Light Rail Performance Initiatives Update February 4, 2014

Transcript of Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround...

Page 1: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Light Rail Performance

Initiatives Update

February 4, 2014

Page 2: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Performance • On June 4, 2013,

initiatives to improve light rail performance were outlined

• On-Time Performance up from 47% in May to 51% in January, driven mostly by an increase in early arrivals and decline in late arrivals

47.4% 46.8% 47.2% 47.2% 47.1% 49.8% 50.3% 50.4% 50.7%

18.92% 20.19% 21.43% 21.37% 20.67% 23.25% 24.31% 25.67%

28.03%

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14

On-Time Performance - Light Rail

On-Time Early

Page 3: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Light Rail Delays

• Hours of delay down from 452 hours of vehicle delay in May to 414 hours of vehicle delay in December (8% decline)

• Delays continue to be concentrated with vehicle issues

• One delay in the subway majorly impacts all lines

Muni Related Accident, 1%

Train Control System Delay,

13%

Vehicle Mechanical Issues, 75%

Non-Muni Related

Accident, 1%

Operator Necessity

, 3%

SFPD or SFFD Blocking, 3%

Other, 3%

Rail Delays by Type

Page 4: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Major Issues to Address to Improve

Service

1. Operations

2. Light rail vehicle maintenance

3. Infrastructure maintenance

4. Technology & Communications

Initiatives already underway and completed!

Page 5: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Operations Improvements

Page 6: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Operations: Embarcadero Improvements

• Increased supervision and focus on turnarounds

• Improved turnaround time from 7.1 minutes to 5.3 minutes

• Results: – Improved train turnaround capacity

(17 trains to 23 trains!)

– Increase in early departures from Embarcadero

• Adjusting schedules for Spring 2014

• Installed queue markings at Embarcadero

Almost two minutes in

savings!

Page 7: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Operations: Shuttles

• Launched three car shuttle train in October

– Operates during the morning and evening weekday commutes from West Portal to Embarcadero

– Popular with customers in the subway

– Customers like getting a seat through the congested subway

• Tested concept of an N-Judah Shuttle to Hillway where trains are often crowded

– One car shuttle during morning commute worked

– Planning on starting regular pilot in Spring 2014

Page 8: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Operations: Supervision and Training

• Rail supervisors trained by rail maintenance

on troubleshooting to help expedite delays –

Reduction in delay length

• Finalizing troubleshooting card and training

program for operators to reduce delays

• Repositioning rail

supervision staff

to better address

system needs

Page 9: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Operations: Reduce Slow Zones

• Increased the travel speed between Castro and

West Portal Stations from 35 MPH to 45 MPH

after extensive safety testing

• Reviewed and

reassessed mandatory

stop locations on the rail

lines

• Removed over half of

locations (73 total)

• Overall gain in 2-4

minutes on travel time!

Page 10: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Operations: Focus on Portal Entries

• Each time a train does not attain automatic control at the entrance to the subway, the train is delayed and could lead to reduce speed in the subway

• Focusing on operator, vehicle, and infrastructure issues related to failed entries – Retraining of operators with multiple failed entries

– Inspecting vehicles after failed entries

• Failed entries down 50%

Page 11: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Operations: Switchbacks

• Implemented stricter switchback guidelines in Spring 2013

• Using alternative techniques to rebalance service and minimize switchbacks

• Down from over 700 incidents in Spring to 300 at the end of 2013

• Focus on customer communications via social media and electronic signage

• Implemented Nextbus update to update predictions when switchback implemented

Page 12: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Vehicle Improvements

Page 13: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Vehicles: Light Rail Fleet

• Door problems

continue to be largest

failure type

• Vehicle performance is

flat

• Must continue to invest

in fleet in order to last

for 10 more years

ATCS, 17.3%

DOORS/STEPS, 36.4%

PROPULSION, 24.3%

OTHER, 21.9%

Light Rail Vehicle Roadcall Type

Page 14: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Vehicles: Rehabilitation Program

• 74 cars completed to date

– Replaced the communications link between the LRV, ATCS and the wayside equipment

– Redesigned and replaced articulation wiring harnesses and yoke pins to allow for significant reductions in troubleshooting, repairs, and cost

– Replaced traction motor bearings in the LRVs to extend the useful life of the equipment

• Following rehabilitation, the door performance was unchanged on rehabilitated cars, as a result the scope of the existing contract was modified to:

– Remove rehabilitation of doors/steps from contract

– Substitute rehabilitation of trucks for same price as doors/steps

– Remove partial rehabilitation of air supply units

– Include propulsion rehabilitation items that were not included in the existing contract

Page 15: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Vehicles: Propulsion

• Current propulsion equipment has exceeded is useful life, resulting in an unacceptable level of failures.

