Logistic Manual - Sept 2015 Rev.04
-
Upload
gelo-almayda -
Category
Documents
-
view
215 -
download
0
Transcript of Logistic Manual - Sept 2015 Rev.04
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
1/81
THE AVENUE
PHASE -2
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
2/81
CONTENTS
LIST OF APPENDICES ..........................................................................................
1.0 INTRODUCTION & AIM ..............................................................................
1.1: DISCLAIMER RELATING TO INFORMATION..............................................
1.2: FUTURE REVISIONS ..................................................................................
1.3: FITOUT WORKS POST CENTRE OPENING ..............................................
2.0 PROJECT LOCATION AND SITE OPENING HOURS ................................
2.1: SITE LOGISTICS PLAN ...............................................................................
2.2: PROJECT LOCATION AND SITE OPENING HOURS .................................
3.0 PROJECT TEAM ........................................................................................
4.0 EMERGENCY PROCEDURES AND NUMBERS ........................................
4.1: TENANT OBLIGATIONS ..............................................................................
4.2: EMERGENCY EVACUATION OF SITE ........................................................
4.3: EMERGENCY SERVICES ...........................................................................
4.4: EMERGENCY CONTACT NUMBERS .........................................................
4.5: FIRE PREVENTION AND PROTECTION ....................................................
5.0 ACCIDENTS AND INCIDENTS REPORTING .............................................
6.0 HEALTH AND SAFETY (Outside the uni ts) ..............................................
6.1: PERSONAL PROTECTION EQUIPMENT (PPE) .........................................
6.2: HEALTH AND SAFETY INDUCTION ...........................................................6.3: SUMMARY OF HEALTH AND SAFETY RULES...........................................
6.4: PERMITS TO WORK ...................................................................................
6.5: COSHH REGISTER .....................................................................................
6.6: TOOLBOX TALKS .......................................................................................
6 7: HOUSEKEEPING
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
3/81
7.5: PRAYER AREA............................................................................................
8.0 TEMPORARY POWER, LIGHTING AND WATER ......................................
8.1: TEMPORARY POWER SUPPLY .................................................................
8.2: TEMPORARY THREE PHASE POWER SUPPLY .......................................
8.3: TEMPORARY LIGHTING AND TASK LIGHTING ........................................
8.4: TEMPORARY WATER SUPPLY ..................................................................
8.5: CABLING AND SOCKETS ...........................................................................
8.6: SAFE WORKING PRACTICE .......................................................................
9.0 SECURITY OF UNITS.................................................................................
9.1: RETAIL UNIT SECURITY ............................................................................
10.0 SAFE SYSTEM OF WORK, PERMISSIONS AND PERMITS TO WORK (O
10.1: WORK METHOD STATEMENT AND RISK ASSESSMENT ......................
10.2: PERMIT TO WORK (NO PERMIT, NO WORK) .........................................
10.3: HOT WORKS .............................................................................................
10.4: REMOVAL OF SAFETY CONTROLS ........................................................
10.5: USE OF HAZARDOUS MATERIALS (COSHH) .........................................
10.6: CONFINED SPACE ENTRY PERMIT.........................................................
10.7: ACCESS PERMIT TO ROOF AREAS ........................................................
10.8: ACCESS PERMITRISER/LIFT SHAFTS....................................................
11.0 MATERIALS DELIVERY AND ACCESS .....................................................
11.1: SITE ACCESS ...........................................................................................
11.2: BULK DELVERY ........................................................................................
11.3: MATERIAL OUTP-PASS ............................................................................
11.4: PEDESTRIAN ............................................................................................
11.5: SECURITY .................................................................................................11.6: TENANT’S PERSONNEL SITE ACCESS PASSES (AURORA CARDS) .....
11.7: VISITORS PASSES ...................................................................................
11.8: DELIVERY/LOADING DOCKS ...................................................................
11.9: LIFTS .........................................................................................................
11 10: OVERSIZE DELIVERIES
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
4/81
14.0 REMOVAL OF TENANT’S WASTE ............................................................
15.0 PROTECTION OF WORKS ........................................................................
15.1: GENERAL RESPONSIBILITY ....................................................................
15.2: PROTECTION OF LANDLORD’S AREAS .................................................
16.0 HOARDINGS (IF REQUIRED) ....................................................................
17.0 INSPECTIONS AND MONITORING ............................................................
18.0 CO-ORDINATION MEETINGS ....................................................................
19.0 PLANT, EQUIPMENT AND TOOLS ............................................................
20.0 BASE BUILD MEP SERVICES ...................................................................
20.1: FIRE ALARMS SYSTEMS..........................................................................
20.2: ELECTRICAL SUPPLY ..............................................................................
20.3: WATER ......................................................................................................
20.4: GAS ...........................................................................................................
21.0 BASIC SITE RULES ...................................................................................
APPENDICES ........................................................................................................
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
5/81
LIST OF APPENDICES
APPENDIX A Basic Site Safety Rules
APPENDIX B Induction Booking Process
APPENDIX B1 Induction Booking Form
APPENDIX C Visitors Site Safety Briefing Form
APPENDIX D Gate Pass
APPENDIX E1 Site Logistic Plan (Basement)
APPENDIX E2 Site Logistic Plan (Ground Floor)
APPENDIX F Unit Attendance Form
APPENDIX G Hot Works Permit
APPENDIX H Hoarding (Tenant Fitout Contractor)
APPENDIX I Removal of Safety Controls Permit
APPENDIX J Permit to Use Hazardous Materials (COSHH)
APPENDIX K Confined Space Entry Permit Form
APPENDIX L Incident Report Form
APPENDIX M Accident Report Form
APPENDIX N Prohibition Notice
APPENDIX O Tenant Improvement Notice
APPENDIX P Permit to Access to Roof Areas
APPENDIX Q Minimum PPE requirements
APPENDIX R Project Team Details
APPENDIX S Tenant Fitout Contractor Bulk Delivery Booking Fo
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
6/81
1.0 INTRODUCTION & AIM
The Tenant Liason Manual has been prepared by Al Futtaim Carillion (AFC) to
the Tenant and the Tenants Fit out Contractors in regards to execution of w
logistics and provisions/services to be provided by AFC.
The enclosed set of procedures, controls and checks have been develo
construction and fit out works and to clearly define what AFC’s scope of service
The intent of this manual is to give clear guidance in regard to the logistics op
with which the Tenant Fit out Contractor shall comply therefore creating a
environment.
This document forms the basis of the logistics package and may be subject
on the ongoing site conditions or conditions specific to Tenants or tenancies.
This manual is to be read in conjunction with all other documents issued by
part of the Tenant Fit-out contract documents. Any discrepancies between
discussed with the Client for clarification.
The Tenant Fitout Contractor is responsible for their personnel’s Health and
working inside their respectful units within the City Walk Project. AFC will not b
any works being carried out within the unit or in the event of any accident o
occur within the unit. AFC is responsible for overall site safety and logistics
Fitout Contractors, being outside of their units, are obliged to follow AFC’s
practice including but not limited to full PPE and logistics routes.
1.1: DISCLAIMER RELATING TO INFORMATION
All descriptions, statements and other particulars in this document are
at the time of publication. The Tenant must, however, satisfy themse
otherwise as to the correctness of each of them.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
7/81
1.3: FITOUT WORKS POST MALL OPENING
In the event that a Tenant fitout works are not complete prior to the Op
works carried out whilst the Mall is open for trading, the obligations
document are superseded and will no longer be applicable.
2.0 PROJECT LOCATION AND SITE OPENING H
2.1: SITE LOGISTICS PLAN
The Tenant will be provided with a copy of the Site Logistics Plan, show
tenant’s unit, and the routes to and from the same. The Tenant is re
personnel adhere to those routes (see next page).
This plan attached also identifies the location of the Welfare facilities (i.e.
N.B. This will be subject to change due to site requirements and cu
informed at the site induction. All updates to routes will be displayed on sit
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
8/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
9/81
2.2: PROJECT LOCATION AND SITE OPENING HOURS
Refer to Appendix E, for project location and site logistics plans.
Day shift – Saturday to Thursday 07:00am – 5:00pm
Night shift – Saturday to Thursday 6:00pm – 3:00am
Site Material Deliveries – 24/7
Fridays and all national public and religious holidays the site will be
Any work required to be undertaken outside of these hours is to be
the Client for approval at least 72 hours in advance of the work w
AFC prior to commencing same.
For safety and security reasons it is essential that out of hour
arrangements with AFC.
