![Page 1: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/1.jpg)
Local Agency Bridge Program
2017 Bridge Conference
![Page 2: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/2.jpg)
Local Bridge Program Summary
FY 2016- 113 Local Bridge Projects Let to Contract: Total
= $62 million- 115 Total Projects = $63 million
![Page 3: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/3.jpg)
Local Bridge Program Summary
FY 2016- 113 Local Bridge Projects Let to Contract: Total
= $62 million- 115 Total Projects = $63 million
Project Breakdown- 41 Replacement Projects = $38 million- 11 Rehabilitation Projects = $10 million- 63 PM Projects = $15 million
![Page 4: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/4.jpg)
Local Bridge Inventory Condition
![Page 5: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/5.jpg)
Local Bridge Inventory Condition2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase) ~ $48
million in funding (Same past 10yrs) 89 Projects selected for FY 2019 Replacement – 29 Projects Rehab/PM - 60 Projects
“Mix of Fixes” – improves long term bridge condition vs replacement only
![Page 6: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/6.jpg)
Local Bridge Inventory ConditionBut…………..How long will it take and at what
cost to replace 900+ Poor/Serious/Critical Local Bridges?
Approx. 2 million sqft of Poor/Serious/Critical Deck area.
Estimating $300 per sqft of deck plus approach cost ($200,000 per structure)
![Page 7: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/7.jpg)
Local Bridge Inventory ConditionBut…………..How long will it take and at what
cost to replace 900+ Poor/Serious/Critical Local Bridges?
Approx. 2 million sqft of Poor/Serious/Critical Deck area.
Estimating $300 per sqft of deck plus approach cost ($200,000 per structure)
Total Replacement Estimate - $800 million Local Bridge Program Budget - $48 million
![Page 8: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/8.jpg)
Local Bridge Inventory Condition 16+ years to replace 900 bridges! Assumes spending all LB funds on replacement No bridges in the Fair category will move to
Poor Current Selection Mix “Mix of fixes” - 60% Replace/40% Rehab/PM by
dollars. Current rate to replace 900 bridges……
![Page 9: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/9.jpg)
Local Bridge Inventory Condition 16+ years to replace 900 bridges! Assumes spending all LB funds on replacement No bridges in the Fair category will move to
Poor Current Selection Mix “Mix of fixes” - 60% Replace/40% Rehab/PM by
dollars. Current rate to replace 900 bridges……
27 years to replace 900 Poor/Serious/Critical Bridges!
![Page 10: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/10.jpg)
Local Bridge Inventory Condition Local Bridge Program did not receive any
additional funds from the $1.2 Billion State Transportation bill.
Encourage the Local Agencies to dedicate a portion of the new funding they received thru ACT 51 to bridge replacement.
The Local Bridge Program can not adequately fund all the local bridge needs.
![Page 11: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/11.jpg)
Local Bridge Funding
Local Bridge Program Federal Funds
Off-System federal funds $18.4 million
State Funds½ cent of gas tax $27.1 million
~$48 million Total (incl. 5% Local Match) Budget has been almost flat for past decade
![Page 12: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/12.jpg)
Local Bridge Funding
$1.2 billion in new State Road funding – Act 51 Distribution 39% Counties - $468 million 22% Cities/Villages - $264 million
Annual distribution when fully implemented in 2021.
Relaying on Locals to fund additional bridge projects with new Local Funds.
