cost $3,846,029

Actual Cost To-Date $1,053,484

% Complete of Current Estimated Project Cost 8%

As part of the West Fork source control projects for the Lower Mill Creek Partial Remedy (LMCPR), this project is being designed to provide enhancements for the CSO 125 sewershed and includes stream separation, construction of two storm water detention basins, and construction of 5,300 linear feet of 48-inch diameter Basin Outlet Pipe. The North Basin on Kirby Avenue will control storm water originating from 838 acres of predominantly undeveloped land that currently enters the combined sewer through two large stream inlets. The Martha Basin at Martha Avenue and Virginia Avenue will control storm water originating from 52 acres of predominantly undeveloped land currently entering the combined sewer through four inlets in the vicinity of Martha Avenue. The Basin Outlet Pipe will convey the storm water from the two basins at the controlled rate to the West Fork Channel. Construction of the basins and basin outlet pipe will remove over 280 million gallons of stream flow annually from the combined sewer, eliminating it from treatment at the Mill Creek Wastewater Treatment Plant, and return it to the natural environment. This project will also remove over 100 million gallons of combined sewer overflow from CSO 125. The West Fork source control projects in the LMCPR will reduce overflow volumes in the entire West Fork watershed by 173 million gallons in a typical year.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Dates Float Status

PTI Submittal 12/31/2016 255 days No delay

Start Construction 12/31/2017 104 days No delay

End Construction 12/31/2018 104 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $145.

Page 6: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

CSO 127 and 128 Stream Separations Project Status as of September 30, 2015

Project IDs 11243840

Municipality Cincinnati

Basin Mill Creek

Project Phase Construction

Current Activities and Accomplishments

Substantial completion of construction occurred in August 2015. Look Ahead

Final completion of construction is expected in the fourth quarter 2015. Issues and Risks

There are no issues at this time.

Planner Sharon Jean-Baptiste

Project Manager Daniel Anderson

Planning Consultant ARCADIS/Malcolm Pirnie

Design Consultant In-house (Mark Chapman)

Construction Manager Efrain Quinones

Contractor Sunesis Construction

Construction Inspector Mike Davis

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated December 2014 (Construction)

2013 CIP (Design) December 3, 2014

(Construction)

100% Planning June 24, 2012

100% Design December 2014 December 2, 2014

Permitting (PTI Submittal) October 2014 October 17, 2014

ROW Acquisition December 2015 May 1, 2015

Bidding & Construction

Bidding March 2015 March 11, 2015

Start Construction May 2015 May 1, 2015

Complete Construction August 2015 August 2015

Current Estimated Project Cost $469,271

Legislated Project Cost $518,350

Actual Cost To-Date $295,078

% Complete of Current Estimated Project Cost 63%

This project consists of installing a total of approximately 400 linear feet of storm sewer segments under West Fork Road to redirect the two streams from the Mount Airy Forest that currently enter the combined sewer system prior to CSO 127 and CSO 128. Off-loading the natural drainage will result in a reduction of 20 million gallons of overflow volume in a typical year at these CSOs and reduce the surcharging in the interceptor pipe which is hydraulically connected to the West Fork Branch channel with grates. The West Fork sustainable watershed project includes multiple projects that have been evaluated and prioritized for inclusion in Phase 1 with the remainder available for consideration in the Lower Mill Creek Partial Remedy (LMCPR). The West Fork watershed was evaluated in full but only three CSO sewersheds were prioritized for the LMCPR . In summary, CSO 125 is the largest CSO in the West Fork Watershed and includes stream separation and detention projects. Once the basin discharge pipe from the detention basins reaches capacity, the emergency overflow discharges to the combined sewer. In addition to addressing CSO 125, two other partial separations will be completed (CSO 128 & 127) to help redirect flow from Mount Airy Forest area to the West Fork Branch. The West Fork source control projects in the LMCPR will reduce overflow volumes in the entire West Fork watershed by 173 million gallons in a typical year. This project is located in the Northside neighborhood of the City of Cincinnati.

Milestone Date Float Status

PTI Submittal 12/31/2016 --- Met

Start Construction 12/31/2017 --- Met

End Construction 12/31/2018 --- Met

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $48.

This picture shows the installation of the storm pipe (36” RCP).

Page 7: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

CSO 181 Real Time Control Project Status as of September 30, 2015

Project IDs 11240020

Municipality Bond Hill / St. Bernard

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments

The consultant finished evaluating weir options for function and layout within the existing easement. The task order for design has been prepared and has been submitted to the County for review. 30% design was submitted in August 2015. Look Ahead

Once the task order for design is approved by the County, the 60% design will begin. Legislation for construction funds is scheduled for 2017. Issues and Risks

The design schedule was revised and right-of-way acquisition was revised accordingly.

Planner Laith Alfaqih / Tom Lyon

Project Manager Casey Walter

Planning Consultant CDM Smith/Black & Veatch

Design Consultant CDM Smith

Construction Manager Len Bauer

Contractor TBD

Milestone Dates Float Status

PTI Submittal 12/31/2016 303 days No delay

Start Construction 12/31/2017 213 days No delay

End Construction 12/31/2018 27 days No delay

This project consists of a new real time control facility (RTC) coupled with regulator improvements at CSO 181 to use in-system storage within the existing 10-foot by 15-foot combined trunk sewer. The primary objective of the Bloody Run source control solution is to remove stormwater from the combined system to reduce the volume and frequency of CSOs and to reestablish flows to the Bloody Run open channel and Mill Creek. Ultimately, this project will capture and separate storm water from approximately 1,200 acres, utilize existing system for storage, and utilize existing opportunities for detention and water quality enhancements. During this first phase of the source control solution, an estimated 93 million gallons of overflows will be eliminated via construction of a real time control facility. This project is located in Bond Hill, St. Bernard, and Elmwood Place.

