Lessons Learned from Design, Building, Commissioning and...

89
Lessons Learned from Design, Building, Commissioning and Operation of Mount Holly Microgrid Aleksandar Vukojevic, P.E. Manager, Emerging Technologies - Duke Energy North Carolina State University, PhD Candidate 2019 Duke Energy - All Rights Reserved

Transcript of Lessons Learned from Design, Building, Commissioning and...

Page 1: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Lessons Learned from Design, Building, Commissioning and Operation of Mount Holly

Microgrid

Aleksandar Vukojevic, P.E.Manager, Emerging Technologies - Duke EnergyNorth Carolina State University, PhD Candidate

2019 Duke Energy - All Rights Reserved

Page 2: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Emerging Technology and Grid Solutions

TECHNOLOGY EXPLORATION

▪Opportunities/risks of new technologies

▪New technology standards

▪Applied technology maturityEmer

gin

g Te

chn

olo

gy

GRID INFRASTRUCTURE & TECHNOLOGY APPLICATION

▪Modern grid capabilities

▪Scaled deployments

Gri

d

Solu

tio

ns

GRID & TECHNOLOGY OPERATION

▪Operation and maintenance

Op

era

tio

ns

• Pre-scale Deployments

• Prototypes• Capability Maturity Models

• Scale Deployments • Business requirements

2019 Duke Energy - All Rights Reserved

Page 3: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Research Objectives – Reliable and Secure Microgrid P&C Design

DER Design

1

Grounding

2

Seamless Islanding

3

Rate of change of frequency

(ROCOF)

4

Inrush current mitigation

5

Microgrid Operating

Modes6

Grid re-synchronization

9

Seamless Islanding vs. black-start

8

Future research

10

7

P&C in islanded

mode

2019 Duke Energy - All Rights Reserved

Page 4: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Duke Energy DER Pilot Feeder

Substation with battery & super-capacitor

storage system

Recloser1.2MW Solar

Farm

Voltage Regulator

Mount Holly Microgrid

2019 Duke Energy - All Rights Reserved

Page 5: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid - video

2019 Duke Energy - All Rights Reserved

Page 6: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Switchyard

4-WAY Switchgear

Grounding Transformer

BESS

PCC

PCC Relay

Inverter PLC & PCS

DI/DO

2019 Duke Energy - All Rights Reserved

Page 7: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Solar Farm

150kW PV Farm

100kVA PV Inverter

DC-coupled BESS

2019 Duke Energy - All Rights Reserved

Page 8: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Switchyard

POI

9.3kW DC system

EVCS

2019 Duke Energy - All Rights Reserved

Page 9: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Generator and Microturbines

2-65kWmicroturbines

450kVA generator

2019 Duke Energy - All Rights Reserved

Page 10: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid –

One Line Diagram

2019 Duke Energy - All Rights Reserved

Page 11: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

1. DER Design

• During the literature review that consisted of reading more than 500 publishedpapers, masters thesis, PhD thesis, conference presentations, books on microgridsand system protection and control, three major microgrid design flaws werediscovered in vast majority of the literature:

a. PV systems as the only DER within the microgridb. Microgrid DERs with Yg – Δ transformersc. Lack of Grounding Transformer

2019 Duke Energy - All Rights Reserved

Page 12: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

1. DER Design

Simulink 100kW PV Farm Model2019 Duke Energy - All Rights Reserved

Page 13: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

100kW PV Farm Model – Simulation after PCC Opens

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 14: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

100kW PV Farm – What happens in the field after loss of AC on PV inverter side

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 15: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

100kW PV Farm Model – Properly designed PV inverter controls

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 16: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

1. DER Design

Model of typical feeder with 1LG fault – no DER

2019 Duke Energy - All Rights Reserved

Page 17: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

1LG fault on the feeder as seen from the substation relay

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 18: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Model of typical feeder with 1LG fault - with DER connected with Yg – Delta Transformer

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 19: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Fault current as seen by the substation breaker relay – DER with Yg-Delta Transformer