AFC reserves the right to refuse permission for out of hours worki
Meraas.
3.0 PROJECT TEAM
The parties involved with the Tenant Liason works are as follows:-
Developer/Client Meraas
Project Manager Morganti
Tenant Liason Manager Al Fut taim Cari ll ion
RDD Coordinator Funtastic
4.0 EMERGENCY PROCEDURES AND NUMBER
4.1: TENANT OBLIGATIONS
The Tenant and the Tenant Fit out Contractor are reminded of their resp
care to all persons entering the development and the general public
development and their employees
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
10/81
4.2: EMERGENCY EVACUATION OF SITE
The site emergency evacuation procedure will be issued to Tenants an
at the site induction. Any subsequent revisions will be notified to T
contractors by the Client as they occur. The Tenant and Tenant’s con
with AFCs site emergency evacuation procedure, however for inciden
the units, their own policies and procedures will be implemented/followe
4.3: EMERGENCY SERVICES
In case of emergency the below numbers are provided: (Tenant
numbers and information within their own Health and Safety documenta
CONTACT NAME TEL / FAX / M
Nearest Hospital for life threatening injuries
Rashid Hospital
T: 04 219 100
T: 04 219 200T: 04 337 11
F: 04 311 322M: Rashid@d
Nearest Hospital for non-life threatening injuries
Iranian Hospital(Jeremiah Road)
T: 04 344 025
F: 04 344 032M: [email protected]
AFC Site Emergency (24 hour) M: 056 682 5
Civil Defence T: 997 Ambulance T: 998
Police/Emergency T: 999
Environmental Health and Safety AuthorityT: 04 881 188ehs.customer
Dubai Health AuthorityT: 800 342F: 04 311 311
4.4: EMERGENCY CONTACT NUMBERS
It is mandatory that each tenant clearly posts the contact numbe
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
11/81
As a minimum the Client should ensure that the following is in place with
All fire exits will be suitably marked and kept free from obstruction.
A permit to work for hot work is mandatory and controlled by the Cli
Smoking is only permitted in the designated smoking areas and s
area of the retail mall will be removed from the site.
Tenant contractors must provide sufficient numbers of fire ext
blankets for their unit.
Any fire extinguished, must be immediately reported to the AFC
mobile number 056 682-5100.
5.0 ACCIDENTS AND INCIDENTS REPORTING
Tenants and Tenants Fitout Contractors will comply with the AFC Incid
accident reporting procedures and report all incidents, accidents, environmcomplaints which occur outside of their works, as soon after the incident/ac
incidents or accidents which occur within the units will be managed v
reporting procedures for same will be issued via Meraas.
An incident/accident report form must be completed and submitted w
incident. The location of an incident or accident must be made safe
secondary incidents mitigated. Should any fatality, lost time injuries and serious environmental inci
the following procedure should be followed (In accordance with AFC ac
Summon the help of a first aider if one is not already on the scene.
AFC safety staff are first aid trained and can provide immediate ass
Call the site doctor or male nurse for assistance. The clinic w
nurse/doctor and call the ambulance to provide immediate medical All incidents or accidents must be reported directly to the AFC HSE
6.0 HEALTH AND SAFETY
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
12/81
Within the unit, Meraas are to ensure that additional task specific PP
risk assessments or method statement shall be provided by the Tena
involvement.)
If a Tenant is carrying out work that creates noise in excess 80 db, he
suitable ear protection zone. He must also supply suitable ear prote
this is worn whenever a person enters any ear protection zone. This i
formally to AFC by Meraas before works are executed.
AFC will strictly enforce the PPE rule for entry onto the Project and
within the unit will be the sole responsibility of Meraas and the Tenant
If the Tenant and/or Tenant Fitout Contractor fail to provide any of the bas
appendix Q, offenders will be immediately removed from the site and r
record will be redrawn. The same person will not be eligible to attend safet
enter the City Walk site.
6.2: HEALTH AND SAFETY INDUCTION
All the employees of the Tenant Fitout Contractor and his subcontra
induction course at the AFC Induction office prior to be permitted access to
The exception to this rule will be the Tenant who will be required to obtain a
escorted by the Tenant Fitout Contractor supervisor at all times, with ap
Appendix Q). All visits to site should be arranged via Meraas, who will in t
planned visits.
All Induction courses will be conducted daily throughout the day
(Refer Appendix B/B1).
Allow a minimum time of approximately 2 hours.
The Tenant will be required to submit the details of the Tenant con
complete list of the contractor/subcontractors employees requiring
security pass.
All requests are to be submitted a minimum of 72 hours in adv
induction date.
All valid insurance documents for the works must be in place and a
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
13/81
Full name as it appears on the national identity card
Job title e.g. supervisor, electrician, labourer, fitter, etc.
Nationality
Date of birth
Home address
Legal entitlement (permit to work)
If subcontractor, provide name of main contractor
Unit number
Emergency contact details (name, address, contact number)
Full details of Employer (name, address, supervisor, contact details)
Following receipt of the Induction Booking Form (Refer Appendix B1), the
will notify the Tenant of the date and time of their induction session.
On the date of the scheduled Induction, the Tenant’s personnel are
time and must be in possession of all the personal protective equipmen
Tenant’s personnel are also required to bring their national identity
ex-patriot personnel, so that the information given on the booking for
site administration.
Site access cards will not be issued until personal data has been v
national card or passport.
Staff arriving for Inductions will be refused entry to the induction room
identity card or passport, not listed on the induction booking form or lat
The Tenant will be required to rebook these personnel for another
later date.
After the Tenant’s personnel have been checked against the induct
checks on PPE have been completed, they will be taken to the ad
photographs in preparation for the production of site ID cards. O
process, staff will be returned to the induction office.
All inductions are conducted in English or Arabic, Malayalan & Urd
languages than mentioned will not be inducted during regular inductio
induction sessions must be prior booked and any interpreter services
the Tenant.
All induction records for tenant fitout subcontractors will be issues to
personnel on site.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
14/81
All persons are required to undertake a site induction, prior to carrying
All Tenant and Tenant Fitout Contractor personnel, when entering the helmets, safety shoes or boots, safety glasses, gloves and reflective h
All PPE is to be provided by the Tenant/Tenant Fitout Contractor.
Entry will be denied without PPE as specified above.
Fire-fighting equipment within the unit must be provided by the Te
Contractor and should be provided in all permanent facilities and tem
unit is to be provided with a minimum of one fire extinguisher an
Tenant’s contractor. Additional equipment will be required for laresponsibility of Meraas to ensure the fitout contractors have the
provisions within the units.
All employees must be aware of the location of fire extinguishers and
trained in their method of operation.
Emergency procedures shall be planned for all places of work
emergencies, for evacuating the premises and for summoning a
emergency services. The procedures shall be posted on notice boar
work area. All staff must familiarize themselves with and adhere to thes
High standard of cleanliness, hygiene and housekeeping shall be m
within the units.
Safe and clear means of access to and egress from places of work
maintained by AFC The storage of materials and equipment mus
obscure any sign. All safety signs will be inspected regularly by b
safety manager to ensure that they are in the proper position and are c
Employees found to be under the influence of alcohol and/or drugs wil
immediately and be subject to disciplinary procedures. Each employe
other employees who are believed to be in this condition to the superv
No-one shall knowingly be permitted or required to work while his ab
impaired by fatigue, illness, temperature or other cause that might ex
others to injury. It is equally the responsibility of each employee to rep
if they feel unable to continue work due to any of these conditions.
A no smoking policy is in place on site, whereby smoking is only perm
smoking areas (designated areas are shown on the site logistics pla
required to comply with this policy. Any designated areas within the u
between the Tenant fitout contractors and Meraas with formal recordin
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
15/81
6.4: PERMITS TO WORK OUTSIDE THE UNIT
Any works to be executed outside of the unit must be done so in accordaand Safety procedures. A permit is to be obtained via AFC and full Method
Assessment will be carried out by the Tenant fitour contractors and be app
to issuing said permits. Copies of all permits to work should be displayed o
to allow easy inspection by the AFC HSE staff.
6.5: COSHH REGISTER
A list or register of all materials kept in the unit that are hazardous to hea
and a copy displayed on the unit notice board. Where material safety dat
supplied with the materials, a copy of the MSDS must also be retained in t
available should an accident occur. The MSDS must be shown to the att
doctor in the event of an incident. All hazardous material to be removed
same day/night shift. All records pertaining to COSHH within the unit will b
by Meraas.
