Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 1
DELIVERY PARTNER
Parklife Football Hubs London Programme
• Details of the background, strategic context and aims of the funding programme
• 3 Stage Funding Process
• ‘Expressions of Interest’ by 4pm Friday 15th July 2016
Revision 001 May 2016
Prospectus
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 2
Contents
1.0Introduction
2.0KeyProgrammePrinciples
3.0TheFundingProcess
4.0AreYouReady?
5.0Measurement
6.0CaseStudy
7.0FurtherInformationandGuidance
Appendix1-ParklifeProcessFlowChart
3
8
11
12
13
14
15
16
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 3
1.0 IntroductionParklife Football Hubs Programme – London
InEngland,around1.8mpeopleparticipateweeklyinsomeformoffootballrangingfromthetraditional11v11gamethroughtoinformalsmall-sidedandrecreationalfootball.Inadditiontotheplayers,thereareanestimated1.5mvolunteerswhoarealsoinvolved–asparents,coaches,referees,ground-staffandadministrators.Asa‘NationalGame’,footballhasalwaysplayedanimportantroleinthecommunity–notonlyofferingopportunitiestogetinvolvedinsportandphysicalactivitybutalsoasanimportantmeansofdeliveringawiderangeofpositivesocialoutcomesinareasofhealth,education,communitydevelopmentandsafety.Thescale,reachandrelevanceofthegamehasneverbeengreater.Despitethis,therearesomedifficultchallengesbeingfacedwithinmanycommunitiesaslocalgovernmentsubsidiesaregraduallyreducedandchanginglifestyleshasmeantthatplayers,ascustomers,wantamorevariedfootballoffer.
TheFA,thePremierLeagueandSportEnglandhaveforsome time been working together to develop aprogramme of investments that target areas wherepressures on the local game are greatest – this isknownasthe‘ParklifeFootballHubsProgramme’
The Programme will provide significant newinvestmentintolocal,accessiblefacilitieslocatedintheheartofcommunitiesacrossthecountry
ItdiffersfromtraditionalfootballinvestmentstreamsastheFundingPartnersarekeentoseeaportfolioapproachtoprovideanareawidesolution,ratherthanoneoffsiteinvestment
The programme will tap into theexcitementaswebuildtowardstheEuro2020championships,the final stagesofwhich arebeing held in London, andhelps to deliver thecommitment tosecurealegacyfromtheevent
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 4
Aims
ParklifeFootballHubswill:
• Befinanciallysustainableandbasedonstrongbusinessplans,withsitescapableofincomegenerationhelpingsustainaportfolioapproachandreducerelianceonpublicsubsidy
• BedesignedcollaborativelywithlocalpartnersincludingtheFA,CountyFA,localprofessionalclub(s),thelocalfootballcommunityandlocalauthorities
• Encouragepeopletoplaymoreregularly,ortobecomeactiveandindoingso,achievewidersocialoutcomes
• Beaffordable,openandaccessibletoall
• Beflexible–cateringforfootballactivity,othersportsandalsootherprogrammessuchaseducation,healthandwidercommunitydevelopmentinitiativesasappropriate
• Offerahigh-qualitycustomerexperienceandprovideasafeandwelcomingenvironmentforfootball-ledandotherdemand-ledlocalprogrammestoflourish
• Provideanewmanagementandoperationalapproachtograssrootsfootballfacilities.
The national Funding Partners - The FA,PremierLeagueandSportEngland-havecommittedtoaninvestmentprogrammeoverthenextfiveyearsandthereisanimmediate opportunity for LondonBoroughstobecomeinvolvedaspartofalocalbidconsortiummadeupofarangeofotherlocalpartners.
