London Underground - Pozament...be placeable within a limited time frame, but also to achieve these...
Transcript of London Underground - Pozament...be placeable within a limited time frame, but also to achieve these...
London Underground
New London Underground slab track cast in-situ
You might think that B2F stands
for “Back to the Future”. In fact, it
is the acronym chosen by London
Underground to signify its project
to renew the track in tunnels
between Baker Street and Finchley
Road on the Metropolitan line.
Back to the future, though, would
not be a bad interpretation as the
project is all about an innovative
process that LU has developed, in
conjunction with its partner Tarmac,
and which shows promise for many
more applications in the future.
The task facing LU was how to
replace 3.2km of life-expired bullhead
rail, timber sleepered, ballasted
track in seven single-bore tunnels.
These range in length between 185
and 720 metres. The track drainage
had largely failed and the conditions
arising from that were making track
maintenance increasingly difficult.
The solution that LU aspired to was
to replace all the ballasted track in
the tunnels with a concrete slab track
form, giving the benefits of minimal
maintenance requirements and a
design life of 100 years. But how
to achieve this economically with
short track access periods on this
intensively used underground line
close to central London? The answer
was to be found by deploying a very
specific type of concrete (and by LU
granting itself slightly longer night-
time access periods than the norm).
Product PQ-X Cement
Client London Underground
SPECIAL MIX
Tarmac’s Pozament brand which
provides high performance building
products, had developed concrete
mixes for similar situations. These
had been successfully used for
surface bay replacements on the
M42 and M54 motorways and on
runways at Birmingham International
and London City airports.
So Tarmac was approached by LU
in the latter half of 2015 to develop
a modification of its concrete
specification to meet some particular
performance requirements. These
were to not only have a good
strength gain over time and to
be placeable within a limited
time frame, but also to achieve
these within a wide temperature
range from 10°C to 30°C.
The newly designed mix, which would
cope with this temperature range
and reach a strength of 15 N/mm2
two hours after placement, was ready
for the work to commence in May
2016, the start of a two year project.
Roger Eke, technical sales manager
for Pozament, explained that, because
it was not feasible to transport a
wet mix into the tunnels, LU wanted
a dry concrete mix that could be
produced within the tunnels and have
water added close to the point of
placement. Therefore the pavement
quality PQ-X mix, previously used on
the M42 and other projects, was re-
engineered for the specific application
of the track slab in tunnels.
PQ-X is mixed with 0/4mm washed
sand and 4/20mm aggregate from
the Tarmac owned Tyttenhanger
Quarry, near St Albans. The
materials from this source were
specially selected because of the
regular particle size distribution,
which results in a homogeneous
and workable concrete mix.
Tyttenhanger Quarry has allocated
specific reserves to achieve
consistent quality from the extracted
materials for the life of the project.
Using land-based aggregate rather
than a marine source also avoids
any potentially adverse chloride
reaction. The PQ-X cement is
manufactured at Tarmac’s specialist
facility at Swains Park in Derbyshire.
As part of the final refinement and
approval of the modified PQ-X
cement, the London Underground
project representatives were
invited to Swains Park to witness
a typical pour of PQ-X based
concrete and to agree on the
appropriate slump characteristic.
The concrete performance was
then re-engineered by Pozament’s
laboratory which is responsible
for research and development,
together with quality control.
The actual mixing of the concrete takes place
within the tunnel on an engineering delivery train which includes a special volumetric mixer wagon.
TRACK REPLACEMENT
The actual mixing of the concrete
takes place within the tunnel on an
engineering delivery train which
includes a special volumetric mixer
wagon. The rail-mounted wagon
is one of a range manufactured
by the Italian company, Blend.
This wagon has compartments
for segregating the constituent
materials, a cement hopper for up
to 5.0m3 of the PQ-X cement, a
sand hopper of 8.0m3 capacity, an
aggregate hopper of 9.0m3 capacity
and a 5,000 litre water bowser.
The volumetric mixer can be
programmed to deliver a specific
mix from these compartments.
Sand and aggregate are gravity fed
onto a conveyor belt and are then
transferred to an auger rotating at
300rpm, at which point the cement
and water are added. The high speed
of the auger mixing process ensures
that sufficient energy is imparted
to activate the superplasticisers
and other additives included in
the mix design. The output from
the auger is then dropped onto
another conveyor belt at a steady
rate and delivered to the placement
area. The mix is designed to have
an S4 slump characteristic.
David Sloane, project manager for LU,
explained the planning and delivery
arrangements. Extended engineering
possession hours of 22:00 to 05:30
each night on Monday, Tuesday
and Wednesday were taken on the
Metropolitan line for installation
of the track slab. Within this time
period it is possible to install 10.5
metres of new track per night.
The works are dependent on an
engineering train, which consists of
locomotive/GP wagon/ mixer wagon/
DISAB/GP wagon/locomotive. The
first operation is to use the DISAB
vacuum machine to excavate all the
old track ballast from the length to
be replaced that shift. The DISAB
process is also able to remove all the
old drain components along with the
ballast. All material up to the soffit
of the rail baseplates is removed, the
bullhead rail and chairs having been
previously replaced by flat bottom
rail and baseplates in readiness for
formation of the new track slab.
Once the area under the rail and
baseplates downwards has been
cleared, shuttering is placed ready
for casting the track slab. A base
reinforcement mesh is also positioned
75mm from the tunnel invert. The
overall depth of the concrete slab
is typically 400 to 480mm.
Mixing, delivery, placement and
vibration of the concrete can be
achieved within 45 minutes. It is
interesting that, in the early stages
of the project, it was found that the
concrete was not remaining workable
for long enough and LU asked the
Pozament team to slow down the mix.
It was impressive how they were able
to do this very accurately whilst still
preserving the required specification
and properties of the finished
product. Another striking feature of
the process is that, in programming
the concrete mix, the volume of
concrete required for each pour
can be produced very accurately.
The site team is made up
of 16 personnel from Track
Partnership (a Balfour Beatty
and London Underground JV).
INTEGRAL DRAINAGE
A new square-section U-shape
four-foot drain is cast into the top
surface of the slab and is provided
with a GRP cover. This drain runs
to the end of each tunnel section
and then goes through a transition
slab at the beginning of each open
track section where the drainage
crosses into the six-foot drain.
Prior to the works in the tunnels
commencing, trials of the concrete
placement had been carried out
on a mock-up of the tunnel cross-
section. This was a full-scale model
approximately 15 metres in length,
constructed at an LU facility at
Northwood. The purpose of these
trials was to ensure the feasibility of
placing and compacting the mix into
the fairly constricted area between
the tunnel invert and the shuttering
for the surface drain, and to prove the
curing and strength gain aspirations
of the process were achieved.
In addition to the mix design for the
main work of the track slab, Pozament
also produce a rapid-setting flowing
repair concrete for application on
small sections where it is necessary
to effect localised patching and
small section slab track pours of
approximately three linear metres.
Once the project is complete by
mid-2018, London Underground
should expect very low maintenance
within these tunnel sections for a
number of years, having achieved
the transition to an innovative
track form with minimal disruption
to Metropolitan line customers.
Tarmac can be proud that its
expertise and skill in designing
specialised concrete mixes has
been further refined and applied to
a new situation and to one which
looks capable of extension more
widely within the LU network and
on other metro systems worldwide.
As featured in Rail Engineer Magazine
- December 2016
TARMAC.COM
For more information on our range of
Cement solutions please visit pozament.co.uk