Replacement Inhibitors for Tank Farm Cooling Coil Systems (U)
Lincoln Avenue Pump Station Fuel Tank Replacement Project AVE… · Lincoln Avenue Pump Station...
-
Upload
trinhkhanh -
Category
Documents
-
view
227 -
download
0
Transcript of Lincoln Avenue Pump Station Fuel Tank Replacement Project AVE… · Lincoln Avenue Pump Station...
Lincoln Avenue Pump Station Fuel Tank Replacement ProjectLincoln Avenue Pump Station Fuel Tank Replacement ProjectCategory: Tanks, Water and Sewage Treatment
PlantsProject ID #: 1004237757
Street Address: Lincoln Ave. Saugus MA 01906 Confirmed Value $150,000.00County: Essex Stage: SUBBIDS: ASAPBid Date: 1/19/2017 , 02:00PMArchitect:Documents Available: Plans, Specs available in Insight Plans available from Tighe & Bond - WestfieldLast Update: 12/24/2016 Plans,Specs were Added/Updated
NotesNotes
Scope Site work for a civil project in Saugus, Massachusetts. Completed plans call for site work for a water /sewer project. Lincoln Avenue Pump Station Fuel Tank Replacement Project Project requires thereplacement of one underground storage tank, day tank and associated appurtenances. The workconsists of the removal of one 2,000-gallon underground storage tank and installation of one newunderground storage tank. The location and volume of the new tank is detailed on the projectDrawings. Bids shall be on a lump sum basis. Minimum Wage Rates as determined by theCommissioner of Department of Workforce Development under the provision of the MassachusettsGeneral Laws, Chapter 149, Section 26 to 27D, as amended, apply to this project. It is theresponsibility of the Contractor, before Bid opening, to request if necessary, any additionalinformation on Minimum Wage Rates for those trades people who may be employed for theproposed Work under this Contract.
Notes Bid Date: 01/19/2017 02:00PM Sealed Bids for the construction of the Lincoln Avenue Pump StationFuel Tank Replacement Project will be received by the Town of Saugus Purchasing Department,Town Hall, 298 Central Street, Saugus, MA 01906 at which time the Bids received will be publiclyopened and read. Sealed Bids must have outer envelope marked as Lincoln Avenue Pump StationFuel Tank Replacement Project, Saugus,Massachusetts, Bid No. 28-16. Pre-Bid Meeting: 01/05/201710:00AM A non-mandatory pre-bid conference will be held at the Lincoln Avenue Pump Station, 24Lincoln Avenue, Saugus, MA Development include(s): Site Work
Details [Division 2]: Building Demolition, Clearing, Dewatering, Paving & Surfacing, Landscaping. [Division 3]:Concrete Formwork, Concrete Reinforcement, Structural Concrete. [Division 4]: Clay Unit Masonry,Marble. [Division 5]: Metal Fabrications. [Division 9]: Tile, Terrazzo, Painting. [Division 11]: FluidWaste Treatment/Disposal Equipment. [Division 14]: Elevators, Material Handling Systems. [Division16]: Alarm & Detection Systems, Voice & Data Systems.
Additional DetailsAdditional DetailsListed On: 12/23/2016 Floor Area:Contract Type: Work Type: AlterationStage Comments 1: Floors Below Grade:Stage Comments 2: Owner Type: CityBid Date: 1/19/2017 Mandatory Pre Bid Conference:Invitation #: 28-16 Commence Date: 2/20/2017Structures: 1 Completion Date:Single Trade Project: Site Area:Floors: LEED Certification Intent:Parent Project ID: Units:Parking Spaces:
Project ParticipantsProject ParticipantsCompany RoleCompany Role Company NameCompany Name ContactContact
NameNameAddressAddress PhonePhone EmailEmail FaxFax
Owner Town of Saugus 298 Central St. ,Saugus, MA 01906
(781) 231-4111
(781) 231-4109
Civil Engineer Tighe & Bond -Westfield
Gary Roberts 53 SouthamptonRoad , Westfield, MA01085
(413) 875-1316
(413) 562-5317
ContractsContractsClassificationClassification ConditionsConditions BondingBonding Bid DateBid Date Bids ToBids To Bid TypeBid TypeGeneral Contractor 1/19/2017 Owner Open Bidding
Report Date: 12/27/2016 7:16:21 AM © 2016 ConstructConnect. All Rights Reserved. Page 1 of 2
HistoryHistoryUserUser ViewedViewed First Viewed DateFirst Viewed Date Currently Tracked?Currently Tracked? Date TrackedDate TrackedAdam Sweet True 12/27/2016 False
Report Date: 12/27/2016 7:16:21 AM © 2016 ConstructConnect. All Rights Reserved. Page 2 of 2
nghe&Bond42" CONTAINMENT SUMP WITH WATERTIGHT LID
3/4" FLEXIBLE DOUBLE WALL PIPING SUPPLY AND RETURN
RGS CONDUIT LEVEL AND SUMP SENSOR WIRING (TYP)
5-GALLON BELOW GRADE SPILL BUCKET UST CONCRETE