• Campaigns for targeted components of the propulsion system were instituted to improve propulsion performance, such as: – Rebuilding line breakers

– Replacing starter relays

– Replacing capacitors

• Finalizing capital program to complete other major subsystems in propulsion

Page 16: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

• Completed 13 focused campaigns to improve reliability, MDBF and safety, such as:

– Door overhaul – 28 cars completed

– ATCS card rehabilitation – all cars

– Replaced Knorr brake communication boards – all cars

– Replaced tachometers – all cars

• Completed 97% of PM inspections on time

Vehicles: Campaigns

Page 17: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Next Generation Light Rail Vehicles

• Procurement of 175 cars

• Bids due in February 2014

• Award expected in Summer 2014

• Cars expected to start arriving at the end

of 2016

Page 18: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Infrastructure

Improvements

Page 19: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Infrastructure: Signal Improvements

• Signal priority up and running on Third

Street and regularly monitored

• Fiber optic communications work underway

to improve benefits

• Signal preemption (change lights to green)

installed at six intersections on Third Street

• Fourth and King Intersection improved to

reduce T-Third delays and more signal

improvements coming

Page 20: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Infrastructure: Signal Standardization

• Coordinating maintenance schedules

between SFMTA Signal Shops to increase

preventative maintenance on signals

• Replaced 29 outdated signals with larger

four aspect heads

• Signal Priority System upgraded to latest

generation of controllers along T Third

Page 21: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Infrastructure: Double Berthing

• Double Berthing: Allows two trains to stop

and load/unload passengers at the

platforms together in the subway

• Upgrade status:

– Programming updated and testing completed

– Awaiting State certification for installation

– Implementation in early Spring

Page 22: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Infrastructure: Train Control

• Old relay system controlling switch operations in subway in conjunction with train control system

• Old relay system not supported and parts hard to procure

• Upgrading train control system to eliminate need for relay system and fully realize benefits of train control system installed in the 1990s

• Phase I underway with final cutover planned for late 2014

• Result will be improved reliability through use of fully modern, supported train control system

Page 23: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Infrastructure: Rail Projects

• Rail replacement completed in the

Embarcadero

• Rail replacement scheduled for Sunset

Tunnel and Twin Peaks Tunnel over next year

• Other Rail Projects:

– Replacement of powered track switches with next

generation equipment

– Replacement of analog axle counters with digital

counters

Page 24: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Infrastructure: Projects Needed to Prevent

Crippling Subway Delays

• Replace Train Control and Signal Wiring

• Replace switch machines which control routing

• Replace train control circuit cards

• Back-up power source for train control system

• Replace subway crossovers

• Divide power circuits on J and N lines

Page 25: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Technology and

Communications

Improvements

Page 26: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Technology & Communications

Improvements

• Communications staffing for Line Management Center from 5am to 8pm

• Regular real time social media and on-street signage updates of incidents

• Prediction system upgrade to communicate when a switchback is occurring

• New subway platform signage and audio system to be installed starting in Summer

• Installation of new cameras in subway with thermal imaging capabilities to improve safety and security this summer

Page 27: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Safety Initiatives

Page 28: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Safety Focused Actions

• Signal standardization completed

• Worker protection completed

• Between car barrier testing underway on 13 cars

• Vehicle camera installation underway in driver cab and additional cameras in passenger area

• Beginning in 2014, ultrasonic testing will identify potential defects in the rail and rail grinding will bring the rail back to original configuration to lower derailment potential

• Replacement of ATCS components in relay rooms and wayside units to improve the reliability of automatic train movement in the subway

Page 29: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

On-Going Challenges

Page 30: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Challenges • Operators not fully staffed

– Many shifts over 11 hours per day

– Heavy reliance on overtime (25% of all operator overtime)

– Staffing up training and dedicating two cars to Training to improve

• Subway infrastructure aging and in need of rehabilitation – Need to prioritize programs to rehabilitate key

systems that could cripple subway

• Vehicles continue to have reliability issues

• Security issues: subway trespassers, autos on the trackway, vandalism, on-vehicle altercations

• Successful integration of new Control Center

Page 31: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Next Steps to Improving Service • Provide update in Summer 2014

• Vehicles: Three pronged approach to improvements

– Improve rehabilitation program

– Continue in-house targeted campaigns

– Advance LRV 4 procurement

• Operational Assessments:

– Review operations of rail lines and reassess service concepts with a

focus on improving subway capacity

• Infrastructure Projects:

– Move forward on improving subway infrastructure vulnerabilities

– Track replacement projects: Twin Peaks and Sunset Tunnel

– Signalization of Church and Duboce

– Irving/Judah Street signal priority

– Focused mid-life overhauls of track and infrastructure

• Adjust baseball game service management plan to improve N Judah and T

Third service

Page 32: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Bus Fleet Improvements

February 4, 2013

Page 33: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Bus Fleet Performance Improving!

