Lecture 3_23Apr SW0[1]
Transcript of Lecture 3_23Apr SW0[1]
-
7/23/2019 Lecture 3_23Apr SW0[1]
1/46
Slide 1
PIPELINES AND SOIL MECHANICS
Pipeline Ancillary Equipment
Presented by: Scott Wright PhD BEng (Hons) [email protected]
-
7/23/2019 Lecture 3_23Apr SW0[1]
2/46
Slide 2
Q: What is pipeline ancillary equipment?
A: Components of the pipeline system other than the physical pipeline.
The list of components is wide ranging but we will take a look at:
Flanges, end fittings and connectors
Bulkheads
Coatings
Insulation
Anodes
Protection
Manifolds
Valves
Flow meters
Controls equipment
Tie-in spools
PIPELINE ANCILLARY EQUIPMENT
When asked to do this lecture I wasnt sure what we should be looking at for pipeline
ancillary equipment.
In the end I decided that it should be all components of the pipeline system other than simply
the physical pipe. In reality there is a wide range of components that make up the pipeline
system, each of which performs an important role. We will take a look at the most significant
of these components, including:
Flanges, end fittings and connectors.
Bulkheads.
Coatings.
Insulation.
Anodes.
Protection.
Manifolds.
- Valves.
- Flow meters.
- Controls equipment.
Tie-in spools.
-
7/23/2019 Lecture 3_23Apr SW0[1]
3/46
Slide 3
FLANGES
Flanges provide a pressure containing connection between two parts of the pipeline
system.
Flanges are traditionally made by hand either onshore or by diver on the seabed.
Principally 2 types of flanges:
API
ANSI / ASME
Flanges provide a pressure containing connection between two parts of the pipeline system.
Flanges are normally made by hand either onshore or by diver on the seabed.
Principally 2 types of flanges:
API - provides face to face seal between the flange faces.
ANSI / ASME Flange faces are separated and interface is provided through the
gasket.
In general, API flanges are smaller than ANSI flanges.
-
7/23/2019 Lecture 3_23Apr SW0[1]
4/46
Slide 4
FLANGE ASSEMBLY
Weld Neck to Weld Neck Connection Weld Neck to Swivel Ring Connection
Weld Neck StudboltsGasket
Weld Neck
Swivel Ring
Subsea flange connections are normally made using weld neck to weld neck flanges or, where
the flange connection needs to be made-up Subsea, using weld neck to swivel ring flanges.
Weld neck flanges consist of a single component comprising a flange with a tapered hub
section to which the pipe is welded.
Swivel ring flanges are made up of two components, an inner part and a outer swivel ring.
The inner part is similar to weld neck flange and is welded to the pipe at the rear of the
tapered hub. The swivel ring freely rotates around the hub for easy alignment of bolt holes
during make up. The flange is bolted together through the swivel ring which bears on the
inner hub.
Between the flanges there is a metal gasket which provides the pressure retaining seal.
-
7/23/2019 Lecture 3_23Apr SW0[1]
5/46
Slide 5
SMALL FLANGE ALTERNATIVES
Compact Flanges SPO, Destec
Hub Clamp Connectors Grayloc, Techlok
Often size and weight is of particular concern in subsea design. There are a number of
alternatives to the traditional ANSI and API flanges, the most common being:
Compact flanges, such as the vector SPO flange and the Destec Compact flange.
Hub connectors, such as the vector Techlok and the Grayloc connectors.
Compact flanges are a smaller and lighter proven alternative to conventional ANSI or API
flanges. Compact flanges are increasingly used in the subsea industry because of their
smaller sizes, lower weight and guaranteed seal integrity.
Hub connectors again provide significant size and weight savings. They also provide reduced
bolting requirements and therefore reduce the time required to make the connection. They are
often the preferred solution where space, weight and joint integrity are critical and can often
be found on flexible riser systems.
-
7/23/2019 Lecture 3_23Apr SW0[1]
6/46
Slide 6
FLANGE RATING
Flanges, indeed many pipeline and piping components, are c lassified by pressure
rating.
