LNG Conference P1

download LNG Conference P1

of 21

Transcript of LNG Conference P1

  • 7/29/2019 LNG Conference P1

    1/21

    The Atlantic LNG Train 2/3Expansion ProjectTurning the Challenges

    Into

    Successes with Technology

    Prepared for

    Gastech 2005 in Bilbao, Spain

    15 March 2005

  • 7/29/2019 LNG Conference P1

    2/21

    Slide 2of 21

    Authors

    Dave Messersmith, PE

    Bechtel Corporation

    LNG Technology Manager

    LNG Group Deputy Mgr.

    Process Engineer

    Carlos Yengle

    Bechtel Corporation

    Advanced Simulat ions

    Process Engineer

    Peter Rutherford

    BP America

    Controls and Instrument

    Engineer for Atlantic LNG

    Trent Yackimec

    BP America

    Process Engineer for

    At lant ic LNG

  • 7/29/2019 LNG Conference P1

    3/21

    Slide 3of 21

    Facility InformationFacility InformationLocated in Point FortinLocated in Point Fortin

    Trinidad and Tobago, WITrinidad and Tobago, WI

  • 7/29/2019 LNG Conference P1

    4/21

    Slide 4of 21

    Facility Informationacility InformationProject History

    96 97 98 99 00 01 02 03 04 05 06

    Start EPC

    May 96

    First LNG

    Mar 99

    Turnover

    Jun 99

    Start EPC

    Feb 01

    CompleteJul 02

    Start EPC

    Nov 99

    First LNG

    Aug 02

    Turnover

    Oct 02

    First LNG

    Apr 03

    Turnover

    Jun 03

    Start EPC

    Jan 02

    First LNG

    4th qtr 05

    Turnover

    Early 06

    Train 1

    Train 2 Train 3

    Train 1

    Upgrade

    Train 4

  • 7/29/2019 LNG Conference P1

    5/21

    Slide 5of 21

    Train 2/3 Expansion Challengesrain 2/3 Expansion Challenges Scope Near Duplicate of Train 1 w/ Key Modifications Capacity Train 1 +10%

    Key Enhancements Turbine Drivers Frame 5D Propane System hydraulics Improvements

    Heat exchanger pressure drop optimization

    Heavies Removal Column mechanical design Improvements Anti-surge valve Upgrades

    Inlet Gas Filtration enhancements

    Molecular Sieve Bed piping optimization

    Challenges Schedule, Cost, Lessons Learned fromTrain 1, Feed Gas Pressure, Inlet Compression

  • 7/29/2019 LNG Conference P1

    6/21

    Slide 6of 21

    Inlet Compressionnlet Compression Expansion included new 24 North Gas Field supply Demand on existing 36 exceeded initial capacity

    Inlet pressure designed for reduction of 15 bar Compression located immediately upstream of LNG

    Facility

    Commercial Requirements

    Contractual Limitations

    Operational Complexities

    No buffer volume for LNG Facility

    Engineering committed late in design Provides gas to all 3 Trains

  • 7/29/2019 LNG Conference P1

    7/21

    Slide 7of 21

    Inlet Compressionnlet Compression

  • 7/29/2019 LNG Conference P1

    8/21

    Slide 8of 21

    Inlet Compressionnlet Compression

  • 7/29/2019 LNG Conference P1

    9/21

    Slide 9of 21

    Inlet Compressionnlet CompressionProcess Requirements 1280 MMSCFD feed flow (normal) 250 MMSCFD (min)

    37.5 barg Inlet Pressure (min) 52 barg Outlet Pressure (min)

    GE Frame 5C Driver

    Follow facility f low transitions as required Prevent cascading trips

    These Process and Operational requirements led to a

    study utilizing a rigorous dynamic computer

    simulation model.

