Lesotho Highlands Water Project - LHWP | PORTAL Report 58 - rev0.pdf · Lesotho Highlands Water...
Transcript of Lesotho Highlands Water Project - LHWP | PORTAL Report 58 - rev0.pdf · Lesotho Highlands Water...
Report prepared for Lesotho Highlands Development Authority
Lesotho Highlands Water Project
Report 58
Report prepared by Environmental Panel of Experts
R Hitchcock, A Inambao, J Ledger & M Mentis
March 2011
Revision 1
PoE Report 58 – March 2011 – Executive summary Page 2 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Executive summary
1. The Panel of Environmental Experts (PoE) for the Lesotho Highlands Water Project
(LHWP) undertook a mission from 6-17 March 2011.
2. The purpose of the mission was to help develop and implement critical projects being
undertaken by the Lesotho Highlands Development Authority (LHDA).
3. The critical projects addressed during the mission, and the way forward on each, were
briefly as follows. LHDA Compensation PoE was asked to review and comment on the Katse and Lejone audit action plan and advise on its adequacy to fast track payment of communal compensation for LLEs upstream of Katse Dam. There are 23 LLEs (co-operatives) upstream of Katse Dam. These LLEs were paid out M11 million in communal compensation. Recommended actions include ensuring of transparency in financial management, regular checks of LLE books and bank account information, enhancement of monitoring of communal compensation funds usage, doing a careful assessment of activities and projects of LLEs and providing lessons learned for future work, engaging in preventive action to reduce corrupt practices, and encouragement of LLE committees to pursue legal action against individuals who used funds for their own purposes or gave funds to others. On the downstream LLEs, of which there are 22 below Katse Dam, the Technical Assistance Unit should follow some of the same recommendations for the LLEs upstream. The Department of Co-operatives should be encouraged to expand the number of field officers working with LLEs. In both upstream and downstream LLEs more work needs to be done in enhancing income generating activities and community development projects (eg hammer mills, road and water system construction, houses for tourists, electrification). Careful work needs to be done on assessing the sustainability of income generating and community development activities and lessons learned must be built on by the TAU and the LLE members. This assessment should be a mix of desk-top reviews and on-site field investigations. Income generation/Technical Assistance Unit A review was undertaken of LLEs training provided/ facilitated by TAU officers and Income Generation Officers in the three branches of Katse, Mohale and ’Muela. In general, it was found that the training provided by the TAU and IGOs was adequate. It could be enhanced through a training of trainers approach, materials made available based on lessons learned from LLE income generating activities and community development. Constraints exist among community members because of relatively low levels of education in some cases and lack of experience in running projects and carrying out entrepreneurial activities. These could be circumvented in part through greater cooperation among LHDA, LLEs, DoC, community councils, local and central government, and non-government organizations in capacity-building at the local level.
Given the increasing rate of embezzlement of communal compensation by LLEs, a review was undertaken of the adequacy of the safeguard measures incorporated in the MOUs between LHDA and the LLEs to protect LLE’s funds against fraudulent practices. It was found that the MOUs as they stand are sufficient to safeguard against fraudulent practices. Efforts must be made to increase monitoring of LLE committee activities, bank accounts, and project management and implementation. Efforts must also be made to expand the training of LLE committees in accounting, financial management, income generating project activities and community development program work. Public relations LHDA met with internal stakeholders (affected communities) and external stakeholders (NGOs, service providers, Ministries, water consumers, general public). Engaging the internal stakeholders must continue. The (new) Chief must be seen take the lead in this, in both formal meetings and by ‘walk-abouts’ meeting staff and community people in their day-to-day activities, to build staff morale and have affected communities that they are taken seriously. Holding
PoE Report 58 – March 2011 – Executive summary Page 3 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
external stakeholder workshops for the sake of tradition is not recommended. Rather maintain surveillance on external issues, treat the substantive ones directly, and address the false negative issues not by direct confrontation but rather by projecting a positive organization image. KFF pilot trout production PoE made a site visit to KFF and reviewed monthly Compliance and Progress reports for November and December 2010. The December report contains the same water quality monitoring results as the November report – a careless mistake. Lesotho Department of Environment has extended the KFF RoD to October 2011. KFF has applied to LHDA for extension of the pilot project into full-scale production. PoE is of the opinion that KFF has complied with most requirements. LHDA must convene a meeting with KFF to review the pilot phase and agree on a way forward. KFF’s concerns about biosecurity are valid and should be incorporated in the draft Lesotho Fisheries Regulations.
ICM PoE considered the report on performance of soil conservation structures in the Bela-Bela sub-catchment at ’Muela, and was conducted over site. The structures are performing well, but the initiative is too little. ’Muela reservoir and Matsoku weir are silting up alarmingly. The proper functioning of the LHWP is under threat. Improving the sustainability of catchment land-use is a critical and strategic issue that requires FOBs to be capacitated to implement the physical work as well as extension. Every opportunity must be seized to widen the economy of the Highlands, reducing dependence on exploitative use of soil and vegetation resources. Workshop the priorities and implementation design.
Instream flow requirements To address the forthcoming consideration of 2
nd tranche compensation
payment for communities downstream of Phase 1A structures, LHDA should commission an independent assessment to make recommendations based on existing monitoring data, PoE Reports and a specially designed field monitoring study. Monitoring of water quality, hydrology and geomorphology should continue in-house for the moment, but an IFR methods workshop – including social IFR monitoring, might be staged in early 2013. Community infrastructure development PoE considered the issues and challenges concerning the management of community infrastructural development covering the 321 resettlements where communities are required to identify suitable and sustainable development programs; upon which LHDA would provide the required financial support that is supposed to be proportionate to the number of resettled individuals in the area. This is supposed to be coordinated with the relevant government ministries. The challenge faced by the program is that LHDA does not provide indicative budgets to enable the communities to plan on, as a result of which communities have tended to choose projects that are costly and would require continued support from government which does not have adequate resource base. Furthermore, LHDA has been slow to respond to some of the proposals for development from the communities. The non-availability of the size of the budgets on community development support is viewed by beneficiaries as lack of transparency in the way LHDA is handling the issue. LHDA should adopt an open policy and inform communities on how much is available for development as well as work with the traditional and civic leadership to determine viable and sustainable development projects.
LHDA performance indicators Performance indicators (PIs) list the things that must be got right, and show the degree to which the essentials are satisfied. PoE supports perseverance with the initiative. LHDA Executive and Managers should buy-into PI reporting (or come up with a better substitute). This should be done by Executive and Manager review, revision, refinement and updating. Current PIs overlook some critical issues, such as progress towards a decision on 2
nd tranche compensation
payment downstream of Phase 1a structures, and construction of a barrier to protect the Maloti Minnow on the Senqunyane River. The present PIs include outcome targets, but they also need to cover performance on processes that ensure targets are met (eg preventive maintenance, scheduled inspections, emergency reporting, emergency drills). Monthly PI reporting by each Manager is recommended as a means focusing management on the things that LHDA must get right.
Strategic planning issues PoE review of the LHDA SP found that the plan requires refining its strategic imperatives in such a way that they clearly lead to addressing issues and challenges likely to compromise its performance and institutional image, promote staff loyalty and improve morale. The LHDA SP analysis did not include a critical internal analysis of management and structural issues
PoE Report 58 – March 2011 – Executive summary Page 4 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
likely to contribute to reduced performance and increased staff turnover. PoE felt that the development of the SP appears to have been constrained by staff anxiety to avoid critiquing management processes and cultures that might be seen as criticizing management, and yet intentions to have these concerns addressed were expressed in the Key Focus Areas statements. Currently the state of readiness of LHDA to meet her mandate to achieve the vision of being one of the best managed water management organizations in the world is decreasing due to the high staff turnover, low staff moral and the failure for the organization to translate plans into action. The organization seem to have concentrated on process and performance and lowered its management of the actors (staff), resulting in failure to effectively manage the translation of plans into action in a timely manner. PoE recommends that LHDA undertakes a joint review of the SP using a multilevel joint workshop to enable appreciation of the strategic roles of individuals in the organization using an outsider to instil team spirit among the different levels of responsibilities in the organization. Maloti Minnow Terms of Reference and Project Brief for construction of barrier(s) and access road were reviewed. The documents lack clarity and must be revised to reflect that there are two very clear and different options for barrier construction on the Senqunyane River, and the EIA Consultant must review the options and recommend one. Work previously conducted by the Lesotho Biodiversity Trust, with input from LHDA engineers, identified one site for a weir at Ha Ts’oeute with a 6.6 km access road and another site for a meander cut waterfall at Ha Nteso with some 2 km further from the weir site. These options have widely differing logistic and cost implications and need to be better stated in the ToR and Project Brief. PoE recommends that a Maloti Minnow Consultant be appointed to oversee this and other urgent interventions. PoE Report # 56 flagged the issue: Maloti Minnow conservation has now become a strategic issue of crisis proportions. Six month later, the crisis has deepened. KLM WATSAN PoE was informed that a new RFP for the construction of VIPs, Waste Disposal Pits and Water systems for Katse, Lejone and Masuku areas has been advertised and a number of bidders have applied. The RFP contained a request to construct the systems based on precast standard designs and did not provide for proposals for innovative designs. PoE believes that the process has excluded innovation or adoption of newer technologies to reduce the costs and improve efficiency and safety of human waste disposal in an environment where pollution of water sources and water tables are important. PoE recommends that an addendum to the RFP/Tender be added to include proposal for innovative systems such as the Hydroloo which would be cheaper and more efficient to use in current circumstances. Phase 2 issues Terms of reference have been prepared for appointment of one Environmental and one Social Specialist to draw up terms of reference (ToRs) for environmental and social impact assessment and management in Phase 2. The appointed individuals and parent organizations should not otherwise be involved in Phase 2. This condition, coupled with the requirements for expertise and experience, are going to make it difficult to make appointments. Alternative development of ToRs (in-house) might be necessary. ToRs to conduct an EIA for construction of a measuring weir and access road at Polihali require revision (inconsistencies, presentation, typographical errors, etc).
4. The Panel thanks LHDA and the Lesotho Highlands Water Commission for friendliness,
help and hospitality, and appreciates the smooth running of the Mission.
PoE Report 58 – March 2011 – Contents Page 5 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Contents
Executive summary .................................................................................................................... 2
Introduction ................................................................................................................................ 6
Critical projects .......................................................................................................................... 8
1. LHDA compensation ...................................................................................................... 8
2. Income generation/Technical Assistance Unit.............................................................. 11
3. Public relations.............................................................................................................. 12
4. KFF pilot trout production ............................................................................................ 13
5. ICM ............................................................................................................................... 14
6. Instream flow requirements .......................................................................................... 17
7. Community infrastructure development ....................................................................... 20
8. LHDA performance indicators ..................................................................................... 20
9. Strategic planning issues ............................................................................................... 24
10. Maloti Minnow .......................................................................................................... 25
11. KLM WATSAN ........................................................................................................ 26
12. Phase 2 issues ............................................................................................................ 27
Appendix 1 Compensation principles and practices in LHWP ..................................... 28
Appendix 5 Technical notes .......................................................................................... 33
Appendix 6a The decision rules .................................................................................... 40
Appendix 6b ToR framework for short-term IFR monitoring ...................................... 41
Appendix 9 LHDA Strategic Plan ................................................................................. 43
Appendix 10 Senqunyane Access Investigation Trip ................................................... 44
Appendix 11 KLM WATSAN ...................................................................................... 49
Appendix 12 ToRs for environmental and social specialists ........................................ 50
PoE Report 58 – March 2011 – Introduction Page 6 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Introduction
The Panel of Environmental Experts (PoE) for the Lesotho Highlands Water Project (LHWP)
undertook a mission from 6 to 17 March 2011. The mission was attended by Professor Bob
Hitchcock and Drs Amusaa Inambao, John Ledger and Mike Mentis.