![Page 13: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/13.jpg)
2017 Call For Applications
Sent out February 6th to CRA and MML – Call for FY 2020 Construction
Deadline – May 1, 2017
![Page 14: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/14.jpg)
2017 Call For Applications
Sent out February 9th to CRA and MML – Call for FY 2020 Construction
Deadline – May 1, 2017
“Call For Projects” Location: www.michigan.gov/mdot, Doing Business, Local Agency Program, Bridge Program, Call For Projects
![Page 15: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/15.jpg)
Call For Applications
Application limit – 5 Total Multiple PM’s count as 1 Application
No limit on structures in multiple PM applicationBundle for cost effectiveness
Minimize Mob and Traffic Control costsGood Estimate Range for PM App - $150k-500k
PM projects are often underestimated Use estimating worksheets Factor in unknowns and small quantities
![Page 16: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/16.jpg)
Call For Applications
Application limit – 5 Total Multiple PM’s count as 1 Application
No limit on structures in multiple PM applicationBundle for cost effectiveness
Minimize Mob and Traffic Control costsGood Estimate Range for PM App - $150k-500k
PM projects are often underestimated Use estimating worksheets Factor in unknowns and small quantities
PM’s selected by RBC consensus – Not by Points
![Page 17: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/17.jpg)
Call For ApplicationsCommon application errors
ADT - Outdated Route Classification incorrect Load Rating and Posting Codes incorrect/outdated
Item 64F is used to determine Load Capacity & Cond. points SI&A Posted Loading not matching bridge site posting Lack detail in item condition description Lack work recommendations Cost Estimates to low
Especially PM projects
![Page 18: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/18.jpg)
Call For Applications
Key Items to include in Applications Complete Narrative Current Resolution Public Utility relocation costs Detailed Cost Estimates – Use Worksheets
![Page 19: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/19.jpg)
Call For Applications
Key Items to include in Applications Complete Narrative Current Resolution Public Utility relocation costs Detailed Cost Estimates – Use Worksheets Proper Scoping of Work
Rehabilitation and PM projects Replacements – Don’t underestimate size of new bridge
Applications - Due May 1, 2017
![Page 20: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/20.jpg)
How to Increase Application Rating
Look for additional sources of funding STP, Safety, Economic Development, etc.
Increase the Local Agencies funding share – Ex. - 5% to 10% or more
Closed bridges – consider removing bridge and cul-da-sac road.
Bundling PM applications Ideas to conserve Local Bridge Program
Funds – “Innovative Ideas”
![Page 21: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/21.jpg)
Innovative Solutions
Need “Innovative Ideas” to reduce bridge costs. Repair options for box beam bridges Concrete/Aluminum Box Culverts Timber bridges where appropriate GRS-IBS bridges Combine multiple projects into one proposal.
Need to be creative in reducing bridge replacement/rehab costs.
![Page 22: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/22.jpg)
Innovative Solutions
![Page 23: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/23.jpg)
Innovative Solutions
![Page 24: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/24.jpg)
Innovative Solutions
![Page 25: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/25.jpg)
Innovative Solutions
![Page 26: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/26.jpg)
Innovative Solutions
![Page 27: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/27.jpg)
Innovative Solutions
![Page 28: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/28.jpg)
Innovative Solutions
![Page 29: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/29.jpg)
Innovative Solutions
![Page 30: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/30.jpg)
Innovative Solutions
![Page 31: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/31.jpg)
Research ProjectMDOT and Wayne State University
Developing Std. Plans/Details for Single Span Bridges
Use Life Cycle Cost to Determine:Most Cost Effective Design Ease of Construction Long Term Serviceability/Longevity
Focus GroupsDesigners, Contractors, Local Bridge Owners
and Fabricators
![Page 32: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/32.jpg)
Research Project Objectives Reduce cost/time for Design Increase serviceability Lower Life Cycle Costs Reduce Construction costs with Plan
Standardization Improve Quality Control (QC)
![Page 33: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/33.jpg)
Research Project Objectives Education seminars for Local Agencies
and Consultants
Timeline Start – Jan. 2016 – Finish - March 2018
Education seminars: Feb/Mar - 2018
![Page 34: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/34.jpg)
Bridge Application - Financial Points Bridge Application Rating Sheet -100 pt. max 64 points calculated 36 points voted - Regional Bridge Council
Financial Points – calculated category MTF funds Miles of Roadway SFT of Bridge Deck Population
![Page 35: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/35.jpg)
Financial Point Changes Bridge Application Rating Sheet Financial
Points Reduced from 30 to 22 max points in 2010 8 to 12 point difference between highest and
lowest local agency financial points Can be less than 1 point difference between
applications. 2016 – Replacement projects – 10
applications had 6 point difference.