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated January 2017 (Construction)

November 6, 2013 (Design, ROW)

100% Planning December 2013 December 31, 2013

100% Design March 2016 Ongoing

Permitting (PTI Submittal) March 2016

ROW Acquisition February 2017

Bidding & Construction

Bidding March 2017

Start Construction June 2017

Complete Construction December 2018

Current Estimated Project Cost $4,321,211

Legislated Funds $790,461

Actual Costs to Date $335,575

% Complete Current Estimated Project Cost 8%

This project is located within the Bloody Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $48.

Page 8: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

CSO 217/483 Source Control - Phase A Project Status as of September 30, 2015

Project ID 11243140 (A1 & A2 Design, A1 Construction) 11243142 (A2 Construction)

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments This project was divided into two separate bid packages: Phase A1 for stormwater detention basins, and Phase A2 for the Kings Run Drive and Winton Ridge Lane Sewer Separation. CSO 217 is nested within the CSO 483 watershed so that improvements to CSO 217 have a direct impact to CSO 483. Phase A1 mitigates the overflow impacts to CSO 217. Phase A2 mitigates overflow impacts to CSO 483.

The Phase A1 90% design was submitted in July 2015 and Phase A2 60% design is underway.

Look Ahead The A2 60% design is due in October 2015.

Right-of-way acquisition is ongoing for ten parcels via partial take and three easements required to construct detention basins in Phase A1. Titles have been ordered and received. It is anticipated that Phase A2 will require 20 easements for acquisition.

Issues and Risks Additional analysis being developed to investigate source control and conveyance options based on the input of residents.

Planner Dave Lorei

Project Manager Daniel Anderson

Planning Consultant BHE Environmental

Design Consultant BHE Environmental

Construction Manager Len Bauer

Contractor TBD

This project consists of converting portions of the combined system to a storm sewer and strategic separation with the installation of 4,300 linear feet of combined sewers, 1,000 linear feet of storm sewers, three detention basins to reduce the peak volume entering the combined system, and one detention basin to reduce peak volume in the storm system. Two of the detention basins are new and two will be retrofitted. The Kings Run source control project is comprised of three components (Phases A, B, C) totaling approximately 13,600 feet of new storm, combined, and sanitary sewers, and includes four storm water detention basins, 3,400 linear feet of stream restoration, and a combined overflow storage tank at CSO 217. The Kings Run source control project will reduce CSOs 217 and 483 volumes by 156 million gallons in a typical year. This project is located in the Winton Hills neighborhood of the City of Cincinnati, in the Kings Run Basin of the Mill Creek sewershed. This project also affects portions of the College Hill and Winton Place neighborhoods of the City of Cincinnati.

This project is located within the Kings Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $193.

Project Phase

Project Activities

Schedule

Phase A1 (Ponds)

Phase A2 (Sewer Separation)

Planning & Design

Project Legislated 2013 CIP June 2016

2013 CIP August 2016

100% Planning May 28, 2010 May 28, 2010

100% Design March 2016 March 2016

ROW Acquisition September 2016 November 2016

Permitting (PTI Submittal) N/A June 2016

Bidding & Construction

Bidding October 2016 November 2016

Start Construction December 2016 January 2017

Complete Construction August 2017 February 2018

Milestone Dates FLOAT BY PHASE

Status A1 (Ponds) A2 (Separation)

PTI Submittal 12/31/2016 N/A 184 days No delay

Start Construction 12/31/2017 377 days 347 days No delay

Complete Construction 12/31/2018 499 days 314 days No delay

Project Project Number

Legislated Funds

Actual Costs

Current Estimated Project Cost

Phase A1 & A2 (Design) 11243140 $4,650,275 $1,873,502 $4,650,275

Phase A1 (Construction) 11243140 $0 $0 $4,326,300

Phase A2 (Construction) 11243142 $0 $0 $5,557,700

Totals $4,650,275 $1,873,502 $14,534,275

Page 9: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

CSO 217/483 Source Control - Phase B Project Status as of September 30, 2015

Project ID 11243141

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Planning

Current Activities and Accomplishments Additional design funds were requested from the Board of County Commissioners (BOCC) in December 2014. These are requested in the draft 2016 CIP.

The design engineer is currently working on the 30% design.

Look Ahead

The 30% design submittal is due in November 2015. Two partial takes and eight easements are anticipated for acquisition. Legislation for construction funds is scheduled for 2017. Issues and Risks

Additional design funds are on hold by the County oversight team while basin flow monitoring is being performed and reviewed to better refine the basin model. Additional analysis being developed to investigate source control and conveyance options based on the input of residents.

