5/2/2006 SaintSoft: Acceptance Test 1 Environmental Monitoring System Acceptance Test by Saint Soft.
Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module...
Transcript of Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module...
![Page 1: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/1.jpg)
Levels of Testing
Chapter 12
Beyond unit testing
![Page 2: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/2.jpg)
LOT–2
Life cycle models
What is a life cycle model of software development?
What is the traditional life cycle model?
![Page 3: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/3.jpg)
LOT–3
V-Model – development & testing
Requirements
DetailedDesign
Moduleimplementation Unit test
Integration test
System test
Acceptancetest
Run
testsW
rite tests
Customer
Developer
Functional
Structural
ArchitecturalDesign
![Page 4: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/4.jpg)
LOT–4
Traditional model
How well do the levels of the traditional Waterfall modelcorrelate with testing?
In what way?
![Page 5: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/5.jpg)
LOT–5
Traditional model – 2
How well do the levels of the traditional Waterfall modelcorrelate with testing?
In what way? Levels correlate with levels of testing
Functional testing is implied
Bottom up testing is implied
![Page 6: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/6.jpg)
LOT–6
Developer – unit testing stage
What is unit testing?
How do we do unit testing?
![Page 7: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/7.jpg)
LOT–7
What is unit testing?
How do we do unit testing?
Testing of individual components
Unit is best understood
Have both functional and structural testing
Developer – unit testing stage – 2
![Page 8: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/8.jpg)
LOT–8
Developer – integration testing stage
What is integration testing?
How do we do integration testing?
![Page 9: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/9.jpg)
LOT–9
What is integration testing?
How do we do integration testing? Testing to expose problems arising from the
combination of components Bottom up
Combine smaller units into larger ones, untilsystem level is reached
Developer – integration testing stage – 2
![Page 10: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/10.jpg)
LOT–10
Developer – system testing stage
What is system testing?
How do we do system testing?
![Page 11: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/11.jpg)
LOT–11
What is system testing?
How do we do system testing?
Testing the complete system prior to delivery
Functional testing
No good structural notation for descriptions
Developer – system testing stage – 2
![Page 12: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/12.jpg)
LOT–12
Acceptance testing stage
What is acceptance testing?
Who does it?
![Page 13: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/13.jpg)
LOT–13
What is acceptance testing?
Who does it?
Testing by clients / users to check that the systemsatisfies requirements
Sometimes called alpha testing
Acceptance testing stage – 2
![Page 14: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/14.jpg)
Basic development methods
What are the three basic methods that can be used todevelop a system?
LOT–14
![Page 15: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/15.jpg)
LOT–15
What are the three basic methods that can be used todevelop a system?
Top down
Bottom up
Big Bang
Basic development methods – 2
![Page 16: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/16.jpg)
LOT–16
Top-down development
How does top-down development work?
![Page 17: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/17.jpg)
LOT–17
Top-down development – 2
How does top-down development work?
Build upper level Test using stubs
Throw away Repeat with next lower level
![Page 18: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/18.jpg)
LOT–18
Bottom-up development
How does bottom-up development work?
![Page 19: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/19.jpg)
LOT–19
Bottom-up development – 2
How does bottom-up development work?
Build lower levels
Test with drivers Throw away Repeat with next higher level
![Page 20: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/20.jpg)
LOT–20
Big bang development
How does big-bang development work?
![Page 21: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/21.jpg)
LOT–21
Big bang development
How does big-bang development work?
Build everything
Then test
No stubs or drivers
![Page 22: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/22.jpg)
LOT–22
Problems with waterfall model
What are the problems with the waterfall model?
![Page 23: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/23.jpg)
LOT–23
Problems with waterfall model – 2
What are the problems with the waterfall model? Too slow Too rigid Too focused on top-down functional development and
bottom-up testing Not the way people work Staffing levels of different types batched at different
times with the levels requiring large resource shiftsfrom low to high and back.
![Page 24: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/24.jpg)
LOT–24
Waterfall spin-off models
Development in stages Level use of staff What types of testing is done?