MAINTENANCE PADwww. tighebond. comSEE CONCRETE PAD
DETAIL THIS SHEETINTERSTITIAL MONITORING HANDHOLE48" TANK MANWAY FIN. GRADEBELOW GRADE TANK
SUMP AND MANWAY s23'-6"
sCM 1r\i
■r—i TRACEABLE WARNING TAPE (TYP)
fM
W'/Af/THOMASJ. Ve7/,'MAHANNAV/ CIVILk NO. 3W Jt
%^/on
tH
4Û
jT VÛ SIFTED COMPACTED BACKFILLxb. 2 ICO<Z12" PROCESSED
GRAVELZ oCO 3" CORRUGATED
CONTAINMENT PIPE, FOS AND FOR PIPING
xM- < KO
fîtCOZ 3/4" RGS CONDUIT
INTERSTITIAL SENSOR WIRING
BRINE RESERVOIR
coKO 2" VENT Vco
AGGREGATE BASE (OOX) I /w(&2" VENT PIPING-
3/4" RGS CONDUIT 1/2" RGS CONDUIT
AUTOMATIC SHUT-OFF VALVE LIMIT CAPACITY TO 95% OF TANK VOLUME
^6" 6"
3" CORRUGATED CONTAINMENT 7»
2" - Q_(TYP)
QUTILITY TRENCH DETAILo
NO SCALEM-kO
GALVANIZED DROP-FORGED TURNBUCKLE (TYP)
12"xl2"xl8' REINFORCED CONCRETE DEADMEN PROVIDED BY THE TANK MANUFACTURER (TYP OF 2)
M AG N ETO RESTRICTIVE LEVEL PROBE WITH FUEL AND WATER SENSORS
SLOPE TOP OF CONC FILL FOR DRAINAGE
12"xl2" - 18' DEADMAN (2)TANK DETAIL13'-9"
NO SCALE<
2,500 GALLON TANK DETAIL 6" DIA, SCH 40 STEEL PIPE, CONCRETE FILLED BOLLARD PAINT SAFETY YELLOW (TYP)
KO
NO SCALE M-
PROVIDE MANWAY WITH A FIBERGLASS OR STEEL BOLT DOWN COVER
RAISE MANWAY 1/2" ABOVE CONCRETE PAD CHAMFER PAD INTO MANWAY
14" GALV STEEL SKIRT
SLOPE SLOPECENTER MANWAY ON TANK SUMP FIN. GRADE
PROVIDE STEEL OR FIBERGLASS COVER - PAINT COVER YELLOW
RAISE MANWAY 1/2" ABOVE CONCRETE PAD CHAMFER PAD INTO MANWAY
x48"
CENTER MANWAY ON SPILL BUCKET
PROVIDE WATERTIGHT SUMP COVER x A À
42 a GALV STEELSKIRTjaCM <a
□---------- sA A 5,000 psi CONCRETEo4/ A-
i A A rsiT—I
PROVIDE 3/4" PEASTONE OR 1/2" WASHED CRUSHED STONE AROUND SUMP & UNDER CONCRETE PAD-------------------
*4PROVIDE A MINIMUM OF 3" CLEARANCE BETWEEN OUTER WALL OF TANK SUMP & MANHOLE SKIRT ON ALL SIDES
A
Department of Public Works
I'S' KO
1’-6”DIAPROVIDE UL LISTED WATERTIGHT TANK SUMPPROVIDE WATERTIGHT
FITTING ADAPTERS FOR EACH PIPE RUN & ELECTRICAL CONDUIT PENETRATION---------
BOLLARD DETAILSUMP MOUNTING COLLAR Lincoln Avenue Pump Station Fuel Tank Replacement Project
UL LISTED 5-GALLON BELOW GRADE SPILL BUCKET WITH LOCKABLE LID
i NO SCALE
0!bl"ô!b^ô?v
t'o9*0
PROVIDE DROP TUBE WITH AUTOMATIC SHUT-OFF VALVE SET TO 95% OF TANK CAPACITY
NOTES:1. PROVIDE WASHED 3/4" PEASTONE OR WASHED 1/2" USE IN THE CRUSHED STONE
BACKFILL, NATIVE SOILS ARE NOT PERMITTED FOR TANK EXCAVATION.
l PROVIDE 3/4" PEASTONE OR 1/2" WASHED CRUSHED STONE AROUND SPILL BUCKET & UNDER CONC PAD
2. CONTRACTOR SHALL CONDUCT AN AIR TEST ON TANK BEFORE INSTALLATION AND AFTER ALL EQUIPMENT IS INSTALLED, BUT BEFORE FILLING. TEST SHALL BE CONDUCTED IN ACCORDANCE WITH THE MANUFACTURER'S SPECIFIED PROCEDURES. PRESSURES SHALL NOT EXCEED 5 psi.
4" FEMALE TANK FITTING (TYP)TYPICAL BELOW GRADE TANK SUMP
Saugus,Massachusetts
NO SCALE
TYPICAL 5-GALLON BELOW GRADE SPILL BUCKETNOTES:TANK SUMPS AND SUMP PENETRATION ENTRY BOOTS AND ADAPTERS SHALL BE INSTALLED BY A CONTRACTOR THAT IS CERTIFIED BY THE MANUFACTURER.
1. NO SCALE 3. PROVIDE A MINIMUM OF 24" OF NEW COMPACTED BACKFILL ON ALL SIDES AND BOTTOM OF TANKS.NOTES:
1. TANK FILL DROP TUBES SHALL EXTEND TO WITHIN 4 INCHES OF THE TANK BOTTOM.ALL SUMPS AND SPILL BUCKETS SHALL BE HYDROSTATICALLY TESTED PRIOR TO INTRODUCING FUEL INTO ANY PORTION OF THE TANK'S PIPING.
2.4. ANCHOR STRAPS MUST BE LOCATED AT THE MANUFACTURER'S DESIGNATED
LOCATIONS. A MINIMUM OF TWO ANCHOR POINTS ARE REQUIRED PER TANK.VERIFY SCALE
3. HYDROSTATIC TESTING WATER SHALL BE INSPECTED FOR THE PRESENCE OF PETROLEUM FOLLOWING THE TEST. WATERS CAN BE DISCHARGED ON SITE IF NO OIL IS PRESENT.
BAR IS 1 INCH ON ORIGINAL DRAWING5. EACH ANCHOR STRAP SHALL HAVE AT LEAST ONE TURN BUCKLE.
0 1 INCH IF NOT ONE INCH ON THIS SHEET, ADJUST
SCALES ACCORDINGLY
6. DEADMEN ARE TO BE LOCATED OUTSIDE THE FOOTPRINT OF THE TANKS.
7. ALL INSTALLED CONCRETE SHALL HAVE A COMPRESSIVE DESIGN STRENGTH OF 5,000 psi.
8. ANCHOR STRAPS AND TURNBUCKLES MUST MEET THE MANUFACTURER'S REQUIREMENTS.#5 BARS AT 12" OC
EACH WAY, TOP & BTM
3" COVER MIN
3/4" CHAMFER ALL EXPOSED EDGES
TOP OF PAD 9. BACKFILL SHALL BE PLACED IN EVENLY DISTRIBUTED 12" LIFTS. BACKFILL MATERIAL SHALL BE WORKED TO FILL ALL VOIDS.2.5" CLASS 1 BITUMINOUS-
CONCRETE BASE COURSE rFINAL GRADE1.5" CLASS 2 BITUMINOUS CONCRETE TOP COURSE
CONCRETE PAD 12/21 Issued for Bidding1
r 10. CONTRACTOR SHALL PROVIDE A COMPLETED "TANK INSTALLATION LIST" UPON COMPLETION OF THE PROJECT.