Planner Dave Lorei

Project Manager Daniel Anderson

Planning Consultant BHE Environmental

Design Consultant TBD

Construction Manager Len Bauer

Contractor TBD

This project consists of a 1.5 million gallon combined overflow storage tank to control flows at CSO 217. The combined flows will be mitigated by the three detention basins upstream of CSO 217 which will minimize the required size of the storage tank. Stream improvements to Kings Run (3,400 feet) will protect the stream from peak flows. While stream improvements do not provide CSO reduction, they are part of the Lower Mill Creek Partial Remedy. The Kings Run source control project is comprised of three projects (Phases A, B, C) totaling approximately 13,600 feet of new storm, combined, and sanitary sewers, and includes four storm water detention basins, 3,400 linear feet of stream restoration, and a combined overflow storage tank at CSO 217. The Kings Run source control project will reduce CSOs 217 and 483 volumes by 156 million gallons in a typical year. This project is located in the Winton Hills neighborhood of the City of Cincinnati, in the Kings Run Basin of the Mill Creek sewershed. This project also affects portions of the College Hill and Winton Place neighborhoods of the City of Cincinnati.

This project is located within the Kings Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Current Estimated Project Cost $16,498,523

Legislated Funds $1,796,023

Actual Costs to Date $602,134

% Complete Current Estimated Project Cost 4%

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated January 2017 (Construction)

2013 (Planning, Design, ROW)

100% Planning December 2014 December 2, 2014

100% Design September 2016

Permitting (PTI Submittal) August 2016

ROW Acquisition April 2017

Bidding & Construction

Bidding May 2017

Start Construction June 2017

Complete Construction November 2018

Milestone Date Float Status

PTI Submittal 12/31/2016 141 days No delay

Start Construction 12/31/2017 191 days No delay

End Construction 12/31/2018 21 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $145.

Page 10: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

CSO 217/483 Sewer Separation - Phase C Project Status as of September 30, 2015

Project ID 10240021

Municipality Cincinnati (Winton Hills)

Basins Mill Creek

Project Phase Design

Planner N/A

Project Manager Bill Lutz

Construction Manager Steve Jones

Construction Inspector Rob Apel

Design Consultant CH2M Hill

Contractor Cincinnati Tunnel Partners

Planner Dave Lorei

Project Manager Daniel Anderson

Design Consultant BHE Environmental

Construction Manager Len Bauer

Construction Inspector TBD

Contractor TBD

This project includes approximately 2,700 linear feet of sanitary sewer along Winton Road to complete a portion of the separation of combined sewers in the CSO 483 drainage area. A 8’ x 14’ combined sewer will be converted to 5,600 linear feet of storm sewer, eliminating combined/sanitary connections. This will allow the two streams currently entering the sewer to be directed to Mill Creek. The Kings Run source control project is comprised of three projects (Phases A, B, C) totaling approximately 13,600 feet of new storm, combined, and sanitary sewers, and includes four storm water detention basins, 3,400 linear feet of stream restoration, and a combined overflow storage tank at CSO 217. The Kings Run source control project will reduce CSOs 217 and 483 volumes by 156 million gallons in a typical year. This project is located in the Winton Hills neighborhood of the City of Cincinnati, in the Kings Run Basin of the Mill Creek sewershed. This project also affects portions of the College Hill and Winton Place neighborhoods of the City of Cincinnati. Current Activities and Accomplishments Additional design funds for right-of-way were requested from the Board of County Commissioners (BOCC) in December 2014, and these are requested in the draft 2016 CIP. The 95% Design review meeting was held on July 1, 2015. Look Ahead This project cannot be constructed for three years after the Cincinnati Department of Transportation and Engineering (CDOTE) paved Winton Road in 2013, based on the City policy of cutting new streets without penalty; therefore, construction funds will be requested for legislation in 2017. The current approved PTI has expired; therefore, a new PTI will be applied for in 2016. It is anticipated that twelve easements are required for acquisition.

Issues Additional design funds for right-of-way are on hold by the County oversight team. Additional analysis being developed to investigate source control and conveyance options based on the input of residents.

Current Estimated Project Cost $6,330,840

Legislated Amount (Design) $1,486,240

Actual Cost To-Date $1,165,974

% Complete Estimated Project Cost 18%

Project Phase Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated February 2017 (Construction) 2009 CIP

100% Planning May 2010 May 28, 2010

100% Design June 2016 Ongoing

ROW Acquisition June 2016 Ongoing

Permitting (PTI Submittal) June 2016

Bidding & Construction

Bidding April 2017

Start Construction July 2017

Complete Construction May 2018

Mill Creek is shown east of the project area, which is outlined in red.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Date Float Status

PTI Submittal 12/31/2016 183 days No delay

Start Construction 12/31/2017 165 days No delay

End Construction 12/31/2018 236 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $96.

Page 11: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Lick Run Property Demolition Project Status as of September 30, 2015

Project ID 11240001

Municipality Cincinnati

Basin Mill Creek

Project Phase Construction

Project Manager Ian Laseke

Design Consultant Cardno ATC (Abatement Inspection)

Construction Manager Shawn Patton

Construction Inspector Keith Mundy

Contractor (Demolition) Contractor (Abatement)

DFS, Sehlhorst, Building Value Environmental Demolition Group, Rainbow, O’Rourke

Current Estimated Project Cost $4,138,579

Legislated Amount (Phase A) Legislated Amount (Phase B) Legislation Amount (Phase C) Legislation Amount (Phase D)

$1,007,179 $660,200 $578,700 $600,200

Final Actual Cost (Phase A) Actual Cost to Date (Phase B) Actual Cost to Date (Phase C) Actual Cost to Date (Phase D)

