  • About the cover: this years cover features Bridge No. 05009, June Road over the

    Mianus River, in the City of Stamford. This bridge rehabilitation project was designed by

    Alfred Benesch & Company, of Glastonbury, Connecticut, and was constructed by McNamee

    Construction Corporation, of Lincolndale, New York.

    Construction work began in August 2013, and was completed in August 2015 at a

    construction cost of approximately $1.6 million. Funding was provided by the State Local

    Bridge Program and the City of Stamford.

    Connecticut Department of Transportation

    Bureau of Engineering and Construction

    Division of Bridges

    Local Bridge Program 2800 Berlin Turnpike, P.O. Box 317546

    Newington, Connecticut 06131-7546

    Telephone: (860) 594-2078

    Website: http://www.ct.gov/dot/localbridge

    Program Manager:

    Priti S. Bhardwaj, P.E.

    Transportation Supervising Engineer

    State Funded Projects

    Francisco T. Fadul, P.E.

    Project Engineer

    Telephone: (860) 594-2078

    E-mail: [email protected]

    Federal Funded Projects

    Marc P. Byrnes

    Project Engineer

    Telephone: (860) 594-3389

    E-mail: [email protected]

    Gustavo M. Melo

    Project Engineer

    Telephone: (860) 594-2888

    E-mail: [email protected]

    http://www.ct.gov/dot/localbridgemailto:[email protected]:[email protected]:[email protected]

  • Local Bridge Program Manual FY 2017

    Page - I -

    TABLE OF CONTENTS

    TABLE OF CONTENTS I

    NEW IN THIS EDITION IV

    LESSONS LEARNED & OPPORTUNITIES FOR IMPROVEMENT IV

    CHAPTER 1: INTRODUCTION 1

    1.1 ABOUT THIS MANUAL ............................................................................................................. 1 1.2 DEFINITIONS ............................................................................................................................ 2

    CHAPTER 2: BRIDGE EVALUATION 5

    2.1 SUFFICIENCY RATING .............................................................................................................. 7 2.2 PRIORITY RATING .................................................................................................................. 10 2.3 PRIORITY LISTS ..................................................................................................................... 11 2.4 EMERGENCY CONDITIONS ..................................................................................................... 11

    CHAPTER 3: FUNDING PROGRAMS 12

    3.1 STATE LOCAL BRIDGE PROGRAM GRANT ............................................................................. 12 3.1.1 Grant Percentages ............................................................................................................... 13 3.1.2 Eligible Costs ...................................................................................................................... 15

    3.1.2.1 Preliminary Engineering: ................................................................................... 15 3.1.2.2 Rights-of-Way: .................................................................................................. 15 3.1.2.3 Utilities: ............................................................................................................. 16 3.1.2.4 Construction: ...................................................................................................... 16 3.1.2.5 Construction Engineering/Incidentals to Construction: ..................................... 16

    3.2 OTHER STATE GRANT PROGRAMS ........................................................................................ 17 3.3 FEDERAL FUNDS .................................................................................................................... 18

    3.3.1 Off-System Bridge STBGP ................................................................................................. 18 3.3.1.1 Replacement and Rehabilitation Projects........................................................... 20 3.3.1.2 Preservation Projects .......................................................................................... 20

    3.3.2 Pilot Program for 100% Design Funding ............................................................................ 22 3.3.3 Other Federal Programs ...................................................................................................... 22

    CHAPTER 4: PROJECT DEVELOPMENT 22

    4.1 PROJECT STEPS AND TYPICAL TIMELINE .............................................................................. 23 4.2 INITIATION/PRELIMINARY APPLICATION .............................................................................. 24 4.3 PROJECT DESIGN ................................................................................................................... 25

    4.3.1 Design Standards State Funds .......................................................................................... 25 4.3.1.1 Geometrics ......................................................................................................... 26 4.3.1.2 Life Expectancy ................................................................................................. 26 4.3.1.3 Load Capacity .................................................................................................... 27 4.3.1.4 Scour Analysis ................................................................................................... 27 4.3.1.5 Hydraulics .......................................................................................................... 28 4.3.1.6 Fatigue ............................................................................................................... 29 4.3.1.7 Longitudinal Barriers ......................................................................................... 29 4.3.1.8 Environmental .................................................................................................... 29

  • Local Bridge Program Manual FY 2017

    Page - II -

    4.3.2 Design Standards Federal Funds ...................................................................................... 30 4.3.3 Permits ................................................................................................................................ 30

    4.3.3.1 Flood Management Certification ....................................................................... 33 4.3.3.2 Flood Management General Certification .......................................................... 33 4.3.3.3 Stream Channel Encroachment Lines ................................................................ 41 4.3.3.4 U.S. Army Corps of Engineer Permits ............................................................... 41

    4.4 SUPPLEMENTAL APPLICATION .............................................................................................. 42 4.5 AGREEMENTS ........................................................................................................................ 43 4.6 PROJECT COMPLETION .......................................................................................................... 44

    CHAPTER 5: GUIDELINES FOR OBTAINING FUNDS 46

    5.1 PROCEDURES FOR STATE FUNDED PROJECTS ....................................................................... 46 5.2 PROCEDURES FOR FEDERALLY FUNDED PROJECTS............................................................... 50

    5.2.1 Consultant Selection............................................................................................................ 50 5.2.1.1 Negotiations ....................................................................................................... 53 5.2.1.2 Contract Monitoring .......................................................................................... 54

    5.2.2 Design Tasks ....................................................................................................................... 54 5.2.2.1 Survey ................................................................................................................ 55 5.2.2.2 Preliminary Engineering .................................................................................... 56 5.2.2.3 Preliminary Design ............................................................................................ 60 5.2.2.4 Regulatory Approvals ........................................................................................ 61 5.2.2.5 Final Design ....................................................................................................... 61 5.2.2.6 Construction Advertising ................................................................................... 62

    5.3 INSTRUCTIONS FOR COMPLETING THE PRELIMINARY APPLICATION .................................... 65 5.3.1 Administrative Project Info ................................................................................................. 65 5.3.2 Preliminary Cost Figures ..................................................................................................... 68 5.3.3 Financial Aid Data .............................................................................................................. 68 5.3.4 Schedule .............................................................................................................................. 69

    APPENDIX 1 ELIGIBLE BRIDGES 70

    APPENDIX 2 GRANT PERCENTAGES FOR MUN