The overall objective of the Mission was to provide the Lesotho Highlands Development
Authority (LHDA) with an independent evaluation of its operations, identifying where things
might be going wrong, how LHDA might improve its performance, and providing guidance
on best practice. The specific terms of reference (ToRs) for the Mission were as follows.
Task # Issue Action
1. LHDA
compensation Review and comment on the Katse and Lejone LLEs
audit action plan and advise on its adequacy to fast-
track payment of communal compensation for LLEs
upstream of Katse Dam.
2. Income
generation/
Technical
Assistance Unit
Review LLE‟s training provided / facilitated by TAU
officers and Income Generation Officers in the three
branches of Katse, Mohale and „Muela and recommend
actions for improvement and sustainability on this
matter.
Given the increasing rate of embezzlement of
communal compensation by LLEs, review the
adequacy of the safeguard measures incorporated in the
MOUs between LHDA and the LLEs to protect LLEs
funds against fraudulent practices and advise LHDA on
the best ways possible.
3. Public Relations Critically review the processes towards hosting LHDA
annual external stakeholders‟ conferences and the
resulting evaluation reports thereof. Advise LHDA on
the best practices to making this review a worthwhile
course to improving LHWP‟s image.
Review the LHDA external stakeholders‟ score card
and LHDA performance against this score-card to date
and advise on the most appropriate steps in undertaking
external stakeholders evaluation and scoring.
4. KFF pilot trout
production Review and comment on KFF latest monthly progress
report(s) and advise accordingly.
5. ICM Review the updated report on the performance of the
soil and water conservation works at ‟Muela post the
recent heavy rainfall.
6. Instream Flow
Requirements
(IFR)
Provide expert advice on how best to sustain IFR
activities in the absence of key IFR monitoring experts
such as Fish and Vegetation specialists and the IFR
Coordinator.
7. Community Review LHDA approach of implementing the
PoE Report 58 – March 2011 – Introduction Page 7 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Task # Issue Action
infrastructure
development
community infrastructure development program and
advise on how to make both internal and external
stakeholders, to appreciate the challenges and how to
overcome any bottle-necks.
8. LHDA
performance
indicators
Review progress on LHDA Performance Indicators
since the last mission and advise accordingly.
9. Strategic
planning issues Following POE review of LHDA five years rolling
Strategic Plan during the previous mission, assess the
readiness of LHDA to meet her mandate given the
current staff turn-over within the organisation.
10. Maloti Minnow
conservation Critically review and comment on the Project Brief of
the Maloti Minnow conservation.
Review and comment on the revised TORs to
undertake EIA for construction of barriers to conserve
Maloti Minnow and access road to the barrier site.
11. KLM WATSAN Critically review and comment on the TORs for
outsourcing KLM WATSAN and advise on the new
technologies that can be adopted to ensure completion
of this project.
12. Phase 2 Issues Critically review and advise LHDA on the
comprehensiveness of the terms of reference (TORS)
for the Environmental and Social specialists for Phase
2.
Critically review and comment on the Project Brief of
the construction of the weir and access road at Polihali
under Phase 2.
Review and comment on the TORs to undertake the
EIA for construction of the weir and access road at
Polihali.
PoE Report 58 – March 2011 – Critical projects Page 8 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Critical projects
Project Present situation Recommendation Finish date
1. LHDA compensation
The Katse and Lejone LLEs Audit Action Plan of January, 2011
was assessed. It was found that many of the LLEs had financial
problems, with funds missing, poor accounting practices, evidence
of financial malfeasance, and lack of information on individuals
who are deceased. There are 23 LLEs (co-operatives) upstream of
Katse Dam. These LLEs were paid out M11 million in communal
compensation. At least 11 of the 23 LLEs had evidence of financial
problems with recommendations for follow-ups on debtors,
investigation of bank balances and bank charges, and the need for
follow-ups with the Department of Co-operatives (DoC) legal
section.
Encourage LLE
committees to pursue
legal action against
individuals who used
funds for their own
purposes or gave funds to
others
2011-04-30
The practice of LLE paying dividends was reported to have
continued in after LHDA advised LLEs to stop paying
dividends – this has continued in a few LLE.
Do follow-ups with the
DoC Legal Section
2011-04-30
Carry out new audits and
ensure better account
keeping through regular
checks of LLE books and
bank accounts
2011-06-30
Upgrade training in
accounting and financial
management by IGOs
and Co-ops officers
2011-05-31
Enhance the oversight
of communal
compensation funds
usage
2011-04-30
Prevent LLEs from 2011-03-31
PoE Report 58 – March 2011 – Critical projects Page 9 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
paying out dividends to
members
Investigate bank charges
that are suspicious and
require banks to repay
LLEs if they have
overcharged them
2011-06-30
In cases where LLEs
are paying themselves
dividends, FOBs
should liaise with the
legal section of the
Department of
Cooperatives to issue
general directives to
stop the practice with
immediate effect and to
prosecute those who
persist in the practice.
2011-05-31
Do careful assessments
of activities and projects
of LLEs and provide
lessons learned for future
work
2011-05-31
When new LLE
committees are elected,
ensure that they are
trained quickly
2011-04-30
DoC has not been able to regularly undertake support
supervision visits through which LLE would have been
guided and advised on their operations, because DoC lacks
resource.
LHDA should provide
resource support to
DoC in terms of
transport and other
logistical arrangements
2011-06-30
PoE Report 58 – March 2011 – Critical projects Page 10 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
to facilitate
undertaking joint
support supervision of
LLEs. A quick assessment of the membership carried out on a sample of
LLE visited in the field found that a small but significant number
of individuals were not members of LLEs and therefore were
excluded from profiting from the communal compensation given
through LLEs. PoE was of the opinion that the difficulties that lead
to the formation of LLEs as cooperatives could be overcome by
involving traditional and civic leadership as community Trustees
that would be monitoring the use of financial resources by the LLE
committees. Although the MoUs clearly state that all affected
households are members of LLE, the adoption of the
cooperative principle that requires membership subscription
has led to those not able to pay subscription being excluded
from membership of particular LLE. The membership to LLE
could be made universal by payment of a small percentage of the
compensation into a separate LLE management account to cover
every member of the community.
LHDA initiate the
inclusion of traditional
and civic leadership in
the monitoring and
supervision of LLE by
change of the MOU
2011-05-31
LHDA develop new
TORs for LLEs to
incorporate the inclusion
of all members of the
community in the
organization
(membership to LLE
should be part of the
compensation paid to
each LLE by LHDA to
ensure that each
affected individual or
family is a member of
2011-05-31
PoE Report 58 – March 2011 – Critical projects Page 11 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
the LLE)
2. Income generation/Technical Assistance Unit
A review was undertaken of LLE‟s training provided/ facilitated by
TAU officers and Income Generation Officers in the three
branches of Katse, Mohale and „Muela and actions for
improvement and sustainability on this matter called for. In
general, the training undertaken by TAU officers and IGOs in the
three FOBs is viewed as adequate. More work needs to be done in
enhancing income generating activities and community
development projects (eg hammer mills, road and water system
construction, houses for tourists, and electrification). TAU and
IGOs have both requested further training for themselves in order
to enhance their training delivery, as well as the production of
materials that can be used in training. Constraints exist among
community members because of relatively low levels of education
in some cases and lack of experience in running projects and
carrying out entrepreneurial activities. These could be
circumvented through greater cooperation among LHDA, LLEs,
DoC, community councils, local and central government, and non-
government organizations in capacity-building at the local level.
Review current projects
to determine the
sustainability of the
income generating
projects being
implemented or planned
2011-05-31
Enhance TAU training
programs by making
them relevant to the
needs of the community
2011-05-31
Improve training by
development and
production of appropriate
and relevant materials
suitable for training of
the communities
2011-06-15
Encourage Dept of Co-
operatives to expand
number of field officers
available to assist TAU
and IGOs
2011-05-31
PoE Report 58 – March 2011 – Critical projects Page 12 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Given the increasing rate of embezzlement of communal
compensation by LLEs, a review was undertaken of the adequacy
of the safeguard measures incorporated in the MOUs between
LHDA and the LLEs to protect LLEs funds against fraudulent
practices. It was found that the MOUs as they stand are sufficient
to safeguard against fraudulent practices. Efforts must be made to
increase monitoring of LLE committee activities, bank accounts,
and project management and training of committees and
community members.
The best way to deal with
these practices is to
increase monitoring of
LLE committee activities
through the establishment
of a resident community
monitoring body
consisting of the village
Chief and Counsellor and
LHDA personnel
2011-04-30
3. Public relations
LHDA external stakeholders
annual conference and score
card
LHDA has two types of stakeholder engagement – (a) with the
affected communities (internal stakeholders), and (b) with other or
external stakeholders.
Continue to engage
affected communities,
but consider dropping the
annual workshop with
external stakeholders
2011-04-30
Regular and frequent engagement with the affected communities
will probably always be necessary. Though LHDA might be well
aware of affected community wants and needs, and its own level of
service delivery, the perception of LHDA‟s caring and
responsiveness are important. Ideally, if the parties (LHDA and the
communities) engage and communicate, the efficiency with which
tasks are performed is liable to be high – collaboration rather than
destructive conflict. In particular, top management (the CEO)
should be seen to take the lead role at both formal gatherings and
in „walk abouts‟. To do this the (new) CEO must have not only a
good understanding of the various facets of LHDA‟s operations,
but must have people skills – this contributes to staff morale and
belief by the communities that they are taken seriously.
Engagement of affected
communities must be led
by the top executive, with
the (new) chief appearing
at formal meetings and
undertaking „walk
abouts‟ to meet staff and
community people in
their day-to-day activities
2011-04-30
Regarding the external stakeholders, again, at this stage in LHWP
LHDA should have a good idea of issues, and holding a workshop
for the sake of tradition is likely to have limited benefit. However,
LHDA should maintain surveillance on stakeholder issues.
Negatives on LHDA should be addressed. Of course if there are
real defects in LHDA function then the remedy is to fix the defect.
In the case of substantive
negative issues from
external stakeholders,
treat each issue on its
merits – meet relevant
stakeholders, fix the
2011-04-30
PoE Report 58 – March 2011 – Critical projects Page 13 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
This might mean workshopping with relevant internal and external
stakeholders, and adjusting the administration and management.
Where allegations and perceptions are against LHDA and are false,
the contemporary PR thinking is not to oppose these head-on (this
is believed to advertise the false information), but rather to project
a positive image of LHDA to the degree that it swamps the
negatives.
administration and
management. In the case
of untruthful allegations
on LHDA, preferably do
not counter head-on but
project a positive image
of LHDA
The score card is rendered redundant by the above. In any case, the
score card method is useful on specific known issues where the
organization wants to measure the stakeholder‟s perceptions of
shortcomings and progress. The score card method is not helpful
about unknowns – the Black Swans.
