LOWER BELLINGER AND KALANG RIVER FLOOD STUDY FINAL REPORT · 2016-10-20 · Lower Bellinger and...
Transcript of LOWER BELLINGER AND KALANG RIVER FLOOD STUDY FINAL REPORT · 2016-10-20 · Lower Bellinger and...
LOWER BELLINGER AND KALANG RIVER FLOOD STUDY
FINAL REPORT
April 2016
Level 2, 160 Clarence Street Sydney, NSW, 2000 Tel: 9299 2855 Fax: 9262 6208 Email: [email protected] Web: www.wmawater.com.au
LOWER BELLINGER AND KALANG RIVER FLOOD STUDY
FINAL REPORT
APRIL 2016
Project Lower Bellinger and Kalang River Flood Study
Project Number 111036-04
Client Bellingen Shire Council
Client’s Representative Phil Buchan
Authors Isabelle Testoni Monique Retallick Mark Babister
Prepared by
Date 11 April 2016
Verified by
Revision Description
Distribution Date
3 Final Report BSC, OEH APRIL 2016 2 DRAFT REPORT BSC, OEH SEPT 2015 1 INITIAL DRAFT REPORT FOR DISCUSSION
ONLY BSC, OEH 4 May 2015
LOWER BELLINGER AND KALANG RIVER FLOOD STUDY
TABLE OF CONTENTS
PAGE
FOREWORD .............................................................................................................................. 1
EXECUTIVE SUMMARY ............................................................................................................ 2
1. INTRODUCTION ........................................................................................................ 3
1.1. Report Outline ............................................................................................ 3
2. BACKGROUND ......................................................................................................... 5
2.1. Study Area .................................................................................................. 5
2.2. Previous Studies ......................................................................................... 5
3. AVAILABLE DATA .................................................................................................. 10
3.1. Rainfall Information ................................................................................... 10
3.1.1. Historic Rainfall Data ................................................................................ 10
3.1.2. Design Rainfall Data ................................................................................. 10
3.2. Water Level Data ...................................................................................... 10
3.2.1. Time Series Water Level Data .................................................................. 10
3.2.2. Peak Flood Heights .................................................................................. 11
3.3. Topographic Information ........................................................................... 12
3.4. Culvert and Structure Data ....................................................................... 13
4. ADOPTED MODELLING APPROACH ..................................................................... 15
5. HYDROLOGIC MODELLING ................................................................................... 16
5.1. Overview .................................................................................................. 16
5.2. Review of Bellinger, Kalang and Nambucca River Catchments Hydrology 16
5.3. 0.05% AEP Event ..................................................................................... 17
6. HYDRAULIC MODELLING ...................................................................................... 18
6.1. Model Configuration .................................................................................. 18
6.2. Boundary Conditions ................................................................................ 18
6.3. Model Calibration ...................................................................................... 19
6.4. Calibration Results and Discussion ........................................................... 19
6.5. Model Verification ..................................................................................... 21
6.6. Verification Results and Discussion .......................................................... 21
7. DESIGN FLOOD BEHAVIOUR ................................................................................ 24
7.1. Boundary Conditions ................................................................................ 24
7.1.1. Design Inflows .......................................................................................... 24
7.1.2. Tailwater Conditions ................................................................................. 24
7.1.3. Entrance Conditions ................................................................................. 25
7.2. Design Event Results ............................................................................... 26
7.3. Sensitivity Analysis ................................................................................... 27
7.3.1. Rainfall Sensitivity..................................................................................... 27
7.3.2. Parameter Sensitivity ................................................................................ 30
7.4. Climate Change ........................................................................................ 31
7.5. Hydraulic and Hazard Categories ............................................................. 32
7.6. Flood Planning Area ................................................................................. 34
7.7. Impacts of Sea Level Rise on Flood Planning Area .................................. 34
8. FLOOD DAMAGES .................................................................................................. 35
8.1.1. Background .............................................................................................. 35
8.1.2. Assessment of Tangible Flood Damages .................................................. 35
8.1.3. Tangible Damages – Residential Properties ............................................. 36
8.1.4. Results ..................................................................................................... 37
9. EMERGENCY RESPONSE ...................................................................................... 39
9.1. Preliminary Flood Emergency Response Planning Classification of
Communities ............................................................................................. 39
9.2. Evacuation Routes and Length of Inundation ............................................ 40
9.3. Correlation between Newry Island U/S Gauge and Newry Island Bridge .. 43
10. TIDAL CALIBRATION .............................................................................................. 44
10.1. Verification to a Tide ................................................................................. 44
10.2. High High Water Solstice Spring ............................................................... 44
11. CONCLUSIONS ....................................................................................................... 45
12. REFERENCES ......................................................................................................... 46
LIST OF APPENDICES
Appendix A: Glossary
LIST OF TABLES
Table 1: Significant Peak Flood Levels at Bellinger Bridge ........................................................ 11
Table 2: Calibration and Verification Events .............................................................................. 15
Table 3: Adopted Manning’s “n” Values..................................................................................... 19
Table 4: Calibration Events - Modelled vs Observed Flood Levels -1974 ................................. 20
Table 5: Calibration Events - Modelled vs Observed Flood Levels - 1977 ................................ 21
Table 6: Verification Events - Modelled vs Observed Water Levels - 2001 ................................ 22
Table 7: Verification Events - Modelled vs Observed Water Levels - 2009 ................................ 22
Table 8: Ocean Boundary Peaks (mAHD) ................................................................................. 25
Table 9: Entrance Erosion ......................................................................................................... 26
Table 10: Design Flood Levels at Key Locations ....................................................................... 26
Table 11: Comparison of 1% AEP Flood Level with Previous Studies ....................................... 27
Table 12: Catchment Average Rainfall Comparison (mm) ......................................................... 28
Table 13: FFA Flow Comparison (m3/s) .................................................................................... 29
Table 14: Changes in Design Flood Level – Bellingen (mAHD) ................................................. 30
Table 15: Sensitivity Analyses ................................................................................................... 31
Table 16: Climate Change Results ............................................................................................ 32
Table 17: Affected Properties .................................................................................................... 37
Table 18: Estimated Flood Damages ........................................................................................ 38
Table 19: Response Required for Different Flood ERP Classifications ...................................... 39
Table 20: Design flood levels at low points in roads. ................................................................. 40
Table 21: Inundation times of road low points ........................................................................... 41
Table 22: Event when access and evacuation is cut ................................................................. 41
LIST OF FIGURES
Figure 1: Study Area
Figure 2: Available Survey Data
Figure 3: Hydrologic Model Layout
Figure 4: Hydraulic (TUFLOW) Model Layout
Figure 5: Manning’s n Values
Figure 6: Model Calibration –Modelled vs Observed – 1974 Event
Figure 7: Model Calibration - Modelled vs Observed – 1977 Event
Figure 8: Model Validation – Modelled vs Observed – 2001 Event – Bellingen Bridge
Figure 9: Model Validation – Modelled vs Observed – 2001 Event – Repton
Figure 10: Model Validation - Modelled vs Observed – 2001 Event – Urunga
Figure 11: Model Validation - Modelled vs Observed – 2001 Event – Newry Island
Figure 12: Model Validation – Modelled vs Observed – 2009 Event – Bellingen Bridge
Figure 13: Model Validation – Modelled vs Observed – 2009 Event – Repton
Figure 14: Model Validation – Modelled vs Observed – 2009 Event – Urunga
Figure 15: Model Validation - Modelled vs Observed – 2009 Event – Newry Island
Figure 16: Model Calibration –Peak Flood Level - 1974 Event
Figure 17: Model Calibration – Peak Flood Level - 1977 Event
Figure 18: Model Validation – Peak Flood Level - 2001 Event
Figure 19: Model Validation – Peak Flood Level - 2009 Event
Figure 20: Design Event Flood Level Profiles – Bellinger River
Figure 21: Design Event Flood Level Profiles – Kalang River
Figure 22: Design Event – Peak Flood Depths and Level Contours – 5 Year ARI Event
Figure 23: Design Event – Peak Flood Depths and Level Contours – 10 % AEP Event
Figure 24: Design Event – Peak Flood Depths and Level Contours – 2 % AEP Event
Figure 25: Design Event – Peak Flood Depths and Level Contours – 1 % AEP Event
Figure 26: Design Event – Peak Flood Depths and Level Contours – 0.5 % AEP Event
Figure 27: Design Event – Peak Flood Depths and Level Contours – 0.2 % AEP Event
Figure 28: Design Event – Peak Flood Depths and Level Contours – 0.05 % AEP Event
Figure 29: Design Event - Peak Flood Depths and Level Contours – PMF Event
Figure 30: Design Event – Peak Flood Velocities – 5 Year ARI Event
Figure 31: Design Event – Peak Flood Velocities – 10 % AEP Event
Figure 32: Design Event – Peak Flood Velocities – 2 % AEP Event
Figure 33: Design Event – Peak Flood Velocities – 1 % AEP Event
Figure 34: Design Event – Peak Flood Velocities – 0.5 % AEP Event
Figure 35: Design Event - Peak Flood Velocities – 0.2 % AEP Event
Figure 36: Design Event – Peak Flood Velocities – 0.05 % AEP Event
Figure 37: Design Event – Peak Flood Velocities – PMF Event
Figure 38: Design Event – Peak Flood Depths and Level Contours – 1 % AEP Event with a 10%
Rainfall Increase
Figure 39: Design Event - Peak Flood Depths and Level Contours – 1 % AEP Event with a 20%
Rainfall Increase
Figure 40: Design Event – Peak Flood Depths and Level Contours – 1 % AEP Event with a 30%
Rainfall Increase
Figure 41: Design Event – Peak Flood Depths and Level Contours – 1 % AEP Event 2050 Sea
Level Rise
Figure 42: Design Event – Peak Flood Depths and Level Contours – 1 % AEP Event 2100 Sea
Level Rise
Figure 43: Ocean Boundary Conditions
Figure 44: Impact of 1% AEP boundary conditions
Figure 45: Hydraulic Categorisation – 1 % AEP Event
Figure 46: Hydraulic Categorisation – PMF Event
Figure 47: Hydraulic Hazard – 1 % AEP Event
Figure 48: Hydraulic Hazard – PMF Event
Figure 49: Flood Planning Area – 1% AEP Event
Figure 50: Flood Planning Area – 1% AEP Event 2050 Sea Level Rise
Figure 51: Flood Planning Area – 1% AEP Event 2100 Sea Level Rise
Figure 52: Flood Planning Area Difference – 1% AEP with Sea Level Rise
Figure 53: Preliminary Flood Emergency Response Planning Classification of Communities
Figure 54: Catchment Time of Inundation in 1% AEP Event
Figure 55: Time of Inundation in 1% AEP Event
Figure 56: Time of Inundation in 1% AEP Event – Newry Island and Urunga
Figure 57: Time of Inundation in 1% AEP Event – Waterfall Way
Figure 58: Time of Inundation in 1% AEP Event – Newry Island Drive
Figure 59: Time of Inundation in 1% AEP Event – Bellingen Bridge
Figure 60: Time of Inundation in 1% AEP Event – Yellow Rock Road
Figure 61: Ground First Inundated
Figure 62: Ground First Inundated - Bellingen
Figure 63: Ground First Inundated - Raleigh
Figure 64: Ground First Inundated - Mylestom
Figure 65: Ground First Inundated – Newry Island
Figure 66: Floor First Inundated
Figure 67: Floor First Inundated - Bellingen
Figure 68: Floor First Inundated - Raleigh
Figure 69: Floor First Inundated - Mylestom
Figure 70: Floor First Inundated - Newry Island
Figure 71: Model Calibration – Modelled vs Observed –Tide – Urunga
Figure 72: Model Calibration – Modelled vs Observed –Tide – Repton
Figure 73: Model Calibration – Modelled vs Observed –Tide – Newry Island
Figure 74: Model Calibration – Peak Tide Depth – Tide
Figure 75: High High Mean Tidal Area
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
1
FOREWORD
The NSW State Government’s Flood Policy provides a framework to ensure the sustainable use
of floodplain environments. The Policy is specifically structured to provide solutions to existing
flooding problems in rural and urban areas. In addition, the Policy provides a means of ensuring
that any new development is compatible with the flood hazard and does not create additional
flooding problems in other areas.
Under the Policy, the management of flood liable land remains the responsibility of local
government. The State Government subsidises flood mitigation works to alleviate existing
problems and provides specialist technical advice to assist Councils in the discharge of their
floodplain management responsibilities.
The Policy provides for technical and financial support by the Government through four sequential
stages:
1. Flood Study
• Determine the nature and extent of the flood problem.
2. Floodplain Risk Management
• Evaluates management options for the floodplain in respect of both existing and
proposed development.
3. Floodplain Risk Management Plan
• Involves formal adoption by Council of a plan of management for the floodplain.
4. Implementation of the Plan
• Construction of flood mitigation works to protect existing development, use of
Local Environmental Plans to ensure new development is compatible with the
flood hazard.
This report is an extension of the RMS Hydraulic Modelling Report – Bellinger and Kalang Rivers
which defined flood behaviour under existing and a changed climate. This report incorporates the
findings of the RMS Bellinger and Kalang Rivers Hydraulic Modelling Report with additional
components addressed which are required to complete the flood study stage.
Bellingen Shire Council has prepared this document with financial assistance from the NSW
Government through its Floodplain Management Program. This document does not necessarily
represent the opinions of the NSW Government or the Office of Environment and Heritage.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
2
EXECUTIVE SUMMARY
The study area includes Lower Bellinger and Kalang river catchments located in Bellingen Shire.
The Kalang River joins with the Bellinger River and discharges to the ocean at Urunga. The
catchment area of the combined Bellinger and Kalang Rivers and their tributaries is 1110 km2.
The Bellinger and Kalang Rivers study area is defined as:
• Upstream to Bellingen Bridge (Lavenders Bridge) on the Bellinger River,
• To 2.5km past the Brierfield Bridge on the Kalang River, and
• Downstream to the Pacific Ocean.
This study builds upon earlier hydrology and hydraulic modelling studies (Reference XX) to
produce a flood study for Council. The hydraulic model has been used to reproduce the historical
flood behaviour from events in 1974, 1977, 2001 and 2009. The TUFLOW model has been used
to define flood behaviour for a range of design events (5 Year ARI, 10, 2, 1, 0.5, 0.2 and 0.05 %
AEP and Probable Maximum Flood).
The study contains further investigations relating to:
• hydraulic and hazard analysis,
• emergency response classification
• evacuation routes and length of inundation and
• a flood damages assessment.
The study also includes community consultation.
The Lower Bellinger and Kalang Rivers Hydraulic Modelling Report has been further assessed
and is considered suitable for future use by Council in the floodplain risk management planning
process.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
3
1. INTRODUCTION
In 2012, Roads and Maritime Services produced a hydraulic model of the Lower Bellinger and
Kalang Rivers as part of the Warrell Creek to Urunga Pacific Highway Upgrade. This model is
described in the document “Lower Bellinger and Kalang Rivers Hydraulic Modelling Report”
(Reference 27). In order to assess the suitability of this model for use in floodplain management
planning, further analysis has been under taken.
