List of Major Permits and License Required During Construction
Sl.No
Clearance Agency Agency
1
.
Right of way for all
corridors to the Facility.
Sate Government /
Concerned Agency
Required to obtained by
Project Company
2.
Consent for thedevelopment of Projectsite
Local Panchayet Required to obtained byProject Company
3.
Boiler & other pressurepart pipes & valveswithin purview of IBR
The Chief Inspectorof Boilers
Will be obtained byContractor(s)
4.
Electrical Plant andEquipment installation(pre & post)
The Chief ofElectrical Inspector,Sate Govt.
Will be obtained byContractor(s)
5.
Pre & Post installationapproval for buildings,pipe racks layout, cableroutes racks, acid andother chemical storage
The Chief Inspectorof Factory, localmunicipality/Concern Authorities.
Will be obtained byContractor(s)
6.
Fire Fighting/ Protectionsystem/Electricalsystem
Tariff AdvisoryCommittee / LossPreventionAssociation (LPA)
Will be obtained byContractor(s)
7.
Chlorine storage Chief Controller of Explosive, Nagpur
Will be obtained byContractor(s)
8.
Fuel oil storage tank Chief Controller ofExplosive, Nagpur
Not Required
9.
Approval of stack airemission levels(excluding groundconcentration)
State PollutionControl Board,Inspector ofChimney
Required to obtained byProject Company
10.
No Objection Certificate(NOC) for Storm Waterdrainage, fromconcerned authorities
MunicipalCorporation:Executive Waterdrainage Design
Will be obtained byContractor(s)
11.
Collection, storage &disposal of waste,effluent
State PollutionControl Board Required to obtained byProject Company
12.
Site clearances, SafetyReport and Safety Audit
State PollutionControl Board
Required to obtained byProject Company
-
8/6/2019 List of Permits and Clearences Construction
2/3
Sl.No
Clearance Agency Agency
13.
Switchyard State ElectricityBoard/ CEA/ CEIG
Will be obtained byContractor(s)
14.
Lift & Cranes Lift Inspector Will be obtained byContractor(s)
15.
Use of wireless set andallocation of frequencyof wireless
ConcernedAuthorities, Wirelessadvisor to Govt. ofIndia
Will be obtained byContractor(s)
16.
Clearance for StackObstruction Light
Directorate of CivilAviation
Will be obtained byContractor(s)
17.
Permission for Hook upwith GPS of Masterclock system
Relevant Authorities Will be obtained byContractor(s)
18.
License for constructionlabour pursuant toContract Labour(Regulation & Abolition)Act 1970
LabourCommissioner,State Govt.
Will be obtained byContractor(s)
1
9.
Registration of workers
required pursuant tosection 2A of EmployeeState Insurance Act1984
Labour
Commissioner,State Govt.
Will be obtained by
Contractor(s)
20.
Consent of Collector ofExplosives to thepossession and use ofexplosives for thepurpose of blasting.
Home Department,State Govt.
Not Required
21.
Approval of temporaryconstruction powerlines within plant area
ElectricalInspectorate, StateGovt.
Required to obtained byProject Company
22.
Road/ Rail permit fortranspiration ofmaterial to Facility site
ConcernedAuthorities
Required to obtained byProject Company
23.
Use of Minerals andnatural aggregates forcivil works
Dept. of Mines &Geology, Sate Govt.
Not Required
-
8/6/2019 List of Permits and Clearences Construction
3/3
Sl.No
Clearance Agency Agency
24
.
Permission for labourcamp
ConcernedAuthorities
Will be obtained byContractor(s)
25.
Work permit forexpatriate personnel
ConcernedAuthorities
Will be obtained byContractor(s)