Fault current seen by the substation relay reduces

with increased DER rating

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 20: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Fault current in neutral of the Yg-Delta Transformer

Fault current seen by the neutral CT in the Yg side of DER transformer increases with increased DER rating

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 21: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Model of typical feeder with 1LG fault - with DER connected with Yg – Delta Transformer

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 22: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Model of typical feeder with 1LG fault - with DER connected with Yg – Y Transformer

Fault current seen by the substation relay does not

changes if DER is connected to Yg – Y transformer (1633A)

1. DER Design

2019 Duke Energy - All Rights Reserved

Page 23: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

2. Grounding

Purpose:

1. To provide solid groundreference for the microgrid

2. To detect the faults within themicrogrid faster and morereliable and secure

3. To enable grid re-synchronization

Neutral CT

Relay

Yg Δ

Grounding Transformer 2019 Duke Energy - All Rights Reserved

Page 24: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

2. Grounding Transformer - Design

Parameters for designing the grounding transformer:

1. Construction type: Yg – Δ or “Zig-Zag”

2. Primary and secondary voltage: 12.47kV Yg – 480V Δ

3. Impedance – designed so that the voltages on un-faulted phases during the ground fault are within the temporary over-voltage capability of the transformer and other primary equipment:

a. IEEE 142 – challenging approach because it is hard to define positive and negative sequence impedances for DER

b. IEEE 1547.8 – more applicable to this application

2019 Duke Energy - All Rights Reserved

Page 25: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

2. Grounding Transformer - Design

4. Steady-state circulating current – maximum level of zero-sequence current seen in theneutral of the grounding transformer

5. Neutral fault current withstand rating – the most critical design parameter since onlyzero-sequence current is present in the grounding transformer neutral during the fault

6. kVA rating:

a) Grounding transformer has no loadb) For solid grounding, desired X/R ratio should be greater than 4c) Higher kVA ratings have higher X/R ratio (500kVA transformers have typically X/R

ratio greater than 5)d) However, transformer with higher kVA rating has higher inrush current, so BESS

might not be able to support this inrush therefore causing the microgrid blackout

2019 Duke Energy - All Rights Reserved

Page 26: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Seamless Islanding

Islanding can be:

a. intentional

b. unintentional

In both cases, islanding can be achieved by:

1. 52a switch from PCC directly wired to the battery controller

2. Battery inverter detects the 27/59/81 state without direct 52a status

3. Battery inverter or PCC relay detects the 27/59/81 state with direct 52a status

2019 Duke Energy - All Rights Reserved

Page 27: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Seamless Islanding – voltage response (simulation)

Voltage during the Grid to Island transition – different simulations2019 Duke Energy - All Rights Reserved

Page 28: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Seamless Islanding – voltage response (microgrid)

Voltage during the Grid to Island transition – actual microgrid response2019 Duke Energy - All Rights Reserved

Page 29: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Seamless Islanding – microgrid response

Grounding Transformer Energization Effect2019 Duke Energy - All Rights Reserved

Page 30: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Seamless Islanding – frequency response (simulation)

Frequency during the Grid to Island transition – simulation in MATLAB/Simulink2019 Duke Energy - All Rights Reserved

Page 31: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Seamless Islanding – frequency response (microgrid)

Frequency during the Grid to Island transition – actual microgrid response

2019 Duke Energy - All Rights Reserved

Page 32: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Transition from Grid to Island

HMIMicrogrid controller

PCC relayIED #1

Microgrid relayIED #2

PCC Breaker

Battery Inverter

DI/DO

1. Initiate Islanding

2. Trip PCC

3. Go to VSI V/F Mode

4. Trip Islanding switch (PCC)

5. PCC Open

5a. Close Grounding

Transformer

1. Grid Disturbance

27/59/81

27/59/81U/O, df/dt

2019 Duke Energy - All Rights Reserved

Page 33: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Seamless Islanding

2019 Duke Energy - All Rights Reserved

Page 34: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. Mount Holly Microgrid – Islanding Detection Scheme