6.6: TOOLBOX TALKS
AFC recommend that the tenant fitout contractor conducts a daily toolb
workforce on the current days work activities and ensure that all and any ha
the job are identified and controls put in place. This should be discussedMeraas.
6.7: HOUSEKEEPING
Good housekeeping in the unit is mandatory for the safety of the works an
their work locations are free from slip, trip and fall hazards created by poor
works areas shall be kept clear of all discarded packaging and other mat
fire hazard and waste material removed at the end of each shift to the des
marked on the attached logistics plan. The management of work within th
the management of Meraas.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
16/81
6.9: COMPETENT PERSONS
The Tenant/Tenant contractor must ensure that only trained and aupermitted to: (Meraas need to satisfy themselves that all personnel are com
Use and / or mount abrasive wheels
Use cartridge operated power tool
Operate technical equipment, tools, plant or vehicles
Work on high or low voltage systems
Work on fire alarm and other life safety equipment Work on gas systems
Work on water systems
Access plant rooms
Access roof areas
Work at heights
Erect scaffold or tower scaffold structures
Additionally, all management and supervisory staff must be able to demo
the supervision of their staff and, ideally be conversant in Arabic and Englis
Note: AFC will not be held responsible for carrying out checks on the above
6.10: FIRST AID BOX
All units are required to hold a first aid box containing sufficient items to cov
working within the unit. Regular checks are to be undertaken by the Tenan
Meraas to ensure compliance.
6.11: MISCONDUCT
The Tenant’s Fitout Contractors are to conduct themselves in a profes
manner at all times. AFC will not tolerate written, spoken or implied abus
site, and offenders will be removed for any misconduct.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
17/81
Failing to adhere to an instruction from any AFC management personn
Any other serious breach of health and safety rules and regulations
Talking on mobile, eating, sleeping, resting, listening music and otheperformed other than designated area
Drawing or writing inappropriate, offensive, rude, discriminative and v
sentences or sketches on walls, material or delivery packages
Not implementing or executing the works in accordance with AFC site
6.12: FIRE EGRESS PLAN
The Tenant Contractor must display a copy of Fire Exit or Emergenc
site within the unit.
Fire exit routes and vehicle access routes will be clearly explained in
Safety Officer. AFC will provide one copy of fire egress plan to Tenant
AFC will provide assembly point and plan to all Tenant Fitout Contract
7.0 WELFARE
7.1: TOILET FACILITIES
The Tenant Fitout Contractor and his subcontractors will be permitted to
toilets provided by AFC. These are located around the site and indicated on
(Appendix E). AFC is responsible for the regular cleaning and maintenance
Any person found defecating at any location other than the WC will be rem
Tenant Fitout Contractor will be fined the minimum 500AED to cover the
infected area. In case of repeated strikes, contractor will be removed
indefinitely.
7.2: DRINKING WATER POINTS
The AFC will provide ‘drinking water’ stations around the site as indicate
Pl E h T t Fit t C t t i t id it bl t bl l
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
18/81
AFC is responsible of maintaining these areas tidy and clean between th
that Tenant Fitout Contractors employees take all waste food and rubbish
this in the bins provided.
7.4: PRAYER AREA
AFC has a designated area for all contractors and subcontractors to
Rooms/Areas. Prayer Rooms/Area will be indicated on Tenant Logistic Plan
8.0 TEMPORARY POWER, LIGHTING AND WATER
8.1: TEMPORARY POWER SUPPLY
The AFC will be responsible for the distribution of a shared temporary singl
to all the Retail Units. AFC will supply distribution boards at 110V, in line
within the pricing document.
The Tenant Fitout Contractor shall submit a written application to Funtastic
it to AFC for action.
Any requirements for 220V or 380V power provisions are to be forw
Funtastic) for approval. Power supply more than 110V shall be supplied o
instruction by Meraas and it will be subject to extra charge and will be ma
work system managed via Meraas.
8.2: TEMPORARY THREE PHASE POWER SUPPLY
The AFC will supply, install and to maintain 3-phase, reduced voltage, 30Alarger units to allow the use of the following equipment:
Arc welder
Th di hi
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
19/81
The Tenant Fitout Contractor shall provide all task lighting to provide an ad
to install their works in a safe manner.
Fluorescent light fittings will be used. LED lights are also encouraged to b
lights.
8.4: TEMPORARY WATER SUPPLY
AFC will provide temporary water points within the units. The quantum of w
the pricing document.
The Tenant Fitout Contractor shall submit a written application to Fun
provision of temporary water supply in the Unit. The Tenant Fitout Con
length of time that this water supply is required.
8.5: CABLING AND SOCKETS
Tenant Fitout Contractor must use IEE regulations and HS code of practice
Industrial sockets must be used only. No open joints in cables. All cab
sealed with insulation tape. Meraas should ensure they are satisfied within
the units.
8.6: SAFE WORKING PRACTICE
Power Supply
Only 110V temporary power supply is to be used at site. It is the Tena
responsibility to manage the use of this power supply in accordance wi
wiring and connections shall be in accordance with the IEE Regulations, H
and AFC’s permit to work system (outside the unit). The Tenant Fitou
interfere with provisions installed by the AFC at any time.
Water Supply
The Tenant Fitout Contractor will be entirely responsible for the control and
Unit. The Tenant Fitout Contractor is alerted to the risk of water damage to
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
20/81
9.0 SECURITY OF UNITS
9.1: RETAIL UNIT SECURITY
The Tenant Fitout Contractor is entirely responsible for the security of th
their control. AFC accept no liability or responsibility for any loss, damage o
10.0 SAFE SYSTEM OF WORK, PERMISSIONS AND PE
Coordination, management, supervision and implementation of over
environment, security, various policies and logistics inside the unit is
Tenant/Tenant Fitout Contractor and will be fully managed by AFC.
10.1: WORK METHOD STATEMENT AND RISK ASSESSMENT
AFC will not be responsible for the checking, approval, administration
contractors activities within the unit.
Any works executed outside of the unit require a Method Statement and
prepared by the Tenant Fitout Contractor unit (including roof and basem
Statement and Risk Assessment in AFC format must be completed an
contractor for approval prior to execution of the works:
Identify all risks and hazards associated with the job.
Select a method of carrying out the job with the least risks or hazards i
Identify any safety requirements associated with the job.
Ensure all workers are briefed on the remaining risks and hazards.
(An example copy is attached for information and guidance ref Appendices
10.2: PERMIT TO WORK
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
21/81
It is encouraged that the Tenant’s Fitout Contractor adapts a Permit to Wo
the Tenant’s Fitout Contractor On-site Project Manager for all activities liste
Work on live ‘life safety systems’ – fire protection / alarms system
switches, panels)
On live mains supplies (gas, electric, water)
Cut and core concrete
Hot works
Confined spaces
Works involving MEWPs and Craneage Works on the roof areas
COSHH – Control of Substances Hazardous to Health
The Tenant’s Fitout Contractor is strongly encouraged to establish acce
other parties required to work inside their unit. AFC will not be responsib
participating in any works within the units.
10.3: HOT WORKS
A Hot Works Permit is required for any work involving open flame, heat o
welding, gas cutting, grinding, metal cutting, soldering, brazing, etc.
Contractor is required to ensure that all safety precautions as listed in the
applied before work outside of the unit starts (Refer Appendix G). The tena
need to liaise with Meraas for requirements within the building unit.
10.4: REMOVAL OF SAFETY CONTROLS
Safety controls are put in place to prevent accidents or incidents happenin
but are not limited to, edge protection (e.g. Guardrails, tow boards etc) an
and horizontal openings (shaft/riser covers). Before works commence withis to be formally issued to AFC to enable the removal of safety controls et
the unit, AFC’s responsibility for the management of Safe System of Wo
cease and it will be controlled and be responsible by Meraas. The Ten
complete a Temporary Removal of Safety Controls Permit (Refer Appendix
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
22/81
10.6: CONFINED SPACE ENTRY PERMIT
A confined space can be described as any space of an enclosed nature wdeath or injury from hazardous substances or dangerous conditions (e.g. la
of oxygen or poisonous gases present). Some adverse conditions may al
confined space but others may arise due to work being carried out (e.g. ga
welding or the use of solvents, adhesives, etc). Before any work can begi
outside of the unit a Work Method Statement, Risk Assessment and Confin
must be completed (Refer Appendix K).
10.7: ACCESS PERMIT TO ROOF AREAS
A permit is required before access will be granted to any roof area outside
roof space. The permit must detail the works to be carried out and be a
Tenant Liaison Manager (Refer Appendix P).