![Page 25: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/25.jpg)
LOT–25
Waterfall spin-off models – 2
Development in stages Level use of staff What types of testing is done?
Testing now entails both
Regression
Progression
![Page 26: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/26.jpg)
LOT–26
Waterfall spin-off models – 3
What are the major types of spin off models?
![Page 27: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/27.jpg)
LOT–27
Waterfall spin-off models – 4
What are the major types of spin off models? Variations involve constructing a sequence of
systems Incremental
Evolutionary
Spiral
![Page 28: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/28.jpg)
LOT–28
Waterfall spin-off models – 5
What is their common modus operandi?
![Page 29: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/29.jpg)
LOT–29
Waterfall spin-off models – 6
What is their common modus operandi?
Waterfall model is applied to each build
Smaller problem than original
System functionality does not change during abuild
![Page 30: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/30.jpg)
LOT–30
Incremental model
Have high-level design at the beginning
Low-level design results in a series of builds Incremental testing is useful System testing is not affected
Level off staffing problems
![Page 31: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/31.jpg)
LOT–31
Evolutionary model
First build is defined
Priorities and customer define next build
Difficult to have initial high-level design Incremental testing is difficult System testing is not affected
![Page 32: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/32.jpg)
LOT–32
Spiral model
Combination of incremental and evolutionary
After each build assess benefits and risks Use to decide go/no-go and direction
Difficult to have initial high-level design Incremental testing is difficult System testing is not affected
![Page 33: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/33.jpg)
LOT–33
Spiral model – advantage
Earlier synthesis and deliverables
More customer feedback
Risk/benefit analysis is rigorous
![Page 34: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/34.jpg)
LOT–34
Rapid prototyping
Specification based life cycle model
Build quick and dirty system Good for risk analysis
Customer feedback
![Page 35: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/35.jpg)
LOT–35
Rapid prototyping – 2
System testing is difficult Where is the specification?
Good for acceptance testing Emphasis is behaviour, not structure
![Page 36: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/36.jpg)
LOT–36
Executable specifications
Specification based life cycle model
Extension of rapid prototyping
Specific behavioural models are built and executed Statecharts Finite state machines Petri nets Z specification language
Customer feedback as for rapid prototyping
![Page 37: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/37.jpg)
LOT–37
Integration & system testing
Need to know difference between integration and systemtesting Avoid gaps and redundancies across levels Set testing goals appropriate for each level
Structural & behavioural views separate integration andsystem testing goals
![Page 38: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/38.jpg)
LOT–38
Threads
What are threads?
![Page 39: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/39.jpg)
LOT–39
Threads – 2
What are threads? Use cases Describe behaviour
Have threads at different levels What are the levels?
![Page 40: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/40.jpg)
LOT–40
Thread levels
Have threads at different levels What are the levels?
Unit
Integration
System
![Page 41: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/41.jpg)
LOT–41
Thread levels – 2
What are the threads at each level? Unit
??? Integration
??? System
???
![Page 42: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/42.jpg)
LOT–42
Thread levels – 3
Unit Path in a program graph
Integration Path in a finite state machine
System level Data context and sequence of port events
![Page 43: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/43.jpg)
LOT–43
Structural insights – integration testing
Assumes unit level testing completed
Can be seen as interface testing What about algorithms at higher levels?
Uses preliminary design What is preliminary design?
![Page 44: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/44.jpg)
LOT–44
Structural insights – system testing
Requirements level
What is the difference between the following? Requirements Preliminary design
What-how and other definitions too vague Inevitability of intertwining specification and design
![Page 45: Levels of TestingLOT–3 V-Model – development & testing Requirements Detailed Design Module implementation Unit test Integration test System test Acceptance test s s Customer LOT–5](https://reader035.fdocuments.us/reader035/viewer/2022071116/5ffcd4f6a6631b16460091c4/html5/thumbnails/45.jpg)
LOT–45
Behavioural insights
System level Deals with port boundaries
What the user sees and does Sequences of integration-level threads
Integration level Deals with boundaries between port and unit
Within the system Sequences of unit-level threads