425.4
2,500
255.4153.110268.25119.6ANSI Pressure @ LowTemperature (bar)
1,500900600400300150ANSI Class
32
164
G
M
G
FPP deff
++=
G = Mean Gasket Diameter
Pd = System Design Pressure
F = Tensile Load
M = Bending Moment
Peff = Equivalent Flange Pressure Loading
Kellogs Equation
20,00015,00010,0005,0003,0002,000API Pressure (psi)
Flanges are classified by pressure rating. If the flange was subject to no other loads it would
be capable of retaining this pressure. However, tensile loading and bending moments acts to
open the flange pair and this reduced the pressure it can withhold.
The Kellogs equation can be used as a first pass to assess flange loading. In this equation the
flanges pressure capacity is apportioned into pressure, tensile and bending moment capacity.
Detailed flange capacity calculations can be performed using the method in ASME VIII and
PD5500. Alternatively finite element analysis can be performed with linearised stress checks
in accordance API 6A or PD5500.
-
7/23/2019 Lecture 3_23Apr SW0[1]
7/46
Slide 7
MECHANICAL CONNECTORS
Mechanical connectors are typically used in flanged-spool repair applications.
They can be fitted to pipe ends to provide a flange connection.
They are proprietary equipment and as a result are more expensive than a traditional welded
flange solution.
The pipe end needs to be cleaned and prepared to the connector manufacturers requirements.
The connector is then slid over the pipe end and tightened. The action of tightening the
connector activates the gripping and sealing mechanism.
-
7/23/2019 Lecture 3_23Apr SW0[1]
8/46
Slide 8
MERLIN CONNECTOR
There are some advanced connectors out there like the Merlin connector. Either side of the
connector is welded to the pipe ends. The pipe ends are then brought together. The annulus of
the connector is pressurised and the two components are displaced together. The annulus is
then depressurised and the connection is complete.
It provides a connection with a high integrity metal to metal seal.
-
7/23/2019 Lecture 3_23Apr SW0[1]
9/46
Slide 9
DIVERLESS CONNECTORS - When is Diverless Technology Required?
Requirement Set by either
Water depth
Safety
Local Legislation
Existing kit
Implication of Water Depth
Increase in Hydrostatic pressure with depth.
Toxicity and impact of respiratory gases under pressure on human tissue.
Fatigue, insomnia, memory loss occur as depth increases >> 300m
Time to decompress increases
e.g. For a dive to 530m, takes 8 day to compress, 18 Day to decompress
Before delving into diverless system requirements, it is worth considering why we would
adopt a diverless system strategy.
In general pipelay can be conducted in a variety of water depths up to 2000m without divers
being required. The primary area that require diver intervention is for the make up of
connections on tie-in spools or for maintenance (intervention) when something needs to be
changed out.
1. Water depth poses a natural limit set by human physiology. Typically saturation divers can
operate safety to about 300m (1000ft). With increasing depth, the gases and in particular
oxygen (in air diving) can become toxic which necessitates differing respiratory gas
combinations depending on depth. At deeper depths, experience has shown that fatigue,
insomnia and memory loss can occur, although divers have achieved 530m in water and over
700m in dry decompression chambers. An additional consideration is the time for
decompression which is limited to approximately 15 meters per day, and this controls the time
required for decompression.
2. A second consideration is safety. Intuitively, placing a diver in the water poses a risk.
Adopting an alternative diverless technique has to be fundamentally safer, although this will
incur a cost delta which may be significant
3. There may be local legislative requirement for the work to be done diverless. This is the
preference in Norway where divers are used only as a last resort for safety reasons.
-
7/23/2019 Lecture 3_23Apr SW0[1]
10/46
This can cause some interesting cases where projects straddle the UK-Norway boundary
where the portion in UK waters has been diver assisted and that in Norwegian waters is
diverless.
4. Finally, if tie-in into existing subsea kit there may be little option but to adopt a similar
philosophy.
