LIU-ABT Systems Review: PS Status and Planning for KFA- 53 1/10/2014 LIU-PS ABT review 1 T. Kramer, L. Ducimetiere, L. Sermeus

description

LIU-ABT Systems Review: PS Status and Planning for KFA-53. T. Kramer, L. Ducimetiere, L. Sermeus. Content. Requested Hardware and future Location Conceptual System Considerations Schedule Budget /Spending Profile Manpower / Resources. What hardware (modification) is needed?. - PowerPoint PPT Presentation

Transcript of LIU-ABT Systems Review: PS Status and Planning for KFA-53

Page 1: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 1

LIU-ABT Systems Review: PS

Status and Planning for KFA-53

1/10/2014

T. Kramer, L. Ducimetiere, L. Sermeus

Page 2: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 2

Content• Requested Hardware and future Location • Conceptual System Considerations• Schedule • Budget /Spending Profile• Manpower/ Resources

1/10/2014

Page 3: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 3

What hardware (modification) is needed?

1/10/2014

Page 4: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 4

What hardware (modification) is needed?

• KFA 53 is a complete new kicker system: • Vacuum tank • Delay line magnet• Pulsed/Controls Cables• Generators (PFL) • Controls • Infrastructure (building, cable ducts, electrical

installation, etc.)

1/10/2014

Page 5: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 5

Received Requirements

• As fast as KFA-45 (rise time 46 ns 1-99%).• Max. deflection angle at 2 GeV: 1.3 mrad.• Beam stay clear aperture: 140x53 mm . • Magnet to be placed in SD53.

1/10/2014

Page 6: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 61/10/2014

KFA-45 KFA-53650 mm available (magnet to be displaced)

Available Space (Tunnel)

Page 7: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 71/10/2014

Page 8: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 8

Available Space(Surface) Reference: KFA-45

1/10/2014

KFA 45: Bat. 365 75+25m²KFA-53: Approx. 50+20?m²

Page 9: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 9

• KFA45 area is crowded already (although controls consolidation could free up some space)

• Cables to SD53 would be too long.

1/10/2014

Page 10: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 10

Where to put the Pulse Generator?

1/10/2014

KFA45KFA53

51m

365

356

131

225

362

Page 11: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 11

Space• 365-1-405: No space available. Cables too

long (should be <50m).• 362: seems to small.(extension?) Cables too

long.• 365: (east end). Seems ok but TE-EPC

owned.• 356: possibly best location but TE-EPC

owned.• If none of the above is possible: New building

between 365 and 356.

1/10/2014

Page 12: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 12

Concept and Main Parameters

1/10/2014

Page 13: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 13

Basic Concept for Magnet (I)• Delay line magnets. • Leave aperture for possible impedance

shielding efforts (+6mm=59mm). • Adapt magnet to rise time requirements in

SC mode.

• Hence KFA 45 modules will not fit anymore (53mm).

1/10/2014

Page 14: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 14

Basic System Concept (II)• Beam rigidity at 2 GeV is 9.29 Tm;• Magnetic length is ~650 mm; • 1.3 mrad kick requires ~850 A;• Usage of RG220 cables desired; • Thus max. 40kV ops max. 33kV nominal 27

kV. -> 27kV/0.85kA -> ~30 Ω system impedance.

1/10/2014

Page 15: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 15

Basic System Concept (III)• 2 delay line magnets to be housed in new

vacuum tank. • Usage of known 60 Ohm low loss cable ( 2

in parallel). • TX cables loaded with ferrites for pulse

shaping.• Refurbishment of 2 EPA generators. • CX 1154 Switches. • Hydraulic group (ELENA type)

1/10/2014

Page 16: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 16

Main Parameters (TDR)

Parameter unit valueDeflection angle (nominal) mrad 1.3ʃ B.dl (max) T.m 0.0187Deflection angle (max) @ 2 GeV mrad 2System impedance Ω 15PFL voltage (max) kV 40Magnet aperture (w × h) mm × mm 140 × 59Beam aperture (w × h) mm × mm 140 × 53Kick rise time (1-99) % ns 46Kick fall time (99-1) % ns 92Kick length (max) ns 2600Kick flat-top ripple % ± 3Post kick ripple % ± 1.5

1/10/2014

Parameter unit KFA53 (SC) KFA45 (term.) KFA45 (SC)

Deflection angle (nominal) mrad 1.3 4.3 4.3ʃ B.dl (max) T.m 0.0187 0.0314 0.0601

Deflection angle (max) @ 1.4 GeV mrad 4.395 8.4

Deflection angle (max) @ 2 GeV mrad 2 3.38 6.5

System impedance Ω 15 26.3 26.3PFL voltage (max) kV 40 80 80

Magnet aperture (w × h) mm × mm 140 × 59 150 × 53 150 × 53

Beam aperture (w x h) mm × mm 140 × 53

Kick rise time (1-99) % ns 46 46 82Kick fall time (99-1) % ns 92 96 92Kick length (max) ns 2600 2600 2600Kick flat-top ripple % ± 3 ± 2 ± 3Post kick ripple % ± 1.5 ± 1.25 ± 1.5

Page 17: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 17

Schedule

1/10/2014

Page 18: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 18

LS2 Draft Schedule - LIU-PS activities (as presented in Chamonix by J. Coupard)

Consolidation work not included!