The Bellinger and Kalang Rivers study area is defined as:
• Upstream to Bellingen Bridge (Lavenders Bridge) on the Bellinger River,
• To 2.5km past the Brierfield Bridge on the Kalang River, and
• Downstream to the Pacific Ocean.
This report details the investigations, results and findings of the flood study for the Bellinger and
Kalang Rivers. This includes some work conducted as part of previous studies and additional
investigations completed as part of this study. Flood study elements undertaken as part of
previous studies include:
• a summary of available data,
• hydraulic model development,
• calibration of the hydraulic model, and
• definition of the design flood behaviour through the analysis and interpretation of model
results.
Additional flood study elements undertaken as part of this study:
• Provisional hydraulic hazard,
• Emergency response classifications,
• evacuation routes and length of inundation and
• a flood damages assessment.
A glossary of flood related terms is provided in Appendix A.
1.1. Report Outline
This report provides background information on the catchment and previous studies in Sections
2. The available data used is described in Section 3. Section 4 describes the adopted modelling
approach.
Details of the hydrologic modelling that was undertaken to determine inflows to the hydraulic
model are contained in the earlier Review of Bellinger, Kalang and Nambucca Rivers Catchment
Hydrology (Reference 3) which investigates known hydrologic issues in the Bellinger, Kalang and
Nambucca River catchments. A summary of this report is included in Section 5. Also included in
Section 5 is the development of the 0.05% AEP flows.
Hydraulic modelling of the Bellinger and Kalang Rivers are detailed in Section 6. This includes
model calibration, verification and sensitivity analysis. Design flood behaviour is discussed in
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
4
Section 7. Section 8 discussed the emergency response classification. Flood damages
calculations are described in Section 9. Tidal calibration and tidal planes are discussed in Section
10.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
5
2. BACKGROUND
2.1. Study Area
The study area (refer to Figure 1) includes the Bellinger River and Kalang River catchments. The
Bellinger and Kalang Rivers are located within Bellingen Shire Council. The Bellinger and Kalang
Rivers join and discharge into the Pacific Ocean near Urunga. The total catchment area of both
rivers is 1110 km2. The catchment area of the Kalang River upstream of its junction with the
Bellinger River is approximately 340 km2.
The headwaters of the catchments are located in the Great Dividing Range and are characterised
by steep topography. The lower reaches are characterised by broad floodplains and farmland.
Residential development within the catchments generally consists of small settlements. Major
centres exist at Bellingen and Urunga.
The Study area is defined as (Figure 1):
• Upstream to Bellingen Bridge (Lavenders Bridge) on the Bellinger River,
• To 2.5km past the Brierfield Bridge on the Kalang River, and
• Downstream to the Pacific Ocean.
2.2. Previous Studies
A number of flood studies and assessments have previously been undertaken within the Bellinger
and Kalang River catchments. These studies range from lot sized flood assessments to large
scale studies encompassing both the Bellinger and Kalang Rivers. A brief overview of the more
significant studies is provided below. A review of the “Lower Bellinger and Kalang Rivers
Hydraulic Modelling Report” (Reference 27) is not contained here as the contents of that report
largely form this report. Council has also recently completed an Estuary Inundation Mapping report
(BMT, 2015) which uses the model and boundary conditions from the current study.
New South Wales Coastal Rivers Floodplain Management Studies Bellinger Valley
(Cameron McNamara, December 1980)
Part of a series of reports on NSW coastal rivers this report (Reference 6) details floodplain
management measures within the Bellinger valley and makes recommendations on policy. The
report contains recorded water levels and selected aerial photographs of historical floods.
Proposed Industrial Area, Urunga NSW (Outline Planning Consultants, May 1984)
The report (Reference 7) covers a proposed industrial area situated adjacent to the Pacific
Highway and the North Coast Railway line, on the northern fringe of Urunga. The site
characteristics and its suitability for the proposed development were assessed. Flooding on the
site was assessed based on available flood maps. The Pacific Highway is noted to act as a levee
and protect some low lying areas in the middle of the site. The majority of the site was found to
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
6
be flood free based on the available data. The northern end of the site was found to be flood
affected from backwater flooding by an intermittent creek.
Bellinger River May 1980 Flood Report (PWD, 1981)
This report (Reference 8) details data collected for the May 1980 flood in the Bellinger Valley and
presents rainfall, flood heights and stage hydrographs for the event. Insufficient information was
available to include this event in the model calibration.
Bellinger River Flood History 1843-1979 (PWD, 1980)
This study (Reference 9) was undertaken to document flood data in the tidal section of the
Bellinger River (up to Bellingen) to be used in preparing flood maps for Bellingen. A flood
frequency analysis was conducted using recorded data for the Bellingen Bridge. Floods with peak
heights greater than 8.3m were included. Due to a lack of data downstream of Bellingen flood
heights determined for the 1%, 2% and 5% AEP events at Bellingen were combined with
estimated flood gradients to determine flood levels and flood maps for downstream towns. The
report details personal recollections of residents about significant historical events. Flood
reference points for significant flood events including the 1962, 1974 and 1977 events are reported
which were used for model calibration.
Lower Bellinger River Flood Study (PWD, 1991)
The Lower Bellinger River Flood Study (1991, Reference 10) investigated flooding in the Bellinger
River below Bellingen and the Kalang River downstream of Picket Hill Creek. A CELLS hydraulic
model was developed to determine flood levels for the 1%, 2%, and 5% Annual Exceedance
Probability (AEP) and extreme design flood events. The 1962, 1974 and 1977 historical events
were used for model calibration and verification. The effects of ocean levels and bed scour were
incorporated into the model. A RORB hydrological model was developed of the Bellinger and
Kalang River catchments to convert rainfall to flow hydrographs. Model data and results from the
hydraulic model developed for this study were used to provide boundary conditions and
topographic information for the Newry Island Flood Study. This report was used as a comparison
with new model results. The hydrologic model subcatchment layout formed a basis for the
hydrologic model layout for the current study.
Lower Bellinger River Flood Study, Location of Flood Marks Engineering Survey Brief
(Cameron McNamara, 1991)
As part of the 1991 Lower Bellinger River Flood Study, a survey of local residents was conducted
of the area downstream of Bellingen (on the Bellinger River) and Picket Hill Creek (on the Kalang
River). The survey identified 46 flood reference points and information on the flood behaviour.
The report (Reference 11) shows the location and photos of the survey reference points.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
7
Lower Bellinger River Flood Study Compendium of Data (PWD, 1991)
This report (Reference 12) provides a review of available data for the Lower Bellingen River Flood
Study. Total rainfall isohyets were drawn for selected events. A summary of results from the
resident survey for the 1950, 1962 and 1974 flood events is presented.
Bellinger and Kalang River’s Floods of February and March 2001 (Bruce Fidge and
Associates, 2003)
Rainfall and flood level information for the February and March 2001 floods is summarized in this
report. Survey of peak flood debris levels was undertaken by Council following the March 2001
event. Based on the design flood behaviour defined in the 1991 Flood Study and Flood History
Report (Reference 13) the recurrence interval for the events at various locations within the
catchments were estimated. The February 2001 event was estimated to have a 5 year Average
Recurrence Interval (ARI) for Repton, 6 year ARI for Newry Island and 10 year ARI for Urunga.
The March 2001 event was estimated to have a 12 year ARI for Repton, 6 year ARI for Newry
Island and 10 year ARI for Urunga. Compared to the February flood, the March 2001 event was
bigger on the Bellinger River. However, the February and March events were of similar magnitude
on the Kalang River and in the vicinity of Newry Island. The 2001 event was used in the current
study for model verification.
Floodplain Risk Management Study Stage 2- An Assessment of Floodplain Management
Options and Strategies (Bellingen Shire Council, April 2002)
The report (Reference 14) was commissioned by Bellingen Shire Council to investigate
management strategies for flood prone land in the Bellinger and Kalang River catchments.
Floodplain risk management options are considered and prioritised. The report recommended
additional rainfall and water level gauges be installed on the Kalang River and Lower Bellinger
River, to improve flood prediction and supplement the existing system. Flood management
recommendations for Newry Island included increasing the level of Newry Island Drive so that
rural residents have access during a 5 and 10% AEP floods and the expansion of Newry Island
bridge to improve evacuation.
Upper Kalang River Flood Assessment, (Bellingen Shire Council, December 2006)
This report (Reference 15) modelled 26.5 km of the Upper Kalang River to Pickett Creek using a
one dimensional MIKE 11 model. Boundary conditions were drawn from the Lower Bellingen
River Flood Study. The Lower Bellinger Flood Study RORB model was adopted for the Upper
Kalang River. An areal reduction factor of 0.6 was adopted to be consistent with the Lower
Bellinger Flood Study and the Upper Bellinger River Flood Assessment. Filtering of the temporal
patterns was undertaken. A critical storm duration of 12 hours was adopted in comparison to 36
hours which was adopted by the 1991 Flood Study. Flood frequency analysis undertaken for this
study used heights which is not ideal as it is unable to take into account the variance in the cross
section. A combined record of the 3 Kooroowi –Scotchman gauges was derived. Peak height
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
8
correlations between the stations was enabled by the establishment of a MIKE 11 model.
The intent of the study is to provide indicative flood levels and therefore the model is not calibrated.
The flood levels should be used for general purposes only and do not have the same reliability as
a flood study. Cross section survey undertaken for this study was used in the current study.
South Arm Road Flood Study (Final) (DeGroot and Benson Pty Ltd, June 2000)
The report (Reference 16) details the hydrologic and hydraulic modelling of the existing conditions
in the vicinity of South Arm Road and the unnamed creek that drains into Boggy Creek. South
Arm Road is subject to flooding from the Kalang River (via backwater flooding from Boggy Creek),
local runoff and a combination of both. The road is subject to frequent inundation between Short
Cut Road and the Riverside Drive subdivision, cutting off the main access to the area. The
hydraulic modelling for this study was undertaken using a water balance model originally
developed for the Central Urunga Flood Study. The report investigates the effect of raising the
road to 2.5, 3.0, 3.5 and 4.0 mAHD. Raising the road was found to have minimal effect on the
flood level at Urunga (<15mm), due to the conveyance capacity of the wetland area at that level.
Details of the culverts under South Arm Road are described in this report. The report recommends
raising South Arm Road to no greater than 3.30 mAHD if the existing culvert arrangement was to
remain.
Upper Bellinger River Flood Assessment (Bellingen Shire Council, 2006)
The Lower Bellinger Flood Study (Reference 10) RORB model was adopted for the Upper
Bellinger River Flood Assessment (Reference 17). An areal reduction factor of 0.6 above Thora
and 1.0 for all other catchments was required in order to fit the flood frequency analysis. Filtering
of the temporal patterns resulted in the 12 hour event being critical rather than the 36hr which was
found to be critical in the Lower Bellinger Flood Study. The RORB model was refined in the Never
Never River catchment to provide inflows to the hydraulic model. On the Never Never River a
larger than standard practice continuing loss (7.5mm/hr) was adopted, with an initial loss of 0mm.
A rating curve extrapolation was undertaken for 900m downstream of Bellingen using the CELLS
model developed as part of the Lower Bellinger Flood Study. This flood assessment provided
flood levels for design events in the Upper Bellinger. A detailed calibration of the hydraulic model
was not undertaken as part of the study. Cross section survey undertaken for this study was used
in the current study.
Newry Island Flood Study Draft (WMAwater, 2008)
The Newry Island Flood Study (Reference 18) developed a TUFLOW model of the Lower Bellinger
and Kalang Rivers. Inflows for the TUFLOW model were derived from the Lower Bellinger Flood
Study RORB and CELLS models. Model calibration and validation was conducted using the 1974,
1977 and 2001 events. Information on the 2001 event derived as part of the Newry Island study
was used to inform the current study.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
9
Warrell Creek to Urunga Upgrade Environmental Assessment (RTA, 2010)
The Warrell Creek to Urunga Upgrade Environmental Assessment (2010) (Reference 5) assessed
the impact of the proposed pacific highway upgrade crossing on the Kalang River on flood levels.
A RORB model was developed of the catchment. In order to fit the flood frequency analysis results
the study adopted the Australian Rainfall and Runoff (ARR) temporal patterns for zone 3 rather
than zone 1.
Review of Bellinger, Kalang and Nambucca Rivers Catchment Hydrology (WMAwater, 2011)
The Review of Bellinger, Kalang and Nambucca Rivers Catchment Hydrology (Reference 3)
investigates known hydrologic issues in the Bellinger, Kalang and Nambucca River catchments.
This area of the NSW north coast has presented a range of challenges for a number of studies
where problems have been encountered matching rainfall runoff modelling with flood frequency
results. As part of the study WBNM models were developed for each catchment and calibrated to
historical events. The hydrology developed as part of the study has been used for the current
study.
Kalang River – 2009 Flood Event (WMAwater, 2011)
This study (Reference 19) modelled the March/April 2009 flood event using the hydraulic model
established as part of the Newry Island Flood Study (Reference 18) using inflows developed by
Reference 3. Overall a good calibration to the observed flood levels during 2009 event was
achieved. This study verifies the calibration of the Newry Island Flood Study TUFLOW model.
Bellinger and Kalang Rivers Flood Event of 31 March 2009 Collection and Collation of Flood
Data (Enginuity Design, 2010)
This report (Reference 20) contains the results of an extensive data collection exercise undertaken
following the 2009 event. The report contains rainfall data and observed flood level marks for the
March 2009 event. This data has been used in the current study to inform the calibration of the
hydraulic model.
Warrell Creek to Urunga: Pacific Highway Upgrade Modelling (WMAwater, 2012)
This report (Reference 24) contains a detailed assessment of the impacts of the Pacific Highway
Upgrade on flood levels in the Bellinger / Kalang River system. The study used the hydraulic
model used for the current study.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
10
3. AVAILABLE DATA
3.1. Rainfall Information
3.1.1. Historic Rainfall Data
Historical rainfall data was obtained at a number of locations within the study area and surrounds.
Daily rainfall and pluviograph data was obtained for a number of gauges within the region from a
number of sources including the Bureau of Meteorology (BoM) and Manly Hydraulics Laboratory
(MHL).
Historic rainfall data available for the 1974, 1977, 2001 and 2009 events on the Bellinger and
Kalang Rivers is documented in Reference 3 and Reference 19. For the 1974 and 1977 events
no pluviograph information was available within the catchment though several pluviometers were
located in adjacent catchments. A limited set of pluviometer records was available for the
historical events examined in the 1991 Flood Study (Reference 10). The largest set of pluviometer
data used in the 1991 Flood Study was for the 1977 event (though none were located within the
catchment). More pluviometer records were available for the more recent events. Resident rainfall
totals collected as part of the post flood data collection for the 2009 event (Reference 20) were
included in the vicinity of Urunga where the official gauges were considered to have under
recorded.