Dispense with the score
card, maintain
surveillance of issues,
counter negative false
issues with positive PR,
and workshop
substantive negative
issues with parties
concerned
2011-04-30
4. KFF pilot trout production
Three PoE members visited KFF on 10 March 2011 and were
taken onto the water to see the facility. New cages have been
acquired, as well as a new barge for servicing the operation.
LHDA management
should visit KFF to see
the new equipment
2011-06-30
The KFF Compliance and Progress Reports for November and
December 2010 were reviewed. The December report has a
careless repetition of water quality monitoring results from the
November report. The latter report includes a Biosecurity Initial
Report. KFF told PoE that it has not been involved as a stakeholder
in development of draft fisheries regulations for Lesotho.
Biosecurity issues are important to the aquaculture industry in
Lesotho and principles of biosecurity should be incorporated into
Fisheries Regulations. KFF are pioneers of aquaculture in Lesotho
and, as interested and affected parties, they should be invited to
participate in the process of drafting fisheries regulations.
KFF to correct the
December report and
submit reports for
January and February
2011
2011-03-31
KFF to participate in
drafting of Fisheries
Regulations.
2011-04-30
KFF has requested LHDA to approve rights to expand the pilot
PoE Report 58 – March 2011 – Critical projects Page 14 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
phase into full production. KFF complains that another party has
been given rights to produce cage trout in Katse before the
conclusion of the KFF pilot project. The grievance is
understandable and LHDA‟s impartiality could be questioned.
LHDA should be the referee and apply the rules consistently.
Questions about whether KFF has complied with the conditions of
the MOU and RoD have been raised by LHDA. PoE‟s view is that
most (if not all conditions) have been met, or can be ironed out by
constructive engagement. PoE believes that there are no outstanding
issues that cannot be resolved by discussion and negotiation. PoE
supports a competitive environment for aquaculture investors, and
uncertainty around conditions and requirements for operators should
be removed as far as possible.
Production – the MOU and RoD both indicate production of 300
tons pa. It seems clear that this is a maximum rather than a
minimum. PoE suggests that as production has reached close to
300 t/a, further debate is not warranted.
Water quality issues – KFF has reported regularly on water
quality and there do not seem to be serious areas of concern.
Spikes in some readings have been noted and discussed.
Training of community members – KFF has trained and
employed a number of people from Ha Lejone; details are
contained in monthly reports.
Monitoring of sediment beneath cages – PoE is aware that
sediment samples have been taken and are currently being
analysed.
Mid-year review – if this is outstanding, KFF must be required to
comply.
Business viability – PoE understands that KFF has supplied
figures that confirm the viability of the business.
LHDA to convene a
meeting with KFF to
review and conclude the
pilot phase, resolve any
outstanding issues, and
make a decision on
expanded production.
2011-04-30
5. ICM
Report on soil conservation
measures at ‟Muela PoE was provided with a report on the performance of the soil
conservations structures in the Bela-Bela sub-catchment during the
Adopt catchment
management as a core
2011-04-30
PoE Report 58 – March 2011 – Critical projects Page 15 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
past summer, and PoE made a site visit. The structures withstood
the heavy rains well. There are too few of these structures in the
‟Muela catchment, and all structures need maintenance. ‟Muela
reservoir is silting up alarmingly (at least by visual inspection), and
this applies equally to Matsoku weir, to the extent that proper
functioning of the engineering systems is threatened. PoE
comprises environmentalists not engineers, but PoE warrants that
the siltation problem requires treatment of the cause – non-
sustainable land-use.
function
As a first step in
capacitating ICM,
appoint 2-3 additional
staff to each FOB to
work primarily on ICM
in collaboration with
each FOB team
2011-06-30
PoE Report 58 – March 2011 – Critical projects Page 16 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Build soil conservation
structures (as done in
Bela-Bela) – the
priorities are other sub-
catchments at ‟Muela,
and in the Matsoku
catchment upstream of
the weir
Start 2011-
07-01. On-
going
Present LHDA commitment to making catchment land-use more
sustainable is inadequate. Since PoE October 2010 mission ICM
work has been transferred to FOBs, but without augmenting human
resources and budgets. There are no quick-fixes. Physical soil
conservation structures are required. The community mindset
needs to be transformed. The economy of the Highlands must be
shifted from dependence on exploitative use of soil and vegetation
to softer kinds of land-use such as tourism, recreation, water and
power production, etc. The scale of the problem is huge. Unless the
siltation issue is resolved, or at least eased, LHWP might bury
itself within a few decades. The situation is not beyond rescue. It is
reported that in South Africa, sediment loads in rivers have
decreased to 40% of the rate in the mid-1900s. This has occurred,
at least in part, by aggressive agricultural extension services,
improved sustainability and productivity of agriculture, and a
widening of the rural economy. Holding meetings with government
ministries to get their buy-in might be necessary, but unless and
Maintain and improve the
construction soil
conservation structures
recommended above
Start 2011-
07-01. On-
going
PoE Report 58 – March 2011 – Critical projects Page 17 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
until LHDA takes primary responsibility for actually doing the
work, no effective progress is likely.
Undertake extension
work to improve the
sustainability and
productivity of
agricultural practices (eg
limited tillage, inter-
cropping, withdrawal of
non-productive land from
cultivation and grassing
of it, etc)
Start 2011-
07-01. On-
going
Widen the rural economy
– facilitate development
of tourism, recreation,
time-share, trout
production, renewable
energy power production,
investing in government
bonds & other such non-
consumptive profit
initiatives
On-going
There are innumerable ICM tasks that could be performed, and it is
necessary to prioritize and design implementation. Each FOB has
its own characteristics, so each FOB should draft its priorities and
plans, and these should workshopped (indoor and outdoor with
relevant staff from all FoBs meeting together, engaging in critical
and constructive debate, and pooling knowledge) among the FOBs
with PoE.
With FOBs capacitated,
hold an ICM workshop to
identify priorities for
each FOB, and design the
implementation (see
opposite under Present
Situation)
2011-08-31
While on site, PoE is asked many questions on technical issues.
Answering all these queries is not feasible in PoE reports, and such
matters are ideally material for workshops. Nevertheless some
technical notes are provided in Appendix 5.
6. Instream flow requirements
Sustaining IFR monitoring LHDA has lost in-house staff capacity to undertake IFR vegetation Prepare ToR for an 2011-12-01
PoE Report 58 – March 2011 – Critical projects Page 18 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
and fish monitoring.
The Decision Rules on whether to pay 2nd
tranche downstream
compensation require monitoring information on vegetation and
fish (Appendix 6a). The decision rules are generous to the cause
for downstream compensation.
A decision on 2nd
tranche payment for IFR reaches 1, 2 and 3 is
due in 2012.
It is implausible that LHDA can now recruit staff to undertake the
necessary vegetation and fish monitoring, but even if that were
possible there ideally needs to be an independent assessment of the
evidence, with gaps filled in as best possible, in the remaining
months of 2011.
independent assessment
of the evidence against
the decision rules
(suggested framework in
Appendix 6b), appoint a
consultant to expedite,
and have the consultant
submit a final report by
December 2011
There is a risk that, if left to her/his own devices, the riparian bush
and fish monitoring does not address the relevant issues in a
statistically acceptable way. To contain risks the Consultant should
deliver monthly reports covering the progress the past month and
plan for the next month.
Involve PoE throughout
the monitoring process,
with monthly reports
from the Consultant and
discussion involving
Consultant, LHDA and
PoE
Every
month
The affected downstream communities have expressed interest in
seeing the results of monitoring. It is not feasible to have
monitoring attended by hordes of people, but it is realistic to have
one or two community representatives attending the sampling. For
example, a community representative (or two) might accompany
the observer in the riparian bush assessment. While community
attendance does have risks, it is an opportunity to show and explain
river resource dynamics, and be transparent about it. The
communities must be cooperative – forewarned and given
advanced notice they should please be punctual.
Invite communities to
send 1-2 representatives
to attend monitoring, and
use this as an opportunity
to show and explain
resource dynamics
2011-04-30
In addition to riparian bush and fish monitoring, LHDA should
continue with water quality, hydrology and geomorphology in-
house.
Continue monitoring
water quality, hydrology
and geomorphology, and
workshop the methods
after the riparian bush
and fish monitoring
2012-03-31
PoE Report 58 – March 2011 – Critical projects Page 19 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
exercise for 2nd
tranche
payment is completed
Social IFR monitoring is being developed. PoE understands that
the Consultant‟s proposals might be tabled soon. However, LHDA
has limited resources and it is necessary to focus on the crisis of
the moment (ie the riparian bush and fish monitoring to inform 2nd
tranche payment).
Include social IFR
monitoring in the
methods workshop
mentioned in the above
bullet
2012-03-31
World Bank Paper Number 200 authored by Haas LJM, Mazzei L
& O‟Leary TJ 2010 entitled Lesotho Highlands Water Project:
Communications Practices for Governance and Sustainability
Improvement states as follows.
…the incidence of woody vegetation, economically the most valuable resource for cooking and heating for highland dwellers, increased rather than declined as predicted. The predicted loss of this vital resource was the basis for more than half of the total compensation payments. According to the LHDA report, this increase in the incidence of woody vegetation was caused by new trees colonizing in the channel islands. This seems to be due to the failure to implement the prescribed flushing flows that would otherwise have removed vegetation as predicted in the EFs studies. However, with the overtopping flood at Katse in 2006 and expected future floods, it is expected that most of the in-channel trees will be removed. This, together with the progressively reduced number of cuttings and seeds to reach these sites (because they will be trapped behind the dam), means that it is likely that, over time, the woody vegetation will decline, as predicted…
The World Bank does not cite PoE Reports nor the article by
Mentis MT & Ledger JA 2005 The effects of reduced river flows
on woody vegetation which LHDA put on its website. The implicit
assumption that vegetation increases are constrained by the
availability of plant propagules is equivalent to believing that the
human population would increase if men produced more sperm.
Plainly, riparian bush propagules on downstream reaches are
superabundant, and the amount of bush is constrained by living
conditions. But nothing will be gained fighting with the World
Bank – that might draw attention to an untruth (see Public
Do not react to dubious
claims about riparian
bush decreases, but rather
concentrate on improving
IFR monitoring and
reporting
On-going
PoE Report 58 – March 2011 – Critical projects Page 20 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Relations above) – and rather LHDA should pursue improving its
IFR monitoring and reporting.
7. Community infrastructure development
Community development programs have been slow and uncertain
in funding as LHDA does not provide information on the funding
levels as well as availability of funding. And recently, the advent
of the municipal councils has led to the call for the funds to be
channelled through area councils.
LHDA needs to develop
a resource directory for
each area to enable the
communities to use that
information to choose
and select viable and
sustainable projects
2011-04-15
The determination of the nature of community development
currently is based on dealing with development needs not covered
or provided for through government efforts. This has led to
selection of issues that may be way beyond the sustainable
maintenance of these projects by the LHDA support.
