Letter of Map Revisions LOMR January 9, 2020 By: Alan Shubert, P.E. Vice President of Operations and Technical Services

Transcript of Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14...

Page 1: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

Letter of Map Revisions LOMR

January 9, 2020

By: Alan Shubert, P.E.Vice President of Operations and Technical Services

Page 2: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 2

What is a Letter of Map Revision Letter of Map Revision (LOMR) – FEMA’s modification to

an effective Flood Insurance Rate Map (FIRM) and/or Flood Boundary / Floodway.

FIRM – the official flood insurance map of a community of which FEMA has indicated the flood hazard areas and the risk premium zones for the community.

Source: www.fema.gov

Page 3: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 3

Recent LOMRs by EPWater and CoEP

Northeast LOMR – Effective June 2018

Pico Norte LOMR – Effective December 2019

Page 4: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 4

NORTHEAST LOMR

Page 5: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 5

Northeast Streams - FP 13 and FP 14

FP 13 – NE Channel 1

FP 14 – NE Channel 2

Page 6: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

NE Rain Events

El Paso Water 6

3’-10” above the channel bridge

Page 7: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

NE Channel 2 Improvements

January 8, 2020 El Paso Water 7

NE Channel 2 – 2011

Page 8: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

NE Channel 2 Improvements

Construction of 19,000+ linear feet of concrete channel to contain the 25-year storm

January 8, 2020 El Paso Water 8

Page 9: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

NE Channel 2 Improvements

January 8, 2020 El Paso Water 9

Page 10: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

Letter of Map Revision (LOMR)

January 8, 2020 El Paso Water 10

Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision – January 2018 Effective – June 2018

Page 11: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

Investment vs. Benefit

January 8, 2020 El Paso Water 11

Investment:– NE Channel 2 Construction - $14.6 M

Benefit:– 5,000 + properties removed from flood zone– Removed properties - Flood Insurance 747 properties have flood insurance *Average flood insurance premium per household - $ 895 Sum of annual premiums - $ 670,000 + If everyone were to have flood insurance – Savings $ 9M

* Data by FEMA

Page 12: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 12

Previous

FEMANortheast

Floodplain Map

Page 13: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 13

Approximately 5,000 properties removed

from the 100-yr flood zone

New

FEMANortheast

Floodplain Map

Page 14: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 14

Additional 610 properties will be

removed from the 100-yr flood zone

Proposed Will Ruth

PondRemoved from 100-yr flood zone

Remain in 100-yr flood zone

** Will Ruth Pond

Page 15: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 15

PICO NORTE LOMR

EAST EL PASO

Page 16: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 16

Pico Norte Rain Events

Page 17: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

Pico Norte Area Improvements

Phase 1 – Pico Norte Pond Improvements Phase 2 – Sam Snead Storm Drain Improvements Phase 3 – Bywood Drive Drainage Improvements

January 8, 2020 El Paso Water 17

Page 18: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

PHASE 1 - PICO NORTE PONDIMPROVEMENTS

Page 19: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

PROJECT DESCRIPTIONPhase 1 – Pico Norte Pond Improvements

• Completed 2016 • Construction Cost $2M

Project Description • Excavate and Expand the Pond• Improve the Pond Side Slopes• Improve the Existing Drainage Structures• Provide New Perimeter Rock Wall

Page 20: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

2014 Flood Damage

Remediation Improvements

Page 21: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

Pico Norte Pond Improvements

January 8, 2020 El Paso Water 21

Page 22: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

Bywood Drive Drainage System Improvements

El Paso Water 22

Sam Snead Storm Drain System

Phase 3 – Bywood

Future Phases

In Construction

Pico Norte Pond

Page 23: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

Previous FIRM

January 8, 2020 El Paso Water 23

Page 24: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 24

New FIRM

Page 25: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 25

Pico Norte LOMR• LOMR Application submitted by City of El Paso’s Land

Development

• City’s H&H Modelers modeled the pond improvements within the drainage area

• 05/21/19 – LOMR Application submitted to FEMA

• 90 day Review Period

• Effective December 2019

Page 26: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 26

Investment vs. Benefit

Investment:– Pico Norte Pond Expansion - $ 2M

Benefit:– 1,110 + properties removed from flood zone

– Removed properties - Flood Insurance Flood insurance – Savings $ 2M

Page 27: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 27

INTERIOR DRAINAGE STUDY

Page 28: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 28

A drainage analysis of the City that is required by FEMA to Certify the levees that provide protection to the City

Its purpose is to determine the effects of the Rio Grande at different stages (high and low) on the levee and the interior drainage systems

It is used to determine flood risk in urban areas

In 2009, El Paso Water and El Paso County Texas entered into an Interlocal Agreement as a collaborative effort to develop regional Stormwater Planning

In 2018, El Paso County had an interest in studying and developing a masterplan for the Montana Sector of the county that was not included in the original El Paso County Masterplan

Both El Paso Water and El Paso County had also identified a need to complete a countywide Interior Drainage Study in order to certify levees within the county limits

What is it

Page 29: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 29

2006 Flood 2009 – City of El Paso SWMP – EPWater and City of El Paso

– Significant Stormwater Infrastructure Improvements 2010 – El Paso County SWMP – El Paso County and EPWater 2013 - Canutillo Phase II – USIBWC 2013 - Courchesne Reach - USIBWC 2014 – City of El Paso Interior Drainage Study – EPWater, City of El Paso, FEMA, USIBWC 2015 & 2019 – American Canal Project - USIBWC 2015 – 2017 – NW Feasibility Study – USACE and EPWater 2016 – International Dam to Riverside Weir – EPWater 2018 - Doniphan Corridor Study – TXDOT 2019 – Countywide Interior Drainage and Levee Certification – EPCounty and EPWater 2019 – Montana Sector SWMP – EPCounty and EPWater

History

Page 30: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 30

Study Area

Page 31: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 31

Activities 2019 - What we’ve done

February – Kickoff meeting– Data collection– Draft data collection and modeling approach report – Modeling coordination with FEMA, USIBWC, County, City and

EPWater– Field investigation of outfalls into the Rio Grande – Field investigation of recently constructed projects

Page 32: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

January 8, 2020 El Paso Water 32

What’s next - Timeline (2020)

March – Draft Interior Drainage Study Report May – Distribute revised report to stakeholders June – Stakeholder meeting July – Distribute final report to stakeholders

Page 33: Letter of Map Revisions LOMR · Project completed in 2011 LOMR Application submitted 07/28/14 Extensive coordination with FEMA Public Outreach – December 2017 Approved Map Revision

December 11, 2019 El Paso Water 10