SAW CUT (TYP)
<7 o 11/16 Issued for Review*4 <7 4<7 <7
Mark Date Description<7AA <<0 4 s<7<7A A (N<7 aA S2127-Task 211. ALL MANWAYS, HANHOLES AND SPILL BUCKETS ARE TO BE RAISED/CHAMFERED 1/2". PROJECT NO:A <7 AA A<74 <7<7 __• • A<7 DATE: 12/21/20164 <7
#4 BARS AT 24" OC A<r <4 A__ <7 12. TANK AND FUELING AREA ORIENTATION SHALL BE CONFIRMED BY OWNER PRIOR TO TANK INSTALLATION.
•4 FILE: S2127-Task2-C-Details.dwg<?
n ’Vf xrx~ f pf v;s
c.O ° o aQO
DRAWN BY: LPT12" PROCESSED AGGREGATE BASE
SELECT NATIVE SOILS
(NCHECKED:: MJV,GMR2 13. PIPE FITTINGS SHALL BE THREADED AS DETAILED IN SPECIFICATION SECTION 15102.12" PROCESSED
AGGREGATE BASE
CNJ3 C' APPROVED: TJM
14. THE TRANSITION FROM UNDERGROUND DOUBLE WALLED PIPE TO SINGLE WALLED ABOVE GROUND PIPE SHALL OCCUR USING CLAMSHELL OR SWAGE FITTINGS INSIDE OF THE CORRUGATED CONTAINMENT PIPE. A LIQUID TIGHT TRANSITION ASSEMBLY SHALL BE INSTALLED TO PREVENT WATER INTRUSION. SEE SECTION 13201 FOR ADDITIONAL DETAILS.
)TVO T6" CRUSHED STONE ■I 11=1 II-1—i DETAILSNOTES:
1. CONCRETE SHALL BE 5,000 psi CONCRETE WITH 3/4" AGGREGATEASPHALT REPAIR
SCALE: AS SHOWNCONCRETE PAD DETAIL
SHEET 3
Last
Sav
ed: 1
2/21
/201
6Pl
otte
d On:
Dec
21, 20
16 —
3:20
pm By
: MJV
Tigh
e &
Bon
d: J
:\S\S
2127
Sau
gus -
Linc
oln
Ave
PS\
02 -
UST
Rep
lace
men
t\Dra
win
gs-F
igur
es\A
utoC
ad\S
heet
s\S2
127-
Task
2-C
-Det
ails
.dw
g
SECTION 02115
UNDERGROUND STORAGE TANK AND PIPING REMOVAL
310 CMR 40.000, Massachusetts Contingency Plan (MCP)
310 CMR 80.00, Underground Storage Tank Systems
American Petroleum Institute (API) Recommended Practice 1604, “Closure ofUnderground Petroleum Storage Tanks”
MADEP Policy, WSC-402-96, “Commonwealth of Massachusetts Underground Storage Tank Closure Assessment Manual”
National Fire Protection Association (NFPA) 326 - Standard for the Safeguarding of Tanks and Containers for Entry, Cleaning or Repair,” latest revision.
Tighe&Bond
S-2127/12/16/16 02115 - 1 Underground Storage Tank and Piping Removal
SECTION 02115
UNDERGROUND STORAGE TANK AND PIPING REMOVAL
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes
1. Removal, cleaning, and disposal of underground petroleum storage tank and conveyance facilities including tanks, piping, associated equipment and appurtenances.
B. Related Sections
1. Section 01350 – Health and Safety Plan
2. Section 02110 – Contaminated Soil Excavation
3. Section 02315 – Excavation, Backfill, Compaction and Dewatering
1.2 REFERENCES
A. 310 CMR 40.000, Massachusetts Contingency Plan (MCP)
B. 310 CMR 80.00, Underground Storage Tank Systems
C. American Petroleum Institute (API) Recommended Practice 1604, Closure of Underground Petroleum Storage Tanks
D. MADEP Policy, WSC-402-96, Commonwealth of Massachusetts Underground Storage Tank Closure Assessment Manual
E. National Fire Protection Association (NFPA) 326 – Standard for the Safeguarding of Tanks and Containers for Entry, Cleaning or Repair, latest revision.
1.3 DEFINITIONS
A. Underground Storage Tank (UST): Any one, or combination of, tanks (including underground conveyance piping related thereto) that is, or was, used to contain an accumulation of petroleum or other regulated substances, and volume of which (including the volume of underground pipes connected thereto) is 10 percent or more beneath the surface of the ground.
1.4 SUBMITTALS
A. No fewer than ten working days prior to performing the Work of this Section, submit:
1. Tank Removal Work Plan as specified herein.
2. Copies of all local, State, or Federal permits and licenses obtained as required herein.
3. Written confirmation that local authorities have been notified of planned tank removal activities in accordance with local requirements.
Tighe&Bond
S-2127/12/16/16 02115 - 2 Underground Storage Tank and Piping Removal
1.5 TANK SUMMARY
A. Underground storage tanks at the Site are located in areas designated on the Drawings. The summary of underground storage tank at the Site which is to be removed under this Section is as follows:
Location Quantity Capacity (gallons)
Contents
Lincoln Avenue Pump Station 1 2,000 Fuel Oil
B. The approximate location of the tank is shown on the Drawings.
C. In the event that additional, previously unidentified underground petroleum storage tanks are encountered during the course of the Work, Owner will advise Contractor if such tanks are to be removed. Should Owner require removal of such tanks, the Work shall be considered a change in scope and performed in accordance with this Section.
1.6 REGULATORY REQUIREMENTS
A. Perform all tank removal, cleaning and disposal work in accordance with local, State, and Federal regulations and the requirements of any permits or authorizations.