$758,180 $207,455

$97,385 $0

% Complete Current Estimated Project Cost 26%

Project Phase Project Activities

Phase A (19 project parcels)

Phase B (12 project parcels)

Phase C (10 project parcels)

Phase D (5 project parcels)

ROW Acquisition (under Valley Conveyance

System)

Project Legislated 2013 CIP May 14, 2014 February 25, 2015

(Demolition) May 20 , 2015 (Demolition)

Start March 1, 2010 March 1, 2010 March 1, 2010 March 1, 2010

Finish (closed) September 10, 2012 September 17, 2013 September 26, 2014 May 12, 2015

Demolition Start June 25, 2013 September 1, 2014 July 2015 July 2015

Finish January 31, 2014 December 2015 February 2016 February 2016

This project consists of the demolition/deconstruction of buildings (including garages) on about 74 project parcels in the footprint of the proposed Lick Run Valley Conveyance system project. The area is bounded by Queen City Avenue to the north, State Avenue to the east, Westwood Avenue to the south, and White Street to the west. This project includes the demolition of structures on acquired properties as well as the demolition of structures on properties that have been identified as necessary for the Lick Run Valley Conveyance, but not yet acquired. Since not all properties will be acquired at once, the demolition work will be done in stages as properties are acquired, which will help to limit the negative impacts on the community such as traffic modification, dust, noise, and the vandalism and public safety hazards posed by abandoned structures. The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year.

Current Activities and Accomplishments

38 buildings have been demolished to date (Phase A, Phase B, Port Authority and McDonalds), Phase C and Phase D demolition inspections were completed in September 2015. Demolition legislation for Phase E was submitted for review in September 2015.

Look Ahead

The remaining 4 buildings in Phase B are scheduled to be demolished in early 2016. Demolition for Phase C and D is expected to be complete by February 2016. 11 properties (12 structures) will be transferred to the Hamilton County Land Reutilization Corporation for use in a grant program. Issues There are no issues at this time.

Milestone Dates Float Status

PTI Submittal N/A --- ---

Start Construction 12/31/2017 --- Met

End Construction 12/31/2018 1,003 days No delay

The design completion date of all demolition is prior to the start of construction of the Lick Run Valley Conveyance System (11240000). Some demolition may occur after the LRVCS construction start date due to the appropriation process for properties in which negotiations have reached an impasse.

Real Estate Activity Number of Project Parcels with Buidlings

Purchased (closed)

60 (5 for Port Authority,

19 in Phase A, 12 in Phase B, 10 in Phase C 5 in Phase D

9 in future phases)

Under Contract (signed) 7

Active Negotiation (verbal agreement/negotiations/ appropriations)

7

Appraisal Stage 0

Total 74

Page 12: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Lick Run Valley Conveyance System Project Status as of September 30, 2015

Project IDs 11240000

Municipality Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments The surveying, geotechnical borings, utility inspections and additional environmental assessments are ongoing. Additional miscellaneous expense funds were conditionally approved in the 2015 Capital Improvement Plan. Coordination with the County is ongoing. Partial redesign legislation was approved by the Board of County Commissioners on August 31, 2015. Right-of-way acquisition is ongoing with 77 of the original 90 full fee takes acquired (86%). In addition, 6 City-owned sites are necessary. The current post-60% design acquisitions, which includes 26 easements, 4 partial takes, and 1 additional full fee takes, have not been acquired (0%). Therefore, a total of 61% of the 127 acquisitions have been acquired. The design consultants received a notice-to-proceed for the 60% partial redesign on September 15, 2015. Look Ahead The City Manager is reviewing a Request for Qualification for construction management services. The 60% partial redesign deliverable will be submitted on January 18, 2016.

Issues and Risks Cincinnati Department of Transportation and Engineering notified the community on April 14, 2015 that the Westwood Avenue Improvement Project may not be pursued at this time due to budgetary reasons. Verification occurred on May 4, 2015. The project has been modified due to the Westwood project cancellation.

Planner Sharon Jean-Baptiste

Project Manager David Hafner

Planning Consultant Strand Associates, Inc.

Design Consultant Strand Associates, Inc.

Construction Manager Len Bauer

Contractor TBD

The Valley Conveyance System is an approximately 8,000-foot hybrid stormwater conveyance system of open channel and subsurface box conduit, to convey natural drainage and stormwater removed from the combined sewer system. The installation includes a low-flow above ground bioengineered conveyance system paired with a closed box conduit to convey the 100-year flood flows to the Mill Creek safely. The Valley Conveyance System will collect stormwater separated by various hillside systems and convey it to Mill Creek. It will be an innovative asset for community revitalization through the use of best management practices, such as green streets, porous pavement treatments and water quality enhancements. A daylighting feature will be located where the historic Lick Run stream once flowed and will include floodplain benefits for open space and access to an enhanced natural system, engineered to serve multiple community needs and benefits and potential for infill of neighboring sites. Planning for this project has been completed under the MSD Sustainable Infrastructure Program (Project 10180900). The project is located between Queen City and Westwood and between White Street and Mill Creek, in the South Fairmount neighborhood of the City of Cincinnati. It includes storm separation projects on Queen City and State Street.

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated August 2016 (Construction) 2013 CIP

100% Planning January 2013 January 2, 2013

100% Design November 2016 Ongoing

Permitting (PTI Submittal) April 2015 April 22, 2015

ROW Acquisition August 2017 Ongoing

Bidding & Construction

Bidding March 2017

Start Construction April 2017

Complete Construction December 2018

Current Estimated Project Cost $165,283,153

Legislated Funds $43,575,410

Actual Costs to Date $32,337,718

% Complete Current Estimated Project Cost 20% .