3.1.2. Design Rainfall Data
Design rainfall data available for the Bellinger and Kalang River is documented in Reference 3.
All of the BoM long term daily and pluviograph gauges within and near the catchment were
analysed on a 24hr 9am restricted basis to produce new IFD estimates. This was supplemented
by at site analysis of other gauges which was incorporated into the surface mapping.
3.2. Water Level Data
3.2.1. Time Series Water Level Data
Manly Hydraulics Laboratory (MHL) operates a number of water level recorders in the Bellinger,
Kalang Rivers catchments. These being:
• Newry Island,
• Urunga,
• Repton, and
• Bellinger Bridge.
Stage hydrograph data was obtained from the MHL operated water level stations. The recorded
time-series of water levels was used for model calibration purposes. It should be noted that these
water level recorders are located within the tidal limit. The opportunity for the water level record
to be translated into a corresponding flow hydrograph is therefore limited except for Bellingen
which is at the very upper limit of the tidal limit and for which rating curves exist. However, the
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
11
recorders do provide a valuable record of flood level behaviour during an actual flood.
A number of temporary gauges operated by OEH and MHL were located on the Bellinger and
Kalang rivers during 2009 as part of a water quality study (Reference 26). Many of the gauges
were damaged during the event or did not record the peak. Where possible these gauges were
used as a comparison to model results eg. for timing of the rising limb.
3.2.2. Peak Flood Heights
The Bellinger and Kalang River Valley’s have a long history of flooding. Flood records for Bellingen
date back to the 1840’s (Reference 9). In comparison to the Bellinger River, there is less observed
peak flood height data available for historical events on the Kalang River. However, most large
floods on the Bellinger occur at the same time as a large event on the Kalang. A summary of
significant events which have occurred in the area is presented in Table 1. The more recent
events for which significant data is available for calibration and validation purposes occurred in
1974, 1977, 2001 and 2009.
The 1962 event though used in previous studies for calibration was not included in this study for
the following reasons:
• No pluviographs within the catchment at the time of the event,
• Limited observed data available including water level recorders,
• The more recent 2009 event was larger and had significantly more data available.
Table 1: Significant Peak Flood Levels at Bellinger Bridge
Year
Gauge Height
(mAHD)
Comment
1870 11.5 Bellingen Flood History 1843 to 1979
1875 10.9 Bellingen Flood History 1843 to 1979
1950 10.4 Bellingen Flood History 1843 to 1979
1946 9.8 Bellingen Flood History 1843 to 1979
1954 9.8 Bellingen Flood History 1843 to 1979
1876 9.6 Bellingen Flood History 1843 to 1979
1974 9.5 Bellingen Flood History 1843 to 1979
1887 9.2 Bellingen Flood History 1843 to 1979
1959 9.1 Bellingen Flood History 1843 to 1979
1890 9 Bellingen Flood History 1843 to 1979
1921 8.9 Bellingen Flood History 1843 to 1979
1967 8.8 Bellingen Flood History 1843 to 1979
2009 8.8 MHL readings
2001 8.77 MHL readings
1894 8.7 Bellingen Flood History 1843 to 1979
1989 8.6 SES readings
1962 8.5 Bellingen Flood History 1843 to 1979
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
12
1977 8.5 Bellingen Flood History 1843 to 1979
1890 8.4 Bellingen Flood History 1843 to 1979
1938 8.4 Bellingen Flood History 1843 to 1979
1887 8.2 Bellingen Flood History 1843 to 1979
1893 8.2 Bellingen Flood History 1843 to 1979
1933 8.2 Bellingen Flood History 1843 to 1979
1963 8.2 Bellingen Flood History 1843 to 1979
1973 8.2 Bellingen Flood History 1843 to 1979
1956 8.1 Bellingen Flood History 1843 to 1979
A review of previous studies and available data found some observed peak flood heights at a
number of locations within or near the study area. The most significant flood events within the
catchment for which suitable calibration data is available occurred in 1974, 1977, 2001 and
April/March 2009. Data for the 1974 and 1977 events are presented in Reference 10. Reference
13 and 20 contain data for the 2001 and 2009 event respectively. Several data collection
exercises have been undertaken to collect peak flood levels and anecdotal evidence of significant
floods in the area (Refer Section 2.2).
3.3. Topographic Information
There is a considerable amount of topographic data available for the study area. However, the
accuracy and suitability of these existing datasets for use in the present study varies. This includes
contours, hydrosurvey, cross sections and Airbourne Laser Scanning.
Council provided topographic contours of the study area in GIS format (at 10 m intervals over the
majority of the catchment and at 2 m intervals over a limited area including Newry Island).
Hydrosurvey of the estuary was available from OEH (Refer Figure 2). The hydrosurvey was
collected between Sept to Nov 2008. It provides waterway cross sections for the estuarine reaches
of the Bellinger River, Kalang River and Pickets Creek. The hydrosurvey shows a significant
amount of sediment at the entrance which OEH staff advised was eroded during the 2009 event.
A significant amount of erosion also occurred on the Kalang River.
Aerial photography collected by the Lands and Property Management Authority was also available
within the catchment boundary. This was utilised in the assigning of Manning’s n values and
identifying catchment changes.
Cross sections from the MIKE 11 models used as part of the Upper Bellinger and Upper Kalang
Flood Assessments (Reference 17 and 15) were also available in the areas where hydrosurvey
was not available.
Airbourne Laser Scanning (ALS) ground levels were provided for the study area. The ALS
collection was part of the Coastal capture program by the Lands and Property Management
Authority. It captures from the coast to the 10m contour interval. Spatial accuracy of the ALS in
the horizontal and vertical directions was reported as 0.8m and 0.3m respectively.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
13
Due to issues with the data processing used to produce the original grids provided, the raw ALS
files were obtained. The non ground strikes were filtered from this data set. Within a 60m buffer
of the waterway the ground strikes and hydrosurvey were tinned and a DEM produced. This DEM
and the ALS grid (outside of the 60m buffer) were combined to create a DEM for use in the 2D
model.
A DEM (Digital Elevation Model) at a 1m grid resolution was used in order to:
• confirm sub-catchment and catchment watershed boundaries; and
• inform the 2D model used in the study.
3.4. Culvert and Structure Data
Details of culverts and structures along the existing highway and Waterfall Way were obtained
from Roads and Maritime Services works as executed plans and culvert database. For local roads
details of culverts and bridge structures were collected on a site visit and based on council records.
Where culvert details were not available a reasonable estimate was made based on upstream
culverts. Some details on culverts and structures under the North Coast Railway were available
from the Newry Island Flood Study (Reference 18).
The Nambucca Heads to Urunga Pacific Highway upgrade currently under construction was
included based on the final construction design plans (option PHU 049 as at 8/10/2014).
3.5. Community Consultation
One of the central objectives of the Flood Study process is to provide the local community with a
community accepted resource that can be utilised for all flood related issues including
development, flood warning, response and management/remediation.
The draft study was on public exhibition from Wednesday, 6 January 201 until Friday 26 February
2016 and was available for viewing during normal business hours at the following locations:
• The Council Administration Centre Bellingen • Bellingen Library • Urunga Library & • Council’s website
Public forums were held at the following times:
• Monday 1 February 2016 at the Uniting Church Worship Hall, Hyde Street Bellingen commencing at 7:00pm
• Tuesday 2 February 2016 at the Urunga Senior Citizens Centre, Bowra Street, Urunga
commencing at 7:00pm
Drop in sessions were also done at:
• Council Administration Centre: o Monday 1 February 2016 - between 1:00pm & 3:00pm o Tuesday 2 February 2016 10:00am to 12:00 midday
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
14
• Bonville Street, Urunga:
o Tuesday 2 2016 - between 1:00pm & 3:00pm
The main concern raised at the drop in sessions was local flooding in the Urunga area. No written
submissions were submitted in the public exhibition period.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
15
4. ADOPTED MODELLING APPROACH
The primary objective of this study is to define the flood behaviour under historical and existing
floodplain conditions in the Study Area while addressing possible future variations in flood
behaviour due to climate change and provide information for its management.
The approach adopted for this study has been influenced by the study objectives, accepted
practice and the quality and quantity of available data. There are two basic approaches to
determining design flood levels namely:
• a flood frequency approach based upon a statistical analysis of the flood record, and
• using a rainfall/runoff routing approach (hydrologic modelling) to obtain flows, and then
inputting these flows into a hydraulic model of the floodplain.
The flood frequency approach was undertaken as part of an earlier study for the Bellinger, Kalang,
and Nambucca River catchments. The results of Reference 3 were used to inform the current
study. Flood frequency analysis was undertaken at Thora, Bellingen, and Kooroowi.
A hydrologic (WBNM, Watershed Bounded Network Model, Reference 4) model was established
for each catchment to determine inflows into the hydrodynamic model. A combined one and two
dimensional hydrodynamic (TUFLOW) model was used to define the flood behaviour using ALS
and hydrosurvey.
The TUFLOW models were calibrated and verified to a range of historical events (Table 2).
Table 2: Calibration and Verification Events
Catchment Calibration and Verification Events
Bellinger and Kalang Rivers 1974, 1977, 2001, 2009
The calibrated hydraulic models were then used to assess the flood levels and hydraulic flood
hazard for the 5 Year ARI, 10%, 2%, 1%, 0.5%, 0.2%, 0.05% AEP and Probable Maximum Flood
(PMF) design events.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
16
5. HYDROLOGIC MODELLING
5.1. Overview
Hydrologic models of the Bellinger, Kalang and Nambucca and Warrell Creek catchments were
established as part of Review of Bellinger, Kalang and Nambucca River Catchments Hydrology
Report (Reference 3). All models were developed using the Watershed Bounded Network Model
(WBNM).
WBNM (Reference 4) is widely used throughout Australia and particularly NSW. WBNM simulates
a catchment and its tributaries as a series of sub-catchment areas linked together to replicate the
rainfall and runoff process through the natural stream network. Input data includes the definition
of physical catchment characteristics including surface area of sub-catchments, proportion of
impervious surfaces, stream length adjustments, initial and continuing losses, temporal and
spatial patterns over the catchment.
Key parameters for WBNM represent the physical characteristics of the catchment. Typical model
parameters include;
• Rainfall Losses: two values, initial and continuing loss, modify the amount of rainfall excess
to be routed through the model sub-catchments;
• Lag Parameter: this affects the timing of the runoff response to the rainfall and is subject
to catchment size, shape and slope; and
• Non Linearity Exponent: adjustment of the non-linearity of catchment response.
The parameters adopted for this study were based on those recommended in ARR 1987
(Reference 1), previous experience and calibration. Some of the information is summarised briefly
below and further details on the parameters used for each of the catchments can be found in
Reference 3). A good fit to observed data was achieved with default lag and no linearity
parameters.
5.2. Review of Bellinger, Kalang and Nambucca River Catchments
Hydrology
Full details of the development of the WBNM model can be found in Reference 3. Figure 3 shows
the hydrological model layout for the Bellinger and Kalang River catchments. As part of the Review
of Bellinger, Kalang and Nambucca River Catchments Hydrology Report (Reference 3) historical
rainfall data was obtained at a number of locations within and surrounding the study area. Historic
stream flow data was also obtained for a number of gauges within the catchments. A number of
stream flow gauges within the catchment were investigated to provide an indication of the reliability
of the rating curves used. Due to the unreliability of the extrapolation techniques used in extending
rating curves for many of the stream flow gauges new rating curves were estimated in locations
where cross sections at the gauge location were available.
Historical event inflows for 1974, 1977, 2001, 2009 were estimated using the hydrologic model.
As with the previous models, temporal and spatial patterns were established from recorded rainfall
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
17
data in the region. The WBNM model was calibrated to known historic flood levels and flows as
part of Reference 3.
Due to concerns over the ARR 1987 design rainfall estimates (and prior to the release of the BoM
2013 IFDs), revised estimates were produced for a range of design events in an approach
consistent with that being proposed for the new version of ARR. Design rainfalls for events up to
the 0.2% AEP event were established from the revised IFDs whilst the PMP estimates were made
using the Generalised Tropical Storm Method as Revised (GTSMR).
Temporal patterns were also applied to the design rainfall as described in Reference 3. Initial and
continuing losses were varied with event size. Losses for the 0.5% and 0.2% AEP were calculated
in accordance with ARR Book IV (Reference 25) by interpolating between the 1% AEP and PMF
losses. More detail on the hydrologic model development can be found in Reference 3. For design
events, the 48 hour storm was found to be the critical duration for the 5 year, 10%, and 2% AEP
events. For the 1%, 0.5% and 0.2% AEP events the 36 hours storm was found to be critical and
the 24 hour storm critical for the PMF.
5.3. 0.05% AEP Event
The 0.05% AEP Event rainfall depths were calculated using the guidance in Australian Rainfall
and Runoff Book VI (ARR, Reference 25) by interpolating between the 2% AEP, 1% AEP and
PMP depths. ARR Book VI recommends that the GTSMR spatial patterns are applied for an
extreme event such as the 0.05% AEP. The GTSMR patterns were found to produce inconsistent
peak flows for the 0.05% AEP when compared to the 0.2% AEP and PMF events and therefore
the ARR patterns as used in the smaller design events were applied to the 0.05% AEP also.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
18
6. HYDRAULIC MODELLING
A model of the study area was developed in the hydrodynamic modelling package (TUFLOW).
TUFLOW (Reference 2) is widely used in Australia and internationally for assessing flood
behaviour and hydraulic hazard. TUFLOW is a finite difference numerical model which is capable
of solving the depth averaged shallow water equations in both the one and two dimensional
domains.
The model extent for each catchment was determined in conjunction with the Roads and Maritime
Services (RMS), Bellingen Shire Council and Office of Environment and Heritage (OEH). The
purpose of the model was to both meet the needs of Council and OEH in terms of the NSW Flood
Study Program and the RMS to assess the impacts of proposed waterway crossings.
A combined one and two dimensional hydrodynamic model (TUFLOW) model of the Bellinger and
Kalang Rivers was established.
6.1. Model Configuration
The model consists of a 2D 15m grid defining the overbank and the channel for the Bellinger
River, lower Kalang River and its tributaries. The upper reaches of the Kalang River are defined
by a combined one and two dimensional model, with the one dimensional network defining the
main channel. The extent of the TUFLOW model is shown in Figure 4.
The model extends a sufficient distance upstream and downstream of the study area such that
the imposed boundary conditions do not influence the model results in the region of interest. The
TUFLOW model limits were:
• Upstream limit on Bellinger River - 3km upstream of the Bellinger River Bridge at
Bellingen,
• Upstream limit on Kalang River – 2.5km past the Brierfield Bridge, and
• Downstream limit – Pacific Ocean.
