Load Flow Analysis Of 132kv Substation using Electrical Transient Analyzer Program (ETAP)
![Page 3: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/3.jpg)
GROUP MEMBERS NAMES REG.NO.
Majeed Khan
Shakeel Ahmad
Momin Khan
Nayed Khan
SU-12-O1-076-028
SU-12-01-076-057
SU-12-01-076-031
SU-12-01-076-049
Supervised by: Engr. Suliman Khan
![Page 4: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/4.jpg)
Introduction Load flow study play a key role in the planning of
additions or expansions to transmission and generation facilities
A load flow solution is often the starting point for many other types of power system analysis
Load flow analysis at the heart of contingency analysis and the implementation of real time monitoring systems
Load flow analysis is the study of the behavior of power system
![Page 5: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/5.jpg)
It determines if system voltages remain with in limits under normal or emergency operating conditions
Whether equipments like transformers and conductors are overloaded
We can get some practical profile of bus voltage
We can identify real and reactive power flow and minimize KW and KVAR losses
It is important to grow and expand our system
Our project is based on ETAP 6.0 software
![Page 6: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/6.jpg)
Problem Statement FDR-ANA does not have capability to provide comprehensive
analysis
The main cause of disturbance in power system is under voltage
Future up gradation of power system network
The voltage at each bus should be known for losses calculation
Assessment of power system:• within operational limits • system is safe
![Page 7: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/7.jpg)
Objectives To monitor and analyze the power system
accurately
To overcome the under voltage problem
To expand the substation in future demand
To improve the power factor of power system
To minimize the losses of power system
![Page 8: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/8.jpg)
Methodology We have collected data of 132kv GSS Cantt Peshawar.
Then we simulate single line diagram in ETAP 6.0 .
After load flow analysis of single line diagram we have seen that all the feeders were operating under voltage.
Also there were more losses on each bus.
we connected suitable devices like Distributed Generator and again simulated.
![Page 9: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/9.jpg)
To overcome the problem we connected DG with each feeder one by one.
When we simulated the single line diagram with DG connected to each bus then concluded that the under voltage problem and losses were improved.
Continue..
![Page 10: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/10.jpg)
Single line diagram of 132kv GSS Cantt Peshawar
![Page 11: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/11.jpg)
Load flow Analysis of 132kv GSS Cantt Peshawar
![Page 12: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/12.jpg)
The under voltage buses of GSS Cantt peshawar
![Page 13: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/13.jpg)
Losses….contiue
![Page 14: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/14.jpg)
Single line diagram after DG connected to each feeder
![Page 15: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/15.jpg)
Load flow analysis of DG connected single line diagram
![Page 16: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/16.jpg)
Losses have improved after DG connection
![Page 17: Load flow analysis of 132 kv substation using etap](https://reader033.fdocuments.us/reader033/viewer/2022061510/587621c41a28ab8b7b8b4cfd/html5/thumbnails/17.jpg)