-
7/23/2019 Lecture 3_23Apr SW0[1]
11/46
Slide 10
DIVERLESS CONNECTORS - When is Diverless Technology Required?
Diving Options
Air Diving: Breathing gas : Normal atmospheric mixture of oxygen and Nitrogen
Limited to a depth of about 58m (190 ft)
More commonly being used for
-
7/23/2019 Lecture 3_23Apr SW0[1]
12/46
Slide 11
DIVERLESS CONNECTORS
Many different Diverless Connection system on Market
Fundamentals of each are similar, but differ locall y in design Vetco (GE) : Icarus, HCCS or VCCS system
Cameron : CVC or CHC system Kvaerner : RTS and BBRTS system FMC : FLYCON, ROVCON, UTIS system
Diverless Lacks benefit of diver dexterity: Bolted clamp no longer possible
=> Adopt either a clamp or collettype solution Clamp must be deployable by ROV
Dedicated structure to enable primary location => An alignment structure is required with guide posts
Method of pulling in either connection required => A dedicated pulling tool required
Method of inserting seal and cleaning sealing faces if dirty
All functions must be conductable by ROVThese compromises / enhancements increase the size, weight, complexity and cost of the connection.
Diverless connection systems are typically classified by the orientation of the connection, i.e.HORIZONTAL OR VERTICAL
The intention with diverless system is to provide exactly the same level of functionality and
flexibility as a diver assisted system. However, divers have a major benefit; that being their
freedom to move and rotate. Any mechanical system trying to provide similar flexibility
needs to be quite complex and is ultimately expensive. The approach taken is to make the
seabed installed sections as cheap and simple as possible (essentially just steelwork), with all
the control and pulling systems located within multi use tying tools.
Considering a comparison with a typical bolted flange assembly, the following applies:
1.
Firstly, bolting a flange is quite a complex operation for a machine. It is easier to
use a clamp with tapered faces, or a collet type connector (see next slide) which
simplifies make up.
2. Ends need to be located within a certain range to enable clamping of both halves.
This requirement dictates the need to positively locate the spools relative to one
another which is done using retrievable guideposts.
3. Generally, the guidepost provides only course initial alignment. A tie-in tool is then
used to clean the connecting faces. To facilitate pull-in, pull-in forces need to be
transferred between each side of the connection and this requires a dedicated pull in
structure. As the forces involved can be large, the tie-in structure itself can be huge.
Once in position the tie-in tool inserts a seal ring, pulls both halves of the connectors
together and makes up the clamp. All these functions are controlled by a work class
ROV operated form the surface.
-
7/23/2019 Lecture 3_23Apr SW0[1]
13/46
A large range of diverless connection system current exist essentially each sub sea
equipment supplier has their own unique system which are all unique. However, ultimately
they may be broken down into the orientation of the connector : either Horizontal or Vertical
and the type of connector used : Collet or clamp type connector.
-
7/23/2019 Lecture 3_23Apr SW0[1]
14/46
Slide 12
DIVERLESS CONNECTORS - Collet And Clamp Connectors
Collet Clamp
Collet (Left) and Clamp (Right) Connectors
The collet connectors has a number of latching fingers (shown in black) and a movable
securing ring (shown in yellow) which is positioned around the pipe hub (gray). In this
diagram the connector is closed with the yellow securing ring engaged.
When the yellow hub is retracted, the fingers open and this allow a mating hub to mate
against the hub within the clamp. The yellow locking ring is then engaged causing the latches
to close and secure the mating hub together. To reverse the operation, the locking ring is
retracted and the fingers open.
The clamp connector operates by means of a 3 piece clamp assembly attached to an ROV
operable trunnion which opens and closes the clamp assembly. The inner surface of the
clamps and the external profile of the hubs are profiled that once the hubs are located with a
certain capture tolerance, the clamp forces both hubs together to form a seal. The yellow disk
is the sealing gasket.