Inadditiontothemainfundingpartners, theprogrammeinLondonisbeingsupportedthrough additionalinvestment from TheMayorofLondon.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 5
Potential partners
Itisanticipatedthatlocalconsortiawillinclude:
• Local authorities, offering political and senior officer leadership and access to keypersonnelinrelevantlocalgovernmentfunctionsincludingplanning,financeandlegal
• Local county football associations,reflectingthespecificneedsoflocalclubsandleagues
• Local professional football clubs and associated community foundations,whoselocalknowledgeandcommunityreachwillenrichtheprogrammeoffer
• Other local partners, whichmayincluderepresentativesfromlocaleducationproviders,communitydevelopmentgroups,leisuretrusts,commercialprovidersandsoon.
TheFundingPartnersareseekingactiveinvolvementfromLondonBoroughswhorecognisethevalue of sport and football within their local communities, who are committed to securinginvestmentthroughacollaborativeapproachwithgenuine involvementfromarangeof localpartnersviaaconsortiumandwhoareabletorespondquicklytodeliverasignificantprogrammeofsport-ledregenerationwithintheirarea.
Inreturn,theFundingPartnersofferanewinvestmentstream,on-the-groundofficersupportandongoingadviceandassistancetoensurethattheresultanthubsitesarehighqualityfinanciallysustainablefacilitiesthataremanagedinaprofessionalway,butthattheyarealsocatalystsforthedeliveryofpositivesocialandeconomicoutcomesinthecentreofthecommunitiestheyserve.
The London Programme
LondonisanimportantcityfortheFundingPartnersasithasgreatpotentialtodeliverpositiveoutcomesagainsttheprogramme’saims.Londonisbeingdeliveredinanearlypathfinderphaseaheadofanationalprogrammeinordertodemonstratehowthehubmodelcansucceedagainstsomeoftheuniquechallengesthecapitalfacessuchashighpopulationdensity,highdemandtoplaythegameandlimitedspacestoplay.
This document sets out the details of the programme, funding process and the journey to deliver a new sustainable model for grassroots football hubs in London.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 6
‘‘
’’
The Parklife Programme will lead to a step change in the provision of grassroots football in England. Over the next five years, we have laid out the ambitious target of creating a network of new football hubs across London to support the delivery of FA and County FA youth development and coach education programmes and to improve the quality of grassroots provision for clubs and teams.
Martin GlennFAChiefExecutive
Background
Wherepeopleplaysportmatters.Whetherit isthepitchyouplayonortheparkyouhaveakickaboutin,easyaccesstotherightfacilitiesisimportant.Buildingtherightthingsintherightplacesmakestakingpartinsportandphysicalactivityarealisticoptionformanymorepeople,andleadstoabetterexperienceforthosealreadyengaged.
Thisisespeciallyrelevantatatimewhenlocalauthoritiesandotherpublicsectorprovidersareundersignificantfinancialpressureandarelookingtostrategicallyreviewandrationalisefacilitiestomaketheirofferascosteffectiveandfinanciallyviableaspossible.
Grassrootsfootballisparticularlyexposedtotheseissuesasover80%ofthefacilitystockisinpublicownership.Despitesignificantinvestmentinlocalprojectsoverrecentyearsthroughlocalauthorities,sportslotteryprogrammesandtheFA,PremierLeague,SportEnglandandtheMayorsSportsLegacyFund(viatheFootballFoundation)therehasbeenageneraldeclineinthequalityoffacilities.Inaclimateofgreatlyreducedlocalauthoritydiscretionaryspend,thequalityandperceivedvalueformoneyofferoffacilitiesinpublicownershipisoneofmanyfactorsthathascontributedtoadeclineinregularfootballparticipation.
TheFACommissionReportofOctober2014recognisedthepotentiallongtermimpactoftheseissuessetinabroadercontextofadecliningnumberofEnglandqualifiedplayersatthenationallevel.TheReportproposedanewsustainablemodel forgrassroots facilitiesownershipanddeliverythroughFootballHubscentredonnew,high-qualityartificialgrasspitches(AGPs)inupto30ofthelargestpopulationcentresinEngland.
TheCommissionoutlinedthefollowingkeyobjectives:
• Reduce football’s reliance on local authority subsidies;
• Build significantly more AGPs; and
• Build a sustainable model that makes this change happen.