B. An application for permit shall be obtained from the local Fire Department, and approved by the Engineer at least 72 hours prior to commencing any UST removal activities.
PART 2 PRODUCTS – NOT USED
PART 3 EXECUTION
3.1 GENERAL
A. Perform operations in a manner which considers the health, safety and protection of all Contractor and Subcontractor personnel, support personnel, Owner and his representatives, and the surrounding environment.
B. The Work of this Section shall be performed only by trained personnel who understand the associated hazards. Such personnel shall be sufficiently qualified, trained, or educated to safely carry out the necessary operations.
C. Verify all existing conditions affecting the Work.
D. Prior to initiating tank removal activities, disconnect all electrical switches supplying electrical current to equipment that may be connected to the tank to be removed.
E. Remove residual petroleum product and other free liquids from the tank prior to removal of the tank from the ground.
1. Contractor shall assume that up to 100-gallons of residual fuel and sediment will be removed from the UST system and transported offsite for disposal, excluding cleaning fluids.
2. The tank shall be rinsed with a minimum of 55-gallons of clean water to remove residual materials. Cleaning fluids shall be removed and disposed of following State and Federal requirements.
Tighe&Bond
S-2127/12/16/16 02115 - 3 Underground Storage Tank and Piping Removal
3. Owner shall approve and sign all waste manifests prior to transporting any waste fuels offsite.
4. Prior to transportation offsite each tank shall be inerted using dry ice as detailed in paragraph 3.4.B of this Section.
3.2 TANK REMOVAL WORK PLAN
A. Develop, implement, maintain, and supervise as part of the Work, a comprehensive Tank Removal Work Plan for tank removal, cleaning, and related operations. The plan shall include, but not be limited to, methods, means and sequence of operations for excavation, removal, cleaning, and ultimate disposal of the tank. The Tank Removal Work Plan shall be based on NFPA 326 and API 1604, Contractor experience, requirements of this Section, and applicable permits, approvals, authorizations, laws, and regulations.
B. At a minimum, the Tank Removal Work Plan shall include:
1. Overall approach to tank removal.
2. Pre-removal investigation activities.
3. Methods to be employed for product, sludge, vapor, and pumpable liquid removal; purging and inerting; and storage/disposal methods.
4. Proposed location(s) of any tank staging area(s) to be utilized for the temporary storage and cleaning of tank.
5. Tank opening and tank cleaning procedures applicable to in-place cleaning, if applicable, and cleaning at tank staging areas.
6. Identification of waste and tank transporters and means of transportation.
7. Treatment, disposal, and alternate facilities, and means of treatment, disposal or remediation.
8. Spill prevention procedures.
9. Spill contingency procedures.
10. Decontamination procedures and safety measures.
C. The Work of this Section shall not be performed until the Tank Removal Work Plan is reviewed by Owner, Engineer and/or representatives, and authorization is given to proceed.
3.3 PREPARATION
A. Determine nature and quantity of tank residuals to facilitate disposal of same. If necessary, sample residual product, pumpable liquids, and sludge. If the data is not adequate, perform additional sampling and analysis to the extent required by the approved off-site treatment/disposal facility. Satisfy all regulatory requirements related to management of tank residuals.
B. Before excavating, drain product piping back to the tank, remove residual liquids trapped in the product lines, and remove all product from the tank.
Tighe&Bond
S-2127/12/16/16 02115 - 4 Underground Storage Tank and Piping Removal
C. Disposal
1. Collect, contain and dispose of all un-salvageable tank products and sludge off the Site for offsite disposal.
D. All equipment used in draining and ventilating the tanks shall be properly grounded to prevent electrostatic discharge hazards.
3.4 INERTING
A. After tank and piping contents have been removed, but prior to excavation beyond top of tank, disconnect all piping (except the piping which may be needed to inert the tank). The tank made inert in accordance with NFPA 326 and API 1604.
B. The tank shall be inerted using dry ice at a rate of 1.5 pounds per 100 gallons of tank volume (30 pounds of dry ice for a 2,000-gallon tank) distributed evenly throughout the tank.
3.5 EXCAVATION
A. Obtain excavation / trench permit from the Town of Saugus.
B. Control excavation areas in accordance with Contractor’s Health and Site Safety Plan (HASP).
C. Excavate exploratory trenches as necessary to determine the tank location, orientation, limits and the location of ancillary equipment.
D. Excavate around the perimeter of the tank so as to limit the amount of potentially contaminated soil that could be mixed with previously uncontaminated soil. If tank is to be cleaned in-place, excavate and remove soil only as required to gain access to the tank and safely perform cleaning operations.
E. Excavate as necessary to remove tank, piping, and ancillary equipment. Install sheeting, bracing, or shoring if required.
F. Implement measures as appropriate to secure open excavations during any period when tank excavations remain open. Backfill the excavations as soon as possible after tank and contaminated soil removals have been completed and confirmation samples have been taken.
G. Implement measures as appropriate to divert surface water or runoff around excavations to prevent water from directly entering into open excavations.
3.6 REMOVAL OF PIPING, ANCILLARY EQUIPMENT, AND TANK
A. Disconnect all piping and ancillary equipment from the tank. Remove all piping and conduit associated with tank to maximum extent possible. Cap all tank ancillary equipment and piping connections, except those connections necessary to inert the tanks within the excavation zone. The piping exterior and ancillary equipment shall be cleaned to remove all soil and inspected for signs of corrosion and leakage. Contaminated soil and/or groundwater is not expected. However, if contaminated materials are encountered during tank and piping excavation, (i.e., stained soil, free product), Owner will advise Contractor
Tighe&Bond
S-2127/12/16/16 02115 - 5 Underground Storage Tank and Piping Removal
if such materials are to be removed. Should Owner require removal of contaminated soil or groundwater, Work shall be performed in accordance with this Section.
B. Remove tank from the excavation and clean the exterior to remove all soil. Inspect for signs of corrosion, structural damage, or leakage. Take photos to document tank condition. All materials coming into contact with the tank, or in the vicinity of the excavation such as shovels, slings and tools shall be of the non-sparking type. After removal from the excavation, place tank in approved tank staging area on a level surface and secure with wood blocks or other devices to prevent movement. Tanks may also be loaded directly onto trucks/trailers for transportation to an approved disposal yard
C. Remove all associated pumps, piping, concrete pads, and associated equipment. It is anticipated that non-contaminated tank-related materials such as concrete debris, tank pad or deadmen will not require management as Contaminated Materials.