![Page 36: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/36.jpg)
Financial Points Changes Local Bridge Advisory Board (LBAB) voted in
Nov. 2016 to reduce Financial Points from 22 to 16 max points. 2 points to ADT (Calculated) – 17 points max 4 points to Discretionary Project Value (Voted) –
8 points max 5 to 9 point difference between highest and
lowest local agency financial points
![Page 37: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/37.jpg)
Financial Points Changes Financial Point Difference: High vs Low Bay: Old: 10 pts New: 5 pts Grand: Old: 8 pts New: 6 pts Metro: Old: 12 pts New: 9 pts North: Old: 8 pts New: 3 pts SW: Old: 9 pts New: 5 pts Superior: Old: 12 pts New: 8 pts University: Old: 9 pts New: 6 pts
![Page 38: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/38.jpg)
Financial Factors
![Page 39: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/39.jpg)
Design - QC/QA Requirement
FHWA and MDOT review of Local design consultant QC/QA Establish MDOT/Local Bridge Design QC/QA
One page QC/QA certification document Page 20 of Bridge Program ApplicationMust be completed prior to obligation of funds
![Page 40: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/40.jpg)
Design - QC/QA Requirement
FHWA and MDOT review of Local design consultant QC/QA Establish MDOT/Local Bridge Design QC/QA
One page QC/QA certification document Page 20 of Bridge Program ApplicationMust be completed prior to obligation of funds
FHWA and MDOT developing Programmatic review of MDOT and Local bridge designs.
![Page 41: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/41.jpg)
Design - QC/QA
![Page 42: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/42.jpg)
Bridge Asset Management
Transportation Asset Management Council (TAMC)
Bridge Asset Management TrainingDivide Workshop into 2 classes
Technical – Engineers/Consultants Non-Technical – Managers/Road Commissioners
Technical Focus on developing Bridge Asset Management Plan Participants use their own inventory to develop asset
management plan.
![Page 43: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/43.jpg)
Bridge Asset Management Bridge Asset Management
Non-Technical Focus on overview of Bridge Asset Management Participants will understand the concepts and
importance of asset management for their bridge networks.
Each class targets a specific group Classes are more efficient use of time - Webinar Classes are tailored to specific audiences Technical Class – Leave with practical asset
management plan for your agency
![Page 44: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/44.jpg)
Bridge Asset Management
![Page 45: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/45.jpg)
Bridge Asset Management
![Page 46: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/46.jpg)
Bridge Asset Management
![Page 47: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/47.jpg)
Bridge Asset Management
![Page 48: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/48.jpg)
Regional Bridge Council Meetings
Financial and Program Update
Bay Region: May 3rd @ 10:00am, Genesee CRCGrand Region: May 10th @ 10:00am, Ottawa CRCMetro Region: April 26th @ 10:00am, St. Clair CRCNorth Region: April 20th @ 10:00am, MDOT Gaylord OfficeSouthwest Region: May 1st @ 10:00am, Van Buren CRCSuperior Region: April 21st @ 8:30am, Marquette CRCUniversity Region: May 8th @ 9:00am, Ingham CDR
![Page 49: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/49.jpg)
Bridge Unit Staff
Keith Cooper: Bridge Program Manager Phone: (517) 373-2346
Mark Harrison: Project Development Engineer Phone: (517) 373-2286
Chris Tennes: Bridge Staff Engineer Phone: (517) 335-2844
Pablo Rojas: Bridge Staff Engineer Phone: (517) 373-2232
Rita Levine: Bridge/Rural Staff Engineer Phone: (517) 373-0041
![Page 50: Local Bridge Programctt.mtu.edu/sites/default/files/resources/bridge2017/c03_cooper.pdf · 2016 Bridge Applications 363 Applications Received $300 million in applications (15% increase)](https://reader035.fdocuments.us/reader035/viewer/2022071001/5fbdd7352483f842a11e4756/html5/thumbnails/50.jpg)
Questions?