TheFA,PremierLeagueandSportEngland(backedbyGovernment)supportedbyadditionalfundingfromTheMayorofLondonhavethereforeagreedtoincreasetheirinvestmentintofootballfacilities.
TheinvestmentintoParklifeFootballHubswillprovideanewinvestmentroutefocussedsolelyonstrategicarea-wideplansforfootball.InLondon,thiswillmeanaborough-wideplanasaminimum,orneighbouringboroughsworkinginpartnershipacrosslocalboundaries.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 7
Againstthisbackground,theFundingPartnershaveagreedtodevelopajointNationalFacilitiesStrategyforFootballwhichwillbecompletedbyAutumn2016.
This will help inform thepriorities of a national rolloutoftheParklifeFootballHubsProgramme laterthisyear.
Strategic Context
ParklifeFootballHubsare apriority in theGovernment’s newSportingFuture strategy. Thestrategyhassetawidercontexttoexpandthefocusbeyondincreasedparticipationinsportandphysicalactivitywithanoverarchingaimtoharnessthepowerofsporttohelpchangepeople’slivesforthebetter.
Withinthiscontext,theFundingPartners–TheFA,thePremierLeagueandSportEnglandhaveallrecognisedtheParklifeProgrammeasakeystrategicpriorityoverthenext5years.Thebestarea-wideplanswillseeablendofprogrammesbeingdeliveredincluding:
• Traditionalcompetitive11v11and9v9formatsofthegamesupportedthroughlocalleaguesandcountyfootballassociations-thereisatargetofaminimumof50%ofminisoccerand9v9footballbeingplayedon3GpitcheswheretheParklifeProgrammereaches
• Opportunitiestoplayacrossall formatsof thegamethroughtargetedprogrammingandgreateropportunitiesforinformalsmall-sidedfootball
• Awidersportingoffer(tobedeterminedlocally)perhapsincludingrugby,cricket,dance,andbroader exercise-based classes where demand exists and to further enhance financialsuitability
• Educationopportunities– ranging fromcoachingandvolunteering through tonon-sportrelatedprogrammesincludingICT,job-readiness,socialenterprisedevelopmentandsoon
• Communitydevelopmentprogrammestargetinghealth,lifestylechoices,out-reachandotherlocallyrelevantinterventions.TheFundingPartnersarekeentoseeamulti-agencyapproach.
TheFundingPartnersrecognisethatthebestbidswillbethosethatarederivedfromalocalconsortia or common interest groups which will include the local authority, local footballrepresentation,thelocalprofessionalfootballclub(s),educationpartnersandotherstoreflectlocalcircumstances.Cross-boroughworkingandpartnershipsarealsopositivelyencouraged.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 8
FortheinitialStage1ExpressionofInterest(EOI),applicantsarerequiredtodemonstrate(andwhereappropriateevidence)commitmenttothefollowingkeyprogrammeprinciples:
1. Evidenceof strong relationshipswith key local football partners and local organisationscapable of driving positive changes in football participation and achieving wider socialoutcomes.Asaminimum,thefollowingagenciesshouldbeinvitedtoprovidewrittensupporttotheEOI-CountyFootballAssociation,CommunityFoundationsofthelocalpro-clubs,keylocalgrassroots leaguesandclubs.Educationproviders,privatesectorpartnersandthecharitablesectormayalsobeinterestedinsupportingyourapplication
2. High-levelpoliticalandofficerlevelsupport(Councilleader/CEO)andidentifiedresourcestodeliverParklifeFootballHubsinthearea
3. Commitmenttoworkwithfootballpartnerstodevelopclear,validatedlocaldataregardingcurrentandpotentialfootballparticipationtrends
4. Commitmenttoraisepartnershipfundingof40%oftotalcapitalcostsperarea(pleasenotethiscanbeaggregatedacrossanareaandmultiplesites)
