LG0564-0616 WST monthlyupdate Oct CN&ENG DRAFT 2 - IBID · Monthly Construction Update | June 2016...
Transcript of LG0564-0616 WST monthlyupdate Oct CN&ENG DRAFT 2 - IBID · Monthly Construction Update | June 2016...
Monthly Construction Update | June 2016
PROJECT BUDGET
$397.1 Millionremaining
$540.9 Million Total
Project Budget
$ 143.8 MillionLand Acquisition and Construction
Costs to Date
MONTHLY BULLETIN
Wall Street Tower Construction Report | October 2016
Chief Investment Officer, Lightstone InvestmentsJonathan Rabinow
Dear Investors,
Lightstone is pleased to update you on the status of Wall Street Tower. Through October 2016, the project moves forward with demolition of building one completed and tie back installation down to the 11th floor of building two’s neighboring building, water and sewer disconnection and approval of demolition drawings by New York’s Department of Buildings for building three. There are, on average, 20-25 workers on-site daily. To date, Lightstone has spent a total of $143.8 million on construction and acquiring the land, and Lightstone estimates that over 95 jobs have been created .
Sincerely
Over 95Jobs Created
Lightstone estimates that over 95 of the 2,000 jobs required by USCIS have been created.
JOB CREATION
CONSTRUCTION TIMELINETARGET
COMPLETION
2015 2016 2017 2018 2019 2020
Permits
Demolition
Excavation
Superstructure
Condo Interiors
NOVEMBER2019
Monthly Construction Update | June 2016MONTHLY BULLETIN
PHOTOS
Demolition of Wall between Buildings Two and Three
Installation of Building Tiebacks
Demolition of Steel Beams Demolition of Floor Slab