10.8: ACCESS PERMITRISER/LIFT SHAFTS
No access will be permitted to any riser or lift shafts without a permit to ente
for any work in the riser shafts and must detail the works to be carri
Contractor is required to ensure that all safety precautions as listed in t
applied before work starts.
11.0 MATERIALS DELIVERY AND ACCESS
11.1: SITE ACCESS
Access and egress arrangements may be subject to change at the discprivate vehicles will be allowed on site. There are no designated parking
parking is off site.
Security gates for access and egress have been established and these mu
b l ki t it (Pl l i ti l tt h d f d
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
23/81
For access to the Tenant’s specific unit refer to the logistics plan (Refer Ap
also includes direction for units without rear access.
11.2: BULK DELVERY
All bulk deliveries are to be notified to the AFC using the Delivery Advice F
name, telephone number, delivery date and time is to be stated on the
(Refer to Appendix ).
The Tenant Fitout Contractor will be required to give 3 working days notic
ensure arrangements are in place to accommodate same.
All deliveries will be met by a representative of the Tenant Fitout Contracto
and escorted to the designated loading bay indicated on Tenant Logistic Pl
E2).
Each delivery will be given 1 hour in the loading bay as a general rule. Unp
be accommodated if there are vacant delivery slots, however there ar
available and unplanned may be turned away.
A Mobile crane (35 ton) and/or telehandler will be provided to Tenant F
request (Refer Appendix S) for material handling outside the unit. This will
unloading, loading and relocation (one time relocation). In the first instan
Material delivery will go to Tenant Liaison Manager who will organize site lo
case of any changes, TFC will be notified accordingly.
11.3: MATERIAL OUT-PASS
The Tenant Fitout Contractor can remove unused or excess material, toosite only through submission of Material Out-pass form (Refer Appendix T
given to Morganti for approval who shall be responsible to check that ta
machinery belongs to Tenant Fitout Contractor. No vehicles will be allo
without this pass in place.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
24/81
AFC will control access and egress to and from the site for deliveries and p
is advised that other construction works will be running concurrent to thei
the Developers areas and in adjacent areas being serviced via the same init is vital that Tenant’s and their representatives comply with all access and
ensure minimum delays.
11.6: TENANT’S PERSONNEL SITE ACCESS PASSES
On completion of the AFC site induction, all personnel will be issued with a
the security pass. First issue of the card will be free of charge. The ca
Operatives at all times to gain access to the site. Anyone without a pass w
the site. Passes are also to be carried at all times when on site and T
required to show their passes when requested by site security or AFC perso
There will be a charge for replacement of passes of 200 AED each.
No security card, no entry to site.
A security card is not issued as a sign of HSE Induction has been carr
issue safety induction sticker to be placed on a safety helmet at a visib
The Tenant Fit-out contractor is to issue AFC with an attendance
presentation on site no later than 9:00AM each day. A copy of this is
Meraas.
11.7: VISITORS PASSES
All Tenants personnel requiring infrequent access to the site for a period
(visitors) will be required to attend Main Contractor visitor safety induction
sign the Visitors Site Safety Briefing Form (Refer Appendix C) and assure t
set of Personnel Protective Equipment (safety boots, safety helmet, safety
and high visibility vest) before being allowed safety induction and access to
Visitors will be provided with a temporary visitors pass for the duration
Visitors pass is valid for one visit only. If a visitor requires multiple vis
attend visitors safety induction again.
The Tenant is required to ensure that a member of their site based
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
25/81
11.8: DELIVERY/LOADING DOCKS
It is the Tenant’s responsibility to ensure that their delivery drivers are informemanual.
Please refer to the site logistics plans Appendix E1 & E2 for location of
area and location of loading docks.
On arrival the driver must have the name and number of the retail
delivering ready to present at the gate on addition to full PPE (Refer Ap The delivery must be met at the gate by a Tenant Fit-out representativ
The Holding area queues are coordinated with the colour coded loadin
When the driver is given permission he must proceed directly to the c
bay following the colour coded signs with his escort.
The driver must display his colour coded card given to him on entry in
Drivers must not obstruct any route, be it vehicular, pedestrian or eme
the permission of AFC. Vehicles found blocking access routes will be removed from the site.
Drivers will be required to leave some form of security at the gate (
card) to ensure that they return the colour coded card when leaving the
The colour coded card will show the route they are to take to the gate
site to the loading bay applicable for their delivery.
The Tenant Fitout Contractors shall meet delivery at entrance and
deliveries with entrance gate opening hours. If the gates are shut on arrival the drivers must not obstruct the Public
Only 3 delivery vehicles per unloading bay are will be allowed to ente
time until they have unloaded and exited the retail site to ensure cong
there is sufficient room at the loading bays to unload in a safe and orde
A loading bay coordinator, security guard(s) and banksmen will be sta
area. The loading bay/banksmen will direct the delivery vehicles into
bay area. Security guard(s) will control access into and egress from the build
permitted to enter the building and must remain with their vehicles to
situations, their vehicles can be moved quickly from the loading bay ar
Each Tenant Fitout Contractor will be required to liaise with their own
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
26/81
Goods or materials left unattended at unloading areas will be dispos
costs to the Tenant.
All materials (unless otherwise approved in writing by AFC) mustloading points via back of house corridors, using goods lifts (where a
the site logistics plan.
The basement Car Park may be used to deliver materials to the up
through the Car Park will be advised and controlled by only AFC. The
will be subject to AFC change due to completions of the Car Park floor
The Tenant Fitout Contractor is advised of the following physical con
size and weight of deliveries thought the Car Park entrance:
o Maximum Headroom 2200mm AFFL (Ramp 2, refer to A
o Maximum Headroom 4300mm AFFL (Service Ramp refe
o Permissible Live Load 30 tons total (truck plus load)
11.9: LIFTS
Tenant Fitout Contractors are to note the sizes of the lifts and doors.
Lifts in building 1, 2, 3, 6 & 8 will be made available. If additional l
agreement to be arranged with Landlord (Refer to Appendix E1 & E2 fo
When scheduling deliveries and maximum sizes of materials (note pro
inside of lift cars).
Lifts will be operated by AFC personal.
Any damaged caused by Tenant Fitout Contractors will be charge
Tenant.
Maximum lift load is 1800kg.
Lift operating time is from 6.30am to 5.30pm.
11.10: OVERSIZE DELIVERIES
Any material which is too large to fit into a lift shall require special arra
for vertical transportation which shall be at the Tenant’s cost.
Prior arrangements must be made with the AFC Tenant Coordinato
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
27/81
11.12: STORAGE AREAS
No storage is available on site and tenants must arrange “just in timdirectly within the constraints of their unit. Due to logistic limitations a
as sand, gravel, etc. has to be delivered in 25kg or 50kg bags.
11.13: LOADING BAY COORDINATION
The Tenant will be responsible for all Loading Bay Coordination.
11.14: HEAVY LIFTING
All lifting operations to be carried out in accordance with AFC safety pr
Details about delivery date, time, load description, size, weight and pla
submitted to AFC through Heavy Load Lifting Request (Appendix V) 48
hours in advance if additional plant has to be provided. With Heavy Load Lifting Request, roof layout with exact location has to
Engineer/Architect (WSP) approval
Required plinths or/and up-stand location shall be checked by Tenant
Additional plinths or/and up-stands build requests are to be coordinate
EI to Main Contractor.
Main Contractor is obliged to provide 35ton crane for lifting purpose. A
crane greater than 35ton must be instructed by Landlord prior to arrang
12.0 TEMPORARY WORKS (Outside the unit)
Temporary works may be defines as: “Any temporary structures required to a
permanent structure or used to support a permanent structure during its erecti
self-supporting”.
Where applicable, all temporary works must be designed and checked, and i
AFC Temporary Works Procedures and must be properly checked and appro
the AFC Temporary Works Coordinator and should therefore be presented
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
28/81
13.0 ACCESS EQUIPMENT AND SCAFFOLDING
13.1: ACCESS EQUIPMENT AND SCAFFOLDING:
Will be the sole responsibility of the Tenant Fitout Contractor.
System scaffolding, Putlog type scaffolding can be used for demandi
works. Aluminium scaffoldings can be used for light weight works or
(up to 4m). Static and Mobile scaffolding tower can be used.
Scaffolding to only be erected, altered and dismantled by third party tra
Scaffolding to be inspected by third party certificated Scaffolding sup
used only after scaffolding approval and green tagging.