LHDA through the FoB
should hold consultation
meetings with area
authorities to identify
viable projects that would
be sustainable
2011-04-30
Collaboration with relevant government agencies to participate in
the planning and implementation of the development projects is
currently weak and the arrangements for handing over these
projects are weakened by the government‟s lack of resources.
LHDA should hold area
development planning
meetings with
communities and relevant
government agencies to
identify development
programs that would
visibly contribute to the
development of the
communities
2011-05-15
8. LHDA performance indicators
Review progress since last
PoE mission PoE Report 56 contained several recommendations, and the
January 2011 Performance Indicator Report was provided for PoE
to assess progress.
PoE recommended that PI reporting be continued. LHDA is
pursuing the reporting on a monthly basis. Reporting is in places
too narrow, eg PI Report January 2011 says KFF has not submitted
its January report, but whether KFF is otherwise up to date is not
reflected. A 2- or 3-month „snapshot‟ might be fairer than the
Continue PI reporting.
Consider expanding
some the indicators to
cover the past 2 or 3
months not just the past
On-going
PoE Report 58 – March 2011 – Critical projects Page 21 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
current month-by-month applied in some instances. month
PoE recommended review, revision and refinement of the
indicators, ensuring they cover all relevant issues, and they truly
measure performance, by 2011-01-31. Reported progress on this is
that review of LHDA indicators requires Board approval. PoE
understands that reviewed and revised indicators have not been
prepared to submit to Board, and getting Board approval (as
necessary as that might be) is liable to add to organizational inertia.
However, the fact that revision is not in effect reflects badly on
organizational performance. The PIs list what LHDA must get
right. The list must be updated continuously – completed items
deleted, new items added, and current items modified if necessary.
Compensation payment to LLEs downstream of Mohale is
effected. The item is history. Some items previously pointed out –
Maloti Minnow barrier, 2nd
tranche payments – are still missing
from the PIs. Since PoE Report 56, ICM is now an item deserving
of measurement, but it does appear under the PIs. If the system of
PI reporting cannot be made and kept relevant we have the
oxymoron of performance measuring not performing well. This is
not simply an M&E function. As recommended in PoE Report 56,
the PI initiative (or an equivalent process) buy-in by Managers is
necessary – if performance is measured then shortcomings can be
identified and remedied. Without „measuring‟ how does one know
where and how to intervene/manage? The Executive and Managers
must review, revise and refine the PIs, ensuring their
appropriateness and relevance (see below). Ideally each Manager
should submit a monthly report on her/his PIs. The report format
can be systematized for each Manager‟s situation, so report writing
is a matter of filling in the new numbers, or updating, and some
annotation and explanation.
LHDA Executive and
Managers review, revise
and refine performance
indicators, and obtain all
necessary approvals.
Consider monthly
Manager PI reporting.
2011-05-31
PoE recommended that corrective measures be developed and
included in the reporting matrix, to show corrective action, people
responsible, timelines and follow-up. The reported progress on this
is that LHDA management has been sensitized, as confirmed by
the monthly performance indicator reports from Managers.
Work on the PIs to
indicate where corrective
action is needed, then
develop corrective
measures including
2011-05-31
PoE Report 58 – March 2011 – Critical projects Page 22 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
However, the insertion of corrective measures in the PI Report is
not evident.
action, people
responsible, timelines
and follow-up
PoE recommended that LHDA Executive get buy-in from all
Managers on the PI system, otherwise come up with a better
substitute. It is reported that Managers are to workshop the issue in
March 2011. The workshop should include the Managers
„sharpening‟ up the PIs appropriate to each management area (see
more below).
Ensure Manager buy-in
of PI system (otherwise
come up with a better
substitute) by a workshop
that includes review,
revision and refinement
of PIs
2011-04-30
The PI January 2011 Report does not reflect the poor performance of
LHDA, as indicated by the current situation.
The delivery tunnel from ‟Muela to Ash River is non-functional
The ‟Muela hydropower station is not functioning
The ‟Muela reservoir is silting up at an alarming rate
The transfer tunnel from Mohale to Katse is closed
The transfer tunnel from Matsoku to Katse is closed
The Matsoku weir is silting up alarmingly
Lower level galleries at Katse are flooded
The low level outlets at Katse cannot be operated
The Katse mini-hydropower station is non-functional
Katse is about to spill, unavoidably
No progress was made on assessing 2nd
tranche compensation
payments since PoE Report 56
Construction of 1 517 VIPs and 88 water systems still outstanding
on Phase 1 WATSAN, and insufficient funds
The ICM function has been handed to FOBs without capacitation
A barrier on the Senqunyane to protect Maloti Minnow is not
constructed
Fish monitoring of reservoir fish stocks and to assess threats to the
Minnow is not being undertaken
LHDA has been without a Chief Executive for >5 years
In review, revision and
refinement of PIs at
workshop with Managers
consider including
additional PIs that
measure process
(preventive maintenance,
scheduled inspections,
emergency reporting,
emergency drills)
2011-04-30
PoE Report 58 – March 2011 – Critical projects Page 23 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
The above is equivalent to a risks & issues log – the important things
that require LHDA‟s action. The PI system must enable such a log to
be prepared, and updated, easily, and LHDA must act effectively on
it. The fact that much of the engineering system is currently non-
functional shows that LHDA is apparently not controlling its risks
adequately. How come? In addition to the other PI shortcomings
already mentioned, the current PIs measure against outcome targets
and do not include enough measurement of processes that ensure the
targets are hit. Examples of process include preventive maintenance,
scheduled inspections, emergency reporting, emergency drills on
worst case scenarios, etc.
Urgently refine the
opposite risks & issues
log.
2011-04-30
For each item on the risks
& issues log devise
appropriate controls –
action, correction,
prevention, emergency
preparedness & response
2011-04-30
Follow-up on the controls
implemented, review &
revise, and update the
risks & issues log.
Monthly
PoE Report 58 – March 2011 – Critical projects Page 24 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
9. Strategic planning issues
Current LHDA 5 Year Strategic Plan has identified 14 Key areas
of Focus which have covered most elements required by the
Mission statement. However, due to the incompleteness of the
internal environmental analysis process undertaken, LHDA has not
been able to effectively translate the strategic imperatives into
action.
LHDA should consider a
joint review of the
strategic plan involving
all the three levels (the
Commission, the Board
and LHDA to ensure
establishment of a
common vision
2011-06-30
Implementation of the various strategic options identified has not
been undertaken or has been delayed by a number of constraints
that include high staff turnover, low staff morale, and slow
decision making process due to what appears to be limited levels of
consultation between the various layers of administration and
policy.
Hold an institutional
management review to
identify and deal with the
reasons for staff
underperformance and
critical resignations
2011-05-30
The organization failure to fill up critical management positions
with substantive management executives and the reluctance to
retain experienced staff will continue to impact on LHDA‟s
performance.
LHDA has to make
concerted efforts to fill
the vacant position by the
end of the second quarter.
This may involve head
hunting for the right
individuals and would
require objectivity on
both parts of the head
authorities
2011-06-30
The imposition of decisions by higher authorities on LHDA
management continues to curtail its ability to respond to emerging
challenges in the field, and even in the appointments of personnel.
Establish a consultative
forum to set up
mechanisms for review
of performance. And
where possible the
various governing bodies
should allow those below
them to make decisions
and only intervene where
there is absolute need
2011-04-30
PoE Report 58 – March 2011 – Critical projects Page 25 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
The strategic intentions in the plans have not been matched with
the organization‟s ability to implement due to staff shortages, job
insecurity and lack of definitive staff development plans.
Review the increasing
staff resignations and
find solution to stop and
attract more qualified
personnel in LHDA
2011-04-30
Personalised management practices at various levels have
negatively impacted on staff performance and the potential for
innovation due to job security concerns.
Although the performance based systems is in place, its use has not
been used to improve staff performance as rewards or sanctions
tied to the performance assessment levels are reported not to be
objectively applied to all individuals.
Review the application of
the performance
management system and
establish impartial
application of the system
in all divisions
2011-4-30
10. Maloti Minnow
PoE notes as follows
PoE Report 54 0f March 2010 recommended retaining the services
of a fish expert (formerly employed by the Lesotho Biodiversity
Trust)
A year later neither this fish expert nor any other has been
commissioned.
In the interim monitoring of invasive fish into Mohale, and the
status of wild and transplanted Maloti Minnow, has lapsed.
The Maloti Minnow is a critically endangered species, and threats
to this red data animal were flagged in the Phase 2b EIA.
LHDA has a Maloti Minnow Policy and Action Plan.
In PoE Report 56 of October 2010 identified Maloti Minnow
conservation has now become a strategic issue of crisis
proportions.
An option is for LHDA to appoint a consultant to implement the
Maloti Minnow Policy and Action Plan, monitoring the wild and
transplanted Minnow populations, monitoring the threats of
invader fish into Mohale, archiving all information and reports
Appoint a consultant to
implement the Maloti
Minnow Policy and
Action Plan.
2011-06-30
PoE Report 58 – March 2011 – Critical projects Page 26 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
relevant to Maloti Minnow conservation, and acting as Champion
for Maloti Minnow conservation.
PoE reviewed the Project Brief and ToR for the EIA for the Maloti
Minnow conservation barrier(s) and access road. Both documents
are confusing and must be revised. The basic inadequacy is that
neither document takes into consideration the preliminary work
done by Lesotho Biodiversity Trust in 2007 to advance the issue of
barrier construction. An overview is provided in Appendix 10.
Briefly, LBT chartered a helicopter in 2007 to take three LHDA
engineers on a site visit to consider barrier options on the
Senqunyane River. They identified two possible sites, one at Ha
Ts‟oeute for a weir (6.6 km access road) and another at Ha Nteso
for a meander cut waterfall (2 km access road from weir site). The
Project Brief does not make it clear that these are both viable
options, and emphasises mainly with the meander cut option. PoE
has previously favoured a weir that can be built and maintained by
local workers. The meander cut is a high risk option and will
undoubtedly be more expensive.
LHDA revisit the
requirements for the ToR
and Project Brief and
rewrite the documents.
The EIA Consultant must
undertake the task of
considering both barrier
options
2011-04-30
11. KLM WATSAN
Resumption of KLM WATSAN has been initiated with a new RFP
for tender to construct the remaining VIPs, disposal pits and water
systems using the same technical drawings that have been used in
previous attempts. The RFP did not provide for use of different
models to increase efficiency and reduce costs in spite of the fact
that there are new toilet technologies that would be suitable for the
Highlands.
LHDA should add an
addendum to the tender
document to enable
inclusion of newer
technologies especially if
they are likely to save
costs on construction
2011-04-15
The new toilet technology available on the market is much simpler
to install, easier and cheaper to maintain and can be moved to a
new location should the household decide to relocate to a new site.
It does not encourage breeding vermin, has less smell and can thus
be located next to the dwelling. See Appendix 11.
