DEPARTEMEN PEKERJAAN UMUM DIREKTORAT JENDERAL SUMBER DAYA AIR INDUK PELAKSANA KEGIATAN PENGEMBANGAN WILAYAH SUNGAI JRATUNSELUNA Alamat: Jl. Brigjen S. Sudiarto 375, Telp. 723212-723070, Fax. 722239, Semarang MONTHLY MEETING FOR WORK PROGRESS AND PRESENT CONDITION OF LODAN DAM SUBPROJECT Lodan, November 2006 PTSL-II

description

Bendung Lodan

Transcript of Lodan

Page 1: Lodan

DEPARTEMEN PEKERJAAN UMUM

DIREKTORAT JENDERAL SUMBER DAYA AIR

INDUK PELAKSANA KEGIATAN PENGEMBANGAN WILAYAH SUNGAI JRATUNSELUNA

Alamat: Jl. Brigjen S. Sudiarto 375, Telp. 723212-723070, Fax. 722239, Semarang

MONTHLY MEETING

FOR

WORK PROGRESS AND PRESENT CONDITION

OF

LODAN DAM SUBPROJECT

Lodan, November 2006 PTSL-II

Page 2: Lodan

Location Map

SLIDE-2

Page 3: Lodan

LAYOUT OF LODAN DAM

Page 4: Lodan

OVERALL PROGRESS (as of October 2006)

• Physical Progress: 45% (~18% behind Schedule)

• Financial Progress: 38.56% (Rp. 13.086 billions)

• Contract Cost: Rp. 33,941,596,529.19

• Construction Period: 450 out of 610 days (Aug 28-Apr

2007)

SLIDE-4

Page 5: Lodan

PT. Wijaya Karya

KU.08.08/01/SKS PPSAJ/VI/2005

03 June, 200515,493,637,826.00 15,493,637,826.0000000000000

CONTRACT PRICE 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

(Rp.) Original Actual Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jun

( % ) ( % )

100.00 60.52

100 100

1 8.02 7.69 98 98

96 0.20 0.70 1.63 2.71 1.33 0.01 0.01 0.04 0.01 0.01 0.23 0.20 0.20 0.04 0.01 0.01 0.01 0.01 0.11 0.11 0.11 96

Target up to this period 7.33 94 94

Actual up to this period 5.26 92 0.34 1.05 2.79 0.46 (0.06) 0.04 0.18 0.47 0.00 92

Actual up to previous period 5.26 90 90

88 88

2 29.56 26.73 86 86

84 0.31 0.54 0.05 0.19 0.91 0.32 0.54 2.00 1.99 2.56 3.88 2.13 2.07 0.91 1.91 2.08 1.73 1.35 1.27 84

Target up to this period 17.48 82 82

Actual up to this period 18.65 80 0.38 0.95 1.43 0.94 0.64 0.41 4.35 0.20 0.09 0.78 0.95 3.74 3.79 80

Actual up to previous period 14.86 78 78

76 76

3 26.85 27.91 74 74

72 1.34 0.36 0.43 0.10 0.69 0.89 0.81 0.21 0.23 3.35 1.87 2.39 5.18 6.24 3.83 72

Target up to this period 10.27 70 70

Actual up to this period 11.10 68 1.05 0.20 0.32 1.20 0.86 2.10 3.16 2.22 68

Actual up to previous period 8.88 66 66

64 64

4 15.24 11.57 62 62

60 0.18 0.27 1.68 2.47 1.82 0.42 0.28 1.29 0.34 0.05 0.44 0.85 1.14 0.01 0.12 0.17 0.05 60