Frequency of inspection will be immediately after erection. Any alterati
weather such as storms, heavy rains etc., and if scaffolding is hit by a
as vehicle or lifting operation requires new inspection and approval.
Tagging system:
o Green Tag – inspected - clear to use scaffolding
o Yellow Tag – inspected, need to be rectified - don’t use scaffo
o Red Tag – not inspected - don’t use scaffolding
Barriers and protections within the unit to be managed by Tenant Fitou
AFC do not envisage being involved with Tenant scaffolds as all works wi
the unit.
14.0 REMOVAL OF TENANT’S WASTE
It is the Tenant’s responsibility to place all waste in designated skips or w
remove; with the exception of hazardous waste.
No loose waste is to be placed outside of tenant’s demises. Tenants
not complying with this will be issued with a clean up notice. This will b
a hazard to health in which case it will be immediate. Photographic e
and will be produced with the improvement notice (Refer Appendix O)
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
29/81
soiled bandages) or any food waste which is to be removed by th
contractors at the end of each working day.
15.0 PROTECTION OF WORKS
15.1: GENERAL RESPONSIBILITY
The Tenant’s Fitout Contractor must ensure that AFC works/finishes are during the movement of materials, plant, equipment and personnel. The c
such works/finishes will be recovered directly from the Tenant.
The Tenant/Tenant’s Fitout Contractor is responsible for the protection of th
for the finishing, sealing, provision of trims between his works at the adja
The protection measure to be applied by the Tenant’s Fitout Contracto
protection must be agreed with AFC prior to commencement of the Tenanwill be charged the full cost of rectification of any damage caused to the wo
The Tenant/Tenant’s Fitout Contractor shall not alter any work done by oth
pay the full costs for the works of others to be modified. Modification will be
the Tenant’s Fitout Contractor, AFCs relevant subcontractor and the AFC.
15.2: PROTECTION OF LANDLORD’S AREAS
Floors in Landlord’s areas outside the units are to be left clean and tidy at
must be kept inside the units and not left outside causing blockages to acce
Movement of materials and bulky equipment is only permitted within th
specified within this document, or approved by AFC.
16.0 HOARDINGS (IF REQUIRED)
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
30/81
Landlord provided unit identification sign to be removed from inside t
temporary AFC hoarding and repositioned on the Tenants hoarding at
The Tenant will require written approval from the Landlord to removeduring the Tenant’s works.
Compliance with the relevant fire regulations must be maintained at all
Tenant need to provide floor protection in low level area within hoardin
The Landlord reserves the right to change the specifications/design and loc
giving the Tenants written notification of any change required.
AFC will not be responsible for ensuring compliance of the above.
17.0 INSPECTIONS AND MONITORING
AFC if directed by Meraas, reserves the right to:
Inspect units and have the Tenant carry out any reasonable request in
reasonable time to satisfy themselves that all requirements of the Site C
being followed.
Be present to witness the testing of the mechanical and electrical installatio
Supervise any connections to the Landlord’s services.
18.0 CO-ORDINATION MEETINGS
Cooperation and coordination is essential to ensure communication is m
stake holders on the project. This will include attendance by the Tenants a
at various meetings required by AFC and/or the Client.
19.0 PLANT, EQUIPMENT AND TOOLS
19.1: PLANT:Plant equipment and tools are the responsibility of the Tenant Fitout Contra
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
31/81
20.1: FIRE ALARMS SYSTEMS
Final connection for the Tenant’s unit to the Landlord’s fire alarm system AFC following prior notification to and approval from the Client Managemen
to notify the Landlord when the final connection has been comple
subsequently test the system to ensure that the fire alarm is operational.
rectified immediately by the Tenant.
20.2: ELECTRICAL SUPPLY
AFC shall provide temporary single phase 110v power to a supply point in
Tenant’s use throughout the Fitout period if a permanent metered power s
220v power supply will be provided only on special request and upon landlo
For any works require power supply more than 110V (220V & 380V) E
obtained.
20.3: WATER
Temporary building water shall be provided by AFC to Tenant Fitout
location. Location to be coordinated with AFC Liaison Manager.
20.4: GAS
If supplied, gas fittings and gas pipes are not to be interfered with or adjuste
written permission of AFC.
20.5: CONNECTION TO PERMANENT SERVICES
The Tenant provided all commissioning provisions such as water, fuel
completes all commissioning works on a stand-alone basis and disposal of
be the responsibility of the Tenant.
It sho ld be noted that the Tenant cannot interfere in an a ith on
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
32/81
systems of data recording or BMS, etc. AFC shall not be responsible for
costs.
MAIN POWER CONNECTION:
No un-authorised connection to electrical distribution network shall be perm
for connection into the Main Contractor systems shall be subject to an
signed by both parties. The following needs to be considered:
The Tenant has to complete his electrical installation within theinspection for approval to Tenant witnessing authority.
The Tenant has to obtain all necessary DEWA NOC’s
The Tenant has obtained DEWA inspection and clearance
All earthing works to be completed and inspected by the Meraas
All metering is provided by Tenant to meet Meraas and DEWA requ
Testing and commissioning of the electrical system to be completed
All relevant documents such as, but not limited to, DEWA Ncommissioning test sheet report, DEWA clearance, etc. Shall be c
to AFC along with formal Power On Request (POR) for approval.
When POR is approved, WSP and Funtastic shall meet at required
energize the Tenant unit.
A 2 day notice period shall b required for this final connection.
No unauthorised connection to the Main Contractor electrical dis
be permitted and all connections shall be subject to an agreed PTboth parties.
Meraas will be fully responsible for managing the above.
WATER, DRAINAGE & HVAC CONNECTION:
No break-ins or tie-ins to either water, drainage or HVAC systems shallrequests for connection into the Main Contractor systems shall be subje
system, signed by both parties. The following needs to be considered:
The tenant should be instructed to use the same chemical treatme
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
33/81
All relevant documents shall be collated and submitted to AF
Connection Request (CR) for approval.
When CR is approved, AFC, WSP and Meraas shall meet at requwill complete the connection.
Meraas will be fully responsible for managing the above.
TELEPHONE AND DATA SYSTEMS CONNECTION:
Telephone and Data System requests shall be direct between the ten
operator.
LPG CONNECTION:
LPG installation within the Tenant unit shall be the responsibility of the Ten
need to use Gulf Gas (Specialist Contractor whom installed the base build
their installation. The Client is to ensure the metering strategy is clearly und
of connection. Upon completion and certification of the LPG installation, theconsidered:
The Tenant has to complete his system installation within the
inspection for approval to Tenant witnessing authority.
A request form with clearance certificates should be submitted to A
connection.
This connection shall only be available after the AFC Main Systcommissioned and available for connection.
All relevant documents shall be collated and submitted to AF
Connection Request (CR) for approval.
A 5 day notice period shall be required for this final connection.
When CR is approved, AFC, WSP and Meraas shall meet at requ
will complete the connection.
Meraas will be fully responsible for managing the above.
FIRE FIGHTING CONNECTION
Sprinkler installation and connection shall be subject to a written request
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
34/81
A 3 day notice period shall be required to make the final conne
interface signals and flow valves, etc.
Meraas will be fully responsible for managing the above.
FIRE ALARM CONNECTION
Sprinkler installation and connection shall be subject to a written request
and re-test all flow and interface devised. The following needs to be conside
The Tenant shall obtain all necessary DCD NOC’s.
The Tenant has to complete his Fire Alarm system installation an
unit and to raise an inspection for approval to Tenant witnessing au
The Tenant shall obtain DCD inspection and clearance to energise
Testing and commissioning of the sprinkler system shall be comple
All relevant documents like, but not limited to, DCD NOC, approved
test sheet report, clearance certificate, etc. shall be collated and suwith formal Connection Request (CR) for approval.
A 3 day notice period shall be required to make the final conne
interface signals and flow valves, etc.
Meraas will be fully responsible for managing the above.
21.0 BASIC SITE RULES
All staff operating within the boundary of the retail site are required to follo
as all other contractors. These basic site rules are shown at Appendix A to this
APPENDICES
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
35/81
APPENDIX ABASIC SITE RULES(SITE CONSTRAINTS MANUAL)
All Tenants, Tenant Fit-Out contractors, contractors, sub-contractors, suppand any other agents acting on behalf of or for Tenants are required to follow the scontractors.
The following rules apply:
Ear and respiratory protection must be worn when the task requires. Full PPE must be worn at all times - Safety footwear, HiViz vest, safety he
and gloves. Know the emergency evacuation procedure and where the assembly points Only use the access and egress routes designated for your unit(s).