The Project managers
should view the
Hydroloo on
www.SABiotech.co.za
2011-03-30
PoE Report 58 – March 2011 – Critical projects Page 27 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
12. Phase 2 issues
ToRs for environmental and
social specialists PoE considered the draft terms of reference. A marked up scan of
the ToRs is provided in Appendix 12. The requirements are
probably too restrictive. Fifteen years on identical projects –
impossible! No two projects are identical. Professionals with at
least 15 years such experience are likely to be scarce, and the pre-
qualifications would exclude able experienced middle-aged
professionals. The expertise and experience of potential appointees
are as important as the ToRs, and it might not be possible to find
suitable candidates. The text of the draft ToR is wordy and should
be trimmed.
Revise the ToRs in the
light of suggested
improvements in
Appendix 12. If suitable
appointees cannot be
found, prepare the
environmental and social
ToRs in-house
2011-04-30
ToRs to conduct an EIA for
construction of measuring
weir and access road at
Polihali
PoE considered the ToRs. A marked-up copy of the documents has
been returned to LHDA with suggestions for improved wording.
Some confusing wording in the document should be revised. Use
of the term “huge experience” in the case of the Environmental
Specialist is not appropriate; how much is “huge”?
Revise the ToRs
according to suggestions
in marked-up hard copy
2011-04-30
The Completed System Prior to the
Construction of the Privacy Enclosure
PoE Report 58 – March 2011 – Compensation Page 28 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 1 Compensation principles and practices in LHWP
The principles for compensation under the Lesotho Highlands Water Project were outlined in
1986 in the LHWP Treaty and the LHDA Order.
These principles were fully incorporated into LHDA‟s 1997 revision of its compensation and
rehabilitation policy (LHDA 1997). The revision was carried out in preparation for Phase 1B
of the Project, the Mohale Dam and associated infrastructure. It was based on then-current
international norms and on LHDA‟s own experience of Phase 1A of the Project – the Katse
Dam, the ‟Muela Dam, and the ‟Muela Hydropower Station and associated infrastructure, and
on the recommendations and experience of the World Commission on Dams and the World
Bank.
One of LHDA‟s legal obligations is to ensure that the LHDA “shall effect all measures to
ensure that members of local communities who will be affected by flooding, construction
works, or other similar Project-related causes, will be able to maintain a standard of living not
inferior to that obtaining at the time of first disturbance” (Kingdom of Lesotho 1986:27).
The LHDA Order of 1986 (Government of Lesotho and Government of South Africa 1986:3)
states that the LHDA shall “ensure that as far as reasonably possible, the standard of living
and the income of persons displaced by the construction of an approved scheme shall not be
reduced from the standard of living and the income existing prior to the displacement of such
persons.”
The compensation package of 1997 consisted of the following.
(1) Replacement of homes and other facilities (e.g. kraals – livestock pens - and latrines).
LHDA built new homes, according to a set of standard designs, at sites chosen by the
families. There was also provision for families to take the cash equivalent and build their own
new homes.
(2) Compensation for loss of arable land. Households moving out of the highlands gave up
their rights to the property and arable land for which they received compensation. They had
the option of choosing annual cash compensation, compensation in the form of grain, or lump
sum compensation for the losses of agricultural fields (calculated on the basis of estimates of
their productivity). Annual payments were to be made for 50 years. It should be noted that the
original compensation policy for Phase 1A had called for payments to be made for a total of
15 years, after which time it was anticipated that the households would have recovered to the
point where they were before first disturbance.
(3) Compensation for communal resources, including grazing, shrubs (used for firewood,
construction, or manufacturing of goods), thatching grass, and medicinal plants. This
compensation came in part in the form of the Rural Development Program (RDP).
(4) Replacement of community assets lost such as schools or churches.
(5) Relocation of graves and the holding of ceremonies at or around the time of re-interment.
(6) Cash payment for garden lands, which are generally are under 400 square meters, and
usually close to households, where fruit and vegetables are grown.
(7) A Disturbance Allowance paid to households for three years after relocation or
resettlement.
(8) In addition, there was to be a Minimum Threshold Payment for each project-affected
household whose minimum income fell below an estimated poverty level of 3,960 Maluti
(M7,558.80 at 2005 rates). It was to be provided in the form of cash as a top-up payment to
PoE Report 58 – March 2011 – Compensation Page 29 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
ensure that each affected household remained above the threshold level, and it was to be paid
annually for 10 years from the time of relocation or resettlement.
Communal compensation in the form cash and the Rural Development Program was provided
for losses of woody vegetation (e.g. thatching grass, fuel wood), fish, medicinal plants, and
other natural resources to project-affected communities. To participate in the RDP people
were required to form co-operatives, grazing associations or other kinds of local legal entities
(LLEs). The co-operatives enabled their members to purchase agricultural inputs and to
market their products, including seed potatoes and maize; the grazing associations were
intended to improve the management of the communal range; grain mills provided a service
where none was previously available; other components included tourism, infrastructure,
fisheries, health, water and sanitation and youth development
While the individual compensation and threshold payments were intended to ensure that
affected families were at least no worse off after than before resettlement, the 'communal
compensation' was meant to bring 'development' and improved standards of living both to the
affected families and to their hosts. It was recognised that dislocation of the Mohale
communities was likely to have particularly adverse consequences for people with little or no
land, for the old and dependent, for sick and disabled people, and even for young people with
no land rights. For them compensation for the loss of assets and of production could be quite
inadequate to prevent their falling into poverty. The provision for compensating the holders
of 'secondary rights' (see 5 above) and the Minimum Threshold Payment were designed to
prevent this. Despite the difficulties of implementing these policies, they were sincere
attempts by the LHDA to avoid harming the weak and the vulnerable.
LHDA, under its development programme, has supported a range of institutions and activities
including co-operatives, range management associations, and agricultural extension services
for the benefit of both the resettlers and their hosts. Co-operatives and LLEs are the
organizations that are legally constituted and which can receive and manage communal
compensation. Co-operatives s are upstream of the dams, or in the resettlement host villages
and receive compensation for communal resources lost by resettlers and “earned” by host
villages who are impacted by the greater population impacts of receiving resettlers. LLEs
receive communal compensation as a function of negative impacts caused by the reduction of
water in the rivers that flow past them. While there are disagreements as to the impacts of
reduction of waters (e.g. on downstream vegetation and fish populations), the first tranche of
compensation was paid to affected communities downstream.
In the Phase 1A project area all such organizations have been formed. There are 23
registered co-operatives in the Katse, Lejone, and Matsoku (“KLM” ) area, which have so far
been paid a total of approximately M 11 million. They have begun 22 businesses, while 13
more are in preparation. Downstream of the dam, 22 LLEs have been formed, which have so
far received M 27 million in compensation. Table 1 shows the numbers of co-ops and LLEs
in the LHWP Phase 1 Area. It can be seen that there are 131 co-ops and LLEs
Table 1 Co-operatives and Local Legal Entities (LLEs) in the LHWP Phase 1 Area
Area Upstream Downstream Total
Phase 1A Katse-Lejone-„Muela 23 22 45
Phase 1B Mohale 54 32 86
77 54 131
PoE Report 58 – March 2011 – Compensation Page 30 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
in the upstream and downstream areas. A total of 77 co-operatives have been planned for the
Phase 1 area (upstream). While some, including the seed potato and maize growing co-
operatives clearly flourished, at least at first, others are harder to assess. Co-operatives in
general have a record of being complicated to implement in Lesotho, and people tend to be
wary of committing their own resources to them. Individuals may enrol as members on a
tentative basis, to see if the co-operative brings any tangible benefits, and if not they leave
after a year or two. The number of co-operatives established therefore gives no assurance that
they will survive or thrive. The Department of Co-operatives of the Ministry of Agriculture is
understaffed and the support it is able to offer new co-operatives and LLEs at the early and
crucial stages of their development is therefore limited. LHDA should encourage the DoC to
hire additional qualified staff to work with IGOs and TAU personnel.
Based on two recently compiled reports (2011), the Katse and Lejone LLEs Audit Action
Report Derived from Latest Audit (January, 2011) and the Report on Status of Embezzlement
of LLE Funds, LLEs Downstream of Katse Dam (February, 2011) it is clear that many of the
co-operatives and LLEs are having difficulties in managing funds, ensuring appropriate
expenditures, record-keeping, and project implementation. Recommendations have been
made in this POE report as to how to address some of these issues, including pursuing legal
action against wrong-doers, enhancing monitoring and auditing of LLE finances,
investigating potential bank overcharges, expanding the training of IGO and TAU personnel
and of LLEs, following up issues with the DoC Legal Section, engaging in preventative
actions to reduce corruption, improved reporting systems, and carrying out new audits
expeditiously. Lack of entrepreneurial skills among LLE members has resulted in some high
operating costs that culminated in substantial losses Getting around these problems will
require greater cooperation among stakeholders in capacity-building and sustainable project
implementation. Efforts must also be made to expand the training of LLE committees in
accounting, financial management, income generating project activities and community
development program work.
As LHDA's resettlement and compensation programme draws to a close, and funding for its
various components, including the RDP, terminates, the question of sustainability becomes
paramount. Without detailed socioeconomic investigations of the co-operatives and LLEs it is
difficult to say how effective they are. It is, however, possible to say that (1) Many of the co-
operatives are engaging in entrepreneurial enterprises. (2) There are at least 16 different kinds
of activities in which co-operatives and LLEs are involved. The returns on the investment
vary considerably, but some of the activities are proving to generate income and enhance
livelihoods in other ways (e.g. reducing labour of women through the availability of hammer
mills to grind maize, sorghum and other goods). Some co-operative members produce and
sell tree seedlings, flowers, vegetables, and fruits. There are also co-operatives that produce
and sell goods such as coffins, face creams, and crafts.
The business plans of the various co-operatives and of the LLEs vary considerably. Some are
very short without much detail. Others are lengthy documents, 20 or more pages, with
detailed costing and rates of return. It appears that the variability is due in part to the
availability of an experienced IGO, Technical Assistance Unit member or DoC representative
who has the time to work with the cooperative or LLE to develop a business plan.
In the past, there was an income generation officer/business plan advisor based in LHDA
who advised communities how to go about doing business planning. The problem was that
PoE Report 58 – March 2011 – Compensation Page 31 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
the advice was complex and the business plan models provided as examples were in many
cases beyond the capacity of rural community members to handle without having some
experience as accountants. In POE Report No. 56, it was recommended that LHDA should
review the current business model to ensure that only approval of lump sums would be based
on bona fide business to avoid later destitution of households. This was done, according to
LHDA, in 2010 to tighten controls, and it was approved for use by all Compensation
Officers. LHDA admits, however, that the revised business model has not stopped lump sum
recipients from using their money carelessly.
The Community Infrastructure and Development Policy (LHDA 2009) was reviewed along
with plans for its implementation. As noted in POE 51, this Policy addresses infrastructure
development in the 44 highlands, foothills, and lowlands villages hosting the Phase 1B
relocated and resettled households. In general, the Community Infrastructure and
Development Policy overall is sound. While there are debates about this issue, the POE feels
strongly that communal compensation funds should go to the affected communities and their
LLEs that are owed this compensation and their host communities and community councils
and not to government, something that has been recommended in some quarters. Instead,
work should be done with all stakeholders, including the communities, government, local
institutions, and traditional authorities, to come up with a way to handle the communal
compensation issues, including disputes, and ways to ensure that the funds are used
effectively, efficiently, and ethically.