5. Demonstrateacommitmenttobringaboutwidersocialoutcomessuchashealth,educationandsocialcohesionthroughanarea-widefootballdevelopmentplan
6. Commitmenttoprovideclearevidenceofstrategicneedforproposedfacilitiesincludinganup-to-datePlayingPitchStrategy(PPS),oracommitmenttoundertakeoneaspartoftheParklife Football Hubs Programme process. Also a commitment to undertake demandmodellingbasedontheParklifetemplatemodel
7. AbilityandwillingnesstoestablishorbeapartofaSpecialPurposeVehicle(SPV)/TruststructuretomanageandmaintainfacilitieswhereassetsareofferedacrosstotheSPVonalong-termpeppercorn lease.Therevenuegeneratedby theSPVshallbering-fencedforreinvestmentintograssrootsfootballinthelocalarea
8. Commitment tomaintain the required levelof football revenuesubsidy toallowtheParklifeFootballHubsProgrammesitestomatureanddemonstratefinancialsustainability.AnylongertermreductioninsubsidyshouldbeagreedbytheSPVandbeinlinewiththeoutcomesofthemodellingfortheareabasedonareductioninpitchesbeingrequiredtobemarkedforfootball
9. AbilityandwillingnesstoprocureadedicatedOperatorandtotakeaninnovativeapproachtothefinancialmodelatalocallevel,includingconsideringtherolethatincomegenerationthroughcommercialsportandleisurefacilitiescouldplaywithinParklifeFootballHubs
10. Willingnesstousenewprogrammespecificconsultancyandconstructionframeworkstoachievevalueandconsistencyofdesignacrossthecountry
11. Commitmenttoprogressarea-wideplansatspeed.Ifallocatedwithinthefirsttrancheoforganisationstheremaybearequirementforinyearspendin2017/18.
2.0 Key Programme Principles
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 9
What will Parklife Football Hubs look like in London?
AParklifeFootballportfoliowilltypicallycomprise:
• Twoorthreeindividualhubsitesacrossanarea
• Eachhubsitecontaining:
O MinimumoftwoAGP’s
O Changingaccommodation
O Insomecases,belinkedtohealthandfitnessorothercommercialprovisionwhichwillprovidearevenuestream
O Potentiallyothersportsandfacilitiesinadditiontothecorefootballoffer–flexibleindoorspaceswillbeconsideredonacase-by-casebasis.
Basedonprogrammedeliverytodate,adoubleAGPwithchangingaccommodationtypicallycostsaround£3-4m.
LondonParklifeFootballHubswillbe governed by a singlenot-for-profittrustasexplainedinmoredetailonpage10
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 10
Football Trust Special Purpose Vehicle (SPV)
TheFundingPartnerswillestablishanewCharitableTrusttoprovidestrategicmanagementandoverviewoftheParklifeFootballHubsProgramme.TheTrustwillbeabletoholdpropertythroughpeppercornleasearrangements,holdlifecyclefundsfor3GreplacementandmanageoperatorrelationshipsacrossthehubsnetworkinLondon.TheFundingPartnersbelievethatthisisakeycomponentthatallowsfootballtotakemoreresponsibilityandinvolvementinthemanagementofgrassrootsfacilities,andwillprovideaconsistentcustomerexperienceandlessrelianceonthepublicsector.
Anylicensefeesreceivedfromanoperatoratboroughlevel(orcrossboroughpartnerships)willberingfencedforthatborough/partnershiptoreinvestbackintofootballfacilitiestoeitherreduceongoingsubsidy,increasepitchmaintenanceregimestoprovidebettercustomerexperienceortominorcapitalinvestmentintootherfootballsitesthatcouldbeleasedtothefootballtrust.
ThecostofestablishingtheCharitableTrustwillbecoveredbytheFundingPartnersanddetailsofhowboroughswillinteractwiththeTrustwillbeoutlinedatStage2andwillbuilduponthekeylearningsfromthepathfinders.