All injuries, however trivial, must be reported and recorded in the Site Acwho and where the first aiders are located and how they are identified. Diabetics, asthma & epilepsy sufferers and persons using drugs for medica
report their condition to their managers to allow suitable work to be allocatewill be treated confidentially.
Alcohol, drug and solvent abuse is not permitted on site at any time. Anbeing under the influence of alcohol / drugs / solvents whilst attempting to erefused entry.
Anyone found on site under the influence of alcohol, drugs or solvents will
liable to disciplinary action, which will involve removal from site, and/or Polic A high standard of housekeeping shall be maintained - keep welfare faciland put all rubbish in the bins provided.
No fires are allowed to be lit on site, whatever the circumstances. This contract operates a waste-recycling scheme where waste is to b
separate skips and anyone found abusing the system liable to disciplinary a Consumption of food on site is prohibited, except within offices, welfare
designated areas. Smoking is only permitted in designated smoking areas. Anyone cau
unauthorized area may be removed from the site. Radios and Walkman personal stereos, etc. are not permitted on site. Do not indulge in horseplay. Anyone involved in fighting will be permanentl
site. Urinating or defecating on site except in the toilet facilities provided is
Offenders will be permanently removed from site. Personnel are requested not to cause a public nuisance keep swearing
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
36/81
APPENDIX ABASIC SITE RULES
(SITE CONSTRAINTS MANUAL)
Reversing on site is forbidden except under the control of a trained Banksmen.
Passengers must not be carried on items of plant except where the manufacturer’s fitted passenger seat.
Do not stand at the back of, or on the blind side of machines, plant or vehicwithout warning. Make sure the driver/operator knows you are there.
Engines are to be switched off when plant is not in use or left unattended.
Fuel and oil spillage' are to be reported and cleaned up as soon as practicwhere the emergency spillage kit is located.
Scaffolds must not be altered except by trained /competent scaffolders. Mobonly to be erected and altered by trained personnel.
Edge protection in the form of toe boards, handrails and mid rails are to be scaffolding including mobile towers that exceed 2m in height. However, Riskwarrant that these measures be taken for platforms lower than 2m.
Full body safety harnesses must be worn when working at height and securesupport the full weight of a falling person.
Ladders are only to be used for short duration work and must be either tied anfirmly held by a co-worker before use.
Vertical and Horizontal voids are not to have the protection removed until theWork has been received from JV HSE team.
Do not enter barricaded off areas unless authorized to do so. No excavation is to be entered unless authorized to do so by a JV manager.
Lifting Equipment must have a valid 6 month test certificate. Damaged slings oused.
Trained and authorized banksmen / riggers / slingers are required during all lifti
Do not walk or drive through a crane slewing radius if there is material suspenhook. Always look up when approaching a crane, and if necessary find an alter
Material Safety Data Sheets are required prior to the use of any paints, solventread the instructions and apply them.
Wear any additional PPE / equipment specified. Ensure you provide your staassessment for the particular product.
Do not decant COSHH materials into unsuitable or unmarked containers.
Under no circumstances should oil, paraffin or flammable solvents be kept in stored separately and in a locked metal mesh container with adequate fireavailable at the location
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
37/81
APPENDIX APERMITS ARE REQUIRED FOR THE FOLLOWING OPEOR ADJUSCENT TO AFL WORKS:
Permit to work on live services.
Permit to Access the roof areas.
Permit to Discharge (waste water).
Permit to enter (Confined Spaces).
Permit for Hot Works, including welding brazing, grinding and cutting.
Permit to Remove Horizontal and Vertical opening protection.
Permit to Provide Electrical connection.
Permit for isolation of hazardous energy (Lockout/Tagout).
The main contractor (AFC) retains the right to introduce and enforce additio
required at any time without prior notice.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
38/81
APPENDIX B
SITE SAFETY INDUCTION BOOKING PROCESS
All Tenant Fit-out contractors are required to attend a site safety induction before b
City Walk site. The Site Safety Induction Booking Form can be found appendix B1 to this T
The Site Safety Induction and the system orientation will take approximately 90 minutes to
Complete all details in the Booking Form and deliver to AFC Senior HSE Advisor M
him at:
and must be copied to Funtastic team.
On receipt of your booking form, HSE department will arrange a date and tim
induction. They will call the contact person shown on the booking form and info
have any problems with the date and time arranged you must contact the above
reschedule your inductions. Please ensure that your staff arrives on time for the in
All staff must arrive for the induction with the following items:
o Personal Protection Equipment (PPE): Safety Helmet, HiViz Vest, Safety
Boots
o Proof of Identification: Original National Identity Card or Passport
Personnel arriving without the above items will not be inducted or allowed on site
Personnel will first be checked against the names on the booking form and thei
then take all personnel to safety induction.
Personnel will then be handed over to the Tenant Contractor’s senior supervisor
correct access routes to and from their units.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
39/81
APPENDIX B1
TENANT FITOUT CONTRACTOR / VISITORS – SITE SAFETY INDUCTION BOOKING
FROM (Company Name): NAME OF CONTACT PERSON: TELEPHONE NUMBER:
UNIT NUMBER: UNIT TRADING NAME: EXPECTED START DATE:
____ / ____ / ____
Enter the full details of all staff who will be working on the City Walk 2 project in the building number as shown abo
different buildings. This form is to be submitted at least 48 hours in advance of required induction date. This form has to be
further processing and record. After review and approval the same shall be forwarded (CC’d) to AFC HSE Safety Man
Tenant Liaison Manager ([email protected] )
Full Name, as it appears onNational Identity Card or Passport
Job Title Nationality Dat
__
__
__
__
__
__
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
40/81
APPENDIX B1
TENANT FITOUT CONTRACTOR – SITE SAFETY INDUCTION BOOKING FORM
Full Name, as it appears onNational Identity Card or Passport
Job Title Nationality Dat
__
__
__
__
__
__
__
__
__
__
__
__
__
__
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
41/81
APPENDIX CVISITOR SAFETY BREIFING
This site safety briefing sheet must be read and signed by all visitors to the City Wa
the sheet to indicate their understanding and acceptance of the conditions of entry as detailed
Stay with your host at all times.
The minimum personal protection equipment (PPE) required on site is a hard hat, s
glasses, gloves and high visibility vests. You must bring your own PPE as described
SITE ACCESS.
Additional PPE, such as ear protectors, may be required if you are visiting areas wit
cutting/grinding operations and will be provided by your host prior to arriving on site.
Do not approach working plant or machinery unless the plant has stopped work and
clearly
Do not enter barricaded areas or walk inside edge protection markers.
Obey all instructions given to you by the site Engineers or Safety staff.
No private vehicles are allowed on site. All private vehicles must be parked in the de
CFC Tenant Fit-Out Offices. AFC nor CFC will not accept responsibility for any dam
may occur.
On arrival you will be issued a visitor pass which must be worn at all times whilst on
On leaving the site, please check out with reception and return your visitor pass.
Visitor Name (Print): ________________________________________
Visitor Signature: ________________________________________
Company: ________________________________________
When signing this form the host is confirming that they have previously undergone a
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
42/81
APPENDIX D City Walk
GATE PASS
FROM (Company Name): TO (Consignee):
REMOVED FROM (Location): VEHICLE TYPE and COLOR:
VEHICLE REGISTRATION:
Item No. Make/Model Full Description of Item Qty Serial/Reg No
Sub-Contractor Use Only – To be signed by the Project Manager Security Gate Only
I, the undersigned, herby declare that the above items are the property of our company. This form is to be returned to the DFC Tena
Name: Security Guard Name:
Job Title: Security Guard Work No.:
Identity Card No.: Gane No.:
Signature Signature
Date: Date and Time:
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
43/81
APPENDIX E1
SITE LOGISTIC PLAN – BASEMENT
SAFAROAD
Service Ramp
Ramp 2
LABOUR MESS
APPENDIX E2
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
44/81
SITE LOGISTIC PLAN – GROUND FLOOR
Service Ramp
Ramp 2
TOILETS
S
A
F
A
R
O
A
D
POLI CE STATI ON
TOILETS
1
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
45/81
APPENDIX FSITE ATTENDANCE BOOKING FORM
This attendance sheet forms part of the emergency evacuation procedureas such must be completed and updated on daily basis by the senior responsible peEach Unit must complete an attendance form daily and post the form on the exit doof an emergency evacuation, this form must be taken by the senior responsible
assembly point allocated to your Unit and all workers checked off. Also see the further details.