1/10/2014

• installation slot (PS tunnel) currently from August 2018 to mid November 2018 (3.5 month)

Page 19: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 19

Planned Schedule

1/10/2014

KFA-53

2014 LIU-TDR (done)

EOY 2014 Functional Specification available.

EOY 2014 Site for generator found. Cable routing confirmed. Cable choice confirmed.

Mid 2015 Detailed system design & Technical Specification available (approved).

EOY 2015 Integration done.1st drawings available. Long lead items ordered.

Q1/2016 All Drawings available. Production for “in-house” subcomponents started.

Q3/2016 Magnet and generator assembly starts.

Q2/2017 Assembly finished - Lab testing of complete system.

Q3/2017 Generator building available.

Q4/2017 Installation of Generator and PFL.

Q3/2018 Installation of magnet and cables

Q1/2020 HW/Beam commissioning

Page 20: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 20

Budget

1/10/2014

Page 21: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 21

Budget breakdown

• Total Budget is currently 1.940 MCHF.• Detailed breakdown to be done. • Costs for building or adaption work of

existing building not included so far.

1/10/2014

Page 22: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 22

Metrics per year in kCHF

APT Node LIU-PS 9.3 : New kicker design

Description Manufacture and commission KFA53

APT wu 113135

Wu responsible [email protected]

Budget code 99253

Metrics per year in kCHF

Year 2013 2014 2015 2016 2017 2018 2019 2020 Total

PV 116 423 633 618 150 1940

EV 0

New PV 0 423 749+250 618+50 150 1940+300

Spending Profile KFA53

Preliminary estimates for (minimum) building adaption work in red..

1/10/2014

Additional 10kCHF planned for commissioning (2019) in APT wu 113136

Page 23: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 23

Manpower / Resources

1/10/2014

Page 24: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 24

Manpower/Resources• No detailed manpower planning available yet.

• Conceivable that additional manpower is needed.

• Integration/design effort to be estimated and requested at design office.

• Assembly area for magnet and generator will be 867 (within controlled zone).

• HV-Test cage for system testing needed in 2017.

1/10/2014

Page 25: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 25

Other: Consolidation of KFA-45

• A refurbishment of the KFA-45 controls is envisaged as very similar KFA-53 controls needs to be developed anyway.

• The replacement of the KFA-45 SF6 cables is foreseen.

• Extension of cable shed for spare cable drum to be discussed.

1/10/2014

Page 26: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 27

Conclusions• KFA 53 requirements received. • Conceptual design for LIU-TDR delivered. • Functional Specification to be written until

December.• Resources estimate and Budget/Manpower

planning to be done.• Technical Specification to be delivered in mid

2015. • Delivery of KFA-53 magnet and generator as

foreseen in 2018.

1/10/2014

Page 27: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 28

Outlook w.r.t lessons learned during LS1

• KFA53 project goes in parallel with many other consolidation and LIU projects.

• Injector restart after LS1 showed many unplanned events and subsequently unscheduled interventions (source sometimes outside ABT responsibility!).

• Also commissioning of renovated systems showed that time for correction of non-conformities was necessary.

• Staged approach of accelerator ramp up looks excellent in theory but for hardware sections it means that troubleshooting for already running CPS overlaps with PS/SPS commissioning whilst there is still installation work in the LHC ongoing. This has to be covered by the same manpower.

• With combined efforts it was manageable for LS1 but it will be a totally different challenge to deliver and commission several completely new (and additional) systems beside the usual start up business (and changing staff).

1/10/2014

Page 28: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

1/10/2014 LIU-PS ABT review 29

Page 29: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

Reserve slides

1/10/2014 LIU-PS ABT review 30

Page 30: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 31

362• KFA28 and storage• Tx cables >50m • More a shed than a building (in case of usage to be completely

rebuild?)

1/10/2014

Page 31: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 32

365

1/10/2014

• Within TE-EPC responsibility.• Ok for Tx-cable length. • Extension possibility for cable

shed.

Page 32: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 33

356

1/10/2014

• Within TE-EPC responsibility.• OK for Tx-cable length. • Extension possibility for cable

shed.

Page 33: LIU-ABT Systems Review: PS Status  and  Planning for KFA-53

LIU-PS ABT review 34