Target up to this period 9.23 58 58

Actual up to this period 8.40 56 1.04 0.11 1.55 1.46 1.34 0.79 0.88 1.24 56

Actual up to previous period 7.17 54 54

52 52

5 3.86 2.80 50 50

48 0.32 2.32 0.15 48

Target up to this period 2.80 46 46

Actual up to this period 1.73 44 0.59 0.08 0.06 0.07 0.94 44

Actual up to previous period 1.73 42 42

40 40

6 0.34 0.31 38 38

36 0.00 0.00 0.17 0.06 0.07 0.01 36

Target up to this period 0.31 34 34

Actual up to this period 0.10 32 0.08 0.01 0.01 32

Actual up to previous period 0.10 30 30

28 28

26 26

7 11.20 20.45 24 24

22 2.89 3.41 4.41 3.55 1.55 4.65 22

Target up to this period 15.80 20 20

Actual up to this period 0.00 18 18

Actual up to previous period 0.00 16 16

14 14

12 12

8 4.95 2.54 10 10

8 0.28 0.38 0.38 0.64 0.64 0.22 8

Target up to this period 0.00 6 6

Actual up to this period 0.00 4 0.02 (0.02) 4

Actual up to previous period 0.00 2 2

0 0

Total Target up to this period #REF!

Total Actual up to this period #REF!

Total Actual up to previous period #REF!

0.00 6.79 0.00 0.00 2.01 0.00 0.00 0.84 0.00 0.00 1.56 0.00 0.00 0.00 0.00 0.00

0.00 20.00 0.00 0.00 5.92 0.00 0.00 2.49 0.00 0.00 4.58 0.00 0.00 0.00 0.00 0.00

0.00 20.00 20.00 20.00 25.92 25.92 25.92 28.40 28.40 28.40 32.99 32.99 32.99 32.99 32.99 32.99

0.00 0.12 0.49 1.27 1.00 0.30 0.22 0.69 1.47 0.23 0.66 0.97 1.07 1.30 3.11 2.46

0.00 0.34 1.43 3.74 2.95 0.88 0.64 2.03 4.35 0.69 1.94 2.86 3.16 3.84 9.17 7.25

0.00 0.34 1.77 5.51 8.45 9.33 9.97 12.00 16.35 17.04 18.98 21.83 24.99 28.83 38.00 45.25

0.00 0.07 0.24 0.66 1.10 1.09 1.07 1.08 1.05 1.06 1.15 2.11 2.60 3.07 3.09 2.01 3.08 2.93 2.96 2.18 0.77 0.56 0.00

0.00 0.20 0.70 1.94 3.25 3.21 3.15 3.18 3.10 3.11 3.40 6.21 7.67 9.06 9.10 5.93 9.09 8.62 8.72 6.43 2.27 1.66 0.00

0.00 0.20 0.90 2.84 6.08 9.29 12.45 15.63 18.73 21.85 25.24 31.45 39.13 48.18 57.29 63.22 72.30 80.93 89.65 96.07 98.34 100.00 100.00

*) Temporary Schedule

Reference: Schedule Chart Wet Season (irrigation period)

Progress Chart Dry Season (un-irrigation period)

SECONDARY IRRIGATION

CANAL AND RELATED

STRUCTURE WORKS

MAIN IRRIGATION CANAL AND

RELATED STRUCTURE WORKS

( % )

`

WEIGHT

3,799,940,036.91

10,032,448,457.18

Billion Rupiah

( % )

Billion Rupiah

SCA

LE (%)

TOTAL CONTRACT AMOUNT (Excluding VAT) :

DESCRIPTION OF WORKS

SCALE(%)

Year 2006 0

33,941,596,529.19

Maintenance Period

TIME ELAPSE

Year 2007

Last Revised Projection

Billion Rupiah

Final Hand Over

Financial Accomplishment

(Payment Progress)

Physical Accomplishment

Physical Accomplishment

(Actual Progress)

Figure - LDN

610 Calendar Days JBIC Loan No. IP-505 for PTSL-II

Construction Schedule and Progress of Lodan Dam & Main Irrigation Works

Source of Fund

August 29, 2005 ~ May 1, 2007

Month: October 2006

Notice to Proceed (NTP)