A 15 metre digital terrain model (DTM) was created using the topographic data outlined in Section
3. Within the one dimensional component of the model cross sections were derived from the
hydrosurvey and cross sections from the Upper Bellinger and Upper Kalang Flood Assessments
(Reference 15 and 17). Culverts under a number of roads and the North Coast Railway Line were
incorporated in the model including culverts under both the old and new Pacific Highway’s.
6.2. Boundary Conditions
Inflows and boundary conditions for the TUFLOW model consist of a number of time varying flow
hydrographs developed using the WBNM model. At the downstream boundary of the model, a
tailwater level defining the river entrance was used. The tailwater conditions were based on
recorded tide levels at Coffs Harbour, experience on nearby catchments and OEH guidelines
(Reference 22). Figure 4 shows the inflow locations and boundary condition types.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
19
6.3. Model Calibration
Model calibration was undertaken using historical data for the 1974 and 1977 flood events. These
events were adopted as a reasonable amount of observed data exists within the catchment. Time
varying water level data is also available in the lower estuary for these events. Previous studies
on the Bellinger/Kalang system have used these events for calibration and been able to reproduce
observed flood behaviour.
Inflows to the hydraulic model for these events were developed as part of Reference 3.
The hydraulic efficiency of the creeks is represented (in part) within the TUFLOW model by the
roughness or friction factor, Manning’s “n” value. Manning’s “n” is used to describe the influence
of the following factors on flow behaviour:
• channel roughness,
• channel sinuosity,
• vegetation and other debris/obstructions in the channel, and
• bed forms and shapes.
As part of the calibration process the Manning’s “n” roughness value was adjusted within
reasonable limits to best match the recorded flood heights along the creek system. Adopted values
were selected based on an assessment of the ground cover types and vegetation density within
the floodplain. The adopted values (Refer to Table 3 and Figure 5) were then used for the hydraulic
modelling of the design events and assessment of the proposed highway (refer to Reference 24).
Table 3: Adopted Manning’s “n” Values
Description Manning’s “n” Value
Low Density Residential, Farms 0.04
Medium Density Residential / Overbank 0.06
Dense/Thick vegetation 0.08 - 0.1
Grass/open space 0.04
Main channel 0.025
Vegetated Creeks 0.045
Roads/railway line/culverts 0.02
Other Channel 0.025
6.4. Calibration Results and Discussion
The 1974 and 1977 events were used for calibration of the hydraulic model. These events were adopted for calibration as they had been used by previous studies which achieved a good calibration to observed values. Time varying water level data was only available for Bellingen Bridge for these events. Observed water levels were based on SES data and only available near the peak of the event. The model calibrated reasonably well to observed flood levels (Table 4 and
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
20
Table 5). Peak flood levels and depths for the 1974 and 1977 events are shown in Figure 16 to
Figure 17. Comparison of modelled and observed time varying water levels at Bellingen Bridge in
shown on Figure 6 and Figure 7.
The modelled levels for the 1974 event were generally within 0.4 m of the observed values. The
model showed a bias towards being slightly high. A fair calibration was achieved to the observed
points in Bellingen. Some of the observed peak flood levels in Bellingen appear to contradict each
other. The model however provides a good fit to the time varying water levels at Bellingen (Figure
6). A poor calibration was achieved to an observed level in the Upper Kalang River (Observed
9.7mAHD, Modelled 7.55mAHD). There could be many reasons for such a mismatch between
levels including accuracy of the observed level, datum error or sparsity of pluviograph information.
The accuracy of this observed level is thought to be suspect due to a datum error. The sparsity of
pluviograph rainfall information makes calibration to early events difficult as it is difficult to know
what the temporal pattern of rainfall was. Modelled flood levels in the lower Bellinger and Kalang
were strongly influenced by the entrance conditions used.
The modelled levels for the 1977 event were generally within 0.1m of the observed levels except
for:
• Downstream of the entrance where the adopted entrance erosion conditions strongly
influence the modelled levels,
• At Bellingen where modelled water level is 8.74mAHD and the observed peak is 8.2mAHD.
However the time varying water level recorded by the SES peaks at 8.52mAHD.
Table 4: Calibration Events - Modelled vs Observed Flood Levels -1974
River
Location Observed
Level
(mAHD)
Modelled
Level
(mAHD)
Difference
(m)
Bellinger
Bellingen Bridge 9.5 9.46 -0.04
Dowle St, North Bellingen backwater 9.8 9.59 -0.21
Cnr. Hammond and Black Sts., North Bellingen
backwater 9.3 9.82 0.52
0.4km DS Bellingen Bridge 9.2 8.89 -0.31
Black St., North Bellingen backwater 9.2 8.86 -0.34
Old Butter Factory, East Bellingen 8.7 8.45 -0.25
Fernmount E. Cox 5.7 5.58 -0.12
Raleigh Road Bridge 4.2 4.33 0.13
Raleigh McBaron 4.1 4.27 0.17
Raleigh house 0.4km west of MaBaron 4.1 4.31 0.21
Raleigh CDA Factory 3.9 4.22 0.32
0.1 km US Man Arm Creek Jn. 3.6 4.02 0.42
Summer Breeze Cabins Raleigh 2.6 2.95 0.35
Kalang
Jn, Kalang River & Spicketts Creek 9.7 7.55 -2.15
Northern trip Newry Island 2.7 2.93 0.23
Newry Island opposite Golden Fleece 2.6 2.89 0.29
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
21
Table 5: Calibration Events - Modelled vs Observed Flood Levels - 1977
River
Location Observed
Level
(mAHD)
Modelled
Level
(mAHD)
Difference (m)
Bellinger
Bellingen Bridge 8.52 8.74 0.22
Raleigh McBaron 3.4 3.41 0.01
Raleigh house 0.4km west of McBaron 3.4 3.46 0.06
Kalang
Newry Island opposite Golden Fleece 2.3 2.37 0.07
Yellow Rock Road Paxton 2.2 2.11 -0.09
0.7km DS Urunga Road Bridge Privett 2.2 1.71 -0.49
Urunga Pinfolds boatshed 2.1 1.39 -0.71
6.5. Model Verification
Model verification was conducted, using the calibrated model and parameters (as discussed in
Section 6.3). The 2001 and March/April 2009 events were used for model calibration. A significant
amount of observed levels and rainfall data was available for these events. Time varying water
level data was also available for the lower estuary for both these events at Bellingen, Repton,
Urunga and Newry Island. The March/April 2009 event is the largest event for which calibration
data is available on the lower Bellinger and Kalang Rivers.
Both events were modelled previously using the Newry Island Flood Study TUFLOW model
(Reference 18 and 19). A reasonable calibration was achieved by the previous studies. Reference
18 postulated that the Newry Island U/S gauge was suspect during the 2001 event but no solid
proof of this could be found. Reference 19 on face value confirmed this to be the case.
6.6. Verification Results and Discussion
Peak flood levels for the 2001 and March/April 2009 events are shown in Figure 18 and Figure
19. Comparisons of modelled and observed time varying water levels for Bellingen, Repton,
Urunga and Newry Island gauges are shown in Figure 8 to Figure 15.
For the 2001 event the model calibrated well to observed flood levels. The modelled levels were
generally within 0.2 m of the observed values except for Bellingen Bridge where the model was
0.4m high. A comparison of observed and model levels are shown in Table 6.
For the March/April 2009 event a poor calibration was achieved to observed levels in the Upper
Kalang River (refer to Figure 19). Sensitivity testing indicated that a 1.5 increase in local flows
would not result in a good calibration. A similar difference between modelled and observed was
noted for the 1974 event in this area. Further investigation into local effects not modelled is
warranted. It is possible these level discrepancies are caused by a bias in the local datum control
or very localized rainfall, as it is not possible match these observed levels with any reasonable
modification of parameters. A comparison of observed and model levels are shown in Table 7.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
22
Near Bellingen the March/April 2009 event was approximately a 10% AEP event. In the lower
reaches of the Bellinger River the event is between a 10% and 2% AEP event. On the Kalang
River the event was significantly larger. Upstream of Newry Island the event has a return period
in the order of 0.5% AEP. At Newry Island the event is between a 1% and 0.5% AEP event and
at Urunga in the order of a 2% AEP event.
Table 6: Verification Events - Modelled vs Observed Water Levels - 2001
River Location Observed Level
(mAHD)
Modelled Level
(mAHD)
Difference
(m)
Bellinger
Bellingen brigde 8.77 9.19 0.42
Norco Depot 8 7.81 -0.19
Marx Hill Bridge 6.6 6.38 -0.22
Burdett Park Creek 5.9 5.99 0.09
Connells Bridge 4.8 4.67 -0.13
Camerons Corner 4.4 4.34 -0.06
Repton 3.24 3.23 -0.01
Kalang
Newry Island 2.38 2.57 0.19
Caravan Park, Urunga 2.13 2.09 -0.04
Urunga 1.84 1.73 -0.11
Table 7: Verification Events - Modelled vs Observed Water Levels - 2009
River
Location Observed Level
(mAHD)
Modelled
Level
(mAHD)
Difference
(m)
Bellinger
110 Gleniffer Road 10.1 10.05 -0.05
110 Gleniffer Road 9.94 10.05 0.11
1301 Waterfall Way 9.56 9.27 -0.29
1301 Waterfall Way 9.49 9.27 -0.22
Lavenders Bridge 8.81 8.94 0.13
Waterfall Way 7.01 7.74 0.73
Waterfall Way 7 6.98 -0.02
794 Waterfall Way 6.38 6.08 -0.30
895 North Bank Road 5.1 4.58 -0.52
Valery Road 4.24 3.99 -0.25
North Street 3.9 3.78 -0.12
Repton Gauge 3.56 3.44 -0.12
474 Yellow Rock Road 3.09 2.82 -0.27
476 Yellow Rock Road 3.07 2.82 -0.25
Reserve 3.03 2.90 -0.13
427 Yellow Rock Road 2.95 2.77 -0.18
427 Yellow Rock Road 2.94 2.77 -0.17
427 Yellow Rock Road 2.93 2.78 -0.15
Kalang
2 Hains Lane 10.69 9.12 -1.57
32 Hains Lane 10.17 9.02 -1.15
88 Hains Lane 9.79 8.77 -1.02
88 Hains Lane 9.24 8.53 -0.71
1046 South Arm Road 7.2 6.63 -0.57
915 South Bank Road 6.69 6.44 -0.25
869 South Arm Road 6.35 6.39 0.04
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
23
?? Martells Road 4.33 4.32 -0.01
504 South Arm Road 4.26 4.39 0.13
Newry Island Gauge 4.19 4.35 0.16
1053 Martells Road 4.24 4.40 0.16
5 Burrawing Parade 3.65 3.75 0.10
110 Newry Island Drive 3.58 3.55 -0.03
Pacific Hwy 3.56 3.37 -0.19
114 Newry Island Drive 3.54 3.55 0.01
219 Newry Island Drive 3.54 3.62 0.08
21 Newry Island Drive 3.53 3.50 -0.03
2 Marshall Place 3.53 3.46 -0.07
57 Newry Island Drive 3.51 3.53 0.02
Cnr Short Cut Road 3.36 3.46 0.10
Urunga Gauge 2.82 2.87 0.05
MHL Temporary Gauge Site 10 1.7 1.54 -0.16
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
24
7. DESIGN FLOOD BEHAVIOUR
7.1. Boundary Conditions
7.1.1. Design Inflows
As with the historical events the TUFLOW inflows for the 5 Year ARI, 10, 2, 1, 0.5, 0.2 and 0.05%
AEP and Probable Maximum Flood (PMF) design events were obtained from a number of time
varying flow hydrographs taken from the WBNM model (refer to Section 5 and Reference 3).
These inflow hydrographs were then applied to the calibrated TUFLOW hydraulic model to
produce design flood levels.
7.1.2. Tailwater Conditions
In addition to runoff from the catchment, the lower reaches of the estuary can also be influenced
by backwater effects resulting from elevated ocean levels. Hence, the height of the tide at the
time of the arrival of the peak runoff from the catchment can also have an influence on flood levels
in the lower reaches. However, these two distinct flooding mechanisms may or may not result
from the same storm. Consideration must therefore be given to accounting for the joint probability
of coincident flooding from both catchment runoff and backwater effects due to elevated ocean
levels.
A full joint probability analysis is beyond the scope of the present study. Traditionally, it is common
practice to estimate design flood levels in these situations using a ‘peak envelope’ approach that
adopts the highest of the predicted levels from the two mechanisms.
The 1991 Lower Bellinger Flood Study and the 2008 Newry Island Flood Study (draft) adopted a
1% AEP (100 year ARI) ocean tide boundary condition of 2.6mAHD.
Design tidal hydrographs in this study were based on the experience in nearby catchments,
previous studies in the area, and OEH guidelines. Reference 22 recommends the use of a 2.6
mAHD 1% AEP tide (including wave run up, wave setup etc) for a small untrained narrow and
shallow entrance. (ie. small creek or river with no seawalls). The Bellinger River Entrance in
contrast is large and a large amount of seawalls keeping the entrance open. For large entrances
(such as the Bellinger entrance) it suggests a site specific assessment be undertaken. The
recommended 2.6mAHD includes ocean components that would not be present for the Bellinger
entrance such as wave set up and runup. These effects are of a short term nature and due to the
large storage volume in the estuary and the long period of flooding. Wave setup would not persist
for long enough to effect flood level on the Bellinger and Kalang Rivers.
Based on the characteristics of the entrance of the Bellinger River discussed above WMAwater
recommend the use of 2.1mAHD for the 1% AEP ocean boundary. In order to support this
recommendation a sensitivity analysis was undertaken to determine the area which would be
impacted by a change in the 1% AEP ocean boundary (Figure 44). Therefore the model was run
with a small river event (10% AEP) and either a 2.1mAHD or 2.6mAHD ocean boundary. The
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
25
influence of these varying boundary conditions were mainly confined to the lower reaches (e.g.
downstream of Urunga). Therefore a shift from the currently adopted ocean boundary condition
(2.6mAHD and associated flood planning level) to 2.1mAHD would not affect any major areas of
development other than the Council Caravan Park.
While either 1% AEP boundary condition (2.1 or 2.6) could be adopted for current conditions this
will have longer term planning issues for Council with incorporation of sea level rise in the future.
A 1% AEP ocean level of 2.6mAHD plus 0.9m sea level rise will not be very defensible and would
classify large areas as undevelopable. It is therefore suggested that Council adopt a 2.1mAHD
1% AEP ocean level. Council could opt to adopt the 2.1mAHD ocean level plus 0.4m Sea level
rise which would result in a similar planning level to the current one.