TheBoardofTrusteeswillreflectthedesireforfootballtotakemoreresponsibility-TheFAandprofessionalgamewillhavetheabilitytoappointTrusteesalongsideotherkeystakeholders,butthe board will include independent representation in order to provide skilled and diverseleadership.
Iftherearesomekeyfootballsites inaBorough’sportfoliothatcannotbetransferredtotheFootballTrust,thefundingpartnersmaydecidetoenterintoaprofitsharescenariothatwouldseetheownershipandmanagementremainwiththeexistingorganisation.However,acrosstheportfoliothisshouldbeintheminorityandeachsitewillbeconsideredonacase-by-casebasis.
Any concerns over the management and operational structure outlined aboveshouldbedetailedwithinacoveringletterforreviewbytheFundingPartnersatStage1EOI.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 11
3.0 The Funding Process
Stage 1 – Expression of InterestEligibleorganisationsareinvitedtosubmitanEOIformviaemailtoSportEngland at [email protected] with supporting evidence (whererequired)outliningtheircommitmenttothekeyprinciplesofthefundby4pmonFriday15thJuly2016.
Stage 2 – Submission of Area-wide Plan Successfulorganisationswillthenbeinvitedtodevelopadetailedarea-wideplansettingoutaportfolioofParklifeFootballHubsitesagainstwhichanoverallfundingenvelopecanthenbeconsidered.TheFundingPartnerswilloffer support at a local level towards producing a business case, outlinedesigns and an appropriate evidence base for investment. The ProjectInvestmentGroupwillconsiderthebusinesscaseandstrongsubmissionswillbegivenatargetfundingenvelopeforStage3.
Applicants are able at this stage to apply for Project Development Coststowardsexpenditurerelatedtofeasibilityanddesignofpitchandconstructionworks.
Stage 3 – Submission of Individual Hub ApplicationsSuccessful organisations will be invited to develop individual grantapplicationsonasite-by-sitebasisforconsiderationforafundingawardviatheFootballFoundation.AtthisstagetheFoundationteamwillworkwithapplicantsprovidinggrantsandtechnicalexpertisetodevelopbidstoanappropriate levelof readiness.Anassessmentwill beundertakenby theFootballFoundationwhowillgrantanExchequerawardtobespentwithinthegivenfinancialyear.
Forfurtherdetails,seeAppendix1-ParklifeProcessFlowChart
OrganisationsconsideringsubmittinganExpressionof Interest (EOI)shouldbeawareof theminimumeligibilitycriteriaforthefundintheFrequentlyAskedQuestions.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 12
Beforeapplying,youneedtoconsiderwhetheryouarereadytoengagewiththeprocesstodriveamajorstructuralchangeinthedeliveryoffootballfacilitiesandfootballopportunitiesacrossyourarea.
Issuesyouwillhavetoembracewillincludeastrategicreview,rationalisationandare-provisionoffacilities.Thiswillinvolveassettransferoffacilitiestoanewarea-wideFootballTrust–youwillhavetoprovidelong-termleases,andwillceasetooperateorcontrolpolicyandprogrammingofanumberofstrategicallyselectedsites.
Youwillneedahigh levelofcommitment fromyourorganisation.LocalauthoritieswillneedelectedmembersupportandofficersupportfromyourleaderandCEOdowntofrontlinestaff.
YouwillneedanominatedStrategicLeadtoactasSeniorResponsibleOfficer(SRO)andresource(s)todriveworkwithinandacrosstheCouncil (typicallysport,parks,health, regeneration, legal,planningandeducation).Experiencesuggeststhataminimumofonefull-timepostwillberequired.
‘Buyin’fromkeylocalpartnerswillalsobeneeded-theCountyFootballAssociationandlocalprofessionalclubcommunityfoundation(s)willneedtobefullycommittedtotheprocess.Youwillalsoneedtoengagewitharangeoflocalstakeholders.
Timescales
TheopportunitytosubmitanEOIviathefirstcompetitiveapplicationroundwillopenon24thMay2016andcloseon15thJuly2016at4pm.