The 1995/1996 Phase 1B Resettlement and Development Study, which formed the basis of
the subsequent resettlement and development program, had stressed that participation in the
development program should not be taken as a form of individual compensation for economic
losses sustained on account of the project. Some LHDA officials nevertheless have taken the
view that although some of the affected families seemed to be falling into poverty they would
nevertheless benefit from the development program and would ultimately be better off. If
LHDA is to meet its treaty obligations, then greater efforts must be made to ensure that
individual and communal compensation and development programs are implemented
effectively.
References Cited
Government of Lesotho and Government of South Africa (1986) Treaty on the Lesotho
Highlands Water Project Between the Government of the Kingdom of Lesotho and the
Government of the Republic of South Africa. Maseru, Lesotho: Government of Lesotho and
Pretoria and Cape Town, South Africa: Government of the Republic of South Africa.
Katse Field Operations Branch (2011a) Katse and Lejone LLEs Audit Action Report Derived
from Latest Audit (January, 2011). Katse, Lesotho: Katse FOB.
Katse Field Operations Branch (2011b) Report on Status of Embezzlement of LLE Funds,
LLEs Downstream of Katse Dam (February, 2011). Katse, Lesotho: Katse FOB.
Kingdom of Lesotho (1986) The Lesotho Highlands Development Authority Order 1986.
Maseru, Lesotho: Government of Lesotho.
Lesotho Highlands Development Authority (1997) Compensation and Rehabilitation Policy
(Revised). Maseru, Lesotho: Government of Lesotho.
PoE Report 58 – March 2011 – Compensation Page 32 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Lesotho Highlands Development Authority (2009) Community Infrastructure and
Development Policy. Maseru, Lesotho: Government of Lesotho.
PoE Report 58 – March 2011 – Appendix – Technical notes Page 33 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 5 Technical notes
Grass species suitable for erosion control and rehabilitation
Catalepis gracilis Lesotho kweek. A rhizomatous or stoloniferous short-growing grass
tolerant of grazing and trampling in the Lesotho Highlands. Occupies niché similar to
common kweek Cynodon dactylon. Propagate with runners or sods, otherwise collect seeds.
Chloris gayana Rhodes grass. Tolerant of low rainfall. Low-growing bunch grass with
stoloniferous habit. Not grazing-tolerant. Seed at 5-10 kg per ha. Possibly suitable for
Lesotho Lowlands and Foothills.
Cynodon dactylon Kweek. Low-growing hardy rhizomatous grass. Modest forage value (at
best). Under low soil fertility is patchily established. When soil fertility is raised taller
growing grasses displace it unless the sward is kept short, when kweek is then competitive.
Seed 1-2 kg per ha, or plant runners. Performs poorly in presence of Rhodes and Smuts when
the robust species are properly fertilized and managed. Suitable for Lesotho Lowlands and
Foothills.
Eragrostis curvula Weeping love grass. Medium-sized bunch grass. Hardy and tolerant of a
wide range of conditions. Can survive lower soil fertility than Smuts finger grass, does
respond to fertilization, but forage value is low. Seed at 2-7 kg per ha. Not first choice for
rehabilitation of mining-disturbed land on Eastern Highveld where it is vulnerable to fire
when underdefoliated.
Eragrostis tef Teff. Medium-sized hardy annual bunch grass widely used as a cover or nurse
crop to protect land while slow-to-develop species establish. Seed at 10-12 kg per ha.
Paspalum notatum Bahia grass. A tufted grass with a horizontally creeping rhizome that can
form dense sods thriving where annual rainfall is 800 mm or more. If N fertilizer is applied it
is productive but it can survive low soil fertility. This is a naturalized species in southern
Africa, originating apparently from South America. Its behaviour is supposed to be that of
mid-seral grass, and is liable to be displaced by native climax grasses. Because of the dense
mats of rhizomes it can form it can be used to stabilize erosion prone areas. Suitable for
Lesotho Lowlands and Foothills. It is normally established from seed at a seeding rate of 20-
25 kg/ha.
Pennisetum clandestinum Kikuyu. Under conditions of high fertility is a tough, grazing-
resistant high-production rhizomatous grass offering supreme protection against raindrop
impact and overland flow. There is a seeded variety but is best established by planting
runners or sodding. It is not invasive unless introduced to eutrophic (nutrient rich) situations
such as N and P enriched streambanks.
Phragmites communis Common reed. This „grass‟ grows in damp soil and shallow water up
to 2 m deep. It has robust densely-growing rhizomes. It is suitable for stabilizing permanently
damp or wet gully floors except in the high mountain zone. Propagate by transplanting
rhizomes. Do not confuse with Spanish reed Arundo donax an alien invader with longer
thicker, often slightly curved, stems, and that can grow on dry land.
PoE Report 58 – March 2011 – Appendix – Technical notes Page 34 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Seedbed preparation and fertilization for erosion control and rehabilitation
1. If soil is compacted, reverse compaction by ripping to at least 30 cm.
2. Disk and harrow to break up clods.
3. In soils low in organic carbon apply chicken litter, compost, manure or straw at 5-30
t/ha.
4. Incorporate organic material (mulch) into top 10 cm of soil.
5. In absence of laboratory soil fertility analysis, default fertilizer application is P at 20
kg/ha and N at 50 kg/ha, applied at time of grass seeding.
6. Do not apply mulch or inorganic fertilizer to wetlands.
7. Roll with Cambridge roller or, if small area, pat down with spade.
8. Apply grass seed, or plant the rhizomes or runners.
9. Roll again.
10. Through the summer months (October-March) when grass comes into flower slash,
remove cuttings and topdress with N at 50 kg/ha. Never N-topdress grown out grass.
Never N-todpress in winter (April-September).
Control of woody alien invader plants
1. Trees or shrubs taller than 1.5 m should be felled close to ground level, and basal stem
treatment applied (immediately after felling apply a systemic herbicide to cut stump).
2. Saplings up to 1.5 m can be sprayed with a systemic herbicide.
3. Seedlings can often be hand-pulled or also sprayed with a systemic herbicide.
4. There are numerous suitable herbicides available from agricultural suppliers,
hardware stores, garden shops (eg Chopper, Garlon).
5. Always follow the manufacturer‟s instructions on use and precautions.
6. Avoid using products that are highly toxic and require extreme precautions.
7. Instruct and supervise use.
8. Obtain Material Safety Data Sheets (MSDS) and hold on site. An example of MSDS
for Chopper is appended below.
PoE Report 58 – March 2011 – Appendix – Technical notes Page 35 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Business Center
South Africa &
Sub-Sahara
Safety Data Sheet Page: 1/ 5
BASF Safety data sheet according to 91/155/EEC
Date / Revised: 24.11.2004 Version: 1.3
Product: CHOPPER 693 09 H
(30145550/SDS_CPA_EU/EN)
Date of print 25.11.2004
1. Substance/preparation and company identification
CHOPPER
Company: BASF Aktiengesellschaft
Unternehmensbereich Pflanzenschutz
67056 Ludwigshafen, Deutschland Telephone: +49-621-60-79321/ 79145
Telefax number: +49-621-60-79519
E-mail address: [email protected]
Emergency information:
Fire brigade BASF Ludwigshafen Telephone: +49-621-60-43333
Telefax number: +49-621-60-92664
2. Composition/information on ingredients Chemical nature crop protection product, herbicide, water-soluble concentrate (SL)
Preparation based on: IMAZAPYR ISOPROPYLAMIN
Hazardous ingredients
imazapyr Content (W/W): 9.4 %
CAS Number: 81334-34-1
Hazard symbol(s): Xi, N R-phrase(s): 41, 50/53
Nonylphenol ethoxylate Content (W/W): 8.5 %
CAS Number: 68412-54-4
Hazard symbol(s): Xn, N R-phrase(s): 22, 41, 51/53
The wording of the hazard symbols and R-phrases is specified in chapter 16 if dangerous ingredients are mentioned.
3. Hazard identification Irritating to eyes.
Toxic to aquatic organisms, may cause long-term adverse effects in the aquatic environment.
4. First-aid measures
General advice: Avoid contact with the skin, eyes and clothing. Remove contaminated clothing.
if difficulties occur: Obtain medical attention.
Show container, label and/or safety data sheet to physician.
If inhaled: Keep patient calm, remove to fresh air, seek medical attention.
On skin contact: After contact with skin, wash immediately with plenty of water and soap.
If irritation develops, seek medical attention.
In case of Emergency 082 900 8440 /
0800172743. BASF SA – 011 203 2400
PoE Report 58 – March 2011 – Appendix – Technical notes Page 36 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
On contact with eyes: Immediately wash affected eyes for at least 15 minutes under running water with eyelids held open, consult an
eye specialist.
On ingestion: Rinse mouth immediately and then drink plenty of water, seek medical attention.
Do not induce vomiting unless told to by a poison control center or doctor. Never induce vomiting or give anything by mouth if the victim is unconscious or having convulsions.
Page: 2 / 5
BASF Safety data sheet according to 91/155/EEC Date / Revised: 24.11.2004 Version: 1.3
Product: CHOPPER 693 09 H
(30145550/SDS_CPA_EU/EN)
Date of print 25.11.2004
Note to physician:
Treatment: Treat according to symptoms (decontamination, vital functions), no known specific antidote.
5. Fire-fighting measures Suitable extinguishing media: water spray, water fog, carbon dioxide, foam, dry extinguishing media
Specific hazards: carbon monoxide, nitrogen oxides The substances/groups of substances mentioned can be released in case of fire.
Special protective equipment: Wear self-contained breathing apparatus and chemical-protective clothing.
Further information:
In case of fire and/or explosion do not breathe fumes. Keep containers cool by spraying with water if exposed to fire.
Collect contaminated extinguishing water separately, do not allow to reach sewage or effluent systems.
Dispose of fire debris and contaminated extinguishing water in accordance with official regulations.
6. Accidental release measures
Personal precautions: Use personal protective clothing.
Avoid contact with the skin, eyes and clothing. Remove contaminated clothes, undergarments and shoes immediately.
Environmental precautions: Do not discharge into the subsoil/soil. Do not discharge into drains/surface waters/groundwater.
Methods for cleaning up or taking up: For small amounts: Pick up with suitable absorbent material (e.g. sand, sawdust, general-purpose binder,
kieselguhr).
For large amounts: Dike spillage. Pump off product.
Collect waste in suitable containers, which can be labeled and sealed.
Clean contaminated floors and objects thoroughly with water and detergents, observing environmental regulations. Incinerate or take to a special waste disposal site in accordance with local authority regulations.
7. Handling and storage
Handling No special measures necessary if stored and handled correctly.
Protection against fire and explosion: No special precautions necessary. The substance/product is non-combustible.
Product is not explosive.
Storage
Segregate from foods and animal feeds.
Segregate from oxidants.
Further information on storage conditions: Keep away from heat.
Protect from direct sunlight.
Storage stability:
Storage duration: 24 Months Protect from temperatures above: 40 °C
Changes in the properties of the product may occur if substance/product is stored above indicated temperature for extended periods of time.
PoE Report 58 – March 2011 – Appendix – Technical notes Page 37 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
8. Exposure controls and personal protection
Personal protective equipment
Respiratory protection: Respiratory protection not required.
