LIFT FORM SLAB CONSTRUCTION

SUBMITTED BYNAME- NEERU HOODAB.ARCH- 7TH SEM

Page 2: Lift form slab construction

Lift slab construction is a method of constructing concrete buildings by casting the floor or roof slab on top of the previous slab and then raising the slab up with hydraulic jacks, sobeing cheaper and faster as it does not need forms & shores as it is needed for cast-in-place slabs. Lift-slab construction can be more economic than conventional construction when thebuilding is vertically uniform, such as for hotels, apartment buildings, and dormitories,and where the slab designs are repetitive.

INTRODUCTION

Page 3: Lift form slab construction

After the slabs have cured long enough to reach a prescribed strength, powerful hydraulic jacks mounted on top of the columns lift the slabs into their respective positions. A console connected to each hydraulic jack synchronizes the number of turns of the check nuts to assure that the concrete slab is being raised the same amount at all points.Lift slab can be used for heights up to about 16 stories.Economical column spacing ranges from 22 to 32 feet. Columns may be pipe, tubes or wide flange sections;concrete columns may be used in 3- to 4-story buildings.

Page 4: Lift form slab construction
Page 5: Lift form slab construction
Page 6: Lift form slab construction
Page 7: Lift form slab construction
Page 8: Lift form slab construction
Page 9: Lift form slab construction

Lift-slab construction method becomes more advantageous in buildings with similar floorplans throughout the height of the building and where flush slab may be desired.• This method eliminates the need for redundant formwork as only shuttering required onthe edges, therefore casting concrete slabs is the simplest stage in whole constrictionprocess of lift-slab method.• Lift-slab method may be employed with ribbed slabs not only flat slabs with somecompromise of the ease of casting.Another advantage is reduced handling and hoisting of materials and supplies that can simply be placed on top of the slabs and lifted with them.

ADVANTAGES

Major limitationsThis method not to be use for multistorey building, only use for 15- 16 storey building.No large span slab are constructed in this type of construction.

LIMITATIONS

Page 10: Lift form slab construction

Sequence of Lifting Slabs The sequence of lifting slabs is influenced by the followingfactors:• Weight of the slabs.• Height of the building.• Lifting capacity of jacks.• Cross sectional area of columns during initial lifting.

Page 11: Lift form slab construction

Sequence of lifting the slabs of a five-storey building.

Page 12: Lift form slab construction

Summary• Lift slab construction is a method of constructing concrete buildings by casting the floor or roof slab on top of the previous slab and then raising (jacking) the slab up with hydraulic jacks, so being cheaper and faster as it does not need forms & shores as it is needed for cast-in-place slabs.• This method eliminates the need for redundant formwork as only shuttering required on the edges, therefore casting concrete slabs is the simplest stage in whole constriction process of lift-slab method.• Lift-slab construction method becomes more advantageous in buildings with similar floor plans throughout the height of the building and where flush slab may be desired.• The sequence of lifting slabs is influenced by the following factors: weight of the slabs; height of the building, lifting capacity of jacks, cross sectional area of columns during initial lifting.• Slabs are lifted by jacks, operating on the top of the building columns, this jacks lift a pair of steel rods attached to each lifting collar in the slab being raised.• This system requires a central and accurate control to provide a uniform lift from all directions.