Table 8: Ocean Boundary Peaks (mAHD)
Event Peak Ocean Level (mAHD)
5 Year ARI 1.45
10% AEP 1.64
2% AEP 2
1% AEP 2.1
In addition to the above it is not unreasonable to expect that the effects of a severe storm in terms
of ocean levels and runoff could be coincident for a catchment of this size. Hence to establish the
design flood levels in the present study, the relative phasing of the ocean levels was adjusted
such that the peak of the tidal hydrograph would approximately coincide with the peak of the
catchment runoff. For example a 1% AEP catchment event was run with a 0.9 variable tide. A 1%
AEP ocean event was run with a 10% AEP catchment event. These 2 scenarios were enveloped
to form the 1% AEP event.
For the 0.5%, 0.2% AEP, and 0.05% AEP and PMF events, the 1% AEP design tidal hydrograph
was adopted. All other events were enveloped with the corresponding AEP tide case.
Table 8 and Figure 43 Present the adopted ocean boundary conditions.
7.1.3. Entrance Conditions
The hydrosurvey represented a fairly accreted condition for Bellinger and Kalang Rivers entrance.
Advice from OEH officers is that the river was eroded significant in 2009 after the hydrosurvey
collection. Due to the extremely trained nature of the entrance, it is likely that this accreted material
would erode during a large flood event. As a result the amount of erosion was varied with the size
of the event. Table 9 summarise the amount of erosion applied to the different size design events
in the hydraulic model. The amount of erosion was determined based on the calibration events.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
26
Table 9: Entrance Erosion
Event Average Erosion Depth Compared to Hydrosurvey (m)
5 Year ARI, 10% AEP 0
2% AEP -2.6
1% AEP and rarer events -4.1
7.2. Design Event Results
Peak flood level profiles for the 5 Year ARI, 10, 2, 1, 0.5, 0.2 and 0.05 % AEP and Probable
Maximum Flood (PMF) design events are presented in Figure 22 to Figure 29. Peak velocities
within the study area for the design events are presented in Figure 30 to Figure 37. Table 10
documents design flood levels at key locations.
Table 10: Design Flood Levels at Key Locations
ID
Location Flood Level (mAHD)
5YR
ARI
10%
AEP
2%
AEP
1%
AEP
0.5%
AEP
0.2%
AEP
0.05%
AEP
PMF
1 Fernmount 4.65 5.49 7.18 7.83 8.32 8.97 9.90 12.78
2 U/S PacificHighway
Bellinger River 2.88 3.46 5.09 5.61 6.03 6.60 7.39 10.07
3 Mylestom 2.13 2.48 3.35 3.82 4.32 5.13 6.30 8.66
4 Confluence Bellinger and
Kalang River 1.81 2.00 2.05 2.17 2.94 4.05 5.44 7.50
5 D/s NewryIsland 1.99 2.32 3.01 3.45 4.01 4.87 6.12 8.49
6 U/S NewryIsland 2.15 2.56 3.50 3.90 4.34 5.08 6.26 8.75
7 U/S Brierfield Bridge 5.68 6.65 8.66 9.38 9.82 10.44 11.96 16.77
8 Confluence Picket Hill Ck 2.29 2.80 4.06 4.56 5.03 5.68 6.83 9.88
9 OppNorco 2.59 3.17 4.62 5.01 5.36 5.88 6.77 9.22
10 MHL Newry Island U/S
Gauge 2.18 2.62 3.58 3.99 4.41 5.14 6.31 8.89
11 MHL Urunga Gauge 1.98 2.30 2.89 3.29 3.87 4.77 6.03 8.36
12 MHL Repton Gauge 2.40 2.91 4.15 4.57 4.97 5.62 6.62 9.10
13 Bellingen Bridge 7.65 8.78 10.78 11.42 11.87 12.51 13.39 16.54
Table 11 compares estimates of the 1% AEP flood level at Kalang River, Bellingen Bridge and
Urunga from the current and previous studies. Differences between the 1991 Flood Study and the
current study are a result:
• The use of a two dimensional model (current study) compared to a one dimensional model
(1991 study),
• Improved IFD estimates in the current study, and
• Change in hydrologic model to one with more realistic parameters.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
27
Table 11: Comparison of 1% AEP Flood Level with Previous Studies
Study Kalang River (Just upstream of
Newry Island) (mAHD) Bellingen Bridge
(mAHD) Urunga
1991 Lower Bellinger Flood Study (PWD)
3.9 10.9 3.2
Upper Bellinger Flood Assessment (2006)
- 11.1 -
Newry Island Flood Study (2008)
3.6 - 3.2
RTA – 2010 4.11 - -
Current Study 3.99 11.42 3.29
7.3. Sensitivity Analysis
The model established for this study relies on a number of assumed parameters, the values of
which are considered to be the most appropriate for the study area. A range of sensitivity analysis
was undertaken on different key parameters in order to quantify potential variations corresponding
to different modelling assumptions.
7.3.1. Rainfall Sensitivity
The Review of Bellinger, Kalang and Nambucca Rivers Catchment Hydrology (Reference 3,
referred to herein as the Regional Study) investigates known hydrologic issues in the Bellinger,
Kalang and Nambucca River catchments. This area of the NSW north coast has presented a
range of challenges for a number of studies where problems have been encountered matching
rainfall runoff modelling with flood frequency results.
7.3.1.1. Approach
For the mid north coast region an assessment of the effect of the new BoM 2013 IFD’s on design
flood quantile estimates was undertaken for OEH (Reference 30). A summary of the analysis for
the Bellinger and Kalang Rivers is reproduced here. Comparisons were undertaken for the
following:
• Catchment average rainfall to a key location,
Design flow estimates compared to FFA, and
• Change in flood level.
7.3.1.2. Catchment Average Rainfall Comparisons
Catchment average rainfalls to a key point in each catchment (corresponding to the flow
comparison locations undertaken in Section 7.3.1.3) were extracted from the 1987 and 2013 IFD
grids (Table 12). The change in catchment average rainfall as a percentage was found to be less
than the resultant change in flow. All Catchment Average rainfalls are for the 48 hour duration.
For the catchments covered by the Regional Hydrology study the IFDs developed as part of the
Regional Hydrology study are also included in Table 12. These estimates are similar to the 2013
IFD.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
28
Table 12: Catchment Average Rainfall Comparison (mm)
EVENT
Thora Bellingen Kooroowi
1987 IFD
Regional Study
2013 IFD
1987 IFD
Regional Study
2013 IFD
1987 IFD
Regional Study
2013 IFD
20% AEP/ 5Y
ARI
387 324 300 372 341 313 381 317 325
10% AEP 459 397 371 440 416 385 453 385 396
5% AEP 551 - 442 529 - 457 546 - 466
2% AEP 680 571 540 652 596 556 674 549 560
1% AEP 784 651 619 752 678 634 778 624 632
Note:
• The 5 Y ARI and 20% AEP are not equal but presented together here for simplicity. The 1987 IFD and Regional
study values are 5 Y ARI values while the 2013 IFD is a 20% AEP estimate.
• A 20 Y ARI/ 5 % AEP estimate was not developed as part of the Regional Study
7.3.1.3. Design Flow Estimates Comparison
Design flood estimates were extracted from the previous hydrologic modelling (Reference 3)
For the Bellinger and Kalang Rivers design flow estimates were available using an IFD method
similar to the 2013 IFDs and the 1987 IFDs using the same parameters. Estimates were compared
at the key gauging sites of:
• Bellinger River @ Bellingen,
• Bellinger River @ Thora, and
• Kalang River @ Kooroowi.
The design parameters used for the previous modelling were applied to the 2013 IFD’s with no
changes to understand the change in flow estimate. Table 13 summaries the flow estimates.
At Thora, Bellingen and Kooroowi design flow estimates reduce by 20-35% for the 2013 IFDs
compared to the 1987 IFDs across the full range design events. In the Bellinger and Kalang
catchments this produces an estimate closer to the FFA estimates at the gauge locations. It is
possible in the Bellinger and Kalang valleys that small changes to the adopted model parameters
would result in similarly good fits to the FFA as those achieved in Reference 3.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
29
Table 13: FFA Flow Comparison (m3/s)
EVENT
Thora Bellingen Kooroowi
1987 IFD
Regional Study
2013 IFD
FFA 1987 IFD
Regional Study
2013 IFD
FFA 1987 IFD
Regional Study
2013 IFD
FFA
20%
AEP/
5Y ARI
1010 690 580 530 1340 1070 900 1170 470 320 340 270
10Y
ARI
10%
AEP
1380 1040 910 810 1850 1600 1390 1620 630 480 500 480
20Y
ARI
5%
AEP
1950 - 1390 - 2660 - 2100 2220 860 - 690 680
50Y
ARI
2%
AEP
2900 2290 2130 2170 4000 3520 3220 3370 1250 960 990 920
100Y
ARI
1%
AEP
4090 2960 2840 3020 5680 4570 4270 4590 1700 1200 1260 1060
Note:
• The 5 Y ARI and 20% AEP are not equal but presented together here for simplicity. The 1987 IFD and Regional
study values are 5 Y ARI values while the 2013 IFD is a 20% AEP estimate.
• A 20 Y ARI/ 5 % AEP estimate was not developed as part of the Regional Study
7.3.1.4. Conversion of Flows to Height - Bellingen
In order to assess the sensitivity of design flood levels to these potential changes in flow, flow
estimates at Bellingen were converted to levels using the stage-flow rating curve (Reference 3).
Note that the losses were the same for all cases. Both the Regional Study and the 2013 IFDs
produce lower flood levels than the 1987 IFD. Flood levels are up to 0.4m lower than those
currently adopted by Council (Table 5) although the change in flow from that adopted is generally
less than 10%. The 1% AEP level developed for the Regional Study is 0.2m higher than that
derived for the 2013 IFDs.
Note that the model parameters were not changed from those adopted in the Regional Study for
the 2013 IFD estimate and the Regional Study calibrated well to flood frequency. It is likely that
minor changes to parameters to fit the FFA would result in similar estimates for the Regional Study
and the 2013 IFDs. While there are significant changes in flood level between the cases presented
because the flood heights are anchored on flood frequency analysis the design flood levels would
only change marginally.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
30
Table 14: Changes in Design Flood Level – Bellingen (mAHD)
EVENT 1987 IFD Regional Study
(Adopted) 2013 IFD
20% AEP/ 5Y ARI 8.1 7.6 7.0
10Y ARI
10% AEP
8.9 8.6 8.2
20Y ARI
5% AEP
9.7 9.3 9.2
50Y ARI
2% AEP
10.7 10.4 10.1
100Y ARI
1% AEP
11.9 11.1 10.9
Note:
• The 5 Y ARI and 20% AEP are not equal but presented together here for simplicity. The 1987 IFD and Regional study values
are 5 Y ARI values while the 2013 IFD is a 20% AEP estimate.
7.3.1.5. Advice on Rainfall
For the Bellinger, Kalang and Nambucca catchments the 2013 IFDs are a significant change from
the 1987 IFDs. It is likely that flood frequency analysis can be matched without the use of
unorthodox parameters. Given the Regional Hydrology study used IFDs similar to the 2013 IFDs
there is no need to revise the flood studies to the 2013 IFDs.
7.3.2. Parameter Sensitivity
The following scenarios were considered to represent the envelope of likely parameter values:
• ± 0.5mm/hr change in loss rates in the WBNM hydrologic model,
• ± 20% change in the C storage routing parameter in the WBNM hydrologic model,
• ± 20% change in Manning’s “n” value, and
• Ocean Boundary Conditions (2.1mAHD and 2.6mAHD for the 1% AEP).
For the scenarios listed above the hydrologic/hydraulic models were run for the 1% AEP design
storm and the results are provided in Table 15.
Changes in the continuing losses resulted in a change in flood levels of ±0.1m. A ±20% change
in the storage routing parameter resulted in up to a 0.4m change in flood levels.
A 20% increase and decrease in Manning’s n value resulted in up to 0.4m change in flood levels.
All bridges with spans less than 6m and all culverts were blocked by 50% to determine sensitivity
to blockage. The impacts of blockage are localised to the structures and minimal. The model is
relatively insensitive to changes in parameter values.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
31
Table 15: Sensitivity Analyses
Location
1% AEP
Flood
Level
(mAHD)
Flood Level (mAHD)
+ Loss -Loss +20%
C
-20%
C
+20%
Mannings
-20%
Mannings
50%
Blockage
Fernmount 7.83 -0.07 0.06 -0.32 0.34 0.31 -0.31 0.00
U/S Pacific Highway
Bellinger River 5.61 -0.06 0.06 -0.23 0.26 0.21 -0.21 0.00
Mylestom 3.82 -0.07 0.07 -0.21 0.23 0.21 -0.22 0.00
Confluence Bellinger
and Kalang River 2.16 -0.10 0.11 -0.22 0.25 0.02 0.20 0.00
D/s Newry Island 3.45 -0.09 0.08 -0.21 0.24 0.16 -0.15 0.00
U/S Newry Island 3.90 -0.06 0.06 -0.16 0.17 0.16 -0.17 0.00
U/S Brierfield Bridge 9.38 -0.09 0.04 -0.35 0.31 0.42 -0.48 0.00
Confluence Picket Hill
Ck 4.57 -0.07 0.07 -0.20 0.20 0.27 -0.32 0.01
Opposite Norco 5.01 -0.04 0.05 -0.17 0.20 0.16 -0.15 0.00
MHL Newry Island U/S
Gauge 3.99 -0.07 0.06 -0.16 0.17 0.18 -0.20 -0.01
MHL Urunga Gauge 3.30 -0.10 0.08 -0.22 0.25 0.16 -0.17 0.00
MHL Repton Gauge 4.58 -0.07 0.06 -0.20 0.21 0.19 -0.21 0.00
Bellingen Bridge 11.39 -0.03 0.06 -0.32 0.33 0.30 -0.22 0.00
7.4. Climate Change
The 2005 Floodplain Development Manual (Reference 211) requires that Flood Studies and
Floodplain Risk Management Studies consider the impacts of climate change (sea level rise and
rainfall increase) on flood behaviour. The following climate change scenarios (rainfall by the year
2070) are considered in this climate change assessment:
• Increase in peak rainfall and storm volume:
- low level rainfall increase = 10%,
- medium level rainfall increase = 20%,
- high level rainfall increase = 30%.
• Sea level rise:
- a 0.4m increase in level by year 2050
- a 0.9m increase in level by year 2100
A high level rainfall increase of up to 30% is recommended for consideration due to the
uncertainties associated with this aspect of climate change. It is understood that work currently
being undertaken by Engineers Australia, CSIRO and the Bureau of Meteorology as part of the
revision of Australian Rainfall and Runoff which will provide better direction on the possible
impacts of climate change on rainfall.
A 10% increase in rainfall results in up to a 0.55m increase in flood levels with an increase of
approximately 0.3m at most locations. A 30% increase in rainfall increases flood levels for a 1%
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
32
AEP event by almost a metre. A 0.4m and 0.9m sea level rise result in an increase in flood levels
in the lower to mid reaches of the Bellinger and Kalang rivers. A 0.4m and 0.9m increase in sea
levels would result in a 0.36m and 0.85m increase in 1% AEP flood levels at the confluence of the
Bellinger and Kalang Rivers. Table 16 summarises the impact of climate change on the 1% AEP
flood levels. Table 16 and Figure 38 to Figure 42 present the climate change peak flood levels
and depths.