-
7/23/2019 Lecture 3_23Apr SW0[1]
15/46
Slide 13
DIVERLESS CONNECTORS - Horizontal Tie-in System
Make up: Metrology conducted and spool fabricated on
shore to fit. Landing bucket and inboard connector pre-
attached to structure
Spool lowered from Vessel and ROV used toensure stab-in pins lands within Landingbucket (primary alignment)
Tie-in tool lowered from Vessel and slidesdown V shaped receptacles over bothconnectors.
ROV controls stroking operation from top Both halves pulled together, ROV engages
Collet clamp and conducts back seal test. Tie-in tool removed.
Considerations Low connection height required, typically 1.5m
minimum Low height allows protection from Fishing and
dropped objects However, larger probably of stirring seabed
with ROV di rt in connector Spool needs to be made short to allow fit-up
=> Spool prestressed during pull-in
Landing bucketattached to structure(Primary alignment)
In board Connector onStructure
Outboard hub withcolletconnector
Tie-in Tool (lands overeither half and strokes
halves together andmake up collet)
Tie in spool withStabinpin in Funnel
A Cameron Horizontal Connector tie-in system is shown above. The Landing bucket and
inboard connectors are preinstalled on the structure during the structure fabrication.
Once the structure and pipeline is installed metrology is conducted to determine the
finalised length of the tie-in spool, within a permissible tolerrance. Metrology is required as
all subsea structures can only be installed to a certain level of accuracy typically within +/-
2m.
One the metrology measure is known, the spool is fabricated with the outboard half of the
connector attached, pressure tested, rigged for lifting and shipped offshore for installation.
Each outboard connection has a vertical stab-in pin which is used for primary location of the
connector. In the figure above, this is located within the landing bucket and is not visible.
Both sets of hubs are separated by a known distance which is large enough to allow any
protection covers to be removed and to facilitate seal ring insertion / cleaning of the mating
surfaces.
The tie-in tool is then deployed and lands over both hubs. The yellow ring around the hub is
the reaction structure onto which the Tie-in tool lands and reacts against to pull both halves
together.
In the present case, a collet type connector is shown. The orange ring is pulled down over the
fingers to secure both halves of the clamp together and complete the tie-in procedure.
A fundamental consideration with a horizontal system is that as a gap is required, the spool
must be made short to ensure fit. During the stroking operation the spool is prestressed into
position and stresses must be assessed to ensure these are within permissible limits.
-
7/23/2019 Lecture 3_23Apr SW0[1]
16/46
Horizontal connectors can be positioned approximately 1.5m above seabed. However, the
lower the connector, the larger the possibility that ROV will sir up dirt that may foul the
sealing surface, which may require the connection to be remade. A back seal test facility is
typically provided to give an indication that the seal is good.
-
7/23/2019 Lecture 3_23Apr SW0[1]
17/46
Slide 14
DIVERLESS CONNECTORS - Vertical Tie-in System
Make up: Metrology conducted and spool fabricated on
shore to fit. Spool configured in W or M configuration to
allow expansion Inboard connector pre-attached to structure
Spool with pull-in tool preinstalled droppedfrom vessel and landed over Inboard Hubs.
Tie-in tool secured and pull-in operationbegun
Both halves pulled together, ROV engagesCollet clamp and conducts back seal test.
Tie-in tool removed.
Considerations Spool generally span between connection
points Height of connection typically>3m
Reduces potential for dirt in connection fromROV operations.
Height causes a concern where Fishing anddropped objects are a problem. More difficultto protect.
Spool made of exact length => Spool doesnot become pre-stressed during tie-in
Inboard Hub onStructure
M-shaped Spools
Combined alignmentand tie-in tool
The vertical system is similar to the horizontal system except orientated in the vertical plane
which causes the assembly to be much taller and more snagable where fishing interaction is
likely.
The tie-in spool is usually orientated vertically and configured in a U or W shape to allow
expansion. Metrology is conducted and the spool is fabricated and shipped to site for
installation. One key difference from the horizontal system, is that as both end are landed at
the same time, there is no need for the spool to be fabricated short. Additionally, gravity helps
to locate either end. The pulling and latching of the collet connector is conducted similar to
the process described for the vertical connector.