2019 Duke Energy - All Rights Reserved

Page 35: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

3. How fast is current Mount Holly islanding detection scheme?

Scheme can detect islanding for PL=PG

Island TRIP due to LROV

2019 Duke Energy - All Rights Reserved

Page 36: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

4. Transformer inrush current mitigation

2019 Duke Energy - All Rights Reserved

Page 37: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

5. Microgrid Operating Modes

objective: minimize kW WAY 1

subject to:

kW WAY 1 = kW WAY 2 + kW WAY 3 + kW WAY 4

kW WAY 4 = kW VSI BATTERY + kWAUX. BATT + kWAUX. INVERTER

kW WAY 2 = kWPV + kW CSI BATTERY + kWLOAD BANK + kWBLDG

PCC closed

SOCmin < SOC < SOCmax

kWPV = f(MPPT) (i.e. no curtailing)

kWLOAD BANK is in [0 - kWMAX] range

V min < V < V max, for VSI Battery

f min < f < f max, for VSI Battery

kW CHARGE RATE VSI BATTERY is in [0 – kWMAX CHARGE] range

kW DISCHARGE RATE VSI BATTERY is in [0 – kWMAX DISCHARGE] range

objective: minimize time for PCC = CLOSED

subject to:

kW WAY 2 + kW WAY 3 + kW WAY 4 = 0

kW WAY 4 = kW VSI BATTERY + kWAUX. BATT + kWAUX. INVERTER

kW WAY 2 = kWPV + kW CSI BATTERY + kWLOAD BANK + kWBLDG

SOCmin < SOC < SOCmax

kWPV = f(MPPT) (i.e. no curtailing)

kWLOAD BANK is in [0 - kWMAX] range

V = 1.0 p.u. for BESS

f = 1.0 p.u. for BESS

Net-0 Mode Auto Mode

This operating mode was implemented within the microgrid controller at the actual utility’s microgrid

and it ran seamlessly and without any interruption for over 4 months without any user input!!!

2019 Duke Energy - All Rights Reserved

Page 38: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

5. Microgrid Operating Modes - Net-0 and Manual

2019 Duke Energy - All Rights Reserved

Page 39: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

2019 Duke Energy - All Rights Reserved

Page 40: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

6. Seamless islanding vs. Black start

Source: S&C Electric – Selection Guide for Transformer Primary Fuses in Medium and High Voltage Utility and Industrial Substations

2019 Duke Energy - All Rights Reserved

Page 41: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

6. Seamless Transition vs. Cold-Load Pick-up Operating Mode

Source: S&C Electric – Selection Guide for Transformer Primary Fuses in Medium and High Voltage Utility and Industrial Substations

2019 Duke Energy - All Rights Reserved

Page 42: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

6. Seamless Transition vs. Cold-load Pick-up Operating Mode

2019 Duke Energy - All Rights Reserved

Page 43: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

6. Seamless Transition vs. Cold-load Pick-up Operating Mode

• If we are designing the microgrid for seamless transition with inverter-based DERs, DERrating (BESS) should be based on the peak microgrid loading (unless there is volt/VARcontrol mechanism, demand response system or load shedding system implemented,which can reduce the load within the microgrid within 20ms);

• If we are designing the microgrid for cold-load pick-up with inverter-based DERs, DERrating (BESS) should be based on the total transformer kVA/MVA rating within themicrogrid and historical cold-load pick-up quantities. This might require the addition ofrotating mass generation as additional DER.

• Using single pole operation device with controller that switches based on the residualmagnetism can significantly reduce the inrush current, which is a proposition also forgrounding transformer as well as cold-load pick-up operation

• Using line reclosers can further improve the reliability of this scheme by sectionalizing thefeeder and energizing it section-by-section