Table 16: Climate Change Results
Location
1% AEP
Flood Level
(mAHD)
Change in Flood Level (m)
10% Rainfall
Increase
20% Rainfall
Increase
30% Rainfall
Increase
0.4m Sea
Level
Rise
0.9m Sea
Level
Rise
Fernmount 7.83 0.35 0.67 0.99 0.00 0.00
U/S PacificHighway
Bellinger River
5.61 0.30 0.58 0.87 0.00 0.01
Mylestom 3.82 0.35 0.71 1.11 0.01 0.04
Confluence Bellinger
and Kalang River
2.16 0.55 1.06 1.63 0.36 0.86
D/s NewryIsland 3.45 0.38 0.78 1.21 0.02 0.09
U/S NewryIsland 3.90 0.30 0.62 0.99 0.01 0.04
U/S Brierfield Bridge 9.38 0.34 0.65 0.96 0.00 0.00
Confluence Picket Hill
Ck
4.57 0.29 0.61 0.94 0.01 0.04
OppNorco 5.01 0.24 0.48 0.74 0.00 0.01
MHL Newry Island
U/S Gauge
3.99 0.29 0.60 0.96 0.01 0.04
MHL Urunga Gauge 3.30 0.38 0.80 1.25 0.03 0.10
MHL Repton Gauge 4.58 0.27 0.55 0.88 0.00 0.01
Bellingen Bridge 11.39 0.35 0.66 0.97 0.00 0.00
7.5. Hydraulic and Hazard Categories
For the purposes of floodplain risk management in NSW floodplains are divided into one of three
Hydraulic categories (floodway, flood storage and flood fringe) and two Hazard categories (low or
high). These terms are defined in Reference 21. Further details of this process are provided in
the NSW Governments Floodplain Development Manual (2005, Appendix L) (Reference 21).
The provisional hazard categorisation was determined quantitatively based on available hydraulic
and survey information. High Hazard was assumed where either the peak flood depth is 1 m or
greater, or the velocity depth product (peak velocity x the peak depth) is 1 or greater. Low hazard
is where, should it be necessary, a truck could evacuate people and their possessions; able-
bodied adults would have little difficulty in wading to safety. Figure 47 and Figure 48 present
hydraulic hazard for the 1% AEP and PMF events.
It is considered that the hydraulic hazard does not need to be refined to reflect other factors that
influence hazard (such as warning time, flood readiness, rate of rise, duration of flooding,
evacuation problems, effective flood access and the type of development).
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
33
Hydraulic categories describe the flood behaviour by categorising areas depending on their
function during the flood event, specifically, whether they transmit large quantities of water
(floodway), store a significant volume of water (flood storage) or do not play a significant role in
either storing or conveying water (flood fringe). As with categories of hazard, hydraulic categories
play an important role in informing floodplain risk management in an area. Although the three
categories of hydraulic function are described in the Floodplain Development Manual (Reference
21), their definitions are largely qualitative and the manual does not prescribe a method to
determine each area. The Manual gives one indication of how to quantitatively differentiate
floodway and flood storage, when it states that flood storage areas, when completely filled with
solid material, will not raise peak flood levels by “more than 0.1 m and/or would cause the peak
discharge anywhere downstream to increase by more than 10%”.
The use of velocity and depth to delineate areas of different hydraulic category follows the
approach proposed by Howells et al. in their 2004 paper (Reference 28). At each grid cell, the
peak velocity (v), peak depth (d) and their product (v*d) is considered, and the cell is categorised
based on the following criteria.
1. If both v*d > 0.25 and v > 0.25, then ‘floodway’
2. If both v > 1 and d > 0.15, then ‘floodway’
3. If neither of the above apply and d > 0.7, then ‘flood storage’
4. Otherwise, ‘flood fringe’.
The areas were expanded by first changing any ‘islands’ of non-floodway to floodway, that is,
areas that are surrounded by floodway. Then flood runners were manually added to the floodway
area, and their width was increased until they were sufficiently wide.
Lowering the thresholds of v, d and v*d may also be used to select more area; however, this was
not possible for the study area, as a number of features on the floodplain, including roads and
irrigation canals, obstructed small flood runners, and so considering v, d or v*d does not produce
any unbroken flood runner or flow path outside the high flow zone.
Hydraulic categorisation is presented in Figure 45 and Figure 46 for the 1% AEP and PMF events.
The majority of the Bellinger River floodplain and Newry Island is considered floodway.
Managing the floodplain: a guide to best practice in flood risk management in Australia (Reference
29) provides revised hazard classifications which add clarity to the hazard categories and what
they mean in practice. The classification is divided into 6 categories which indicate the restrictions
on people, buildings and vehicles:
• H1 - No constraints,
• H2 – Unsafe for small vehicles,
• H3 - Unsafe for all vehicles, children and the elderly,
• H4 - Unsafe for all people and all vehicles,
• H5 - Unsafe for all people and all vehicles. Buildings require special engineering design
and construction, and
• H6 - Unsafe for people or vehicles. All buildings types considered vulnerable to failure.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
34
Figure 47 and Figure 48 present the alternate hazard classifications. Under this classification for
a 1% AEP event much of the floodplain between Bellingen and Urunga is considered unsafe for
all people and all vehicles with buildings require special engineering design and construction. With
large areas upstream of the Pacific Highway crossing of the Bellinger River considered
unconditionally dangerous. In a PMF only small fringe areas of both the Bellinger and Kalang
Rivers are not classified as unconditionally dangerous.
7.6. Flood Planning Area
The flood planning level (FPL) is used to define land subject to flood related development controls
and is generally adopted as the minimum level to which floor levels in the flood affected areas
must be built. The FPL includes a freeboard above the design flood level. It is common practice
to set minimum floor levels for residential buildings, garages, driveways and even commercial
floors as this reduces the frequency and extent of flood damages. Freeboards provide reasonable
certainty that the reduced level of risk exposure selected (by deciding upon a particular event to
provide flood protection for) is actually provided.
The Flood Planning Area is defined as the 1% AEP event plus a freeboard. In the Bellinger and
Kalang Rivers the use of a 0.5m freeboard is considered appropriate. Figure 49 shows the
proposed Flood Planning Area.
7.7. Impacts of Sea Level Rise on Flood Planning Area
The impacts of a 0.4m increase in level by year 2050 and a 0.9m increase in level by year 2100
on the 1% AEP planning level was determined. This includes a 0.5m freeboard. Figure 50 shows
the proposed Flood Planning Area with 2050 Sea Level Rise. Figure 51 shows the proposed Flood
Planning Area with 2100 Sea Level Rise. Sea level rise is unlikely to result in any significant
change in flood planning area as the floodplain is already inundated to the steep foothills. The
majority of the change in flood planning area occurs in the Urunga Lagoon area and is due to
roads being overtopped where minor culverts are not included in the model (Figure 52). There is
no infrastructure, public land and property affected by the increase in planning area.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
35
8. FLOOD DAMAGES
8.1.1. Background
A flood damages assessment was also undertaken as part of this Flood Study. The cost of flood
damages and the extent of the disruption to the community depends upon many factors including:
• the magnitude (depth, velocity and duration) of the flood,
• land usage and susceptibility to damage,
• awareness of the community to flooding,
• effective warning time,
• the availability of an evacuation plan or damage minimisation program,
• physical factors such as erosion of the river bank, flood borne debris, sedimentation.
Flood damages can be defined as being “tangible” or “intangible”. Tangible damages are those
for which a monetary value can be assigned, in contrast to intangible damages, which cannot
easily be attributed a monetary value (stress, injury, loss to life, etc.).
Some historic floor level survey was available from the Floodplain Risk Management Study
(Reference 15). Floor level survey was conducted for the remaining properties within the PMF
extent. Each of the 984 properties was “assigned” a GIS tag which was then used to obtain a flood
level for the full range of design flood events. This level was then used with the appropriate
formulae and damages curve to determine the tangible property damages for each event.
There are a number of issues with “assigning” a single flood level to a property to estimate flood
damages. These include:
• no account is taken of the actual openings where floodwaters could enter a building relative
to the applicable flood gradient. Thus a rear door may allow the water to enter rather than
the front door,
• the level “assigned” is usually taken as the flood level midway across the property. For
areas with low flood gradients this is appropriate, however in “long” properties and factories
or areas with strong flood gradients this may not necessarily be appropriate.
• the “assigned” flood level is only relevant for estimating flood damages and should not be
used for development control purposes. These latter levels must be obtained from
interpolation of the flood contour maps.
8.1.2. Assessment of Tangible Flood Damages
Quantification of tangible flood damages is generally based upon data derived from post-flood
damage surveys obtained following historical flood events and is industry practice in NSW. Floods
by their nature are unpredictable and conditions variable. It is therefore unlikely that a self-
assessment survey would have predicted the scale or extent of the damages which occurred in
Nyngan in 1990 or North Wollongong in August 1998. For this reason it was decided to use the
post-flood damage approach in assessing flood damages for the study area.
The most comprehensive damage surveys include those carried out for Sydney (Georges River -
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
36
1986), Nyngan (1990), Inverell (1991) and Katherine (1998). Some of the problems in applying
data from these studies to other areas can be summarised as follows:
• varying building construction methods, e.g. slab on ground, pier, brick, timber,
• different average age of the buildings in the area,
• the quality of buildings may differ greatly,
• inflation must be taken into account,
• different fixtures within buildings, e.g. air-conditioning units, machinery, etc.,
• change in internal fit out of buildings over the years or in different areas, e.g.
more carpets and less linoleum or change in kitchen/bathroom cupboard
material,
• external (yard) damages can vary greatly. For example in some areas vehicles
can be readily moved whilst in other areas it is not possible,
• different approaches in assessing flood damages. Are the damages assessed
on a “replacement” or a “repair and reinstate where possible” basis? Some
surveys include structural damage within internal damage whilst others do not,
• varying warning times between communities means that the potential versus
actual damage ratio may change significantly,
• variations in flood awareness of the community.
8.1.3. Tangible Damages – Residential Properties
Tangible direct damages are generally calculated under the following components:
• Internal,
• Structural,
• External.
Tangible indirect damages can be subdivided into the following groups:
• accommodation and living expenses,
• loss of income,
• clean up activities.
Damages may be calculated as either estimated actual damages or estimated potential damages.
If potential damages are calculated an Actual/Potential (A/P) ratio is assigned based upon (as well
as other factors) the likely flood awareness of the community and the available warning time.
The flood awareness of the majority of the Bellinger and Kalang Rivers community is likely to be
high and the available flood warning time in the order of 12hrs. Based upon the limited data
available it is considered that the A/P ratio for the communities within the Bellinger and Kalang
Rivers would most likely be similar to that applicable at Nyngan and Inverell.
The approach adopted for estimating flood damages was therefore based on that derived from
the Nyngan and Inverell flood damages surveys with updating for inflation and the different type
of buildings in the catchment.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
37
8.1.3.1. Direct Internal Damages
Internal damages are based upon the following formulae recommended by OEH (Reference 21).
Allowing for inflation and differences in the types of buildings and their contents, a contents value
of $60,000 was adopted for this study for houses. Structural damages were not included in the
above figures.
8.1.3.2. Direct Structural Damages
Structural damages were assumed follow the relationship adopted in Reference 21 for houses. In
floods larger than the 1% AEP event there is the possibility that some buildings may collapse or
have to be destroyed. The cost of these damages have not been included in the analysis.
8.1.3.3. Direct External Damages
External damages (laundry/garage/yard/vehicle) were assumed to $6700 for houses as
recommended by Reference 21. This assumes that the majority of vehicles are moved by
residents.
8.1.3.4. Indirect Damages
Indirect damages were assumed to be a linear relationship from $0 at 0 m above floor level to a
maximum of $4,000 at 0.5 m.
8.1.4. Results
The number of buildings inundated above floor level along with the estimated flood damages are
summarised for the range of design flood events in Table 18. Table 17 indicates the number of
yards inundated. Due to the frequent flooding of low lying areas houses at low levels would have
been raised. The majority of properties are located above the 100yr ARI level. A significant
increase in the number of flooded properties occurs between the 100 year ARI and 200 year ARI.
Table 17: Affected Properties
Event
RESIDENTIAL COMMERCIAL TOTAL
No.
Properties
Affected
Flooded
Above Floor
Level
No.
Properties
Affected
Flooded
Above Floor
Level
No.
Properties
Affected
Flooded
Above Floor
Level
20% 36 8 1 0 37 8
10% 73 17 4 2 77 19
2% 259 98 17 14 276 112
1% 405 187 20 18 425 205
0.50% 512 367 21 21 533 388
0.20% 644 534 23 23 667 557
0.05% 830 775 30 29 860 804
PMF 925 911 63 54 988 965
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
38
Table 18: Estimated Flood Damages
Event No.
Properties Affected
No. Flooded Above
Floor Level Total Damages for Event
Ave. Damage Per Flood Affected Property
20% 37 8 $ 416,600 $ 11,300
10% 77 19 $ 1,051,000 $ 13,600
2% 276 112 $ 7,526,400 $ 27,300
1% 425 205 $ 14,220,500 $ 33,500
0.5% 533 388 $ 25,817,800 $ 48,400
0.2% 667 557 $ 48,705,400 $ 73,000
0.05% 860 804 $ 86,301,100 $ 100,400
PMF 988 965 $ 133,037,100 $ 134,700
Average Annual Damages (AAD) $ 1,058,700 $ 1,100
Note: * Excludes all damages to public assets. Includes external damages that may or may not occur with building floor
inundation.
The standard way of expressing flood damages is in terms of Average Annual Damages (AAD).
AAD represents the equivalent average damages that would be experienced by the community
on an annual basis, by taking into account the probability of a flood occurrence. By this means
the smaller floods, which occur more frequently, are given a greater weighting than the rare
catastrophic floods. The Average Annual Damages (AAD) based on the above values is
estimated to be $1,058,700. Most dwellings are located above the 1% AEP flood level.
Figure 61 to Figure 65 show the event at which the ground is first inundated, while Figure 66 to
Figure 70 show the event at which the floor level of a property is first inundated. Flood levels first
enter the grounds of properties in Bellingen in a 10% AEP event, Newry Island, Mylestom, Urunga,
Raleigh in a 5 yr ARI event. Above floor flooding in Bellingen occurs at the golf course and Show
grounds in a 5 yr ARI event. Flooding in a 2% AEP event flooding of residential buildings in
Bellingen above floor level occurs. Flooding above flood level occurs in Mylestom, Urunga,
Raleigh in a 5 yr ARI event. Houses are flooded in a 5 Year ARI event include a group of holiday
rentals and houses on Yellow Rock Road downstream of Tuckers Island. These properties are
located in a low flood island.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
39
9. EMERGENCY RESPONSE
9.1. Preliminary Flood Emergency Response Planning Classification of
Communities
The Floodplain Development Manual (NSW State Government, 2005) requires flood studies to
address the management of continuing flood risk to both existing and future development areas.