D. After the tank and associated equipment has been removed from the ground, Engineer will examine and test adjacent and underlying soils for any evidence of contaminated soil. Should the Engineer’s examination or testing identify soils as contaminated soil, Owner may require removal of contaminated soil or groundwater. Removal of contaminated soil shall be performed in accordance with this Section. Perform contaminated soil excavation in accordance with Section 02110 – Contaminated Soil Excavation.
E. Take no fewer than 8 photographs of this Work.
3.7 TANK CLEANING
A. All tank cleaning/decontamination will be conducted at the Site in designated tank staging area(s), as approved by Owner. No tanks will be permitted to leave the Site until such Work has been completed.
B. Tank cleaning may be conducted with tank in-place, or at a tank staging area, and shall be in accordance with approved Tank Removal Work Plan.
C. The tank shall not be cut open or otherwise partially demolished for cleaning or transportation at the Site.
D. Prior to cleaning the tank interior, monitor tank atmosphere for combustible vapors. If required, purge or inert in accordance with this Section.
E. Clean exterior of tank, piping, and associated equipment, as required, using non-sparking tools, to eliminate soil deposition on roadways during transportation to temporary storage area and to simplify tank cutting.
F. Plug or cap all accessible openings after the tank has been cleaned and freed of vapors. Leave a one opening with a minimum 1/8-inch diameter vent hole in one fitting. Position tank fittings and the vent on top during storage and transportation to an approved disposal facility.
3.8 TRANSPORTATION AND DISPOSAL REQUIREMENTS
A. After the tank, piping, and ancillary equipment have been cleaned, transport the tank off-site for disposal. Cutting or otherwise dismantling the tanks on site is not allowed.
Tighe&Bond
S-2127/12/16/16 02115 - 6 Underground Storage Tank and Piping Removal
1. A form FP-292 must be completed and approved by the local authorities before the tank can be transported offsite. A copy of the FP-292 shall accompany the tank to the disposal yard.
2. Provide a copy of the completed and approved FP-292 to the Owner within 48 hours of transporting the tank offsite.
B. The tank shall be disposed of at a disposal facility approved as such by the Massachusetts State Fire Marshal’s office.
1. The Contractor shall provide a copy of the tank disposal receipt (FP-291) to the Owner within 48 hours of transporting the tank offsite.
C. Transport all tank-related materials and any ancillary equipment for off-site disposal in accordance with applicable regulations.
3.9 CONFIRMATION TESTING BY THE ENGINEER
A. Following tank removal, if Engineer does not require contaminated soil excavation, or following the work of contaminated soil excavation if required by Engineer, Engineer will collect confirmation samples from the tank area in accordance with The Massachusetts Department of Environmental Protection requirements.
B. Should the results of Engineer’s testing indicate additional contaminated soil excavation is required, Engineer will define those areas beyond the original excavation limits where additional contaminated soil excavation is required. Contaminated soil excavation shall be performed in accordance with Section 02110 – Contaminated Soil Excavation.
END OF SECTION
J:\S\S2127 Saugus - Lincoln Ave PS\02 - UST Replacement\SPECS\Div 2\02115.docx
Tighe&Bond
S-2127/12/16/2016 13201-1 Fuel Storage Equipment
SECTION 13201
FUEL STORAGE EQUIPMENT
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes
1. Fuel storage tank, piping, pump and associated equipment
2. As-Built Documentation
B. Related Sections
1. Section 15050 – Piping - General
2. Section 13426 – Fuel Tank Monitoring System
1.2 REFERENCES
A. 527 CMR 1.00 – Massachusetts State Fire Code
B. National Fire Protection Association (NFPA) Standard 30 - Flammable and
Combustible Liquids Code, latest edition
C. NFPA 31 – Standard for the Installation of Oil Burning Equipment, latest edition
D. Steel Tank Institute R912-00 – Installation Instructions for Shop Fabricated
Stationary Aboveground Storage Tanks for Flammable, Combustible Liquids
E. Uniform Fire Code, Article 79 – Flammable and Combustible Liquids, latest edition
F. Underwriters Laboratories, Inc. (UL) Standard 971 – Standard for Nonmetallic
Underground Piping for Flammable Liquids, latest edition
G. UL Standard 1316 – Standard for Glass-Fiber Reinforced Plastic Underground
Storage Tanks for Petroleum Products, Alcohols, and Alcohol-Gasoline Mixtures,
latest edition
1.3 SUBMITTALS
A. Shop drawings and manufacturer's product information for equipment not provided
by the Owner.
B. Factory and field test reports.
C. Warranty information.
1.4 QUALITY ASSURANCE
A. Equipment manufacturers shall have a minimum of ten years of experience in the
design and manufacture of equipment of similar size, type, and capacity.
Tighe&Bond
S-2127/12/16/2016 13201-2 Fuel Storage Equipment
B. Contractor shall have a minimum of ten years of experience in the installation of
equipment of similar size, type, and capacity and complete 10 projects of similar
scope within the past two years.
C. Contractor shall verify tank integrity at the time of delivery from the manufacturer
and the integrity of the tank and piping system upon completion of the installation.
PART 2 PRODUCTS
2.1 UNDERGROUND STORAGE TANK
A. Provide one 2,500-gallon double-walled fiberglass, cylindrical, horizontal,
underground storage tank with one factory installed sump collar.
1. The tank shall be manufactured in a manner that produced a non-air inhibited
and high gloss laminate to provide a fully cured inner and outer surface.
B. The double-walled tank shall have a monitoring space between the walls to allow for
the free flow and containment of leaked product from the primary tank. The
monitoring space shall provide equal communication in all directions.
C. The tank shall have an integrally mounted annual space reservoir installed on the
tank for factory-installed brine and continuous monitoring.
1. The reservoir shall be constructed of fiberglass reinforced plastic material and
be included in the tank warranty.