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Dates Float Status

PTI Submittal 12/31/2016 --- Met

Start Construction 12/31/2017 249 days No delay

End Construction 12/31/2018 12 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $541,855.

Page 13: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Quebec Heights Sewer Separation Project Status as of September 30, 2015

Project IDs 11240170

Municipality Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments

The Capital Expenditure Core Team approved on July 7, 2015 the authorization to construct the project and authorization to accept the Northeastern Area State and Private Forestry Competitive Allocation Grant for this wet weather improvement project. Right-of-way negotiations are underway to acquire 14 easements and two City-owned properties. Twelve easements are acquired. Remaining properties are in appropriation. Duke Energy is reviewing the plans for potential utility conflicts. Approval to accept the grant by the Board of County Commissioners occurred on September 30, 2015. Look Ahead

An agreement is ongoing with Cincinnati Parks for MSD to maintain an asset installed on the Park’s property. The 100% design will be submitted after all permits are received and right-of-way is finalized. As a condition of the Nationwide Permit, wetland credits will be purchased prior to the start of construction. This project is expected to advertise to bid for construction in 2016. Issues and Risks

There are no issues at this time.

Planner Sharon Jean-Baptiste

Project Manager Ian Laseke

Planning Consultant Strand Associates, Inc.

Design Consultant Strand Associates, Inc.

Construction Manager Efrain Quinones

Contractor TBD

The Quebec Heights Sewer Separation project utilizes a natural channel for sustainable conveyance of flows to the valley conveyance system. The project includes approximately 5,600 linear feet of naturalized open channel, 2,170 linear feet of separated storm sewer, and an extended wetland detention feature to convey drainage from approximately 83 acres. The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year.

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated August 2015 (Construction) June 2013 (Design)

100% Planning April 2012 April 30, 2012

100% Design July 2015 Ongoing

Permitting (PTI Submittal) March 2014 March 17, 2014

ROW Acquisition September 2015 Ongoing

Bidding & Construction

Bidding November 2015

Start Construction January 2015

Complete Construction February 2017

Current Estimated Project Cost $4,825,576

Legislated Funds $1,272,009

Actual Costs to Date $921,569

% Complete Current Estimated Project Cost 19%

.

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Dates Float Status

PTI Submittal 12/31/2016 --- MET

Start Construction 12/31/2017 726 days No delay

End Construction 12/31/2018 691 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $54,901.

Page 14: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Quebec Road Sewer Separation Project Status as of September 30, 2015

Project IDs 11240110

Municipality Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments The consultant is working with the U.S. Army Corps of Engineers to determine if a Nationwide Permit is required. Coordination with Duke Energy for the gas main relocation is ongoing. Coordination is also ongoing with Cincinnati Bell. Titles have been ordered for 21 easements and one full take of a portion of one parcel is required for right-of-way acquisition.

Location of the buried utilities is complete. The 60% design submittal is due in October 2015.

Look Ahead The 90% design is due in January 2016. Right-of-way activities will be initiated as design gets closer to 90%. Duke and CBT will required updated plans. Construction funds will be requested for legislation in 2016.

The construction schedule is being coordinated with the Sunset Avenue Sewer Separation (11240010).

Issues and Risks There are no issues at this time.

Planner Sharon Jean-Baptiste

Project Manager Casey Walter

Planning Consultant Strand Associates

Design Consultant Infrastructure Development Engineering (IDE)

Construction Manager Steve Jones

Contractor TBD

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated 2014 CIP (ROW)

March 2016 (Construction)

100% Planning February 2012 February 14, 2012

100% Design November 2015 Ongoing

Permitting (PTI Submittal) N/A

ROW Acquisition February 2017

Bidding & Construction

Bidding March 2017

Start Construction May 2017

Complete Construction May 2018

Current Estimated Project Cost $9,310,235

Legislated Project Cost $2,318,435

Actual Cost To-Date $839,129

% Complete of Current Estimated Project Cost 9%

This project consists of approximately 8,500 feet of storm sewer (12-inch to 60-inch), a structural separator Best Management Practice (Vortech unit), and 400 feet of water main relocation. The proposed improvements are located in the street right-of-way of Quebec Road, Thinnes Street, Forbus Street, Lierman Street, Jonte Avenue, Graebe Street, Lorna Lane, Margaret Street, Schoedinger Avenue, and Westwood Avenue, as well as private properties that will need utility easements, in the South Fairmount neighborhood of the City of Cincinnati. It is part of the Lick Run source control project. The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year. This project is being coordinated with the Quebec Road Sewer Replacement project (10240365) and Faehr Street Sewer Replacement (910240530).

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Date Float Status

PTI Submittal 12/31/2016 --- N/A

Start Construction 12/31/2017 226 days No delay

End Construction 12/31/2018 224 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $111,729.

Page 15: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Queen City and Cora Avenue R/W Sewer Separation Project Status as of September 30, 2015

Project IDs 11240150

Municipality City of Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments

Right-of-way acquisition is underway for four partial takes, five easements, and one County-owned property. Four properties are acquired. Look Ahead

An agreement with the County to construct a detention basin on County property is under review. Right-of-way acquisition is expected to be complete by January 2016. Two appropriations are anticipated at this time. The 100% design will be submitted after all permits are received and right-of-way is finalized. Appropriation and construction funds are scheduled to be requested for legislation in 2015. Issues and Risks

There are no issues at this time.