• Bus performance increasing!

• Mean distance between failure up 25%

3,712 3,427

3,771 3,914 3,876

3,735 4,040 4,021

4,661

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13

• New maintenance procedures introduced

• Focused campaigns paying off

Page 34: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

3902

5457.5

7485

1347

3089

0

1000

2000

3000

4000

5000

6000

7000

8000

Motor Coach 60' Motor Coach 40' Motor Coach 30' Trolley Coach 60' Trolley Coach 40'

MDBF By Fleet

Mean Distance Between Failures (MDBF) is the average number of miles a coach travels before breaking

down and causing a delay. The higher the MDBF, the more reliable the equipment and the service.

November 2013

Page 35: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Bus Campaigns and Rehabilitation

• Rehabilitating 80 Neoplan buses to

improve reliability – Completion in June

• Trolley coach air compressor campaign

completed – Major contributor to improved

performance

• Articulated diesel coach differential

replacement – 80 completed, 0 failures

compared to approximately 3 per month

prior

Page 36: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

New Buses are Here!

• 112 New Flyer

buses are here

and are in

service!

• MDBF of over

12,000 miles!

• Entire fleet will

be replaced

within five years

Page 37: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Fleet Appearance • Interior repainting

campaign to clean the fleet! – 59 out of 83 40’ trolley

coaches completed

– 58 out of 61 60’ trolley coaches completed

• Mobile cleaning crew started in Fall – 116 graffiti calls per week

– Cleaning vehicles at the terminals

– Responding to ~30 calls per week for dirty coaches

Page 38: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Bus Safety Initiatives

• Installation of new cameras completed on over 300 buses!

– Cameras will be installed fleetwide by June

• Safety scaffolding – In use at all divisions

• Installation of 23 new in-ground hoists underway to replace 30+ year old equipment

• Rear door modification on fleet to improve customer safety – Completion in February

Page 39: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Cable Car Improvements

February 4, 2013

Page 40: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Successful Delivery of Key Cable Car

Reliability Projects

• Over 5000 cable pulleys replaced, improving cable position and height to reduce wear and tear

• Rebuilt seven track switches completely including one that had been out of service for many years

• Installed camera on cable to catch damage faster than the visual inspections

• Retrained operators on where and how to best pick up the cable

• Performed analysis of gearboxes and developed scope schedule and budget for rehabilitation of the Cable Car propulsion system

• Began capital program to rewire the traffic controls for Cable Cars.

Page 41: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Cable Car Safety Initiatives

• Installation of a left turn signal for automobiles at Hyde and California

• Upgraded control tower signal wiring at California and Powell to reduce potential cable car crossing conflicts

• Turntable latch assembly redesigned, built and installed at Powell and Market

• Replaced turntable position light to make it more visible to operators at Powell and Market

• Safety netting installed in Cable Car shop areas

• Fall protection installed in Cable Car machinery areas

• Guard railings installed around motors and gearboxes in the Cable Car facility

• Confined space training completed, including: – Calibrating and replacing as necessary gas testing equipment

– Fire protection system inspection and repair at the Cable Car facility

Page 42: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Historic Streetcar

Improvements

February 4, 2013

Page 43: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Rehabilitation Programs Underway

• Rehabilitation of 15 SEPTA cars

completed

• Bids received for rehabilitation of next 13

cars

• Success delivery of program will support

F-Market/Wharves reliability and ability to

launch the E-Embarcadero line

Page 44: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Service Initiatives & TEP

February 4, 2013

Page 45: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Major Initiatives • Two pilots launched

for Transit Effectiveness Project (TEP)

• Church Street Red Lane pilot launched in March 2013

• Lane from Duboce to 16th Street

• Travel time improved by 10% on segment (6-7 min before, 5-6 min after)

Page 46: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

5L Fulton Limited

• Launched in late October – 12 month pilot

• Expanded service by 30% on the Fulton

corridor

• Very popular with customers!

Page 47: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Transit Effectiveness Project (TEP)

• TEP progress moving rapidly

• Public outreach across the City beginning in February

• Planning Commission for Environmental Impact Review (EIR) certification in March

• Public hearing with MTAB in March to:

– Adopt EIR Project Description

– Legislate travel time reduction proposals ready for bid

– Legislate service changes

Page 48: Light Rail Performance Initiatives Update Transit Operations...on turnarounds •Improved turnaround time from 7.1 minutes to 5.3 minutes ... generation equipment –Replacement of

Route & Frequency Changes Proposed

• 10% increase in service hours

recommended for FY15/16 two year

budget

• Final plan will be determined after

February outreach