2. The monitoring port fitting shall be a 4-inch NPT fitting.
3. The monitoring system, when installed, shall be capable of detecting a breach
in the inner and outer tank under the following conditions:
a. When the primary tank is empty.
b. When the primary tank is partially or completely full and the ground
water table is below the tank bottom.
c. When the primary tank is partially or completely full and the tank is
partially or completely submerged in groundwater.
4. The hydrostatic monitoring solution shall a calcium chloride solution,
compatible with the tank and be of a contracting color to the tank.
D. The underground storage tank shall meet the following load conditions:
1. External hydrostatic pressure: buried in ground with a maximum of 7-feet of
burden over the top of the tank, the excavation fully flooded and a safety
factor of 5:1 against general buckling.
2. Surface loads: tank shall be installed to withstand surface H-20 axle loads.
3. Internal loads: primary and secondary tanks shall withstand 5 psig air
pressure test with 5:1 safety factor.
E. The tank shall be provided with a 30-inch flanged manway as shown on the
Drawings.
Hold down straps shall be anchored to the deadmen using galvanized drop- forged turnbuckles sized in accordance with the manufacturer’s requirements.
Looped wire rope may be substituted for one turnbuckle on each hold down strap. Looped wire rope shall meet the tank manufacture’s installation requirements.
All threaded fittings shall be located on a manway cover or within 12” of the tank top center line. Fittings to be supplied with temporary thread protectors or threaded plugs.
All standard fittings shall be 4” diameter NPT half couplings.
Tank shall be capable of storing liquids with a specific gravity of 1.1.
Tank shall be capable of storing:
Diesel fuel oil to include No. 2 fuel oil, biodiesel blends with up to 100% biodiesel.
Tighe&Bond
S-2127/12/16/2016 13201-3 Fuel Storage Equipment
F. Tank Sumps
1. The tank shall be provided with a factory installed, fiberglass reinforced
plastic, secondary containment collar with a minimum diameter of 42-inches.
a. Secondary containment collar shall bear a UL label.
b. The collar shall include an internal adhesive channel for affixing the
containment sump.
c. The collar shall be included in the tank warranty.
2. Tank sumps & collars shall be listed by Underwriters Laboratories for
petroleum fuels and all blends of alcohol (same as tank). Collar and sump
shall be tested and listed as a complete sump system.
3. Tank sump components shall be constructed of fiberglass reinforced plastic.
The tank sump shall be 42-inches in diameter and must mount to the
secondary containment collar. The sump height shall meet the requirements
shown on the Drawings.
4. A 34-inch watertight lid shall be installed to provide a watertight seal to the
sump enclosure with 12-inches of water above the lid and remain leak free.
G. Concrete deadmen shall meet the following criteria:
1. Design shall be in accordance with ACI 318 to the minimum number and
dimensions shown on the Drawings.
2. Manufactured using 4,000 psig concrete.
3. Provide adjustable anchor points for hold down straps.
H. Fiberglass hold down straps of the size and quantity specified by the storage tank
manufacturer.
1. Hold down straps shall be anchored to the deadmen using galvanized drop-
forged turnbuckles sized in acc“rdance with the manufacturer’s requirements.
2. Looped wire rope may be substituted for one turnbuckle on each hold down
stra”. L““”ed wire r“”e shall meet the tank manufacture’s installati“n requirements.
I. All threaded fittings shall be located “n a manway c“ver “r within 12 “f the tank top center line. Fittings to be supplied with temporary thread protectors or threaded
plugs.
J. All standard fittings shall be 4 diameter NPT half c“u”lings.
K. Tank shall be capable of storing liquids with a specific gravity of 1.1.
L. Tank shall be capable of storing:
1. Diesel fuel oil to include No. 2 fuel oil, biodiesel blends with up to 100%
biodiesel.
Tighe&Bond
S-2127/12/16/2016 13201-4 Fuel Storage Equipment
2. Gasoline, alcohol-gasoline blends with up to 100% ethanol and alcohol-
gasoline blends with up to 100% methanol.
M. Pipe fittings, bushings, anchors, electrical wiring and ancillary required to provide
the Owner with a fully functional fuel system.
N. Steel manhole rings and covers as shown on the Drawing.
1. The steel manhole ring and tank top leak detection sump and cover and
concrete pad shall be of design and construction to meet an H-20 load rating.
The steel ring frame shall have a galvanized steel skirt of at least 10-inches
in depth and of at least 14-gauge steel construction. The manhole ring, cover
and concrete pad shall be of size and design to be compatible with the
manhole/sump riser system.
2. Manhole ring and covers shall be set ½-inch above finished grade of the
concrete pad. The concrete pad shall be sloped around the manhole
perimeter to direct water away from the manholes.
2.2 PIPING
A. General
1. Provide one ¾-inch fuel oil supply and one ¾-inch fuel oil overflow / return
piping from the underground storage tank to the new day tank, and from the
day tank to the generator.
a. ¾-inch piping shall be of double walled construction with the primary
and secondary containment piping made of materials that have
demonstrated compatibility for use with fuel oil.
b. The primary and secondary containment piping shall be factory
assembled.
c. Piping shall be run from the tank containment sump to the pump station
in a continuous run. No splicing shall be allowed.
2. All piping located below grade shall be of double-walled construction in
accordance with the requirements of UL971 and bearing the UL label.
3. Aboveground piping shall be constructed of Schedule 40 single-walled steel.
a. Aboveground steel pipe shall be painted in accordance with the
requirements of Section 15102.
4. Transitions between the double-walled underground pipe to the single-walled
aboveground pipe shall be completed within the 3-inch corrugated
containment pipe.
a. Clamshell or swage fitting shall be protected within the corrugated
containment pipe.
b. Provide a liquid tight transition assembly where the steel piping exits
the containment pipe, OPW Flexworks PTA-4175 or equal.
Piping shall be constructed at the factory consisting of a primary pipe and secondary pipe capable of containing release from the primary pipe for the purpose of leak detection.
Piping shall be pitched a minimum of 78-inch to 14-inch per foot so that the low end of the pipe is located at the tank sump.
Flexible double-walled pipe from the tank to the transition to single-walled pipe shall be installed as a single pipe without tears, cuts or splices.