Contract Effectiveness

( % )

Last Revised Projection

(Schedule Progress)

Financial Accomplishment

Contract No. JBIC Approval (NRC) July 25, 2005

Accumulated Financial Accomplishment (%)

Accumulated Physical Accomplishment (%)

Accumulated Last Revised Projection (%)

2,721,708,364.00

Central Java Province Date of Contract August 1, 2005 Project Location

Name of Contractor Contract Period

SECONDARY IRRIGATION

Year 2005

DAM

GENERAL ITEM

MAIN IRRIGATION CANAL

SPILLWAY

OTHER DAM FACILITIES

115,735,087.97

1,678,811,108.22

1,309,010,309.26

5,171,760,226.74

9,112,182,938.91

`

`

`

SLIDE-5

Page 6: Lodan

PRESENT SITE CONDITION

SLIDE-6

Present site condition

Page 7: Lodan

SLIDE-7

Main Dam ( view from upstream )

MAIN DAM (UPSTREAM VIEW)

Main Dam (View from upstream)

Page 8: Lodan

SLIDE-8

MAIN DAM (DOWNSTREAM VIEW)

Main Dam ( view from downstream )Main Dam (View from downstream

Page 9: Lodan

SLIDE-9

Slope adjustment of Downstream on Main Dam

DOWNSTREAM SLOPE ADJUSTMENT

Page 10: Lodan

SLOPE BLANKET AT LEFT-BANK

SLIDE-10

Page 11: Lodan

SLOPE BLANKET AT RIGHT BANK

SLIDE-11

Page 12: Lodan

Completed Instrumentation House

Completed Monitoring Panel

INSTRUMENT

HOUSE

SLIDE-12

Page 13: Lodan

SPILLWAY-SIDECHANNEL

SLIDE-13

VIEW FROM DOWNSTREAM VIEW FROM UPSTREAM

Page 14: Lodan

SPILLWAY-DOWNSTREAM

SLIDE-14

EXCAVATION AROUND

STILLING BASIN

CONNECTION OF SPILLWAY

WITH EXISTING RIVER

Page 15: Lodan

TREATMENT OF EXISTING RIVER

SLIDE-15

Treatment of Existing River

EXISTING WATER-SUPPLY PIPE

Page 16: Lodan

INCLINED INTAKE

SLIDE-16

Inclined Intake and Intate Box

Page 17: Lodan

Access Bridge and Weir in existing River

ACCESS ROAD BRIDGE AND DOWNSTREAM WEIR

SLIDE-17

Page 18: Lodan

BATCHING PLANT

SLIDE-18

Batching Plant Cliff on Right Bank

RIGHT BANK HILL

Page 19: Lodan

IRRIGATION SYSTEM

SLIDE-19

Completed Main Canal ( Concrete lining ) Completed Main Canal ( Stone masonry with Plastering )

CONCRETE LINING

(UPSTREAM REACH OF MAIN CANAL

STONE MASONRY LINING

(DOWNSTREAM REACH OF MAIN CANAL)

Page 20: Lodan

IRRIGATION SYSTEM

SLIDE-20

Existing Main Canal ( Not start yet )

EXISTING STONE MASONRY LINING

(MIDDLE REACH OF MAIN CANAL)

Page 21: Lodan

IRRIGATION SYSTEM-SECONDARY CANAL

SLIDE-21

Completed Secondary canal on Lodan Kiri Secondary canal on Lodan Wetan ( Not start yet )

STONE MASONRY LINING

(UPSTREAM REACH OF LODAN KULON

STARTING POINT OF LODAN WETAN

(NOT YET STARTED)

Page 22: Lodan

HEAVY EQUIPMENT MONITORING

SLIDE-22

Operation Broken

Heavy Equipment operation on September and October

Page 23: Lodan

COMPLETED EMBANKMENT WORKS

SLIDE-23

Completed Embankment on Main Dam Completed Embankment on Slope Blanket