Lessons from a Deep, Dark Confined Space: A Case Study and ... miller aiha... · Confined Spaces in...
Transcript of Lessons from a Deep, Dark Confined Space: A Case Study and ... miller aiha... · Confined Spaces in...
September 17, 2015
Lessons from a Deep, Dark Confined Space: A Case Study and A Brief on the New Construction Standard
Presented by Sally K. Miller, CIH
and Patrick Walz, PE
AECOM
Confined Spaces in Construction:
OSHA’s Final Rule
• History and Timeline of the Final Standard
• Construction Standard Overview
• Main Differences between the General
Industry and Construction Standards
• Effect on Other OSHA Standards
• Minor Differences, Subtle Effects and Nuanced
Interpretations
History and Timeline
29 CFR 1926, Subpart AA:
Confined Spaces in Construction
1979:
Const. CSE
Training
Provision
issued
1993: Gen.
Ind. CSE
Std.
1910.146
issued
OSHA
agreed to
propose
Const. CSE
Std.
2003: Draft
Const. Std.
developed
2007:
Proposed
Const. CSE
Rule
published
May 4,
2015: Final
Rule
published
Aug. 3,
2015: Rule
effective,
but
extension
granted
Oct. 3,
2015:
Const. CSE
Std.
EFFECTIVE
Confined Spaces in Construction
29 CFR 1926, Subpart AA • 1926.1201 Scope
• 1926.1202 Definitions
• 1926.1203 General Requirements
• 1926.1204 Permit Required Confined Space Program
• 1926.1205 Permitting Process
• 1926.1206 Entry Permit
• 1926.1207 Training
• 1926.1208 Entrants
• 1926.1209 Attendants
• 1926.1210 Entry Supervisors
• 1926.1211 Rescue
• 1926.1212 Employee Participation
• 1926.1213 Provision of Documents
General Industry vs. Construction?
Final Construction Confined Space Standard =
General Industry Confined Space Standard
“Plus”
Construction CS Standard: Overview
• What is a confined space?
– Large enough to enter
– Limited or restricted means for entry and exit
– Not designed for continuous employee occupancy
• Examples in Construction: Tanks, bins, boilers,
vaults, sewers, elevator pits, manholes, crawl
spaces, attics…
Construction CS Standard: Overview
• What is a Permit Space?
A confined space with one or more of the
following:
• Contains or has potential to contain hazardous
atmosphere
• Contains engulfment hazard
• Configured so as to pose entrapment or asphyxiation
risk
• Contains any other recognized serious hazard
Construction CS Standard: Overview
What does the Employer need to do?
• Competent person must identify CS and evaluate
– Are they Permit Spaces?
• Decide if your employees will enter permit spaces
• If no, must take steps to prevent your employees from entering
• If yes, employer becomes Entry Employer
• Post DANGER signs to inform all on site
• Develop and post permits for entrants
Construction CS Standard: Overview
• Entry Employer must develop Permit Space
Program
– Plans for training for exposed employees, attendants,
entrants & entry supervisors; also rescuers
– Plans for elimination or isolation of physical hazards
– Plans for testing, monitoring and ventilating
– Determination of required PPE
– Plans for rescue and summoning emergency help
– Annual program review
Confined Spaces in Construction:
What’s Different?
• Continuous monitoring of
atmospheric required
• Early-warning system for engulfment hazards
required
• Emergency responders required to agree to
notify employer if they are unavailable
Confined Spaces in Construction:
Multi-Employer Worksites
• Specific information exchange for multi-
employer worksites required
– Host Employer
• Owns or manages property
– Controlling Contractor
• Has overall responsibility for construction at site
– Entry Employer
• One who decides that an employee it directs will enter
a permit space
Confined Spaces in Construction
Information Exchange
Host Employer
Controlling Contractor
Entry Employer Subcontractor
Pre-Entry Post-Entry
Coordinate
during entry
Pre-EntryPre-EntryPost-Entry
Post-Entry
Confined Spaces in Construction:
What’s Different?
• Alternate Procedures: It’s now allowable to
prevent exposure to physical hazards through
isolation (not just elimination)
• Permits may be suspended (instead of
cancelled) in response to temporary changes
• If you’re doing both construction and
maintenance, follow Construction Standard
Confined Spaces in Construction:
Effect on Other Standards
• Rule does replace any other construction
standard (except old CS standard)
• Subpart V- Power Transmission, Generation &
Distribution
– Now requires compliance with Subpart AA
– “Enclosed Space”- one designed for periodic
employee entry under normal conditions
• Do hazards interfere with escape?
• What is a “normal” atmosphere in the space?
Confined Spaces in Construction:
Effect on Other Standards
• Explicitly excluded from the rule:
– Subpart Y - Diving
– Subpart P - Excavation
– Subpart S - Underground Construction, Caissons, Cofferdams
• OSHA “taking this opportunity” to clarify scope of Subparts P and S
– Key question is: Excavation vs. non-excavation work?
Other Exemptions?