Male and female piping connections shall be made using stainless steel swivel type fittings.
Tighe&Bond
S-2127/12/16/2016 13201-5 Fuel Storage Equipment
B. Double-walled Pipe
1. Pipe specifications:
a. Pipe size: ¾-inch
b. UL Certification: UL 971
c. Maximum working pressure: 145 psig
d. Minimum bend radius: 18-inches
2. Piping shall be constructed at the factory consisting of a primary pipe and
secondary pipe capable of containing release from the primary pipe for the
purpose of leak detection.
3. Piping shall be pitched a minimum of 1/8-inch to ¼-inch per foot so that the
low end of the pipe is located at the tank sump.
4. Flexible double-walled pipe from the tank to the transition to single-walled
pipe shall be installed as a single pipe without tears, cuts or splices.
5. Male and female piping connections shall be made using stainless steel swivel
type fittings.
a. All fitting connectors installed below grade shall be contained within
the piping sump.
1) Fittings at the transition from the double-walled to single-walled
pipe shall be located above grade as shown on the Drawings.
b. Fittings shall have an internal expanding stainless steel coupling and
Viton ring gasket.
c. The installation of the stainless steel fittings shall not cover the
secondary containment pipe, or otherwise interfere with the secondary
pipe.
6. Fuel supply and return piping shall be routed through a single 4-inch
corrugated flexible conduit. The corrugated pipe shall be capable of
withstanding an H-20 loading when properly installed.
7. Piping compatibility shall be consistent with that of the underground storage
tank as detailed in paragraph 2.1.L of this Section.
8. Flexible sump entry boots shall be provided at each pipe and conduit
penetration through the sump wall.
a. Entry boots shall be bonded to the sump wall in accordance with the
manufacturer’s installati“n instructi“ns.
b. All sump penetrations shall be watertight.
c. Pipe and conduit penetrations shall exit through the sump wall at an
angle perpendicular to the sump wall.
Grade level cover shall be marked “DO NOT FILL”
“CAUTION - WHEN ALARM BELL SOUNDS TANK IS FILLED TO CAPACITY - DO NOT OVERFILL”
Tighe&Bond
S-2127/12/16/2016 13201-6 Fuel Storage Equipment
d. The angle of pipe and conduit penetrations shall not exceed 10 degrees
off the centerline of the entry boot flange.
C. Single-Walled Pipe
1. Pipe specifications:
a. Pipe size: ¾-inch
b. Construction: Schedule 40
c. Maximum working pressure: 1,000 psig
2. Pipe supports shall meet the requirements of the Massachusetts Building
Code.
3. Interior and exterior pipe shall be painted in accordance with Section 09900.
2.3 UNDERGROUND STORAGE TANK EQUIPMENT
A. The following ancillary equipment shall be provided:
1. One automatic shut off valve.
a. Automatic shut off valve shall be set to limit the tank volume to 95%
capacity.
b. Valves shall be compatible with the material stored.
c. Drop tube shall extend to within four-inches of the tank bottom.
2. One five-gallon below grade spill bucket, OPW model 101BG, EBW model
705, or equal.
a. Surface loads: spill bucket cover shall be installed to withstand surface
H-20 axle loads.
b. Grade level spill bucket cover shall be painted yellow indicating diesel
fuel storage.
3. Interstitial monitoring hand hole as shown on the Drawing.
a. Surface loads: spill bucket cover shall be installed to withstand surface
H-20 axle loads.
b. Grade level c“ver shall be marked DO NOT FILL
B. Fuel tank monitoring system console, level probe, lead detection sensor and alarm
shall be provided in accordance with the requirements of Section 13426.
2.4 SIGNAGE
A. Provide the following sign posted on the building, adjacent to the audible / visual
overfill alarm:
1. CAUTION – WHEN ALARM BELL SOUNDS TANK IS FILLED TO
CAPACITY – DO NOT OVERFILL
Tighe&Bond
S-2127/12/16/2016 13201-7 Fuel Storage Equipment
2.5 DAY TANK
A. Day Tank specifications:
1. Capacity: 50-gallons
2. UL Certification: UL 142
3. Tank style: rectangular, double-walled
4. Maximum internal working pressure: 5-psig
5. Pump flow rate: minimum of 5-gallons per minute
6. Electrical requirements: Single-phase
B. The day tank shall be provided with the following equipment:
1. Fuel supply pump meeting the requirements specified in paragraph 2.5.A of
this Section.
2. 3-inch legs, front and back
3. Hand pump for tank priming
4. ¾-inch engine supply drop tube
5. ¾-inch siphon drain drop tube
6. Minimum ¾-inch overflow port
7. Minimum 1-inch engine return port
8. Minimum 2-inch vent port
a. Vent pipe shall be routed outside of the pump station
9. Minimum 2-inch manual fill drop tube
10. ¾-inch hand pump mounting drop tube
11. ¾-inch pump connection drop tube
12. 1-inch float switch inspection port
13. 4-inch primary tank emergency vent
14. 4-inch interstitial tank emergency vent
PART 3 EXECUTION
3.1 INSTALLATION AND TESTING
A. Sump and spill bucket testing:
1. Contractor shall conduct a hydrostatic test of the piping leak detection sump
and spill bucket by filling the sump with water to the level that activates the
leak detection sensor.
Tighe&Bond
S-2127/12/16/2016 13201-8 Fuel Storage Equipment
2. The test will be considered a failure if there is a loss of 1/8-inch or greater of
water over a period of one hour.
3. Should the sumps fail the hydrostatic test, the contractor shall be responsible
for repairing or replacing the sump and /or spill bucket and retesting the
failed equipment at no cost to the Owner.
4. Provide records of the hydrostatic test to the Owner and Engineer. The
records shall include the results of the test, date and time of the test and the
name and company of the individual performing the test.
B. CONTRACTOR, prior to installation, shall obtain the required state and local
permits.
C. Furnish all labor, materials, equipment and supervisory, operating and monitoring
personnel to conduct the Work as shown on the plans and specified herein in a safe
and professional manner. All work shall be conducted in accordance with NFPA 30
and 30A, 527 CMR 1.00, API RP 1615, UL 1316, UL S615. PEI Recommended
Practice 100 and PEI Recommended Practice 300.