IfyourEOIissuccessfulyouwillthenworktowardssubmissionofadetailedarea-wideplanwhich,withsupportoftheFundingPartners,islikelytotakebetweenaminimumof3upto12monthsdependingonthecomplexityoftheschemeandlevelofworkrequired.
Followingapprovalofthearea-wideplanbytheFundingPartners,applicationsforindividualhubsitestotheFootballFoundationwillbeconsideredonaregularbasis.
Key Performance Indicators (KPIs)
KPIstomeasuresuccesswillformpartofanemergingMonitoringandEvaluationFrameworklinkedtotheGovernment’sSportingFuturestrategy.
Thesewillbedevelopedbylocalpartnersagainstanationalframeworkinrelationtoparticipation,socialdevelopmentandfinancialsustainability.
TheKPIswillformpartofthebusinesscaseandapplicationprocessatStage2.
4.0 Are you Ready?
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 13
The Funding Partners require measurement and data capture to be fully embedded in theoperationofsuccessfulfacilities.Appropriatedigitaltechnologycapabilitywillneedtobebuiltintothedesignofthefacilitiesandsupportingoperationalinfrastructure.
ThemeasurementdatawilltransfertoaDataHubcapturinganonymisedpersonaldatatosetstandards, tracking participants for use by both Partners and Trusts/Operators to informcontinuousimprovementandfurtherlocalplanninganddelivery.
Successful applicantswill alsobe required toprovide informationon financial performance,footballoutcomesandsupply/demandinrelationtofootballparticipation.
Decision making
AProjectInvestmentGroup,madeupofDirectorsrepresentativeofeachoftheFundingPartners,underdelegatedauthorityfromtheirrespectiveorganisations,willmakedecisionsonStage1EOIandStage2area-wideplanssubmissions.
AtStage1,allEOIswillbeconsideredbytheProjectInvestmentGroupandthosebestmeetingtheProgramme’skeyprincipleswillbeinvitedtoStage2.
AtStage2,thefollowingfundingcriteriawillbeappliedinordertomeasuretherobustnessofthefootballhubarea-wideplanproposals.
• Impact-LA’swillbeaskedtoprepareafootballdevelopmentplanwhichdetailshowtheproposalswillimpactonParklifeFootballHubsProgrammeaims
• Sustainability–LA’swillneedtodetailhowtheneedanddemandfortheareahasbeenestablishedaswellaspreparingabusinessplantodemonstratehowthefacilitieswillbeoperatedandfinanciallysupportedovera25-yearperiod(minimum)
• Deliverability–LA’sshould,withtheirappointeddesignteam,prepareacapitaldeliveryplandemonstratingreadinesstoundertakethecapitalbuildanddrawdownExchequerfunding,normallywithinagivenfinancialyear.
Inaddition,theleadorganisation(andtheirprojectteam)willrequireFundingPartnersign-offatkeystagesofdesignandprocurement.AmemberoftheParklifeFootballHubsProgrammeteamwillworkcloselywiththeapplicantthroughthisprocess.
AtStage3,decisionsonindividualsiteapplicationswillbemadebytheFootballFoundationwhichwillfallunderthreecategories:
• Award–anofferofgrantthroughanExchequerFundingAgreement
• Deferral–furtherworktobeundertakenontheapplicationpriortoanawardtobereconsidered
• Rejection–theapplicationisnotsupportedforspecificreasonsalignedtothecriteriaofthefund.
ForfurtherinformationpleasecontactSportEngland’[email protected]
PleasealsoreviewtheinformationwithintheFrequentlyAskedQuestionsdocument.
5.0 Measurement
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 14
6.0 Case Study
Sheffield Parklife Football Hubs Programme
ThequalityofSheffieldCityCouncil’spitcheshasdeclinedover time.Likemany localauthorities, the Council no longer has sufficient resources to maintain pitches to anacceptablestandarddespiteprovidingasubsidytothegrassrootsgameduringthe2015/16season.Theplayingpitchstrategyidentifiedashortfallofpitchesacrossanumberofsportswhichwouldbenefitfromahubapproach.Thequalityofstockandthecouncil’sfinancialpositionwasconsideredunsustainableandTheFAtogetherwiththeCouncilpioneeredthehubportfolioapproachinSheffield.