Hand protection: Suitable chemical resistant safety gloves (EN 374) also with prolonged, direct contact
(Recommended: Protective index 6, corresponding > 480 minutes of permeation time according to EN
374): E.g. nitrile rubber (0.4 mm), chloroprene rubber (0.5 mm), polyvinylchloride (0.7 mm) and other
Eye protection: Tightly fitting safety goggles (splash goggles) (EN 166)
Body protection: Body protection must be chosen depending on activity and possible exposure, e.g. apron, protecting boots,
chemical- protection suit (according to DIN-EN 465).
Page: 3 / 5
BASF Safety data sheet according to 91/155/EEC
Date / Revised: 24.11.2004 Version: 1.3
Product: CHOPPER 693 09 H
(30145550/SDS_CPA_EU/EN)
Date of print 25.11.2004
General safety and hygiene measures: The statements on personal protective equipment in the instructions for use apply when handling crop-protection agents in final-
consumer packing. Avoid contact with the skin, eyes and clothing.
Wearing of closed work clothing is recommended. Take off immediately all contaminated clothing.
Store work clothing separately.
Keep away from food, drink and animal feeding stuffs. No eating, drinking, smoking or tobacco use at the place of work.
Hands and/or face should be washed before breaks and at the end of the shift.
9. Physical and chemical properties
Form: liquid
Colour: dark red
Density: approx. 1.06 g/cm3 (20 °C)
Solubility in water: soluble
10. Stability and reactivity
Thermal decomposition: No decomposition if stored and handled as prescribed/indicated.
Substances to avoid: oxidizing agent
Hazardous reactions: No hazardous reactions if stored and handled as prescribed/indicated.
Hazardous decomposition products: No hazardous decomposition products if stored and handled as prescribed/indicated.
11. Toxicological information LD50/oral/rat: > 5,000 mg/kg
Information on: imazapyr LC50/by inhalation/rat: > 1.3 mg/l / 4 h
---------------------------------- LD50/dermal/rat: > 2,000 mg/kg
Primary skin irritation/rabbit: non-irritant
Primary irritations of the mucous membrane/rabbit: Severely irritating. Sensitization/guinea pig: Skin sensitizing effects were not observed in animal studies.
Additional information: The product has not been tested. The statement has been derived from products of a similar structure and composition.
Misuse can be harmful to health.
12. Ecological information Ecotoxicity
Information on: imazapyr
PoE Report 58 – March 2011 – Appendix – Technical notes Page 38 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Toxicity to fish: Oncorhynchus mykiss/LC50 (96 h): > 100 mg/l ----------------------------------
Information on: imazapyr Aquatic invertebrates: Daphnia magna/EC50 (48 h): > 100 mg/l ----------------------------------
Information on: imazapyr Aquatic plants: Selenastrum capricornutum/EC50: 71 mg/l Anabaena flos-aquae/EC50: 11.7 mg/l Lemna gibba/EC50: 0.024 mg/l
----------------------------------
Persistence and degradability Elimination information
Evaluation: Not readily biodegradable (by OECD criteria).
Additional information Other ecotoxicological advice: The ecological data given are those of the active ingredient.
Do not discharge product into the environment without control.
13. Disposal considerations
Must be dumped or incinerated in accordance with local regulations.
Contaminated packaging:
Contaminated packaging should be emptied as far as possible and disposed of in the same manner as the substance/product.
Page: 4/ 5
BASF Safety data sheet according to 91/155/EEC Date / Revised: 24.11.2004 Version: 1.3
Product: CHOPPER 693 09 H
(30145550/SDS_CPA_EU/EN)
Date of print 25.11.2004
14. Transport information Land transport
ADR : Class 9
Packaging group III
UN-number 3082 Designation of goods ENVIRONMENTALLY HAZARDOUS SUBSTANCE, LIQUID, N.O.S.
(Contains: IMAZAPYR 9%, NONYLPHENOLETHOXYLATE 9%)
RID : Class 9
Packaging group III
UN-number 3082 Designation of goods ENVIRONMENTALLY HAZARDOUS SUBSTANCE, LIQUID, N.O.S.
(Contains: IMAZAPYR 9%, NONYLPHENOLETHOXYLATE 9%)
Inland waterway transport
ADNR : Class 9
Packaging group III
UN-number 3082 Designation of goods ENVIRONMENTALLY HAZARDOUS SUBSTANCE, LIQUID, N.O.S.
(Contains: IMAZAPYR 9%, NONYLPHENOLETHOXYLATE 9%)
Sea transport IMDG/GGVSee : Class 9
Packaging group III
UN-number 3082 Marine pollutant YES
Exact technical name ENVIRONMENTALLY HAZARDOUS SUBSTANCE, LIQUID, N.O.S.
(contains IMAZAPYR 9%, NONYLPHENOLETHOXYLATE 9%)
Air transport ICAO/IATA : Class 9
Packaging group III
UN-number 3082 Exact technical name ENVIRONMENTALLY HAZARDOUS SUBSTANCE, LIQUID, N.O.S.
(contains IMAZAPYR 9%, NONYLPHENOLETHOXYLATE 9%)
15. Regulatory information Regulations of the European union (Labelling) / National legislation/Regulations
EEC Directives: Hazard symbol(s)
PoE Report 58 – March 2011 – Appendix – Technical notes Page 39 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Xi Irritant.
N Dangerous for the environment.
R-phrase(s)
R36 Irritating to eyes. R51/53 Toxic to aquatic organisms, may cause long-term adverse effects in the aquatic environment.
S-phrase(s) S2 Keep out of the reach of children.
S13 Keep away from food, drink and animal feeding stuffs.
S20/21 When using do not eat, drink or smoke. S26 In case of contact with eyes, rinse immediately with plenty of water and seek medical advice.
S35 This material and its container must be disposed of in a safe way.
S46 If swallowed, seek medical advice immediately and show this container or label. S57 Use appropriate container to avoid environmental contamination.
Hazard determinant component(s) for labelling: IMAZAPYR
Other regulations For the user of this plant-protective product applies: 'To avoid risks to man and the environment, comply with the instructions for
use.' (Directive 1999/45/EC, Article 10, No. 1.2)
16. Other information
Full text of hazard symbols and R-phrases if mentioned as hazardous components in chapter 2:
Xi Irritant.
N Dangerous for the environment.
Xn Harmful. 41 Risk of serious damage to eyes.
Page: 5 / 5
BASF Safety data sheet according to 91/155/EEC
Date / Revised: 24.11.2004 Version: 1.3 Product: CHOPPER
693 09 H
(30145550/SDS_CPA_EU/EN)
Date of print 25.11.2004
50/53 Very toxic to aquatic organisms, may cause long-term adverse effects in the aquatic environment. 22 Harmful if swallowed.
51/53 Toxic to aquatic organisms, may cause long-term adverse effects in the aquatic environment.
Vertical lines in the left hand margin indicate an amendment from the previous version. The information contained herein is based on the present state of our knowledge and does not therefore guarantee certain properties.
Recipients of our product must take responsibility for observing existing laws and regulations.
PoE Report 58 – March 2011 – Appendix – Decision rules Page 40 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 6a The decision rules
The following is extracted from PoE Report 41 of April 2005 and represents an agreement
between LHDA, The World Bank, the IFR Consultant and PoE on how 2nd
tranche payment
of compensation to downstream communities is to be decided.
Decision rules regarding 2
nd tranche of compensation for proximal reaches
(a) assume that changes in resource amount are flow-related unless there is contrary evidence
(b) if woody vegetation resources increase or decline <10% then no 2nd
tranche compensation
payable
(c) if woody vegetation resources decline 10<25% then compensation is payable for wood
losses as per Metsi reports and IFR Procedures
(d) if woody vegetation resources decline by >25% then determine in a cost-effective but
defensible manner a revised compensation amount
(e) apply the above decision rules on woody vegetation to fish
(f) if compensation is due on wood resources and/or fish then include compensation for other
resources (ie forage, medicinal plants and wild vegetables) at the appropriate level (at level
under (d) above if wood or fish resources declined by >25%, otherwise at level under (c)
above)
Approach distal reaches as follows
(g) Accept that even though change in resources might be detected by monitoring, it probably
will not be possible to establish on balance of evidence that the change is flow-related &
caused by LHWP
(h) Monitor woody vegetation resources to determine change to fall into one or other of
following classes
Class A – Increase or decline <10%
Class B – Decrease 10<25%
Class C – Decrease >25%
(i) If change falls in Class A then no compensation is warranted
(j) If change falls in Class B then intervention (viz community compensation or development)
is warranted at the level indicated in Metsi reports
(k) If change falls in Class C then enhanced intervention (viz community compensation or
development) is warranted at a higher level than indicated in Metsi reports – a level that
must be determined on the basis of the percentage decline in resources
(l) If (j) or (k) arise the intervention is a decision that probably cannot be substantiated on
„proven‟ LHWP flow-related (see (g) above) but can and should be defended on the
developmental & economic principle that government decisions should always be biased
towards the interests of the poor (eg downstream communities)
(m) Proceed with (l) unless there is irrefutable evidence that resource loss was not LHWP flow-
related
(n) The above approach to wood resources must be applied to fish resources as well
(o) The most severe loss determined for wood and fish resources should be deemed to apply to
the other resources (ie forage, medicinal plants and wild vegetables) and the intervention or
enhanced intervention decided and defended as described above under (j), (k) and (l)
PoE Report 58 – March 2011 – Appendix – IFR monitoring Page 41 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 6b ToR framework for short-term IFR monitoring
1. The purpose of the assignment is to make an independent assessment of IFR
monitoring evidence against the decision rules regarding the payment, or withholding
of payment, of compensation to riparian communities downstream of LHWP Phase 1a
structures.
2. As set out in the decision rules, the issues of concern are riparian vegetation and fish
only.
3. Divide the assessment into proximal reaches (IFR reaches 1,2 & 3) and distal reaches
(IFR reaches 4, 5 & 6).
4. The historical evidence to be used must include IFR monitoring reports, PoE reports
and photographs, but other evidence can be used as may be relevant.
5. Collect further evidence as follows.
Woody vegetation
6. Source pre-construction and post-construction photographs, air photos and/or satellite
images of the relevant reaches on the Matsoku, Malibamatso and Senqunyane Rivers,
as well as the Senqu upstream of the its confluence with the Malibamatso. The Senqu
is included as a control – it is still pre-construction.
7. Make visual assessment of the amount of riparian woody vegetation pre- versus post-
construction. Quantify/semi-quantify the visual assessment with crude methods such
as placing grid over riparian zone and counting squares with and without visible
woody vegetation, or even just length of river bank without or without apparent
woody vegetation.
8. Supplement the desk-top visual assessment with a simple field assessment along the
following lines.
Locate ~15 random sample sites on each IFR Reach. Use Google Earth – measure
distance along the Reach (ie develop chainage), and use random number generator to
identify random starting points for the sampling sites. Record the GPS coordinates for
each starting point.
Go to starting point. Measure 5 m from water‟s edge under base flow conditions.
Adopt the point-centre-quarter method (PCQ).
In each quarter identify the species of woody plant within 5 m and taller than breast
height. Record presence of a woody plant within 5 m as 1, and absence as 0.
Walk 20 m, parallel to and 5 m from water‟s edge, and repeat the PCQ recording.