Vertically connectors are typically used where fishing interaction is not likely. The assistance
of gravity in make up means they can be more lightweight (primarily as friction loads do not
apply).
As such they can be positioned at a higher elevations relative to the seabed and are less likely
to be subject to fouling from dirt stirred up by the ROV fans.
-
7/23/2019 Lecture 3_23Apr SW0[1]
18/46
Slide 15
DIVERLESS CONNECTORS - Horizontal vs Vertical Connectors?
Considerations
Seabed Conditions
No defined seabed in some deeper water developments
Gradual change in density from water to soil
Concern to ensure connecting surfaces are clean
Vertical connector position 5-6m above seabed provide an advantage.
Fishing interaction
Where fishing interaction is a threat, 5 to 6m high spools are not practical.
Typically adopt horizontal connection where fishing interaction is likely
Typically horizontal connections used < 500m, vertical > 500m
The decision to use horizontal or vertical connectors depends primarily on the seabed
conditions and the level of fishing interaction.
In many West African developments, there is no defined hard seabed, but rather a gradual
change from water to soil. Additionally many of these area are not fished. Thus vertical
connectors are extensively used. In Norway, seabed tend to be either sand or gravel and are in
regions / water depths where fishing interaction remains a possibility. Horizontal connectors
are favoured as they are more squat and thereby easier to protect.
In general, vertical connectors are typicially, but not exclusively, used for very deep water
applications water depths in excess of 500m. Horizontal connectors are used for depth less
than this.
-
7/23/2019 Lecture 3_23Apr SW0[1]
19/46
Slide 16
BULKHEADS
Pipe-in-Pipe End Bulkhead
Where number of pipes terminate at the ends of pipeline bundles, pipe-in-pipe pipelines or
caissons, a bulkhead will be provided to provide mechanical connection between the inner
pipes and the carrier pipe. A bulkhead normally comprises a large steel connection that ties all
of the pipes to the carrier pipe. This connection needs to be designed to accommodate the
different axial loads within each inner pipe and the carrier pipe. The analysis is normally
performed using finite element solid modelling with the results assessed in accordance with
PD5500, API 6A or ASME VIII.
This slide shows a solid finite element model of a pipe-in-pipe bulkhead. Only half of the
assembly is modelled as it takes advantage of a symmetrical boundary along the pipe centre
line. On the left the entire model is shown with the flange, bulkhead and adjoining sections of
pipe. On the right only the bulkhead is shown. The colours indicate the level of stress within
the bulkhead.
-
7/23/2019 Lecture 3_23Apr SW0[1]
20/46
Slide 17
BULKHEADS
Bundle and Caisson Riser Bulkheads
Unlike a pipe-in-pipe system, bundles or caisson riser systems may have a number of internal
pipes. Examples of such cases are illustrated here. The bulkhead generally comprise a thick
connecting plate with nibs that increase in wall thickness as the bulkhead approaches. This
assists in reducing high stresses caused by a the stiffness discontinuity between the pipe and
the bulkhead.
-
7/23/2019 Lecture 3_23Apr SW0[1]
21/46
Slide 18
COATINGS
The pipeline may be coated for a number of reasons, typically:
Submerged weight and stability
External corrosion protection
Insulation
Corrosionprotection
coating
Concreteweight coating
-
7/23/2019 Lecture 3_23Apr SW0[1]
22/46
Slide 19
COATINGS EXTERNAL CORROSION
External corrosion is controlled by a combination of:
Corrosion resistant coating
Cathodic protection (sacrificial anodes)
Typical corrosion resistant coatings include:
Fusion Bonded Epoxy
Thermoplastics polypropylene and polyethelene
Elastomers Neoprene rubber (polychloroprene)
Thermally Sprayed Aluminium
Asphalt Enamel
Wraps
Each coating has an associated breakdown factor
3 layer PP
External corrosion protection is controlled via a combination of:
Corrosion resistant coating
Cathodic protection
Both are necessary as coating systems are not 100% reliable and it is not practical to provide
anodes to protect the entire bare steel pipeline over its design life.