2019 Duke Energy - All Rights Reserved

Page 44: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

7. Grid re-synchronization

HMIMicrogrid controller

PCC relay

Microgrid relayIED #2

PCC Breaker

Battery Inverter

DI/DO

1. Initiate grid-syncsequence

2. Enable grid auto-connect 3. Grid voltage

stable for 5 min

4b. Start grid-synch procedure& switch to VSI PQ mode

5. Grid-synch completed

6. Close Islanding switch (PCC)

7. PCC Closed

8. Stop grid-synch procedure

7. PCC Closed

6a. Open Grounding

Transformer

2019 Duke Energy - All Rights Reserved

Page 45: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

7. Seamless Grid Reconnect

2019 Duke Energy - All Rights Reserved

Page 46: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Microgrid Operation – as seen by IEEE C37.118 enabled relay data

2019 Duke Energy - All Rights Reserved

Page 47: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Lessons Learned from Implementation of Rate-of-change of Frequency (81R) and

Synchophasor-Based Islanding Schemes

Aleksandar Vukojevic, P.E.Manager, Emerging Technologies - Duke EnergyNorth Carolina State University, PhD Candidate

2019 Duke Energy - All Rights Reserved

Page 48: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

How to initiate islanding?

Islanding can be:

a. intentional

b. unintentional

In any case, islanding can be achieved by:

1. 52a switch from PCC directly wired to the battery controller (McAlpine microgrid – 6 cycles to detect the islanding)

2. Battery inverter detects the 27/59/81U/81O state without direct 52a status (Mount Holly microgrid – 2016)

3. Battery inverter or PCC relay detects the 27/59/81U/81O state with direct 52a status (Mount Holly microgrid – 2017)

2019 Duke Energy - All Rights Reserved

Page 49: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

How fast is current Mount Holly islanding detection scheme?

Scheme can detect islanding for PL=PG

Island TRIP due to LROV

2019 Duke Energy - All Rights Reserved

Page 50: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Microgrid islanding detection for different PL/PG ratios

PL/PG = 0.4PL/PG = 1.0

2019 Duke Energy - All Rights Reserved

Page 51: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

81U vs. 81R – Unintentional islanding

2019 Duke Energy - All Rights Reserved

Page 52: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

81R vs. 81U/O pick-up & time-out

2019 Duke Energy - All Rights Reserved

Page 53: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Percentage islanding detection improvement - 81R over 81U/O (with 81R set at ±2.5Hz/s)

2019 Duke Energy - All Rights Reserved

Page 54: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Security testing for 81R

2019 Duke Energy - All Rights Reserved

Page 55: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Synchophasor-based islanding detection

2019 Duke Energy - All Rights Reserved

Page 56: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Synchophasor-based islanding

2019 Duke Energy - All Rights Reserved

Page 57: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Field settings

y=-5x+2.5

y=-(25/7)x-2.5

Synchophasor-based islanding detection is based on:

1. Voltage angle difference –set-point: ≥10°

2. Slip frequency and acceleration

2019 Duke Energy - All Rights Reserved

Page 58: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Synchophasor-based islanding vs. 81R

2019 Duke Energy - All Rights Reserved

Page 59: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Implementation of IEC 61850 Based Protection and Control Techniques within Duke Energy’s

Mount Holly Microgrid

Aleksandar Vukojevic, P.E.Manager, Emerging Technologies - Duke EnergyNorth Carolina State University, PhD Candidate

2019 Duke Energy - All Rights Reserved

Page 60: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Emerging Technology and Grid Solutions

TECHNOLOGY EXPLORATION

▪Opportunities/risks of new technologies

▪New technology standards

▪Applied technology maturityEmer

gin

g Te

chn

olo

gy

GRID INFRASTRUCTURE & TECHNOLOGY APPLICATION

▪Modern grid capabilities

▪Scaled deployments

Gri

d

Solu

tio

ns

GRID & TECHNOLOGY OPERATION

▪Operation and maintenance

Op

era

tio

ns

• Pre-scale Deployments

• Prototypes• Capability Maturity Models

• Scale Deployments • Business requirements

2019 Duke Energy - All Rights Reserved

Page 61: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Switchyard

4-WAY Switchgear

Grounding Transformer

BESS

MU #1 & #2

MU #3 MU #5

MU #6

2019 Duke Energy - All Rights Reserved

Page 62: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Solar Farm

150 KW PV

100 KVA PV Inverter

DC-Coupled Battery

250 KW DC

240 KW / 122 KWhBattery

2019 Duke Energy - All Rights Reserved

Page 63: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Generator and Microturbines