As continuing flood risk varies across the floodplain so does the type and scale of emergency
response problem and therefore the information necessary for effective Emergency Response
Planning (ERP). Classification provides an indication of the vulnerability of the community in flood
emergency response and identifies the type and scale of information needed by the State
Emergency Services (SES) to assist in emergency response planning (ERP).
Criteria for determining flood ERP classifications and an indication of the emergency response
required for these classifications are provided in the Floodplain Risk Management Guideline, 2007
(Flood Emergency Response Planning: Classification of Communities). Table 19 summarises the
response required for areas of different classification. However, these may vary depending on
local flood characteristics and resultant flood behaviour, i.e. in flash flooding or overland flood
areas.
Table 19: Response Required for Different Flood ERP Classifications
Classification Response Required
Resupply Rescue/Medivac Evacuation
High Flood Island Yes Possibly Possibly
Low Flood Island No Yes Yes
Area with Rising Road Access No Possibly Yes
Area with Overland Escape
Routes
No Possibly Yes
Low Trapped Perimeter No Yes Yes
High Trapped Perimeter Yes Possibly Possibly
Indirectly Affected Areas Possibly Possibly Possibly
In undertaking this assessment for the Bellinger and Kalang Rivers, all roads have been
considered trafficable in a flood event, both paved and unsealed. The suitability for use of
particularly unsealed roads should be reviewed with the SES. Figure 53 presents the ERP
classifications.
Most of the main population centres of Bellingen and Urunga are classified as Rising Road Access
as the properties are inundated but flood free access roads provide a retreat to flood free land.
Small parts of North Bellingen, Newry Island and Urunga are classified as High Flood Islands.
Newry Island is classified as a Low Flood Island as practical access is cut and they are inundated
during an event.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
40
9.2. Evacuation Routes and Length of Inundation
Time of inundation in a 1% AEP event shown on Figure 54 for all grid cells within the model. The
majority of areas are inundated for between 10 and 40 hrs. Some low lying areas are inundated
for almost 3 days. Some extremely low lying areas may experience inundation for longer.
Table 20 provides the levels of low points in key evacuation routes within the catchment and the
flood levels at these locations for a range of events. These low points were surveyed as part of
the study or levels were derived from the ALS. This gives an indication of during what size event
these roads are likely to be first cut. Figure 55 and Figure 56 depict graphically when the roads
are first cut. Figure 57 to Figure 60 are event hydrographs at selected low points.
The length of time in a 1% AEP event till a low point in the road is cut and how long it can be
expected to be cut is presented in Table 21. Table 22 shows road low points by SES Flood
Management Zone and what event access via that road is cut, event in which evacuation to that
area is cut and the Emergency Response classification for that area.
Table 20: Design flood levels at low points in roads.
ID
Road Name Level of
low
point in
road
(mAHD)
Design Flood Levels at Low Point (mAHD)
5Y
R
ARI
10%
AEP
2%
AEP
1%
AEP
0.5%
AEP
0.2%
AEP
0.05
%
AEP
PMF
1 Island Pl Newry 2.185 3.99 3.50 4.15 4.86 6.15 8.45
2 The Grove Newry 4.125 4.88 6.11 8.47
3 Marshall Place Newry 3.003 3.53 4.21 4.86 6.16 8.45
4 Newry Island Dr 1.568
2.3
6 2.39 3.24 3.70 4.19 4.99 6.19 8.63
5 Hollis Cl Newry 6.579 8.47
6 Marina Cres 1.699 2.36 3.59 3.48 4.97 4.86 6.14 8.44
7 Yellow Rock Rd 2.884 3.34 3.93 4.84 6.96 8.39
8 Old Punt Rd 4.566 4.85 6.12 8.47
9 Bellingen St 1.867
1.9
8 2.30 2.86 3.26 3.84 4.74 6.76 8.31
10 Allison St 2.7 3.00 3.44 4.30 4.87 6.11 8.49
11 Panorama Parade 2.801 3.00 3.44 4.30 4.87 6.11 8.49
12 Melaleuca Pl 2.95 3.61 4.12 4.94 6.13 8.52
13 Rosedale Dr 2.799 3.66 4.16 4.96 6.17 8.55
14 Tambar Pl 3.408 4.16 4.96 6.17 8.55
15 Myall Ct 2.881 3.65 4.15 4.95 6.17 8.56
16 Pacific Highway 2.876 3.53 4.15 4.86 6.14 8.44
17 South Arm Rd 9.849
18 Riverside Drive 6.307 8.46
19 Crescent Cl 1.82
1.9
8 2.36 2.94 3.38 3.95 4.83 6.79 8.43
20 Ranger St 12.41
21 Gossip Rd 3.611 3.63 4.43 4.51 5.27 6.44 9.70
22 Kalang Br US 2.704 3.67 4.23 4.44 5.17 6.34 9.15
23 Kalang Br DS 2.028 2.62 3.57 3.98 4.40 5.12 6.29 8.86
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
41
24 Waterfall way 16.3343
25 Waterfall way Lowpt 2.949 3.26 5.51 6.93 6.56 7.15 7.95 1.48
26 Mylestom Dr 2.147
2.1
9 2.59 3.58 3.96 4.45 5.24 6.37 8.76
27 Bellingen br 4
7.5
6 8.65 1.52 11.14 11.57 12.19 13.28 16.77
28 Waterfall way US 4.9 5.52 7.36 8.21 8.54 9.24 1.28 13.35
29 South Arm us 1.929
2.3
6 2.96 4.58 5.12 5.63 6.26 7.38 1.30
Table 21: Inundation times of road low points
ID
Road Name Level of low point in road
(mAHD)
Hours before
inundated in 1%
AEP Event
Total time of
inundation (hrs)*
1 Island Pl Newry 2.185 24.75 45.5
2 The Grove Newry 4.125 0
3 Marshall Place Newry 3.003 26 7
4 Newry Island Dr 1.568 20 24.25
5 Hollis Cl Newry 6.579 0
6 Marina Cres 1.699 22.5 17.75
7 Yellow Rock Rd 2.884 27.75 4.25
8 Old Punt Rd 4.566 0
9 Bellingen St 1.867 23.5 16
10 Allison St 2.7 25.5 8.75
11 Panorama Parade 2.801 25.75 8
12 Melaleuca Pl 2.95 28.25 1.5
13 Rosedale Dr 2.799 26 44
14 Tambar Pl 3.408 0
15 Myall Ct 2.881 26.25 43.75
16 Pacific Highway 2.876 26.25 43.75
17 South Arm Rd 9.849 0
18 Riverside Drive 6.307 0
19 Crescent Cl 1.82 22.75 17.5
20 Ranger St 12.41 0
21 Gossip Rd 3.611 23.5 9
22 Kalang Br US 2.704 20.75 19
23 Kalang Br DS 2.028 18.5 26
24 Waterfall way 16.3343 0
25 Waterfall way Lowpt 2.949 19.5 50.75
26 Mylestom Dr 2.147 19.75 24
27 Bellingen br 4 10.75 38.5
28 Waterfall way US 4.9 17.5 22.5
29 South Arm us 1.929 17 29.25
*Inundation is defined as a depth of greater than 0.1m
Table 22: Event when access and evacuation is cut
ID
SES Flood
Management
Zone
When Access Road is Cut When Evacuation is cut ERP
1 Newry Island 2% AEP 2% AEP Low Flood Island
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
42
(Residential)
2 Newry Island
(Residential)
0.2% AEP 2% AEP Low Flood Island
3 Newry Island
(Residential)
1% AEP 2% AEP Low Flood Island
4 Newry Island
(Rural)
5YR ARI 5YR ARI Low Flood Island
5 Newry Island
(Residential)
PMF 2% AEP Low Flood Island
6 Yellow Rock 10% AEP 10% AEP Low Flood Island
7 Yellow Rock 1% AEP 1% AEP Rising Road
Access
8
Yellow Rock 0.2% AEP 0.2% AEP Overland Refuge
Area on High
Flood Island
9 Urunga 5YR ARI 5YR ARI Rising Road
Access
10 Urunga 2% AEP 2% AEP Rising Road
Access
11 Urunga 2% AEP 2% AEP Rising Road
Access
12 Urunga 1% AEP 1% AEP Rising Road
Access
13 Urunga 1% AEP 1% AEP Rising Road
Access
14 Urunga 0.5% AEP 0.5% AEP Rising Road
Access
15 Urunga 1% AEP 1% AEP Rising Road
Access
16 Kalang Rural 1% AEP 1% AEP Low Flood Island
17 Kalang Rural Not cut 2% AEP Not cut
18
Kalang Rural PMF 2% AEP Overland Refuge
Area on High
Flood Island
19 Urunga 5YR ARI 5YR ARI Rising Road
Access
20 Urunga Not cut 0.05% AEP Not cut
21
Kalang Rural 2% AEP 2% AEP Overland Refuge
Area on High
Flood Island
22
Kalang Rural 2% AEP 2% AEP Overland Refuge
Area on High
Flood Island
23
Kalang Rural 10% AEP 10% AEP Overland Refuge
Area on High
Flood Island
24 Bellingen Rural Not cut 10% AEP Not cut
25 Bellingen Rural 10% AEP 10% AEP Not Classified
26 Mylestom 5YR ARI 5YR ARI Low Trapped
Perimeter
27 Bellingen 5YR ARI 5YR ARI Rising Road
Access
28 Bellingen Rural 10% AEP 10% AEP Not Classified
29 Kalang Rural 5YR ARI 2% AEP Not Classified
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
43
9.3. Correlation between Newry Island U/S Gauge and Newry Island Bridge
Diagram 1 depicts the correlation between the Newry Island U/S gauge and Newry Island bridge
based on the hydraulic model. The hydraulic model results for the historical events are also
plotted. No historical observed levels exist at the site of the Newry Island Bridge. As a priority flood
levels in future event should be collected at the bridge.
Diagram 1: Correlation between Flood levels at Newry Island Bridge and Newry Island U/S gauge
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
44
10. TIDAL CALIBRATION
10.1. Verification to a Tide
In order to assess if the model was suitable for assessing tidal planes extent the model was
verified against a period of tidal record with no rainfall or flood events. The period chosen was
March 2008. A reasonably good fit to the tidal record was found (Figure 71 to Figure 73). The
timing of the peaks is slightly early with the second peak within 0.1m. Figure 74 depicts the extent
of the peak water level during this event.
10.2. High High Water Solstice Spring
Manly Hydraulics Laboratory prepared the NSW Tidal Planes Analysis: 1990-2010 Harmonic
Analysis report on behalf of the NSW Office of Environment and Heritage. It was released in
October 2012 and was based on data from 188 tidal monitoring stations from the 1st July 1990 to
the 30th June 2010. The closest long term ocean site is Coffs Harbour. The High High Water
Solstice Spring (HHWSS) (1.077mAHD) was used to determine the tidal inundation for a regular
tidal event. The HHWSS was also modelled in the hydraulic model assuming a 0.4 and 0.9m sea
level rise. Figure 75 depicts the tidal extent for current and future climates.
Under current climate conditions the tidal extent is limited to within the river banks with some
overbank flooding between Back Creek and the Bellinger river, backwater areas upstream of the
Pacific Highway near Short Cut road and a small area near the new Pacific Highway bridge over
the Kalang River. With climate change regular tidal inundation will extend and public infrastructure
is likely to be affected. Inundation will occur around the low lying areas near Urunga, Back Creek
and Boggy Creek and Raleigh. Infrastructure likely to be affected includes Urunga Golf Course,
Crescent Close and Atherton Drive Urunga, Yellow Rock Road, Hebbard Drive, Marina Crescent,
Newry Island Drive and Island Place, Newry Island.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
45
11. CONCLUSIONS
A detailed hydraulic model (TUFLOW) has been developed to quantify the flood behaviour of the
Lower Bellinger and Kalang Rivers, making best use of the data currently available.
This model has been used to reproduce the historical flood behaviour from events in 1974, 1977,
2001 and 2009. The TUFLOW model has been used to define flood behaviour for a range of
design events (5 Year ARI, 10, 2, 1, 0.5, 0.2 and 0.05 % AEP and Probable Maximum Flood).
Community consultation and hazard classification were undertaken. The model developed for the
current study is suitable for further floodplain planning and use in setting planning levels within the
study area.
It is recommended that data collection in future events target the Kalang River above Newry
Island.
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
46
12. REFERENCES
1. Pilgrim DH (Editor in Chief)
Australian Rainfall and Runoff – A Guide to Flood Estimation
Institution of Engineers, Australia, 1987.
2. WBM BMT
Tuflow User Manual – GIS Based 2D/1D Hydrodynamic Modelling
2010
3. WMAwater
Review of the Bellinger, Kalang and Nambucca River Catchments Hydrology
July 2011
4. Boyd M, Rigby T, VanDrie R, and Schymitzek I
WBNM User Guide
2007
5. RTA
Warrell Creek to Urunga Upgrading the Pacific Highway Environmental
Assessment - Volume 1 Environmental Assessment
January 2010
6. Cameron McNamara
New South Wales Coastal Rivers Floodplain Management Studies Bellinger
Valley
December 1980
7. Outline Planning Consultants
Proposed Industrial Area, Urunga NSW
May 1984
8. PWD
Bellinger River May 1980 Flood Report
1981
9. PWD
Bellinger River Flood History 1843-1979
1980
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
47
10. PWD
Lower Bellinger River Flood Study
1991
11. Cameron McNamara
Lower Bellinger River Flood Study, Location of Flood Marks Engineering Survey
Brief
1991
12. PWD
Lower Bellinger River Flood Study Compendium of Data
1991
13. Bruce Fidge and Associates
Bellinger and Kalang River’s Floods of February and March 2001
2003
14. Bellingen Shire Council
Floodplain Risk Management Study Stage 2- An Assessment of Floodplain
Management Options and Strategies
April 2002
15. Bellingen Shire Council
Upper Kalang River Flood Assessment,
December 2006
16. DeGroot and Benson Pty Ltd
South Arm Road Flood Study (Final)
June 2000
17. Bellingen Shire Council
Upper Bellinger River Flood Assessment
2006
18. WMAwater
Newry Island Flood Study Draft
2008
19. WMAwater
Kalang River 2009 Flood Event
2011
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
48
20. Enginuity Design
Bellinger and Kalang Rivers Flood Event of 31 March 2009 Collection and
Collation of Flood Data
2010
21. NSW Government
Floodplain Development Manual: The management of flood liable land
April 2005
22. Department of Infrastructure, Planning and Natural Resources
Floodplain Management Guideline No 5 – Ocean Boundary Conditions
23. NSW Government
Draft Sea Level Rise Policy Statement
2009
24. WMAwater
Warrell Creek to Urunga – Pacific Highway Upgrade Modelling
2012
25. Nathan, RJ and Weinmann, E,
Estimation of Large to Extreme Floods, Book VI in Australian Rainfall and Runoff
- A Guide to Flood Estimation,
The Institution of Engineers, Australia, Barton, ACT, 1999.