Typical corrosion resistant coatings include:
Fusion Bonded Epoxy(FBE) is an epoxy based powder coating that is sprayed onto
a rotating pipe. The name 'fusion-bond epoxy' is due to resin cross-linking and the
application method, which is different from a conventional paint. The resin and
hardener components in the dry powder FBE stock remain unreacted at normal
storage conditions. At typical coating application temperatures, usually in the range
of 180 to 250 C, the contents of the powder melt and transform to a liquid form. The
liquid FBE film wets and flows onto the steel surface on which it is applied, and soon
becomes a solid coating by chemical cross-linking, assisted by heat. This process is
known as fusion bonding.
Thermoplastics, typicallypolypropylene and polyethelene which are extruded onto a
rotating pipe
Elastomers Polychloroprene is normally hot-bonded to the steel using a
vulcanization process in a steam autoclave. This process both cures the rubber and
bonds it to the steel. Polychloroprene provides tough, durable protection for pipelines
and risers with excellent resistance to water take-up, hydrocarbons and ozone.
-
7/23/2019 Lecture 3_23Apr SW0[1]
23/46
Polychloroprene can also be applied as a field joint coating on site being cured using
heated electrical tapes.
Thermally Sprayed Aluminium (TSA). A sprayed coating that is suitable for
relatively high temperatures. It has high thermal conductivity which makes it useful
for cooling and heating spools.
Asphalt Enamelis a plant applied durable coating based on modified bitumen
(asphalt).
Wraps. These are not commonly used but may be suitable for field joints.
Selection of coating type will be based on:
Cost
Operating temperature each coating system is only suitable for a certain
temperature range
Installation method
Thermal requirements (U-value)
Other coatings insulation or concrete weight coating.
Location of coating plant
Etc
Coating layers may be combined. The picture in this slide shows a 3 layer polypropylene
coating which is a very common pipeline coating. It is a multilayer coating composed of three
functional components, a high performance fusion bonded epoxy (FBE) followed by a
copolymer adhesive and an outer layer of polypropylene which provides one of the toughest,
most durable pipe coating solutions available.
Each coating system has an associated breakdown factor. This provides a measure of
protection offered to the pipeline by the coating and is thus used when assessing the cathodic
protection requirements. The coating breakdown factor accounts for coating damage and
water ingress. A break down factor of 0 means 100% electrically insulating whereas a break
down factor of 1 indicates that the coating has no protective properties.
-
7/23/2019 Lecture 3_23Apr SW0[1]
24/46
Slide 20
INSULATION
Pipeline may require insulation for flow assurance requirements.
Pipeline insulation may be provided by:
External wet insulating coating
Soil
Dry insulation, pipe-in-pipe system
Wet insulation systems
Solid polypropylene or polyurethane
Syntactic coatings
In oil production pipelines, wax deposition on the pipe wall may occur if the fluid
temperature becomes too low, leading to a local constriction of the bore. Also, the viscosity of
oil rises as the temperature falls, resulting in reduced flowrate. In gas production pipelines,
hydrates (ice-like material) may form under high pressure conditions if the temperature falls
too low and water is present in the product. Hydrates can block a pipeline and are difficult
and costly to remove. Insulating a gas pipeline prolongs the period between shut-in and the
fluids reaching the hydrate formation temperature and this can help to avoid the requirement
to de-pressurise the system. An alternative to insulating a pipeline transporting wet gas is to
continuously inject a hydrate inhibitor such as MEG into the product. Normally hydrate or
wax survival times of 24 hours are targeted following a shutdown event.
Pipeline may require insulation to maintain the required flow rate and prevent wax and
hydrates forming. Flow assurance predicts the thermal insulation requirement and a coating
system is selected to achieve this.
Pipeline insulation may be provided by:
External wet insulating coating.
Soil. If the pipeline is buried the surrounding soil provides thermal insulation.
Dry insulation, pipe-in-pipe system.