Name of Senior Person in Unit:
Title:
Date:
Unit No.: Assembly Point:
Company Name: ________________________________________
# Name ID No.OnSite(tick)
1
2
3
4
5
6
7
8
9
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
46/81
APPENDIX GHOT WORK PERMIT – CLASS A
WELDING GAS CUTTING BRAZING GRINDING
Issue No. AC Date
Section - I DETAILS OF THE PERMIT RECEIVER
Project / Section Location(s)Permit Receiver (Engineer) Contact Number Mobile
DETAILS OF THE PERMIT HOLDER
Permit Holder (Supervisor) Contact Number Mobile
Name of the Operative Employee Number
Section - II PERMIT VALIDATIONS
Date Issued Valid Till (Not more than 1 shift)
Time Issued Valid Till (E
HOT WORK VALIDATION SHALL NOT EXCEED THE STATED D
Section - III PRE-REQUISITE (Work may be stopped if one of the following
tick for YES and cross for NO Yes N/A tick for YES and cross f
A Flammable materials removed from location K Appropriate working platform
B Welding gensets terminal insulation L Safety/Warning signs in place
C Adequate earthling M Adequate ventilation
D Area of work clean and dry N Condition of the welding cable
E Appropriate fire extinguisher provided O Adequate illumination
F Operatives trained in using fire extinguisher P Flash back arrestors – Gas cy(at least 3m away from workface)
G Fire blankets (non f lammable) provided Q Cylinders kept in trolley an
H Fire watch personal R Regulators in good conditio
I Area barricaded S Gas test required
J Appropriate PPE provided T Isolation of equipment requ
Declaration by the Permit Receiver Declaration by th
I_________________ representing _________________ herebydeclare that I have checked the location and the operative hasbeen briefed about the emergency procedure and a toolbox talkgiven on using the fire extinguisher to ALL involved in the activity.(Attach Copy) N.B. A Fire Warden will remain at the location of theHot Working activity and will undertake checks for up to 1 hour ft th h t k h d
I_________________ represhereby declare that I have chemployees have been briefed aand a toolbox talk given on Hotactivity. (attach copy)
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
47/81
APPENDIX HHOARDING FOR TENANT FITOUT
On the Unit access date a hoarding is required to be fitted by the Tenan
scheduled to be fitted on this date and is to remain in position until the shop front ins
All fitout works are to be undertaken behind a hoarding which the Tenant mat his own costs.
Hoarding is to be positioned 1200mm outside from the demise line or as clobuild conditions.
Of MDF construction 2.4m high with a Perspex vision panel, painted whside as shown above.
Dust protection to be supplied and fitted by the Tenant on a triangular wfixed from the top of the hoarding to underside of the shop-front bulkhead.
Dust protection to be clear PVC sheet and to be fixed by nails to a trianguor 4x4inch timber fixed to the slab soffit.
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
48/81
APPENDIX IREMOVAL OF SAFETY CONTROLS – PERMIT TO WORK
Issue No. AC DateBrief description of the work and location:
REMOVALREQUIRED FOR
BLOCKWORK
FINISHING ACCESS OTHERS (
Section - I DETAILS OF THE PERMIT RECEIVER
Project / Section Location(s)
Permit Receiver (Engineer) Contact Number
DETAILS OF THE PERMIT HOLDER
Permit Holder (Supervisor) Contact Number
Section - II PERMIT VALIDATIONS: one shift ONLY
Permit issue details Date: ________________ Time: _______________ NO EXON THPermit expiry details Date: ________________ Time: _______________
This permit authorises the Removal of Safety controls for entry / work to Al l work entailed after entry shall be covered by the appropr iate WORK PE
Section - III PRE-REQUISITE (Work may be stopped if one of the following
tick for YES and cross for NO Yes N/A tick for YES and cross fo
A Has a risk assessment been completed? F Will the area be monitored du
B
Have a Work Method Statement been
completed G
Have the areas been identifie
agreed?
CIs there a contingency plan during restbreaks?
H Has the method of fail rest be
D
Has authority been given to a nominatedperson responsible for removal and re-instatement of the safety controls?
Nominated Person __________________
IDoes the receiver of the PTWhis workers cannot leave the the covers are replaced?
Details of Employee working onthe opening.
Name, ID No., Trade
Declaration by the Permit Receiver Declaration by th
I_________________ representing _________________ herebydeclare that I have checked the location and that the PermitHolder has been briefed about the hazards of the task and the
d
I_________________ representideclare that I have checked the have been briefed about the haz
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
49/81
APPENDIX J
Issue No.
Section – I
Project / SectionPermit Receiver (Engineer)
Permit Holder (Supervisor)
Name of the Welder
AC/
Location (s)Contact Number
HAZARDOUS MATERIALS – PERMIT TO WORK
Date
DETAILS OF THE PERMIT REC
DETAILS OF THE PERMIT HOL
Contact Number
Employee number
Section – II
Date issued
Time Issued
PERMIT VALIDATIONS
Valid Till
Valid Till
Section -111 CATEGORY OF COSHH MATERIAL (PLEASE TICK)
IRRITANT TOXIC HARMFUL CORROSIVE HIGHLY
Brief Description of the work involving the COSHH Material:
Section – IV
A
B
C
D
PRE-REQUISITE
Yes
(Work may be stopped if one of the foll
for YES and X for No for YES and X for No
Has the MSDS been read and understood?
Has the appropriate PPE been issued?
Has a WMS and RA been approved ?
Is there a controlled issue process in place for theCOSHH material to be used?
NA
E
F
G
H
Is there a need for rethe material?Is forced air ventilation
Are air extraction fans
Is there a procedure fused materials?
Declaration by the Permit Receiver
I_________________ representing _________________ herbydeclare that I have checked the work location and the PermitHolder has been briefed about the inherent hazards andemergency procedures for working with this COSHH Material.
Declaration b
I_________________ reherby declare that I havethat the work party has bemergency procedures aCOSHH Materials
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
50/81
APPENDIX K
Issue No.
ENTRY REQUIRED FOR
Section – I
Project / SectionPermit Receiver (Engineer)
Permit Holder (Supervisor)
Section – II
PERMIT ISSUE DETAILS
PERMIT EXPIRY DETAILS
PAINTING
AC
FINISHING HOT WORKS
CONFINED SPACE ENTRY – PERMIT TO WORKDate
Others
DETAILS OF THE PERMIT RECE
Location (s)Contact Number
DETAILS OF THE PERMIT Holder
Contact Number
PERMIT VALIDATIONS
Date ____________________
Date ____________________
Time ________________
Time ________________
This permit covers ENTRY ONLY to a confined space.
All work entailed in effecting entry and after entry shall be covered by the appropriate W
Section – III
A
B
C
D
E
F
G
H
I
J
PREREQUISITE
for YES and X for No Yes
(Work may be stopped if one of the follow
NA
K
L
N
P
R
S
T
for YES and
If so, are the equipmen
Is the main source of su
Air intake system locate
Work Method Statemen
Adequate illumination t
Appropriate PPE Provid
Watcher(s) required?
Atmosphere in the Confined Space Tested?
Oxygen level is 19.5% (Should not be less/more)
Will the atmosphere be monitored during work?
Continuously/Periodically Specify Interval
Has the space been ventilated before entry?
Will ventilation be continued during work? (LEV)
Was the space found unacceptable?
If so, after ventilation was the area retested?
Have all routes of energy ingress been isolated/Plugged?
Will any other equipment be used in the space?