TheSheffieldprogrammecurrentlycomprisesofthreehubsitesacrossthecitywithtwoAGPsateachsiteandassociatedbuiltfacilitiesforcoacheducation,changingprovisionandsocialspace.Oneofthethreesiteshasagymandstudiotoimprovefinancialreturns,whilstalsoaddressingagapinlocalhealthandfitnessprovision.Itisanticipatedthattwofurther3Gpitcheswillbebuilttofullycompletethedeliveryoftheprogramme.Eachofthehubsiteshasagrasspitchofferandthereisamulti-sportapproachontwoofthethreesites.
Thesiteswillbeleasedtothenewlyformedcharity‘TheSheffieldFootballTrust’whointurnhaveprocuredanoperatortomanage,maintainandoperatethethreesitesprovidingasustainablemanagementsolution.
The commercial viability of the Trust is important to deliver the overall Football Huboutcomesandhelp cross-subsidise future siteswithin the city. TheTrust is currentlydevelopingastrategicvisiondocumentthatwilloutlinehowtherevenueswillbereinvestedlocallytosupportfootball,healthandphysicalactivityoutcomes,butaclearfocuswillbeonaddressingthequalityofthekeyoutlyinggrasssitestobringthemundertheTrustsownershipandreduce,ifnotcompletelyremove,thecouncilssubsidyintofootball.Intime,theSheffieldFootballTrustwillallocatebookingsandberesponsibleforthemajorityofSheffieldCityCouncil’skeyfootballsites.
TheTrust’sBoardismadeupofappointedrepresentativesfromthefollowingorganisations;
• TheFootballAssociation(2Trustees)
• SheffieldUnitedCommunityFoundation(1Trustee)
• SheffieldWednesdayCommunityFoundation(1Trustee)
• SheffieldCityCouncil(1Trustee)
• Sheffield&HallamshireCountyFA(1Trustee)
IndependenttrusteesarealsobeingrecruitedtoensuretheTrusthasaskilledanddiverseboardthatisrepresentativeofthelocalarea.
AlthoughParklifeFootballHubsisaninfrastructuredrivenprogrammethatwillmakethegamemoresustainableatalocallevel,itwillalsoprovideTheFAandpartnerswithagreatdealmoreinsightonhowtoengagewithexistingplayersandencouragethemtoparticipatemoreeachmonth.Alsotoattractnewpeoplefromeverybackgroundtoregularlyandmeaningfully takepart.Workingwith theoperator and local partners challenging keyperformanceindicatorscanbesettohelpdrivegrowthinkeyareasofthegameandsupportwidersocialagendas.Datacapturesystemswillallowthepartnerorganisationstobetterunderstandfootballdemandatalocallevelandtargetprogrammesandincentivestodriveupparticipationlevels.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 15
7.0 Further Information and GuidanceArea-wide Plan requirements
OrganisationswhoaresuccessfulatStage1EOIwillberequiredtodevelopadetailedarea-wideplanforfootballdescribingtheportfolioofFootballHubs.
InLondon,anareaisconsideredtobeboroughwideasaminimumoranareastretchingacrossneighbouringboroughs.Theplanshouldsetoutthepotentiallocation,facilitymixandoutlinecost of the portfolio of hub sites anddescribe the overall participation and intended socialoutcomes,businesscaseviabilityandstrategicplanningevidencethatunderpinstheproposal.
SupportfromtheFootballAssociation,PremierLeagueandSportEnglandwillbeonhandduringthistime.Asaguide,thefollowingareconsideredtobekeycomponentsofanarea-wideplan:
• FootballDevelopmentPlan
• BusinessPlanincorporatingParklifeDemandModelling
• RelevantsupportingevidencefromanadoptedPPS(andBuiltFacilitiesStrategyifappropriate)
• Projectdeliveryplanincorporatingoutlinedesigns,specificationandcostsofindividualsiteproposals
• Evidenceofpartnershipfundingincludingcapitalandon-goingrevenuesupport
• EvidenceofLocalAuthoritycabinetapproval.