External wet insulations generally comprise of:
Solid polypropylene or polyurethane
-
7/23/2019 Lecture 3_23Apr SW0[1]
25/46
Syntactic coatings. Plastic or glass microspheres are mixed with the polymer to
enhance its thermal insulation properties. Syntactic polyurethane (SPU
polyurethane mixed with plastic or glass microspheres).
Overall heat transfer coefficients or U-values as low as 2.5 W/m2K can be achieved using an
external wet insulation system.
-
7/23/2019 Lecture 3_23Apr SW0[1]
26/46
Slide 21
DRY INSULATION - PIP
Pipe-in-pipe systems comprise of two pipes with dry insulation in the annulus:
The insulation may be:
Polyurethane foam
Rockwool
More sophisticated material, such as:
- Aerogel
- Izoflex
- Wacker
Centralisers required to maintain pipe concentricity
As a contingency water stops may be provided.
A pipe in pipe system consists of 2 pipes one inside the other. The outer or carrier pipe
provides a dry annulus around the inner pipe. This enables the use of dry insulation which is
far more effective than wet insulation. Sometimes a vacuum can be provided in the annulus to
improve the thermal insulation. Overall heat transfer coefficients or U-values as low as 0.5
W/m2K can be achieved with pipe-in-pipe systems.
-
7/23/2019 Lecture 3_23Apr SW0[1]
27/46
Slide 22
ANODES EXTERNAL CORROSION
External corrosion is controlled by a combination of:
Corrosion resistant coating
Cathodic protection (sacrificial anodes)
Cathodic protection involves the use of galvanic sacrificial bracelet anodes attachedto the pipeline at intervals along its length.
Anodes are electrically connected to the stee l pipeline.
Typical galvanic anode materials include:
Aluminium
Zinc
Magnesium
External corrosion is controlled by a combination of:
Corrosion resistant coating
Cathodic protection (sacrificial anodes)
External corrosion is covered within the materials module of the course and is therefore not
covered herein.
Corrosion is an electro-chemical process that involves the passage of electrical currents.
Cathodic protection involves the use of galvanic sacrificial bracelet anodes attached to the
pipeline at intervals along its length.
Galvanic anode systems employ reactive metals as anodes that are directly electrically
connected to the steel being protected. The difference in natural potentials between the anode
and the steel, as indicated by their relative positions in the electro-chemical series, causes a
positive current to flow in the electrolyte solution (surrounding water) from the anode to the
steel. Thus, the whole surface of the steel becomes more negatively charged and becomes the
cathode. The anode (anodic reaction) corrodes as it passes electrons to the cathode (steel
cathodic reaction) which does not corrode.
The metals commonly used, as sacrificial anodes are aluminium, zinc and magnesium.
-
7/23/2019 Lecture 3_23Apr SW0[1]
28/46
Slide 23
PROTECTION
Pipelines and spools require protection from f ishing gear and dropped objects.
Untrenched pipeline sections and spools are often provided with additional protection.This typically takes the form of:
Concrete mats
Concrete tunnels Protection frames
Rockdump
Pipelines exposed to a significant possibility of impact from dropped objects, fishing gear or
any other type of harmful interface, must be shown to be capable of retaining their integrity
and operability should such an event occur.
A dropped object assessment is normally performed to assess the potential, based on the
frequency of offshore lifts, of various dropped objects and the probability of these objects
impacting the subsea facilities. Tie-in spools are not normally buried and are often located
adjacent to offshore facilities, where there is an increased risk of dropped object impact.
Surface laid pipelines and spools that are located in areas of frequent fishing activity must be
shown to be capable of surviving interference from the various types of trawl gear that they
are likely to encounter. DNV RP F111 gives guidance on these calculations for trawl gear
pull-over, impact and hooking.
Pipelines smaller than 16 inch diameter are usually trenched and buried for mechanical
protection in the UKCS (united Kingdom Continental Shelf).
Concrete weight coatings, applied primarily for stability, are considered to offer some impact
protection to pipelines.