M Has the toolbox talk bee
O Preparedness for emerg
Q Will any Chemicals be u
Details of Employee working in the confined space
Name, Id.No. , Trade
Details of Equipment and/or Material being used
Declaration by the Permit Receiver
I_________________ representing _________________ herebydeclare that I have checked the location and all the employees
Declaration by the
I_________________ reprhereby declare that I have
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
51/81
INCIDENT REPORT FORM
Incident Report No:
Location/Unit No:
Type of Incident: (Tick where applicable)
Near Miss
Unsafe Act
Property Damage
other (Specify)
Asset Damage Fire
APPENDIX L
Contractor Name:
If Property Damage Caused By:: (Tick where applicable)
Personnel
Crane
Pallet Truck
other (Specify)
Tools Fire
Details Of Operator: (If applicable)
Name:
Time:
Employee No:
Date:
Trade/Jo
Nationa
Details Of Reporter
Name:
Time:
Employee No:
Date:
Trade/J
Nationa
Brief Description of Incident:
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
52/81
APPENDIX M ACCIDENT REPORT FORM
Location: Contract No :
TYPE OF Incident: (Tick where applicable)
Fatality
First Aid
Name:
Date :
Major Injury
Others (Specify):
+3 Days Injury Medical treatment C
DETAILS OF INJUREDEmployee No:
Time: Nationality:
Trad
Age
DETAILS OF INJURIES: (Tick where applicable)
Head Face Neck Back Shoulder Arms Wrist Hands Fingers L
TYPE OF INCIDENT
Struck Against (Running or Bumping)
Fall on Same Level (Slip and Fall, Trip Over))
Fall from Elevation to Lower Level
Caught Between or Under (Crushed or Amputated)
Environmental Release
Struck By (Hit By Moving O
Equipment Failure
Caught In (Pinch and Nip
Caught On (Snagged, Hun
Overstress/Overexposure/
Contact With (Electricity, Heat, Cold, Radiation, Caustics, Toxics, Biological, Noise)
NAMES OF WITNESSES:
Name:
Employee:Trade:
Name:
Employee:Trade:
BRIEF DESCRIPTION OF ACCIDENT:
CAUSATION FACTORS:
City Walk
Person injured does have insurance cover Y
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
53/81
APPENDIX N
TENANT FITOUT PROHIBITION NOTICE
This notice has been served for a condition observed in the Unit or surroundingimmediate risk that could result in ill health, personal injury or loss. The cond
unacceptable and the work stopped until the condition has been rectified.
Name of Inspector
Description of the Work/Activity:
Notice reference number AFC/PRO/Notice/ 000
S
Reason for Stoppage: State what immediate risk to ill health, personal injury or loss is
Actions required by Contractor: Time frame to be agreed at the time of the Observatio
Unit No. Work Location Date Time
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
54/81
APPENDIX O
TENANT IMPROVEMENT NOTICE
City
This notice has been served for a condition observed in the Unit or surrounding with the Local/National regulations or fails to meet industry best practice. The counacceptable and needs rectifying within the stated period.
Name of Inspector Notice reference number AFC/IMP/Notice/ 000
Description of the Work/Activity:
Reason for Stoppage: State what regulations have been contravened:
Actions required by site: Time frame to be agreed at the time of the observation:
Site Work Location Date Time
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
55/81
APPENDIX PPERMIT TO ACCESS THE ROOF
This permit is required for access to any part of the Mall roof areas and is valid Additional permits may be required for types of work that would normally require a permit eg Hroof areas will be granted without this Permit.
Section – I REASONS FOR ACCESSING ROOF
Detailed Description of Work and Area of Roof where work required:
Section – 2
Permit Receiver (Manager)
DETAILS OF THE PERMIT RECEIVERContact Mobile Number
DETAILS OF THE PERMIT HOLDER
Permit Holder (Supervisor) Contact Mobile Number
Section – 3
Date issued
Time Issued
Declaration by the Permit Receiver
I declare that I shall only authorise the work asdescribed above and shall ensure any additional permits,method statements and risk assessments, where required,are available before work starts. All areas where work iscarried out shall be cleared immediately after the work is
PERMIT VALIDATIONS
Date Valid Till
Time Valid Till
Declaration by the
I declare that I shalabove and shall ensure statements and risk assessmbefore work starts. All areas cleaned immediately after material removed from the roo
Name:
Signature:
Date:
PERMIT SIGNATORY (JV Tenant Liaison Manager)
Name:
Signature:
Date:
Section 4
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
56/81
APPENDIX QPERSONAL PROTECTIVE EQUIPMENT (PPE)
Safety Helmet
Safety Glasses
Safe
Safety Vest
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
57/81
APPENDIX RPROJECT TEAM DETAILS
Who Name Address Telephone
Developer
MERAASHOLDING
Emaar SquareBuilding 1, Level 3 &5
P.O. Box 123311Dubai, UAEUnited ArabEmirates
800 MERASS(800-637227)
Engineer/Architect
WSPBoulevard Plaza2502 Tower 1Downtown DubaiUnited ArabEmirates
+971 4 350-5000
Project Manager
MORGANTIEmirates HillsP.O.Box 73346DubaiUnited ArabEmirates
+971 4 434-4416
MEP Consultant
WSPBulevard Plaza2502 Tower 1Downtown DubaiDubaiUnited ArabEmirates
+971 4 350-5000
Main Contractor
AL FUTTAIMCARILLION
Control Tower, 20fl.Motor CityP.O.Box 1811DubaiUnited ArabEmirates
+971 4 333-1200
RDD Coordination
FUNTASTICP.O.Box 39996 Abu DhabiUnited ArabEmirates
+971 2 501-0888
APPENDIX S
TENANT FITOUT CONTRACTOR BULK DELIVERY BOOKING FORM
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
58/81
From (Company) To (Tenant Contractor)
Request Date Building/Unit No.
#Vehicle Size(e.g. 3T truck,
trailer, etc.)
Brief load description(e.g. block work 3 pallets, waterproofing 6 rolls, etc.)
Vehicle Plate No.Delivery
Date(dd/mm/yy)
DeliveryTime
(hh:mm)
Person to wthe gate and
(supe
1. ___ / ___ / ___ ___ : ___
2. ___ / ___ / ___ ___ : ___
3. ___ / ___ / ___ ___ : ___
4. ___ / ___ / ___ ___ : ___
5. ___ / ___ / ___ ___ : ___
6. ___ / ___ / ___ ___ : ___
7. ___ / ___ / ___ ___ : ___
Delivery is subject to AFC approval and shall be submitted th e AFC not less th an 72 hours prior arriva l to City
the site ONLY if arrived at specified date and time otherwise it has to wait for a free time slot (if available).Vehicle mus
Contractor responsible person (supervisor), directed to offloading location and escorted of the site as soon as offloading
(driver, co-driver, labourers etc.) must stay close to the vehicle at all times.
Tenant Contractor use only (at vehicle arrival time) Security Gate use only (at vehicl
Tenant Fitout Contractor welcomed person Security Guard name
ID number Gate No.
Signature Signature
Date & time Date & Time
APPENDIX T
SITE OUT-PASS
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
59/81
Material FromTenant Fitout
Contractor Company
From Building No.
From Unit No.
ItemNo.
Load Description Qty. Qty. UnitVehicle
make/modelVe
1.
2.
3.
4.
5.
6.
7.
Tenant Fitout Contractor use only Security Gate use only
I, the undersigned, hereby declare that above items are the property of our company. This for is to be returned to the DF
Tenant Fitout Contractor Supervisor Name Security Guard Name
ID number Gate No.
Signature Signature
Date & time Date & Time
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
60/81
APPENDIX URETAIL UNIT TEMPORARY PROVISIONS REQUEST
Tenant FitoutContractor Company
Building No.
Unit No.
ItemNo.
Provision Required From Until
1. Electrical supply 110V ___ / ___ / ___ ___ / ___ / ___
2. Electrical supply 220V ___ / ___ / ___ ___ / ___ / ___
3. Running water supply ___ / ___ / ___ ___ / ___ / ___
4. Water supply* _____ lit/__ ___ / ___ / ___ ___ / ___ / ___
5. Gas supply ___ / ___ / ___ ___ / ___ / ___
6. Other_________________ ___ / ___ / ___ ___ / ___ / ___
* Water quantity per time uni t (i.e lit/day, lit/week etc.)
COMENTS:
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
61/81
APPENDIX VHEAVY LOAD LIFTING REQUEST
Tenant FitoutContractor Company
Building No.
Unit No.
Delivery Vehicle Details Weight(in tons)
Size(WxHxD, in cm)
Required Plant*
* AFC will provide 35ton crane for lifting operations. Any other plant required has to be requested withinwill be subject to availability.
ApprovedMethod
Statement Attached
YES / NO Approved Risk Assessment
Attached
YES / NOWSP app
attached
DETAILED LOAD DESCRIPTION AND LIFTING PROCEDURE:
APPENDIX X
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
62/81
UNIT EMERGENCY NUMBERS
TENANT
Contact Person
ASSEMBLY POINT
APPENDIX Y
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
63/81
APPENDIX Y
AFC METHOD STATMENT AND RISK ASSESMENT SA
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
64/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
65/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
66/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
67/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
68/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
69/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
70/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
71/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
72/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
73/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
74/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
75/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
76/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
77/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
78/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
79/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
80/81
-
8/20/2019 Logistic Manual - Sept 2015 Rev.04
81/81