• Home construction is NOT
exempted
– Crawl spaces, basements,
cabinets, etc., are not inherently
free of atmospheric or physical
hazards
– But, in new construction,
employers should organize work
practices to avoid placing
workers in confined spaces
Clarifications in Subpart AA
• Controlling a hazard
– An action that reduces the hazard level in the space
• Isolating a hazard
– Process used to completely protect entrants from the release of energy or other hazard into the space
• Eliminating the hazard
– Removing the hazard from the space completely
Clarifications in Subpart AA
• Limited or restricted means for entry or exit
– Applies when an entrant’s ability to escape in an
emergency would be hindered
– Includes trip hazards, poor lighting, slippery floors,
inclining surfaces, ladders and even stairs - if they
impede egress
Clarifications in Subpart AA
• Noise is a physical hazard
– Will only trigger permit space procedures if it
reaches a level at which it can cause death or
serious physical damage
• In other words, if it is loud enough to interfere with
critical communication
– Can address in permit program by using non-
auditory cues (flashing lights)
Clarifications in Subpart AA
• Training must be in the language and
vocabulary that employees can understand
Confined Spaces in Construction
OSHA’s Final Rule: Summary
• Numerous clarifications plus 5 key differences:
– Employers on site must coordinate activities
– Competent person must evaluate site
– Employers must conduct continuous air
monitoring
– Employers must conduct continuous monitoring
of engulfment hazards
– Employers can suspend a permit for temporary
changes
September 17, 2015
Lessons from a Deep, Dark Confined
Space: Amistad Dam Case Study
• Background
• Scope: Penstock Inspection
• Pre-Task Planning
– Hazard Identification
– Hazard Mitigation
• Implementation and Change Management
• Lessons Learned
September 17, 2015
Amistad Dam: Background
• Constructed by International Boundary Water
Commission (Joint US/Mexico agency that controls
the Rio Grande) in 1969
– Located 12 miles northwest of Del Rio, Texas
MS14
Slide 23
MS14 Shoulde this say "via vertical gate shafts"? Miller, Sally, 9/13/2015
September 17, 2015
Amistad Dam: Background
• Penstock connects reservoir to power generating stations– ~12-foot diameter circular tunnel
– Located 200 feet below dam deck, 150 feet below reservoir level
– Significant side slope – 15-20 degrees
• Only access points from downstream (requires SCUBA) or vertically via gate shafts
MS13
Slide 24
MS13 Shoulde this say "via vertical gate shafts"? Miller, Sally, 9/13/2015
September 17, 2015
Insert dam surface photos
September 17, 2015
Scope: Penstock Inspection
• Damage to penstock rendered it ineffective;
IBWC desired design to permanently plug the
penstock
• Required personnel to enter in order to inspect
and document current conditions of steel and
concrete
• Use instruments (electrodes and other sensors)
and collect chip samples of concrete and steel
Sounds simple, right?
September 17, 2015
September 17, 2015
Pre-Task Planning: Hazard
Identification & Evaluation
• Lockout/Tagout of gate
• Unsophisticated safety protocols
on-site
September 17, 2015
Hazard
Identification
• Confined-Space entry
– Engulfment (from upstream)
– Drowning (if slide
downstream)
– Very slow retrieval from
space
• Isolated work site
September 17, 2015
Pre-Task Planning: Hazard Mitigation
• Developing Lockout/Tagout protocols
• Designing back-up engineering control for steel gate
suspension by structural engineer (use of I-Beams)
Beams secured via
webbing to handrail and
column. Tied with a
‘clover’ knot.
Below each beam
is two 2”x12”
boards (8 ft long)
September 17, 2015
Pre-Task Planning: Hazard Mitigation
• Hiring qualified subcontractor
to design fall protection system
and confined space rescue
protocol
September 17, 2015
Pre-Task Planning: Hazard Mitigation• Developing a comprehensive Entry Permit, HASP &
Contingency/Rescue Plan, reviewed at highest levels of organization’s Safety management team
• Performing safety inspection and practice run prior to actual entry
September 17, 2015
HASP Development/Review took HASP Development/Review took HASP Development/Review took HASP Development/Review took approximately 100 personapproximately 100 personapproximately 100 personapproximately 100 person----hours, hours, hours, hours,
compared to approximately compared to approximately compared to approximately compared to approximately 45 person45 person45 person45 person----hours hours hours hours for the actual inspection.for the actual inspection.for the actual inspection.for the actual inspection.
September 17, 2015
Implementation & Change
Management
• LOTO procedures implemented.
• Engineering controls (beams) required modification; required
concurrence from structural engineer before proceeding.
September 17, 2015
Implementation & Change
Management
• Fall protection/rescue zone establishment
• Practice run indicates extraction is too slow for comfort –
AECOM personnel trained to assist with lift (pulling ropes)
during rescue
September 17, 2015
Implementation & Change
Management• Air quality checks (probe dropped from surface) find
conditions in penstock ideal.
• Safety inspection finds no odors, relatively good traction, comfortable temperature, little mud, good setup by subcontractor.
September 17, 2015
Implementation & Change
Management• Scaffold tie-offs insufficient and improved prior to inspection.
• Inspection completed 8 hours without incident.
• Project scope successful.
• AECOM awarded additional work.
September 17, 2015
Lessons Learned• Pre-Task Planning crucial; short-duration
projects are no exception
• Client procedures – Trust, but Verify!
• Staff projects for safety:
– Employee expertise, experience & comfort level
(fear of heights, claustrophobia)
– Subcontractor expertise and flexibility
• Teamwork!
Thank you!
Sally K. Miller, CIH
AECOM
Denver, CO
720-483-3976
Patrick Walz, PE
AECOM
Austin, TX
512-221-3195
September 17, 2015
Questions?