Planner Sharon Jean-Baptiste

Project Manager Ian Laseke

Planning Consultant Malcolm Pirnie/ARCADIS

Design Consultant Malcolm Pirnie/ARCADIS

Construction Manager Steve Jones

Contractor TBD

This project consists of approximately 2,600 feet of storm sewer (12-in to 42-in), 2,800 feet of natural conveyance system, and three detention basins, with no sanitary sewer or water main relocations. The proposed improvements are located in the street right-of way of Cora Avenue and Fenton Avenue, as well as private properties that will need utility easements, in the Westwood neighborhood of the City of Cincinnati. The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year.

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated November 2015 (Construction)

100% Planning November 2012 November 1, 2012

100% Design September 2015 Ongoing

Permitting (PTI Submittal) March 2014 March 17, 2014

ROW Acquisition January 2016 Ongoing

Bidding & Construction

Bidding February 2016

Start Construction May 2016

Complete Construction May 2017

Current Estimated Project Cost $4,094,405

Legislated Funds $2,138,791

Actual Costs to Date $1,098,675

% Complete Current Estimated Project Cost 27%

.

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Date Float Status

PTI Submittal 12/31/2016 --- MET

Start Construction 12/31/2017 583 days No delay

End Construction 12/31/2018 583 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $67,978.

Page 16: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Queen City Avenue Sewer Separation - Phase 2 Project Status as of September 30, 2015

Project IDs 11240130

Municipality Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments

Due to a tight corridor for underground utilities, location of the existing 84-inch and 60-inch combined sewers is underway. GCWW coordination to determine the location of the 24-inch water line is being developed. Appraisals are under review by MSD for a total of 13 easements required for acquisition. Look Ahead

The underground utility location identification will be completed. The final design will be submitted when the right-of-way and Duke relocation plans are complete. The construction schedule is being coordinated with the Sunset Avenue Sewer Separation (11240010). Issues and Risks

Locating the existing combined sewers and 24-inch water line has delayed 100% design. The schedule for acquisition of right-of-way has been revised accordingly.

Planner Sharon Jean-Baptiste

Project Manager Julie Schroeder

Planning Consultant Strand / Malcolm Pirnie/ARCADIS

Design Consultant GSP/OH, Inc.

Construction Manager Steve Jones

Contractor TBD

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated October 2016 (Construction)

100% Planning December 2011 December 7, 2011

100% Design December 2015 Ongoing

Permitting (PTI Submittal) June 2016 Ongoing

ROW Acquisition November 2016 Ongoing

Bidding & Construction

Bidding December 2016

Start Construction February 2017

Complete Construction December 2018

Phase 2 consists of approximately 7,100 feet of storm and sanitary sewer (12-in to 60-in). The proposed improvements are located in the street right-of-way of Queen City Avenue and East Tower, as well as private properties that will need utility easements, in the Lick Run basin of the Mill Creek sewershed. This project is located in the Westwood neighborhood of the City of Cincinnati. The Phase 1 project consists of approximately 2,800 feet of storm sewer (12-inch to 96-inch, and 4-foot x 14-foot reinforced concrete box culvert), and 350 feet of water main relocation. Refer to “Queen City Avenue Sewer Separation - Phase 1.” The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year.

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Date Float Status

PTI Submittal 12/31/2016 184 days No delay

Start Construction 12/31/2017 325 days No delay

End Construction 12/31/2018 16 days No delay

Current Estimated Project Cost $12,345,151

Legislated Funds $2,612,073

Actual Costs to Date $1,139,356

% Complete Current Estimated Project Costs 9%

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $94,100.

Page 17: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Sunset Avenue, Sunset Lane and Rapid Run Area Sewer Separation Project Status as of September 30, 2015

Project IDs 11240010

Municipality Cincinnati

Basin Mill Creek

Project Phase Construction

Current Activities and Accomplishments The construction notice-to-proceed was issued with a start date of August 3, 2015.

Look Ahead The construction work will start with mobilization, clearing and grubbing, erecting traffic signs, installing a temporary gravel drive. Duke Energy needs to relocate a pole at the start of construction.

The construction schedule is being coordinated with Quebec Road Sewer Separation (11240110) and Queen City Avenue Phase 2 Sewer Separation (11240130). Issues and Risks There are no issues at this time.

Planner Sharon Jean-Baptiste

Project Manager Julie Schroeder

Planning Consultant Strand

Design Consultant HDR

Construction Manager Len Bauer

Construction Inspector Rob Neumeister

Contractor Rack & Ballauer Excavating Co.

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated October 2014 October 15, 2014 (Construction)

100% Planning June 2011 June 17, 2011

100% Design February 2014 February 4, 2014

Permitting (PTI Submittal) N/A N/A

ROW Acquisition December 2014 December 17, 2014

Bidding & Construction

Bidding April 2015 April 8, 2015

Start Construction August 2015

Complete Construction October 2016

Current Estimated Project Cost $8,313,216

Legislated Project Cost $8,736,513

Actual Cost To-Date $1,232,554

% Complete of Current Estimated Project Cost 15%

This project consists of approximately 12,700 feet of proposed storm sewer (12-in to 66-in), and 300 feet of water main relocation. The proposed improvements are located in the street right-of-way of Queen City Avenue, Sunset Avenue, Sunset Lane, Guerley Road, and Rapid Run Pike, as well as private properties that will need utility easements in the Westwood and West Price Hill neighborhoods of the City of Cincinnati. This stormwater separation project is located in the street rights of way of Queen City Avenue, Sunset Avenue, Sunset Lane, Guerley Road, and Rapid Run Pike and some private properties. It is part of the Lick Run source control project. The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year.