  • 7/29/2019 LNG Conference P1

    10/21

    Slide 10 of 21

    Dynamic Modelynamic Model Hysys.plant ver 2.4.1 Scope of Train 1 Model

    Inlet Pipelines

    Inlet Gas treatment

    Refrigeration Systems

    Methane Compression

    NGL Recovery Equipment & Instruments modeled with unit operations

    System volumes and hydraulics based on isos

    Equipment information based on vendor data Control parameters based on actual Train 1 information

  • 7/29/2019 LNG Conference P1

    11/21

    Slide 11 of 21

    Dynamic Modelynamic ModelScenarios1. Feed Gas Compression (FGC) Start up w/ Train 1 &

    2 running normally

    2. Train 1 process shutdown impact on FGC and

    Train 2 and 3.

    3. FGC Trip impact on Train 1, 2 & 3New Feed gas

    BP - 36" Pipeline

    Train 1 gasprocessing and

    liquefactionMetering

    Slug catcherPig receiver

    compressor

    Train 2 gasprocessing and

    liquefaction

    Train 3 gasprocessing and

    liquefaction

    BG - 24" Pipeline

    Metering

    Slug catcherPig receiver

    100%

    50%

    50%

    75%

    25%

    Percentage figures represent proportions o fTrain feed gas sourced from different pipelines

  • 7/29/2019 LNG Conference P1

    12/21

    Slide 12 of 21

    Dynamic Modelynamic ModelFGC TripFGC Trip

    B P F e e d - P r e s su r e [ b a r ]

    35

    37

    39

    41

    43

    45

    47

    49

    0 1 2 3 4 5 6 7 8

    T i m e ( m i n u t e s )

    Train 1 LNG Prod uct - Mass Flow

    [kg/h]

    0

    50000

    100000

    150000

    200000

    250000

    300000

    350000

    400000

    450000

    0 1 2 3 4 5 6 7 8

    T i m e ( m i n u t e s )

    BG Feed- Pressure [bar]

    61.46

    61.48

    61.50

    61.52

    61.54

    61.56

    61.58

    61.60

    0 1 2 3 4 5 6 7 8

    T i me (mi n u t e s )

    BP Feed - Pressure [bar]

    35

    37

    39

    41

    43

    45

    47

    49

    0 1 2 3 4 5 6 7 8

    T i me (mi n u t e s )

    B G F e e d - P r e s su r e [ b a r ]

    61.46

    61.48

    61.50

    61.52

    61.54

    61.56

    61.58

    61.60

    0 1 2 3 4 5 6 7 8

    T i m e ( m i n u t e s )

    Train 1 LNG Product - Mass Flow

    [kg/h]

    0

    50000

    100000150000

    200000

    250000

    300000

    350000

    400000

    450000

    0 1 2 3 4 5 6 7 8

    Time (mi nut es)

  • 7/29/2019 LNG Conference P1

    13/21

    Slide 13 of 21

    Dynamic Modelynamic ModelFGC TripFGC Trip

    Inlet Feed Gas Compre ssor

    Inlet/Outlet Pre ssure

    35

    40

    45

    50

    55

    60

    0 1 2 3 4 5 6 7 8

    T i m e ( m i n u t e s )

    Inlet Feed Gas Compressor Bypass -

    Molar F low [kgmole/h]

    0

    10000

    20000

    30000

    40000

    50000

    60000

    0 1 2 3 4 5 6 7 8

    T i m e ( m i n u t e s )

    Train 1 Feed - Molar Flow [kgmole/h]

    0

    5000

    10000

    15000

    20000

    25000

    30000

    0 1 2 3 4 5 6 7 8

    T im e (m inutes )

    Train 1 Feed - Pressure [bar]

    40

    42

    44

    46

    48

    50

    52

    0 1 2 3 4 5 6 7 8

    T im e (m inutes )Inlet Feed Gas Compressor

    Inlet/Outlet Pressure

    35

    40

    45

    50

    55

    60

    0 1 2 3 4 5 6 7 8

    Ti me (minut es)

    Inlet Feed Gas Compressor Bypass -

    Molar Flow [kgmole/h]

    0

    10000

    20000

    30000

    40000

    50000

    60000

    0 1 2 3 4 5 6 7 8

    Time ( minut es)

    Train 1 Feed - Molar Flow [kgmole/h]