Thearea-wideplanwillbereviewedbytheFundingPartnerswhowilldeterminewhetherthereisasuitablebusinesscasefor investment.Ifthebusinesscaseisapproved,applicationsforindividualsitewillbeinvitedagainstanindicativefundingenvelope.
Parklife Demand Model
TheFAhasdeveloped a supply anddemandmodel that builds uponSport England’sPPSMethodology.ThemodelwillinformhowanAGPhubbasedapproachtofacilityplanningcouldbeimplementedacrossalocalauthoritylandscapetohelpreducetheimpactoflocalauthoritysubsidypressuresonfootball.
TheParklifedemandmodelcalculatesthesupplyrequirementsforbothAGP’sandgoodqualitygrasspitchesbaseduponthedemandfromcurrentlocalauthoritypitchhirers.Themodelallowsflexibilityatalocalleveltoamendthescopetoincludeapercentageofdemandfromcurrentusersofothersiteproviders(e.g.clubleasedsitesetc).Thiscanhelpaddresslocalsupplyissuesandcanhighlightthepotentialrevenuesavingsandcapitalrequirementsassociatedwithdeliveryatalocallevel.
Playing Pitch Strategy development – a flexible approach
AcommitmenttoproducingaPPSisoneofthekeyprinciplesoftheParklifeFootballHubsProgramme. The Funding Partners recognise the resource commitment required by LocalAuthoritiestoundertakesuchastudyandSportEnglandhasdevelopedaflexibleapproach.ThereisscopetotwintrackthepreparationofthePPSwiththefundingapplicationprocess.Inanyevent,aPPSmustbeinplacepriortoaward.
Framework Procurement
TheParklifeFootballHubsProgrammerequiresapplicantstoadoptaframeworkapproachtoprocurementinorderthatreplicablemodelsofhigh-qualityconstructioncanbeachieved.TheFundingPartnershaveprocuredOJEUcompliantframeworkswhichwillhelpachievebestvalueandhigh-qualityfacilities.
Parklife Football Hubs London Programme Prospectus
Revision 001 May 2016 16
Exchequer Award Agreement
Project Scoping
Stage 3 Submission - Individual Hub application to Football Foundation
Project Investment Group Decision
Football Foundation Assessment & Panel
Decision
Stage 2 Submission – Area-wide Plan to Sport England
Project Investment Group Decision
Stage 1 Expression of Interest Submission to Sport England
Delivery/ Post Award Monitoring
High level LA officer commitment to Parklife principles Identification of LA budget and officer resource to support roll-out
Commitment to have an adopted Playing Pitch Strategy
PPS action plan monitoring via SPV Delivery via Frameworks (Consultancy / Modular / AGP)
Outline business plan including operating model (SPV) Individual site proposals, project costs and facility mix
Football participation and social outcomes Outline project delivery plan identifying potential planning constraints
Engage in pre application consultation with Sport England Local Planning Manager
Site specific business plans submitted to Football Foundation Planning application determined
Legal Structure of SPV agreed Project cost tendered, modular design option agreed
Defer – Refinement of Project/ Area
Wide Plan
Defer – Refinement of
Project plan
FA/PL/SE/LA Scoping meeting and bespoke action plan Local steering group undertakes supply & demand modelling supported by FA
Scoping of planning and PPS requirement undertaken with SE / FA Engagement with partners/local stakeholders on priorities and potential sites
Develop wide hub business model Structure of SPV agreed with funding partners, programme for operator procurement
drafted.
Unsuccessful
Exchequer Funding Agreement issued LA commits funding within current financial year
Appendix 1 - Parklife Process Flow Chart
DocumentdesignbyAbacusCostManagement/RobinWilsonConsulting