REQUEST FOR REIMBURSEMENT
PROCEDURES(INVOICING)
Local Agency ProgramGeneral Information
1. Local Agency Program (LAP) is a re-imbursement program
2. Each Invoice to FDOT should only include one invoice from Contractor to Agency
3. Invoice Packages shall be submitted to Kathy White, CC Ops Center
4. Provide Hard copy as well as electronic version via email or CD.
5. Cover letter is Optional6. 3 copies of Invoice Package
a. Construction Reimbursement (10 docs)
b. CEI Reimbursement (2 docs)
Documentation/Info Required
The following forms/documents, twelve in total, will be required with each invoice from the Agency besides the cover letter. These forms/documents should be included in the following order:
1) LAP Project Invoice Summary2) Invoice Summary from Contractor to Agency3) Invoice Submittal Checklist4) Cancelled check or proof of alternative payment
method5) Certification Disbursement of previous payment
to Subcontractors6) LAP Monthly Progress Report7) Cost Summary8) Application and Certification for Payment (AIA
form G702)9) Schedule of Values (includes Over runs/Under
runs)10) Change Order Tracking form11) CEI Weekly Summary of Hours and Activities12) CEI Job Duties
Documentation/Info Not Required
The following documents and or information are not required with the invoice package from the Agency. These documents/information hinder the approval process and will cause the invoice package to be rejected:
Time Sheets (unless specifically required for in house CEI) Personal employee information such as:
Medical/Dental Insurance Premiums paid by employee Child support, Alimony payments PTO /Vacation/Holidays Fringe Benefits
The following is an example of items that will cause the invoice package to be rejected: Not providing the required 12 forms previously mentioned Invoice package too large requiring a 3 ring binder/large
clips Project not in compliance Final Invoice that do not include proper Close Out
documentation Mathematical errors. Incorrect Retainage or not discounting the Retainage
LAP Project Invoice Summary
Form #1
General Information
General Information
Example “2”
Ex “425861-2-58-01”
Ex “AQA-77”
Ex “ June 30 2014”
LAP Project Invoice Summary
Form #1
FinancialInformation
LAP Project Invoice Summary
Starting Date of Billing Period
Ending Date of Billing Period
Does not include other items such as administrative costs
etc..
Per the Agreement (only show if based on
Percentage)
Actual amount FDOT/FHWA has agreed
to pay the AgencyParticipating Amount
Incurred to Date
Rows # 5, #6 and #7 should only reflect the amounts
related to the Participating Amounts.
Participating + non-participating and
doesn’t include other items such as admin
costs
CEI Invoice Example
Form #2
Invoice Submittal Checklist
Form #3
Invoice Submittal Checklist
Form #3
Final Invoice
Invoice Submittal Checklist
Form #3
Invoice Submittal Checklist
Form #3
Checklist QuestionsAre there any questions with respect to the
checklist?
Cancelled Checks/Payment Options
Form #4
Options to Cancelled check include:1. Visa Reimbursement Options2. Electronic Transfer
Disbursement Certification
Form #5
Contractor is certifying that they have paid
their subs
Exception Part- Used if a sub is not getting
paid – Must attach Notification sent to
Subcontractor explaining why payment was
withheldSection where you are
notarizing this form
Monthly Construction Progress Report
Form #6
Dat
a S
ectio
nTe
xt
Sec
tion
Text Section of the Progress Report
Monthly Construction Progress Report
Form #6
Dat
a S
ectio
nTe
xt
Sec
tion
ON
/OF
F S
tate
Hw
y
Cost Summary
Form #7
Summary of invoices from Contractor to
Agency
Application & Certificate for Payment(From Contractor to Agency)
Form #8
Participating + non-participating
items only Only account for
C/O’s approved by FDOT LAP Program
Schedule of Values
Form #9
Schedule of Values
Change Order Tracking Form
Form #10
CEI Weekly Labor Summary
Form #11
CEI Job Duties
Form #12
Ways To Jeopardize Funding
Construct a project prior to entering into an agreement.
Not invoicing regularly
Non Compliance with LAP Agreement requirements - State and Federal
Request For Reimbursement (Invoicing)
FDOT and/or FHWA have the authority to de-obligate project funds
Reimbursement Program
Agency pays 3rd Party (Contractor)
FDOT reimburses AgencyFHWA reimburses FDOT
General Requirements