2-65kWmicroturbines

450kVA generator

MU #4

MU #7

2019 Duke Energy - All Rights Reserved

Page 64: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Islanding Detection Scheme

Traditional Protection

Merging Unit #1

Merging Unit #2

Selector Switch

2019 Duke Energy - All Rights Reserved

Page 65: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Islanding Detection Scheme

2019 Duke Energy - All Rights Reserved

Page 66: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Islanding Detection Scheme

2019 Duke Energy - All Rights Reserved

Page 67: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – Islanding Detection Scheme

Merging Unit #7

Traditional

Selector Switch

2019 Duke Energy - All Rights Reserved

Page 68: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Lessons Learned from Implementation of IEC 61850 Protocol

5 phases of commissioning:

1. Individual vendor merging unit and relay set-up and operability

2. Vendor-to-Vendor set-up and interoperability

3. Microgrid settings implementation

4. 85RIO scheme implementation

5. Load shedding transfer-trip scheme

2019 Duke Energy - All Rights Reserved

Page 69: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Lessons Learned from Implementation of IEC 61850 Protocol

A. Strategic deign approach

B. PTP network traversing

C. Vendor interfaces

D. Fiber switch interface speed

E. Fiber switch partition➢ Install two fiber network switches – one for process bus and one for station bus)

➢ Install one fiber network switch and use VLAN zero

➢ Install one fiber network switch and separate process and station bus within the switch

2019 Duke Energy - All Rights Reserved

Page 70: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

IEC 61850 Protocol – proposed solution architecture

2019 Duke Energy - All Rights Reserved

Page 71: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

IEC 61850 Protocol – current solution architecture

2019 Duke Energy - All Rights Reserved

Page 72: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Lessons Learned from Implementation of IEC 61850 Protocol

F. Global synch vs. Local synch

G. Interoperability

2019 Duke Energy - All Rights Reserved

Page 73: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Duke Energy Emerging Technology Office

Battery Energy Storage System Integration on the DC Bus of the PV

Farm Inverter

Aleksandar Vukojevic, P.E.Manager, Emerging Technologies - Duke EnergyNorth Carolina State University, PhD Candidate

2019 Duke Energy - All Rights Reserved

Page 74: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Battery Energy Storage Systems – AC vs. DC Coupled

Copyright © 2017 Duke Energy Corporation. All rights reserved.

AC-Coupled Hybrid PV + Storage DC-Coupled

2019 Duke Energy - All Rights Reserved

Page 75: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – PV FarmPV System Characteristics at Mount Holly:

1. South Facing system2. 20˚ - tilt ground mount system3. PAC = 100kW; PDC = 149.50kW4. PV irradiance > 700 W/m2

5. GPS Coordinates: 35.29˚ Latitude

DC/AC Ratio Annual Energy AC Production Energy Lost to “Clipping”

1.0 163.06 MWh 0.0 MWh

1.3 193.86 MWh 1.8 MWh (0.9%)

1.5 217.24 MWh 11.0 MWh (4.9%)

*) Table obtained from blog.aurorasolar.com

2019 Duke Energy - All Rights Reserved

Page 76: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – DC Coupled Battery

100 kVA Parker Hannifin PV

Inverter

150kW PV Farm

240kW/122kWhSAFT Battery

250kW DynaPower

DC-DC Converter

RecombinerBox

Combiner Box

Blocking Diode

480V - 315VXMFR

277V – 120VXMFR

2019 Duke Energy - All Rights Reserved

Page 77: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Mount Holly Microgrid – One Line Diagram

SAFT Mini – E240kW

122kWh

RCB

DynaPower 250kWDC-DC Converter

DPS - 250

ABB 200A DC Breaker

Blocking Diode & CT

25 strings with 19 panels in series (total 150 kW)

2019 Duke Energy - All Rights Reserved

Page 78: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Battery DC Bus Integration with PV –Design Considerations

Copyright © 2017 Duke Energy Corporation. All rights reserved.

