Low Cost, Long Haul Gigabit Ethernet Alan Cowie AARNet Pty Ltd January 2004.

16
Low Cost, Long Haul Gigabit Ethernet Alan Cowie AARNet Pty Ltd January 2004

Transcript of Low Cost, Long Haul Gigabit Ethernet Alan Cowie AARNet Pty Ltd January 2004.

Low Cost, Long Haul Gigabit Ethernet

Alan CowieAARNet Pty LtdJanuary 2004

Outline

● Opportunity● Geography/Building Blocks● Proof of Concept● Design● Resource Requirements● Outcome● References/URLs

Opportunity

● The main campus of the University of New England (UNE) is located in Armidale, Northern NSW.

● UNE required a replacement for their expensive, ATM based tail link (8Mbps on E3) to the AARNet hub in Sydney.

● Transgrid offered UNE some surplus bandwidth on existing Transgrid infrastructure.

● AARNet wanted to explore low cost, long haul opportunities.

Geography

330kV Tower

The Transgrid Network

Concept

● Transgrid has long run fibre.● AARNet is a Carrier and has network building

and operating experience.● AARNet and Transgrid formed a partnership to

provide bandwidth to UNE.● Excess capacity could be sold to other customers.● UNE wanted a cost effective IP/ethernet service

from Sydney to Armidale.

Building Blocks

● TG had installed fibre in the Overhead Earth wire on some sections of their 330kV network.

● The fibre is brought to the ground and terminated only at substations and powerstations.

● The Armidale to Sydney section had some long fibre runs (>80km).

● AARNet was already using Cisco CWDM equipment with very good optical properties.

Building Blocks 2

● The CWDM GBICS support 1.25-Gbps full-duplex links with an Optical link budget of better than 30 dB.

● Cisco 3550-12T Gigabit ethernet Switches. Each supports 10 GBIC interfaces and two copper 10/100/1000 ports.

Available Fibre

A end B end KM Attn dBArmidale Tamworth 106 24.18Tamworth Muswellbrook 130 29.3Muswellbrook Liddell 19 4.96Liddell Newcastle 104 22.69Newcastle Eraring 22 5Eraring Vales Point 32 7.6Vales Point Munmorah 8 2.29Munmorah Sydney North 80 17.8Sydney North Sydney West 38 9.04

Proof of Concept

● The Tamworth to Muswellbrook leg was the longest at 130km with a 29.3dB optical loss.

● The PoC was tested on this leg using 1470nm and 1490nm CWDM GBICs in borrowed Cisco switches.

● When tested, the 130km link came up straight away and ran without error for the duration of the test. Power meter readings showed ample signal.

● The 1550nm GBIC were expected to perform better than the 1470 & 1490nm test optics.

Design● Each switch is a OEO

signal regenerator and a breakout node.

● Each switch can support 5 north/south GE paths.

● No provision for OOB management

● Customer separation by QinQ VLAN stacking

● Radio last leg until Broadway substation completed

Multiplex Design

● Initial design supports only 1 GigE path due to MUX losses

● Shorter runs can support CWDM mux

● Longer runs will need amplification to support CWDM mux

Resource Requirements

● >500kms of fibre● 6 x Cisco 3550-12T Gigabit ethernet switches● 12 x Cisco 1000BASE-CWDM GBIC 1550 nm● A few UPSs● Patch leads● Fibre tails from the TG sites to the end users● Clue

Outcomes● Lit up >500km fibre

run with Gigabit Ethernet.

● Six potential customer breakout/access nodes.

● Total cost for all active/optical gear less than cost of one SDH node.

● Potential for up to 8 GE paths.

References/URLs

● http://www.aarnet.edu.au/● http://www.une.edu.au/● http://www.transgrid.com.au/about_us/inset.html● http://www.cisco.com/warp/public/cc/so/neso/olso/nesocdwm/cgbic_ov.htm

● http://mangrove.nswrno.net.au/dist/public/tgune/unetgnet2_frame.htm

● http://xl.nswrno.net.au/tgune/● Alan Cowie – AARNet Sydney

[email protected]