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Date Float Status

PTI Submittal 12/31/2016 N/A N/A

Start Construction 12/31/2017 --- Met

End Construction 12/31/2018 805 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $30,464.

Page 18: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

White Street Area Sewer Separation Project Status as of September 30, 2015

Project IDs 11240090

Municipality Cincinnati

Basin Mill Creek

Project Phase Construction

Current Activities and Accomplishments The bid open date was June 11, 2015. This project was bid for construction coordination with the Fairmount Avenue Sewer Replacement project (ID #10240167). The construction contract was awarded on September 10, 2015.

Look Ahead The Construction notice-to-proceed is expected in the 4th Quarter 2015.

Duke Energy poles require relocation.

Issues and Risk

Coordination with Duke Energy is pending.

Planner Sharon Jean-Baptiste

Project Manager Julie Schroeder

Planning Consultant Strand Associates

Design Consultant CDM Smith

Construction Manager Len Bauer

Contractor TBD

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated April 2015 April 8, 2015

100% Planning September 2011 September 1, 2011

100% Design March 2014 March 14, 2014

Permitting (PTI Submittal) December 2013 December 5, 2013

ROW Acquisition March 2015 March 13, 2015

Bidding & Construction

Bidding September 2015 Ongoing

Start Construction October 2015

Complete Construction December 2016

Current Estimated Project Cost $4,135,933

Legislated Project Cost $5,644,539

Actual Cost To-Date $798,851

% Complete of Current Estimated Project Cost 19%

The project consists of approximately 6,600 feet of proposed storm sewer (12-in to 48-in), 100 feet of sanitary sewer, and 600 feet of water main relocation. The proposed improvements are located in the street right-of-way of Queen City Ave, White St, Richter St, Hillenbrand Ave, Horton Ave, Ley Ave, Bickel Ave, and Fairmount Ave, as well as private properties that will need utility easements. This project is in the South Fairmount neighborhood of the City of Cincinnati. The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year.

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Date Float Status

PTI Submittal 12/31/2016 --- MET

Start Construction 12/31/2017 814 days No delay

End Construction 12/31/2018 748 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $31,575.

Page 19: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Wyoming and Minion Avenues Sewer Separation Project Status as of September 30, 2015

Project IDs 11240030

Municipality Cincinnati

Basin Mill Creek

Project Phase Design

Current Activities and Accomplishments

Offers have been made for right-of-way acquisition of 21 easements. Two are acquired and four are under contract. A design change order (DCOR) request has been approved to prepare the plats for 15 anticipated appropriations and work in underway. Look Ahead

Duke Energy is reviewing the 100% design plans and will provide pole relocation scope and cost estimate to MSD. Construction funds will be requested for legislation in 2015. Appropriation and construction legislation is being prepared. Issues and Risks

There are no issues at this time.

Planner Sharon Jean-Baptiste

Project Manager Sohail Saeed / Melissa Holscher

Planning Consultant Malcolm Pirnie/ARCADIS

Design Consultant Resource International

Construction Manager Len Bauer

Contractor TBD

Project Phase

Project Activities

Schedule for Completion

Actual Date of Completion

Planning & Design

Project Legislated October 2015 (Construction)

100% Planning February 2012 February 1, 2012

100% Design September 2015 Ongoing

Permitting (PTI Submittal) February 2015 February 2, 2015

ROW Acquisition January 2016 Ongoing

Bidding & Construction

Bidding March 2016

Start Construction June 2016

Complete Construction May 2017

Current Estimated Project Cost $3,481,214

Legislated Project Cost $898,635

Actual Cost To-Date $747,828

% Complete of Current Estimated Project Cost 21%

This stormwater separation project is located in the street rights of way of Queen City Avenue, Wyoming Avenue, Westmont Avenue, Latham Avenue and Minion Avenue and some private properties. It is part of the Lick Run source control project. This project consists of approximately 3,900 feet of proposed storm sewer (12-in to 42-in), and 300 feet of sanitary sewer. The proposed improvements are located in the street right-of-way of Queen City Avenue, Wyoming Avenue, Westmont Avenue, Latham Avenue and Minion Avenue, as well as private properties that will need utility easements. This project is in the South Fairmount and West Price Hill neighborhoods of the City of Cincinnati. The Lick Run source control project is comprised of 12 sewer separation projects, including the Lick Run Valley Conveyance System project (Project ID 11240000), totaling approximately 85,000 feet of new conveyance in both closed and open channel designs. Eight storm water detention basins will mitigate peak flow into the valley conveyance system. The Lick Run source control project will separate approximately 499 million gallons of stormwater from entering the combined sewer system tributary to CSO 5, thereby reducing the CSO volume by 393 million gallons in a typical year.

This project is located within the Lick Run Watershed, which is a sub-basin of the Mill Creek Wastewater Treatment Plant Basin, within the Metropolitan Sewer District of Greater Cincinnati.