26. MHL
Bellinger and Kalang Rivers Data Collection – July 2008 to September 2009 (MHL Report Number 1951) NSW Public Works, 2010
27. WMAwater
Hydraulic Modelling Report - Bellinger and Kalang Rivers
2012
28. Howells L, McLuckie D., Collings G., Lawson N.
Defining the Floodway – Can One Size Fit All?
2004
29. Australian Government
Managing the floodplain: a guide to best practice in flood risk management in
Australia
Lower Bellinger and Kalang River Flood Study
WMAwater 111036-04:Lower_Bellinger_Kalang_FS_final_160408:11 April 2016
49
2013
30. WMAwater
Advice on the use of the 2013 Design Rainfall for NSW
2014
Lower Bellinger and Kalang River Flood Study
WMAwater
111036-04 :Lower_Bellinger_Kalang_FS_final_160408:11 April 2016 A1
APPENDIX A: GLOSSARY
Taken from the Floodplain Development Manual (April 2005 edition)
acid sulfate soils
Are sediments which contain sulfidic mineral pyrite which may become extremely
acid following disturbance or drainage as sulfur compounds react when exposed to
oxygen to form sulfuric acid. More detailed explanation and definition can be found
in the NSW Government Acid Sulfate Soil Manual published by Acid Sulfate Soil
Management Advisory Committee.
Annual Exceedance
Probability (AEP)
The chance of a flood of a given or larger size occurring in any one year, usually
expressed as a percentage. For example, if a peak flood discharge of 500 m3/s
has an AEP of 5%, it means that there is a 5% chance (that is one-in-20 chance)
of a 500 m3/s or larger event occurring in any one year (see ARI).
Australian Height Datum
(AHD)
A common national surface level datum approximately corresponding to mean sea
level.
Average Annual Damage
(AAD)
Depending on its size (or severity), each flood will cause a different amount of flood
damage to a flood prone area. AAD is the average damage per year that would
occur in a nominated development situation from flooding over a very long period
of time.
Average Recurrence
Interval (ARI)
The long term average number of years between the occurrence of a flood as big
as, or larger than, the selected event. For example, floods with a discharge as
great as, or greater than, the 20 year ARI flood event will occur on average once
every 20 years. ARI is another way of expressing the likelihood of occurrence of a
flood event.
caravan and moveable
home parks
Caravans and moveable dwellings are being increasingly used for long-term and
permanent accommodation purposes. Standards relating to their siting, design,
construction and management can be found in the Regulations under the LG Act.
catchment
The land area draining through the main stream, as well as tributary streams, to a
particular site. It always relates to an area above a specific location.
consent authority
The Council, government agency or person having the function to determine a
development application for land use under the EP&A Act. The consent authority
is most often the Council, however legislation or an EPI may specify a Minister or
public authority (other than a Council), or the Director General of DIPNR, as having
the function to determine an application.
development
Is defined in Part 4 of the Environmental Planning and Assessment Act (EP&A Act).
infill development: refers to the development of vacant blocks of land that are
generally surrounded by developed properties and is permissible under the current
zoning of the land. Conditions such as minimum floor levels may be imposed on
infill development.
new development: refers to development of a completely different nature to that
associated with the former land use. For example, the urban subdivision of an area
previously used for rural purposes. New developments involve rezoning and
typically require major extensions of existing urban services, such as roads, water
supply, sewerage and electric power.
Lower Bellinger and Kalang River Flood Study
WMAwater
111036-04 :Lower_Bellinger_Kalang_FS_final_160408:11 April 2016 A2
redevelopment: refers to rebuilding in an area. For example, as urban areas age,
it may become necessary to demolish and reconstruct buildings on a relatively large
scale. Redevelopment generally does not require either rezoning or major
extensions to urban services.
disaster plan (DISPLAN)
A step by step sequence of previously agreed roles, responsibilities, functions,
actions and management arrangements for the conduct of a single or series of
connected emergency operations, with the object of ensuring the coordinated
response by all agencies having responsibilities and functions in emergencies.
discharge
The rate of flow of water measured in terms of volume per unit time, for example,
cubic metres per second (m3/s). Discharge is different from the speed or velocity
of flow, which is a measure of how fast the water is moving for example, metres per
second (m/s).
ecologically sustainable
development (ESD)
Using, conserving and enhancing natural resources so that ecological processes,
on which life depends, are maintained, and the total quality of life, now and in the
future, can be maintained or increased. A more detailed definition is included in the
Local Government Act 1993. The use of sustainability and sustainable in this
manual relate to ESD.
effective warning time
The time available after receiving advice of an impending flood and before the
floodwaters prevent appropriate flood response actions being undertaken. The
effective warning time is typically used to move farm equipment, move stock, raise
furniture, evacuate people and transport their possessions.
emergency management
A range of measures to manage risks to communities and the environment. In the
flood context it may include measures to prevent, prepare for, respond to and
recover from flooding.
flash flooding
Flooding which is sudden and unexpected. It is often caused by sudden local or
nearby heavy rainfall. Often defined as flooding which peaks within six hours of the
causative rain.
flood
Relatively high stream flow which overtops the natural or artificial banks in any part
of a stream, river, estuary, lake or dam, and/or local overland flooding associated
with major drainage before entering a watercourse, and/or coastal inundation
resulting from super-elevated sea levels and/or waves overtopping coastline
defences excluding tsunami.
flood awareness
Flood awareness is an appreciation of the likely effects of flooding and a knowledge
of the relevant flood warning, response and evacuation procedures.
flood education
Flood education seeks to provide information to raise awareness of the flood
problem so as to enable individuals to understand how to manage themselves an
their property in response to flood warnings and in a flood event. It invokes a state
of flood readiness.
flood fringe areas
The remaining area of flood prone land after floodway and flood storage areas have
been defined.
flood liable land
Is synonymous with flood prone land (i.e. land susceptible to flooding by the
probable maximum flood (PMF) event). Note that the term flood liable land covers
the whole of the floodplain, not just that part below the flood planning level (see
flood planning area).
Lower Bellinger and Kalang River Flood Study
WMAwater
111036-04 :Lower_Bellinger_Kalang_FS_final_160408:11 April 2016 A3
flood mitigation standard The average recurrence interval of the flood, selected as part of the floodplain risk
management process that forms the basis for physical works to modify the impacts
of flooding.
floodplain
Area of land which is subject to inundation by floods up to and including the
probable maximum flood event, that is, flood prone land.
floodplain risk
management options
The measures that might be feasible for the management of a particular area of the
floodplain. Preparation of a floodplain risk management plan requires a detailed
evaluation of floodplain risk management options.
floodplain risk
management plan
A management plan developed in accordance with the principles and guidelines in
this manual. Usually includes both written and diagrammetic information describing
how particular areas of flood prone land are to be used and managed to achieve
defined objectives.
flood plan (local)
A sub-plan of a disaster plan that deals specifically with flooding. They can exist at
State, Division and local levels. Local flood plans are prepared under the
leadership of the State Emergency Service.
flood planning area
The area of land below the flood planning level and thus subject to flood related
development controls. The concept of flood planning area generally supersedes
the Aflood liable land@ concept in the 1986 Manual.
Flood Planning Levels
(FPLs)
FPL=s are the combinations of flood levels (derived from significant historical flood
events or floods of specific AEPs) and freeboards selected for floodplain risk
management purposes, as determined in management studies and incorporated in
management plans. FPLs supersede the Astandard flood event@ in the 1986
manual.
flood proofing
A combination of measures incorporated in the design, construction and alteration
of individual buildings or structures subject to flooding, to reduce or eliminate flood
damages.
flood prone land
Is land susceptible to flooding by the Probable Maximum Flood (PMF) event. Flood
prone land is synonymous with flood liable land.
flood readiness
Flood readiness is an ability to react within the effective warning time.
flood risk
Potential danger to personal safety and potential damage to property resulting from
flooding. The degree of risk varies with circumstances across the full range of
floods. Flood risk in this manual is divided into 3 types, existing, future and
continuing risks. They are described below.
existing flood risk: the risk a community is exposed to as a result of its location
on the floodplain.
future flood risk: the risk a community may be exposed to as a result of new
development on the floodplain.
continuing flood risk: the risk a community is exposed to after floodplain risk
management measures have been implemented. For a town protected by levees,
the continuing flood risk is the consequences of the levees being overtopped. For
an area without any floodplain risk management measures, the continuing flood risk
is simply the existence of its flood exposure.
flood storage areas
Lower Bellinger and Kalang River Flood Study
WMAwater
111036-04 :Lower_Bellinger_Kalang_FS_final_160408:11 April 2016 A4
Those parts of the floodplain that are important for the temporary storage of
floodwaters during the passage of a flood. The extent and behaviour of flood
storage areas may change with flood severity, and loss of flood storage can
increase the severity of flood impacts by reducing natural flood attenuation. Hence,
it is necessary to investigate a range of flood sizes before defining flood storage
areas.
floodway areas
Those areas of the floodplain where a significant discharge of water occurs during
floods. They are often aligned with naturally defined channels. Floodways are
areas that, even if only partially blocked, would cause a significant redistribution of
flood flows, or a significant increase in flood levels.
freeboard
Freeboard provides reasonable certainty that the risk exposure selected in deciding
on a particular flood chosen as the basis for the FPL is actually provided. It is a
factor of safety typically used in relation to the setting of floor levels, levee crest
levels, etc. Freeboard is included in the flood planning level.
habitable room
in a residential situation: a living or working area, such as a lounge room, dining
room, rumpus room, kitchen, bedroom or workroom.
in an industrial or commercial situation: an area used for offices or to store
valuable possessions susceptible to flood damage in the event of a flood.
hazard
A source of potential harm or a situation with a potential to cause loss. In relation
to this manual the hazard is flooding which has the potential to cause damage to
the community. Definitions of high and low hazard categories are provided in the
Manual.
hydraulics
Term given to the study of water flow in waterways; in particular, the evaluation of
flow parameters such as water level and velocity.
hydrograph
A graph which shows how the discharge or stage/flood level at any particular
location varies with time during a flood.
hydrology
Term given to the study of the rainfall and runoff process; in particular, the
evaluation of peak flows, flow volumes and the derivation of hydrographs for a
range of floods.
local overland flooding
Inundation by local runoff rather than overbank discharge from a stream, river,
estuary, lake or dam.
local drainage
Are smaller scale problems in urban areas. They are outside the definition of major
drainage in this glossary.
mainstream flooding
Inundation of normally dry land occurring when water overflows the natural or
artificial banks of a stream, river, estuary, lake or dam.
major drainage
Councils have discretion in determining whether urban drainage problems are
associated with major or local drainage. For the purpose of this manual major
drainage involves:
• the floodplains of original watercourses (which may now be piped, channelised
or diverted), or sloping areas where overland flows develop along alternative
paths once system capacity is exceeded; and/or
Lower Bellinger and Kalang River Flood Study
WMAwater
111036-04 :Lower_Bellinger_Kalang_FS_final_160408:11 April 2016 A5
• water depths generally in excess of 0.3 m (in the major system design storm as
defined in the current version of Australian Rainfall and Runoff). These
conditions may result in danger to personal safety and property damage to
both premises and vehicles; and/or
• major overland flow paths through developed areas outside of defined drainage
reserves; and/or
• the potential to affect a number of buildings along the major flow path.
mathematical/computer
models
The mathematical representation of the physical processes involved in runoff
generation and stream flow. These models are often run on computers due to the
complexity of the mathematical relationships between runoff, stream flow and the
distribution of flows across the floodplain.
merit approach
The merit approach weighs social, economic, ecological and cultural impacts of
land use options for different flood prone areas together with flood damage, hazard
and behaviour implications, and environmental protection and well being of the
State=s rivers and floodplains.
The merit approach operates at two levels. At the strategic level it allows for the
consideration of social, economic, ecological, cultural and flooding issues to
determine strategies for the management of future flood risk which are formulated
into Council plans, policy and EPIs. At a site specific level, it involves consideration
of the best way of conditioning development allowable under the floodplain risk
management plan, local floodplain risk management policy and EPIs.
minor, moderate and major
flooding
Both the State Emergency Service and the Bureau of Meteorology use the following
definitions in flood warnings to give a general indication of the types of problems
expected with a flood:
minor flooding: causes inconvenience such as closing of minor roads and the
submergence of low level bridges. The lower limit of this class of flooding on the
reference gauge is the initial flood level at which landholders and townspeople
begin to be flooded.
moderate flooding: low-lying areas are inundated requiring removal of stock
and/or evacuation of some houses. Main traffic routes may be covered.
major flooding: appreciable urban areas are flooded and/or extensive rural areas
are flooded. Properties, villages and towns can be isolated.
modification measures
Measures that modify either the flood, the property or the response to flooding.
Examples are indicated in Table 2.1 with further discussion in the Manual.
peak discharge
The maximum discharge occurring during a flood event.
Probable Maximum Flood
(PMF)
The PMF is the largest flood that could conceivably occur at a particular location,
usually estimated from probable maximum precipitation, and where applicable,
snow melt, coupled with the worst flood producing catchment conditions.
Generally, it is not physically or economically possible to provide complete
protection against this event. The PMF defines the extent of flood prone land, that
is, the floodplain. The extent, nature and potential consequences of flooding
associated with a range of events rarer than the flood used for designing mitigation
Lower Bellinger and Kalang River Flood Study
WMAwater
111036-04 :Lower_Bellinger_Kalang_FS_final_160408:11 April 2016 A6
works and controlling development, up to and including the PMF event should be
addressed in a floodplain risk management study.
Probable Maximum
Precipitation (PMP)
The PMP is the greatest depth of precipitation for a given duration meteorologically
possible over a given size storm area at a particular location at a particular time of
the year, with no allowance made for long-term climatic trends (World
Meteorological Organisation, 1986). It is the primary input to PMF estimation.
probability
A statistical measure of the expected chance of flooding (see AEP).
risk
Chance of something happening that will have an impact. It is measured in terms
of consequences and likelihood. In the context of the manual it is the likelihood of
consequences arising from the interaction of floods, communities and the
environment.
runoff
The amount of rainfall which actually ends up as streamflow, also known as rainfall
excess.
stage
Equivalent to Awater level@. Both are measured with reference to a specified
datum.
stage hydrograph
A graph that shows how the water level at a particular location changes with time
during a flood. It must be referenced to a particular datum.
survey plan
A plan prepared by a registered surveyor.
water surface profile
A graph showing the flood stage at any given location along a watercourse at a
particular time.
wind fetch
The horizontal distance in the direction of wind over which wind waves are
generated.