1. Typical ILR are in [1.2 – 1.6] range2. New solar panels were different from the original ones3. PV system is grounded inside PV inverter and battery is

typically floating4. DC-DC Converter has no isolation transformer5. Battery will always report “Negative Grounded” alarm6. Blocking diode installed to prevent the battery “backfeed”

to solar panels7. Additional CT installed to signal the reverse power flow in

case of blocking diode failure8. PV timer needs to be disabled for MPPT algorithm9. Grounding leakage current setting needs to be increased

2019 Duke Energy - All Rights Reserved

Page 79: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Efficiency = 86.2% = .95 * .984 * .99 * .99 * .984 * .984 * .99Efficiency = 89.2% = .95 * .982 * .982 * .984 * .99

DC-COUPLED

HIGHER EFFICIENCY

DC-Coupled Solar + Storage

• 3 power electronic conversions

• 1 battery charge and discharge

• 1 transformer conversion

AC-Coupled Solar + Storage

• 3 power electronic conversions

• 1 battery charge and discharge

• 3 transformer conversions

1

~

=52 G

MV Step-up

transformer

~

=52 2

=

=

~

=

1

2

G

MV Step-up

transformer

Assumed efficiencies:

PV inverter = 98.4% transformer = 99%

Battery inverter = 97.5% batteries = 95% round trip

DC-DC = 98.2%

2019 Duke Energy - All Rights Reserved

Page 80: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

DynaPower DC-DC Converter – DPS 250

Basic

Constant Current

Constant Power

Constant Voltage

Advanced

Clipping

Early Morning/Late Evening Capture

Capacity Firming

Ramp Rate Control

PV Time Shifting

Operating Modes

2019 Duke Energy - All Rights Reserved

Page 81: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

DPS 250 DC-DC Converter

On-board controller in converter communicates directly with the battery BMS

2019 Duke Energy - All Rights Reserved

Page 82: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Operating Modes - Advanced

Copyright © 2017 Duke Energy Corporation. All rights reserved.

Estimated energy that can be captured from clipping with 1.5 ILR: ~5%Early morning/Late evening capture: DC-DC Converter operates in MPPT mode, while PV inverter is OFF

2019 Duke Energy - All Rights Reserved

Page 83: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Operating Modes - Advanced

Copyright © 2017 Duke Energy Corporation. All rights reserved.

Capacity Firming enables the fixed user defined AC inverter output, regardless of the PV DC production

2019 Duke Energy - All Rights Reserved

Page 84: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Operating Modes - Advanced

Copyright © 2017 Duke Energy Corporation. All rights reserved.

2019 Duke Energy - All Rights Reserved

Page 85: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Operating Modes - Advanced

Copyright © 2017 Duke Energy Corporation. All rights reserved.

PV Time Shifting: battery is charged during the peak time and discharged during the non-peak time

2019 Duke Energy - All Rights Reserved

Page 86: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Blocking Diode & CT Transducer

http://www.electronics-tutorials.ws/diode/bypass-diodes.html

CT Transducer

Blocking Diode

2019 Duke Energy - All Rights Reserved

Page 87: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

Copyright © 2017 Duke Energy Corporation. All rights reserved.

PV Inverter

OFFDC- DC Converter

OFF

MPPT

CLIPPING OFF

OFFMPPT

MPPT

OFF PVEMUL

MPPT OFF

OFF

Early MorningCapture

Late EveningCapture

OFF

2019 Duke Energy - All Rights Reserved

Page 88: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

[email protected]

2019 Duke Energy - All Rights Reserved

Page 89: Lessons Learned from Design, Building, Commissioning and …site.ieee.org/pes-yp/files/2019/05/Lessons-learned-from... · 2019. 8. 19. · Research Objectives –Reliable and Secure

[email protected]

“It’s a progress…not a perfection!”

2019 Duke Energy - All Rights Reserved