The Mill Creek basin lies in the heart of Hamilton County stretching from the Ohio River to the northern Hamilton County border and from Reed Hartman Highway west to Colerain Avenue. The Mill Creek basin contains portions of 32 cities, villages, and townships including: the City of Cincinnati, Springfield Township, Colerain Township, Forest Park, Glendale, Wyoming, Springdale, Sharonville, Blue Ash, Amberley Village, Norwood, and others.

Milestone Date Float Status

PTI Submittal 12/31/2016 --- Met

Start Construction 12/31/2017 578 days No delay

End Construction 12/31/2018 578 days No delay

The allowance detail expenditures encumbered under the Sustainable Infrastructure Program are $54,522.

Page 20: Lower Mill Creek Watershed - Project Groundworkprojectgroundwork.org/downloads/l3/...09.30.2015_Lower_Mill_Creek.pdf · NOTE: The cumulative total cost for all Lower Mill Creek Partial

Lower Mill Creek Partial Remedy Asset Management Projects

Project Status as of September 30, 2015

Project Name Associated LMCPR Project Project ID Schedule for Construction Current Budgeted Project Cost

Estimated Cost at Completion Actuals Capital Improvement

Program Year

Cora Avenue Sewer Replacement Queen City and Cora Avenue R/W Sewer Separation 10240027 October 2016 – March 2017 $1,163,528 $1,097,152 $348,728 2014 (Easement)

2016 (Construction)

Faehr Street Sewer Replacement Quebec Road Sewer Separation 10240530 N/A $13,908 $13,908 $13,908 N/A

Fairmount Avenue Sewer Replacement White Street Sewer Separation 10240167 October 2015 – December 2016 $971,045 $927,537 $179,367 2014 (Construction)

Guerley Road Drainage Improvement (SMU) Sunset Lane, Sunset Ave., & Rapid Run Pike Sewer Separation 10180900.65 August 2013 – May 31, 2014

$100,309 (MSD’s portion of

design)

$100,309 (MSD’s portion of

design)

$1,249,942 (SMU + MSD)

2010

McKeone Avenue Sewer Replacement Rapid Run Park Source Control 10240350 June 2016 – September 2016 $182,606 $163,306 $41,571 2016 (Construction)

Quebec Heights Sewer Rehabilitation Quebec Heights Sewer Separation 10240580 January 2016 – June 2016 $3,307,400 $3,307,400 $0 TBD

Quebec Road Sewer Replacement Quebec Road Sewer Separation 10240365 July 2017 – October 2017 $554,456 $534,842 $61,542 2013 (Design) 2017 (Construction)

Queen City & Cora Avenue Sewer Rehabilitation Queen City & Cora Sewer Separation 10240581 May 2016 – October 2016 $1,701,700 $1,701,700 $0 TBD

Wahl Terrace Sewer Replacement Lick Run Valley Conveyance System 10240495 September 2019 – January 2020 $746,754 $746,754 $11,454 TBD (Design) TBD (Construction)

The following asset management projects are in coordination with the Lower Mill Creek Partial Remedy (LMCPR) projects to maximize scope, cost, and community efficiency. Cora Avenue Sewer Replacement - This project proposes to replace approximately 1,138 feet of an 8-inch sewer installed in 1924 that is aging and deteriorating.

Faehr Street Sewer Replacement – This scope of this project, replace 250 feet of a 12-inch combined sewer, has been incorporated into the design and construction of the Quebec Road Sewer Separation project.

Fairmount Avenue Sewer Replacement – This project proposes to replace approximately 1,800 linear feet of 12-inch, 15-inch, and 18-inch existing combined sewer that was installed in 1928 and has deteriorated and resulted in multiple fractures throughout the pipe with new 12-inch, 15-inch, and 18-inch conduit within the same alignment as the existing sewer. Construction is being coordinated with White Street Area Sewer Separation (11240090).

Guerley Road Drainage Improvement (SMU) – This project consists of an earthen detention dam facility, two storm sewer separation locations, removal of invasive plant species, two bio-retention areas, and re-vegetation of the inundation area with native species. The main spillway is a 36-inch diameter pipe that will be connected to the future Sunset Ave. sewer project. The dam is 22 feet high on the upstream side and the emergency spillway is 16 feet high and holds back approximately 100 acre-feet of surface flow.

McKeone Avenue Sewer Replacement – This project proposes to replace 122 linear feet of 15-inch existing sewer with 147 linear feet of 18-inch conduit in a new alignment. The existing 15-inch sewer will be abandoned in place.

Quebec Heights Sewer Rehabilitation – This project will improve the structural integrity of the existing combined sewer system within the Glenway Woods Preserve by lining 6,022 linear feet of combined sewer and repairing 29 manholes.

Quebec Road Sewer Replacement – This project proposes to install 450 feet of new 12-inch sanitary sewer, along with 400 feet of new 15-inch and 16 feet of new 12-inch storm sewer.

Queen City and Cora Avenue Sewer Rehabilitation – This project will improve the structural integrity of the existing combined sewer system within the wooded ravine south of Cora and Fenton Avenues by lining 4,244 linear feet of combined sewer and repairing 7 manholes.

Wahl Terrace Sewer Replacement – This project proposes to replace segments of deteriorated combined sewer, as well as the separation of the storm inlets on Wahl Terrace and the removal of the storm inlets on the combined sewer to the east of Wahl Terrace. The scope of this project is being reconsidered following questions from the County monitor team.