Observe 8 PCQ points for one sample site (ie 4x8 = 32 observations per sample site).
Assess one Reach as a pilot trial. Calculate mean and variance and assess the
sensitivity (power) of the sampling technique. Adjust the sampling technique as might
be appropriate (eg apply stratified random sampling design if data are very variable,
or increase sample numbers, or increase PCQ points per sample). The ideal is to have
the technique capable of demonstrating a 10% change in woody vegetation.
PoE Report 58 – March 2011 – Appendix – IFR monitoring Page 42 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Apply the technique to all IFR Reaches. The technique should require one observer to
perform the PCQ, and a driver to deliver the observer at the beginning of the day, and
fetch her/him at the end of the day. If the team is bigger the job can be done faster.
9. Analyse, interpret and write up results. Relate the visual appearances obtained in the
desk-study with the data obtained in the field exercise.
Fish
10. Adopt the fish sampling method applied in current IFR monitoring. As a pilot trial,
take 3 replicate samples in one Reach. (An important property of replicate samples is
that they are independent. Sampling the same site repeatedly over a period of days or
weeks might not meet the criterion of independence – destructive sampling, fish
become sensitized and take evasive action, etc. Simple random sampling within a
Reach might give very variable results, and this variability might be reduced by
applying stratified random sampling – viz sample riffle sections only.)
11. Using the data from the pilot trial, determine the level of sampling required to
demonstrate a 10% in the fish population. Focus on a simple measure of fish
abundance, such as catch per unit effort, or catch per fixed sampling effort. Consider
the merits of measuring „catch‟ in fish numbers or biomass. Review how realistic it is
to apply such sampling. Decide on the most realistic intensity of sampling.
12. Apply the developing fish sampling technique to all Reaches.
13. Analyse, interpret and write up the results.
PoE Report 58 – March 2011 – Appendix – Strategic plan Page 43 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 9 LHDA Strategic Plan
A Strategic Plan is supposed to identify factors that have contributed to the observed
successes or failures and use this information to determine a path of least resistance for the
betterment of an organization to enable it to carry out its mission and achieve its vision in the
long term. The processes that are often undertaken include a through environmental analysis
by operatives at all levels and the synthesis of this information into a strength, limitations,
opportunities and threats analysis upon which decisions as to what should be done is
undertaken.
In order to be objective, a strategic plan requires that analysis is carried out at all levels
including management systems and culture of the organization. The management systems and
culture of the organization are key factors in determining how and how fast an organization
can respond to changes in the operational environment as well as to emerging issues.
It is important that LHDA undertakes this exercise to identify management policies and
practices hindering the ability of the organization to translate its strategic imperatives into
actions at operational and management levels.
PoE suggests that this process needs to be undertaken in a joint exercise where LHWC,
LHDA Board and LHDA participate as equal participants each able to analyse its role in the
implementation of the strategic plans and at the same time appreciating the roles and
responsibilities of the other institution. This is possible if an experienced facilitator is
engaged to ensure that an objective analysis of the internal environment is carried out without
fear of recriminations from higher authorities that would be subjected to this scrutiny.
PoE Report 58 – March 2011 – Appendix – IFR monitoring Page 44 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 10 Senqunyane Access Investigation Trip
KINGDOM OF LESOTHO LESOTHO HIGHLANDS WATER PROJECT SENQUNYANE ACCESS INVESTIGATION TRIP – MALOTI MINNOW
prepared by L. MATETE, JULY 2007
BACKGROUND
Following the helicopter trip on the 2nd
May 2007, it was observed that access to the two
identified areas (Ha Ts‟oeute & Nteso) for the proposed construction of fish barriers was a
problem. The intension to fly to the two proposed sites was for the team to be familiar
themselves with the terrain and to closely look at the suitability of constructing the two types
of barriers previously considered under.
DESCRIPTION OF THE IDENTIFIED SITES:
Ha Ts’oeute
This site is situated just upstream of Mohale Dam tail pond in the Senqunyane River valley.
At Mohale Reservoir full supply level, the tail water extends to the site. Careful consideration
should be taken if this site is considered, as the pool, if formed, will provide a suitable resting
habitat for predatory fish species that will attempt to overcome the barrier.
The observation made during 2
nd May 2007 trip was that the Ts‟oeute barrier, when constructed
would have a cross-section of 50m, 5m long and about 14m, 2m high. It is envisaged that the most
appropriate design for the weir would be a rock fill type structure, a permeable structure that allow
constant seep-through of water. The structure would need to have a spillway at the central point. This
is intended to channel water to the central point during floods, thus increase velocity so as to limit the
fish to leap over the structures.
Ha Nteso
This site is situated on northwest side of Ha Nteso village, which is further upstream of the Ha
Ts‟oeute site along the Senqunyane River valley. The choice of this site was used as a base to test a
natural approach to establishing an artificial barrier that will imitate the natural waterfall in ecological
and geological longevity as practicably possible. The approach to this is to artificially induce a cut-off
meander to simulate examples observed elsewhere.
PoE Report 58 – March 2011 – Appendix – IFR monitoring Page 45 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
When Nteso barrier is constructed it will result in a drop in height over the length of the cut-off
section forming the waterfall, therefore forming a natural barrier. Nteso waterfall is expected to form
a vertical drop of about 12 to 14 metres high at the outlet and the tunnel cut-off of about 250m to
300m length.
ACCESS ROUTE INSPECTION
The possible access route to the proposed barriers construction sites at Ha Ts‟oeute and Ha
Nteso is through the village of Ha Sekolopata. Ha Sekolopata is on the left bank of the
Senqunyane River Valley and is the last village serviced by feeder roads network around the
Mohale Dam catchment.
PHOTO: 1 Sekolopata Village – Beginning of Formation Access Route
Further going upstream along the Senqunyane River valley towards the proposed Ts‟oeute
barrier site is the formation access route, which was used as the only access during
implementation of WATSON Project. The route was only accessible by 4x4 vehicles for
transportation of building materials and could not be used by heavy vehicles or plant.
During our inspection of the route it was clear that the existing road was last used during the
construction of water and sanitation facilities. Due to very steep terrain from Ha Sekolopata
to the bottom Valley of Senqunyane River, most of the fill material has been washed down
the slopes leaving exposed hard basalt rock. Most of the areas with exposed basalt rock are
on the ridges and that would make driving over them impossible, otherwise the areas will be
very expensive to work on. It was observed that most of the ridges are followed by very steep
slopes of about 1:1 (45o angle) that are almost impossible to manoeuvre with the 4x4
vehicles.
PHOTO 2: Steep Slopes over Ridges without Top Soil
PoE Report 58 – March 2011 – Appendix – IFR monitoring Page 46 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Walking down from the village to the bottom of the valley there are a lot of exposed basalt
ridges that will require blasting to achieve an acceptable road formation. The other areas with
steep slopes, the formation line will have to be rerouted to allow heavy vehicles to make up
the steep slopes.
A few flat areas of the route were observed to have a lot of very clayish material, which
seemed very soft and slippery when wet, especially towards the bottom of the valley.
PHOTO : 3 Areas with Clayish and Soft Top Soil Cover
There were no tests carried out on these flat areas to check the depth of the top soil cover but
the basalt outcrops were spotted nearby within the 10m range. During the formation level
preparation at these flat areas, efforts will have to be made to ensure stability especially for
heavy vehicles drive-over.
The Senqunyane River Valley bottom is the only area along the route to the proposed
Ts‟oeute site that have easy access and that will require less effort in preparing the road
formation. Even though this area is easy to prepare the road formation level, it might require
care when driving over, especially with heavy plant or loaded trucks, as might have soft
underground spots due to alluvium deposits.
PHOTO 4: Few Flat Areas at the Valley Bottom
PoE Report 58 – March 2011 – Appendix – IFR monitoring Page 47 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Walking upstream towards Ha Ts'oeute barrier site for about 1.0km, there are a lot of
alluvium deposits and this could be due the shallow riverbed slope and tail water stand during
the reservoir full supply level. This alluvium deposit will be a big challenge if the barrier is to
be constructed during high floods.
Ha Nteso barrier site is about 2km away from Ha Ts‟oeute barrier site and accessibility by
vehicle is impossible. The terrain is very steep and composed of mainly hard basalt rock.
From Ha Ts‟oeute to Ha Nteso, there is no road formation and a new road for about 2km
would require to be developed using intensive drilling and blasting of hard basalt rock.
PHOTO 5: Alluvium Deposit along Senqunyane River Valley
CONCLUSIONS
The 0.4km of the access route connecting the Feeder Road dead-end and Ha
Sekolopata Village will have to be rerouted due to very steep slopes, therefore
require use of heavy plant at some areas for road formation cut and fill.
Within the village of Ha Sekolopata, road formation (about 0.2km) can be
done through engagement of labour force since the ground is soft.
After the first ridge from the village, the existing route follows a very steep
decline for about 4km to the bottom of the valley and it will have to be
rerouted to cut the slopes. Most of the area will require blasting to cut off the
road formation.
The existing route at the valley bottom for about 2km follows the riverbed
contour all the way to the Ts'oeute barrier site and labour force can be engaged
for construction of road formation.
PoE Report 58 – March 2011 – Appendix – IFR monitoring Page 48 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Quarry sites for rock fill materials to be used for barrier construction will have
to be investigated before access to the quarries is determined.
RECOMMENDATIONS
It is recommended that the upgrading of the existing route to the Fish Barrier sites at Ha
Ts'oeute and Ha Nteso be evaluated since its construction cost could be very high. It is also
recommended that labour force should be utilised as much as possible to cut down the cost
and heavy plant be used only on areas difficult to use labour force.
PoE Report 58 – March 2011 – Appendix – KLM WATSAN Page 49 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 11 KLM WATSAN
The suggested use of new toilet technology is based on the need to reduce construction costs
in terms of time by using prefabricated materials that are durable and long lasting. The
construction of the Hydroloo takes about two to three hours and the basic unit costs less than
R3 500 and the enclosure not more than R3 500 and can be completed in less than a day.
THE HYBRID TOILET SYSTEM INSTALLATION
The System is Filled only once at
installation with Water from any source
prior to backfilling of the tank pit
THE HYBRID TOILET SYSTEM INSTALLATION
Installation is Easily
Accomplished by Manual
Labour
Stand alone unit with ventilation pipe
Can be installed anywhere
including next to an already
existing dwelling as it has no
smell and does not attract flies
PoE Report 58 – March 2011 – Appendix – Environmental & Social Specialists Page 50 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Appendix 12 ToRs for environmental and social specialists
are as follows.
Draw up ToRs and obtain approval from [insert]
Review and advise on ToRs
Assist
Assist
Biophysical resources
Socio-economics (livelihoods)
Public health
Register of individual and communal assets
Assist
Probably too restrictive. Try 10 yrs
PoE Report 58 – March 2011 – Appendix – Environmental & Social Specialists Page 51 of 51
Prepared by Prof Hitchcock & Drs Inambao, Ledger & Mentis Revision 1
Assist
Participate
Liaise
Participate
Monitor
Assist
Establish
No! All facets of Phase 2 have environmental/social consequences
similar to
similar to
LHWP
Probably too
restrictive. Try 10 yrs
three