    0

    5000

    10000

    15000

    20000

    25000

    30000

    0 1 2 3 4 5 6 7 8

    Time (mi nut es)

    Train 1 Feed - Pressure [bar]

    40

    42

    44

    46

    48

    50

    52

    0 1 2 3 4 5 6 7 8

    Time ( minut es)

  • 7/29/2019 LNG Conference P1

    14/21

    Slide 14 of 21

    Dynamic Modelynamic ModelInitial Results Low BP Pressure no flow for about a minute

    Satisfactory BG Pressure Refrigerant system disturbances

    Surge events anticipated for methane system

    Line pack allowed temporary increase in BG flow

    Modified Simulation

    Conserve BP flow for Train 1

    Attempt to satisfy at least feed rate for each train

    Modify controls to isolate BP feed to Train 2/3

    Increase BG flow to Train 2/3 temporarily

  • 7/29/2019 LNG Conference P1

    15/21

    Slide 15 of 21

    Fig. 3 - Train 1 Inlet Feed Gas Molar Flo

    0

    5000

    10000

    15000

    20000

    25000

    3000035000

    0 2 4 6 8Time (min)

    MolarFlow

    k

    mole/h

    Modified

    Solution

    Fig. 4 - Train 1 Inlet Feed Gas Pressur

    40

    42

    44

    46

    48

    50

    52

    0 2 4 6 8Time (min)

    Pressure

    bar

    Modified

    Solution

    Dynamic Modelynamic Model

  • 7/29/2019 LNG Conference P1

    16/21

    Slide 16 of 21

    Field Testingield TestingPlan FGC Commissioned May 03

    Full processing rates in all three trains

    Validate results of simulation

    Trip FGC

    Train 3 reduce BP feed to zero, increase BG feed to 50%

    Train 2 reduce BP feed to zero, maintain BG feed at 50%

    Train 1 Hold BP feed rate to 50%

  • 7/29/2019 LNG Conference P1

    17/21

    Slide 17 of 21

    Field Testingield TestingFig. 7 - Train 1 Inlet Feed Gas Molar Flow- Field Dat

    0

    5000

    10000

    15000

    20000

    25000

    3000035000

    0 2 4 6 8Time (min)

    MolarFlow

    k

    mole/h

    Field Data

    Fig. 8 - Train 1 Inlet Feed Gas Pressure - Field Data

    40

    42

    44

    46

    48

    50

    52

    54

    0 2 4 6 8Time (min)

    Pressure

    bar

    Field Data

  • 7/29/2019 LNG Conference P1

    18/21

    Slide 18 of 21

    Response

    3.5 minutes until f low resumes from BP, low pressure

    6.5 minutes until inlet pressure returns to 51 barg

    Train 1 flow decreased to 22% of capacity slowly

    Many operational deviations, but no equipment trips

    Recovery to 50% rates in about 4 minutes

    No loss of condensing

    Train 2 & 3 rode through the upset smoothly

    Machines not driven to surge

    After the trip, facility was restricted to 50% rate

    The simulation was not limited to rate

    Field Testingield Testing

  • 7/29/2019 LNG Conference P1

    19/21

    Slide 19 of 21

    Closing Remarkslosing Remarks Dynamic model closely predicted actual field results Development of safe operating instruction in advance

    Illustrated operational concerns prior to start-up

    Used to predict other upsets with confidence

    Combined team of specialists reduced risks for system

  • 7/29/2019 LNG Conference P1

    20/21

    Slide 20 of 21

    Schedule 65 days early

    Production & Efficiency exceeded requirements

    Ease of start up 68 days first LNG to turnover

    Schedule 80 days early

    Production & Efficiency exceeded requirements

    Ease of start up 46 days first LNG to turnover

    Over 18 mill ion hours worked at facil ity since last LTA

    Train 2/3 Expansion Successesrain 2/3 Expansion SuccessesTrain 2Train 2

    Train 3Train 3

    SafetySafety

  • 7/29/2019 LNG Conference P1

    21/21

    Slide 21 of 21

    Question or CommentsQuestion or Comments

    ??