D. CONTRACTOR shall furnish and install all other items including hangers, supports,
valves, piping, relief valves, and all other devices required to complete the system.
E. Installation of equipment and materials shall be in accordance with the manufacturer's
recommended practice and appropriate sections of the Project Manual. Where
conflict occurs between regulatory requirements, the manufacturer's recommendation
and the Project Manual or plans, the more stringent requirements will take
precedence.
F. Pipe fittings installed underground and inside building and shall be constructed with
dielectric isolation when necessary.
G. Tank and appurtenance secondary enclosures shall be shop-fabricated as one unit at
the factory and require no assembly, construction or completion at installation site.
H. The tank and piping excavations shall be free from material that may damage the tank
coating. Care shall be taken so that foreign matter is not introduced into the
excavation or backfill during Work.
I. Equipment to perform Work shall be of to ensure that no damage to the tank or
appurtenances occurs.
END OF SECTION
J:\S\S2127 Saugus - Lincoln Ave PS\02 - UST Replacement\SPECS\Div 13\13201.doc
SECTION 13426
FUEL TANK MONITORING
Tighe&Bond
S-2127/12/16/16 13426-1 Fuel Tank Monitoring Systems
SECTION 13426
FUEL TANK MONITORNG SYSTEM
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes
1. Fuel tank level detection, leak sensing and alarm equipment for the new
underground storage tank
2. As-Built Documentation
B. Related Sections
1. Section 13201 – Fuel Storage Equipment
2. Section 16050 – Basic Electrical Requirements
3. Section 16075 – Electrical Identification
4. Section 16120 – Conductor and Cables
5. Section 16131 – Conduit
6. Section 16136 – Boxes
1.2 REFERENCES
A. 527 CMR 1.00 – Massachusetts State Fire Code
B. National Fire Protection Association (NFPA) Standard 30 – Flammable and
Combustible Liquids Code, latest edition
C. NFPA 30A – Motor Fuel Dispensing Facilities and Repair Garages, latest edition
D. NFPA 31 – Standard for the Installation of Oil Burning Equipment, latest edition
E. Uniform Fire Code, 2000 Edition, Article 79 – Flammable and Combustible Liquids
1.3 SUBMITTALS
A. Shop drawings and manufacturer's product information for tank level probes,
interstitial monitoring sensors, alarms boxes and cable.
B. Warranty information.
1.4 QUALITY ASSURANCE
A. Equipment shall be compatible with the existing Veeder-Root TLS 350 console.
B. Manufacturer shall have a minimum ten years’ experience in the design and
manufacture of equipment of similar size, type, and capability.
C. Tank level probe shall be able to detect a leak or discharge of 0.20 gallons per hour
with a probability of detection of 0.95 and a probability of false alarm of 0.05 as
determined by the National Work Group on Leak Detection Evaluators.
Tighe&Bond
S-2127/12/16/16 13426-2 Fuel Tank Monitoring Systems
PART 2 PRODUCTS
2.1 GAUGING AND MONITORING SYSTEM
A. Provide Veeder-Root TLS-300C fuel management system or approved equal.
B. Fuel management console shall be located inside the Lincoln Avenue Pump Station.
1. Control console shall have a digital display and printer.
C. Electronic fuel management system shall include the following:
1. Tank level probe for both fuel and water level sensing in the fuel storage
tank.
a. Metallic probe components shall be of stainless steel construction.
b. Floats shall be compatible with the material stored.
2. Interstitial leak detection between the inner and outer walls of the brine filled,
double-walled storage tank as follows:
a. The monitoring system, when installed, shall be capable of detecting a
breach in the inner and outer tank under the following conditions:
1) When the primary tank is empty.
2) When the primary tank is partially or completely full and the
ground water table is below the tank bottom.
3) When the primary tank is partially or completely full and the
tank is partially or completely submerged in groundwater.
b. Double float reservoir sensor compatible with the brine solution and
capable of providing two alarm points positioned 10-inches apart.
c. The leak detection performance of the monitoring system shall be listed
as a continuous interstitial monitoring method by the National Work
Group on Leak Detection Evaluations (NWGLDE).
3. Piping sump leak detection sensor.
a. Sensor shall be a non-discriminating type sensor installed in the lowest
portion of the sump.
4. Signal wiring of required length for the liquid level sensor and for the leak
detection probes.
D. Provide audible and visible, weather-proof alarm horn in a stainless steel enclosure.
1. Program alarm to activate at 90% of the tank’s capacity.
2. Alarm shall be equipped with a test button and alarm acknowledgment switch.
a. Acknowledgement /test switch shall be located in the exterior of the
building at a minimum height of 4-feet and a maximum of 6-feet.
b. Pressing the acknowledgement switch shall silence the alarm horn.
Tighe&Bond
S-2127/12/16/16 13426-3 Fuel Tank Monitoring Systems
3. Confirm placement of alarm and acknowledgement switch with Engineer and
Owner prior to installation.
2.2 TANK FILLING AND OVERFILL PREVENTION COMPONENTS
A. Provide three copies of an inches-to-gallons tank conversion chart specific to the
installed underground storage tank.
B. Provide tank gauge stick with measurements divided into 1/8 inch increments.
1. Overfill prevention valve shall not prevent Owner’s personnel from using the fill connection to manually gauge the tank contents.
2.3 INSTALLATION
A. Obtain all necessary state and local permits prior to installation.
B. Install the systems and accessories in strict accordance with the manufacturer’s recommendations and applicable fire, building, electrical and environmental codes.
C. Perform system tests in accordance with the manufacturer’s recommendations and NFPA 30 and NFPA 30A.
2.4 DEMONSTRATION AND TRAINING.
A. Demonstrate operation of the fuel monitoring systems in the field following
installation.
B. Provide one 2-hour onsite training sessions to instruct Pump Station personnel on
the operation and maintenance of the monitoring and gauging system. Travel time
to and from the Lincoln Avenue Pump Station is excluded from the 2-hours of
onsite training.
END OF SECTION
J:\S\S2127 Saugus - Lincoln Ave PS\02 - UST Replacement\SPECS\Div 13\13426.doc