Untrenched pipeline sections and spools are often provided with additional protection. This
typically takes the form of:
Flexible concrete mattresses
-
7/23/2019 Lecture 3_23Apr SW0[1]
29/46
Concrete protection tunnels
Protection frames
Rockdump
-
7/23/2019 Lecture 3_23Apr SW0[1]
30/46
Slide 24
CONCRETE MATTRESSES
Concrete mattresses typically dont absorb a great deal of energy but rather spreads the
energy so that it doesnt act as a knife edge impact.
-
7/23/2019 Lecture 3_23Apr SW0[1]
31/46
Slide 25
PROTECTION STRUCTURES
Concrete Tunnels
Tie-in spools are typically protected using flexible concrete mattresses. Where this provides
insufficient protection or the spool cannot have mattresses protection, for instance elevated
free draining spools, protection structures may be adopted.
-
7/23/2019 Lecture 3_23Apr SW0[1]
32/46
Slide 26
ROCKDUMP
Rock may be used for protection or to restrain the pipeline. As protection it may be used
along the entire pipeline length or more normally at crossings and trench transitions.
Rockdump may also be used for intermediate supports on uneven seabeds. Its use is typically
restricted to geographic regions where rock is readily available.
-
7/23/2019 Lecture 3_23Apr SW0[1]
33/46
Slide 27
SUBSEA STRUCTURES - MANIFOLDS
A manifold is a subsea structure housing:
Pipework
Valves
Controls Equipment
Chemical injection and distribution facilities
Metering
for the control and operation of the Subsea field.
A manifold is a subsea structure that houses:
Pipework
Valves
Controls equipment
Chemical injection and distribution facilities
Metering
for control and operation of the Subsea field.
-
7/23/2019 Lecture 3_23Apr SW0[1]
34/46
Slide 28
MANIFOLD DESIGN
Design Activities
Structural analysis
Transportation
Installation
Inplace
- Hydrodynamic Loading
- Foundations
- Impact / Fishing Gear Interaction
Pipe Stress Analysis
Controls Equipment DesignCodesandStandards
Designing a manifold for the system requirement involves:
Structural analysis.The principal purpose of the structure is to protect the
equipment within its envelope. As a result, the structure needs to be suitably designed
for all functional and accidental loads that it may be exposed to throughout its design
life.
Pipe stress analysis.The pipework within the structure should be suitable for the
design operating conditions as well as any functional and accidental loads that it may
be expose to during its design life.
Controls equipment.The controls equipment covers all electrical, hydraulic and
chemical systems that are required for operation of the subsea field. All control
signals are normally provided through a subsea umbilical which terminates within the
manifold. The controls may then be distributed around the manifold, to the trees, to
other developments, etc. through a subsea distribution unit (SDU), also housed within
the manifold.
Shown here is the 8 slot Callanish manifold from the Britannia Satellites development. The
top picture shows the integrated pipework and structure model used for the design and the
bottom picture shows the 3D model of the manifold.
The scale of the manifold is illustrated by the diver standing at the bottom corner. The
structure is the size of a reasonably large building approximately 15m long 6m wide
6.5m high.
-
7/23/2019 Lecture 3_23Apr SW0[1]
35/46
Slide 29
MANIFOLD INSTALLATION
This slide illustrates the Callanish manifold being installed it doesnt look the size of a
building
-
7/23/2019 Lecture 3_23Apr SW0[1]
36/46
Slide 30
TIE-IN SPOOLS
Tie-in spools connect one part of the subsea system to another.
Typically rigid single pipe and, if required, are designed in a configuration to
accommodate pipeline end expansion.
Commonly configured in a Z shape.
Expansion
Manifold
Tie-in Spool
Pipeline
-
7/23/2019 Lecture 3_23Apr SW0[1]
37/46
Slide 31
TIE-IN SPOOL DESIGN
Tie-in spools are typically designed using a non linear structural, piping or finite element
package.Involves non-linear analysis for the pipe to seabed friction modelling.
Design considerations:
Geometry
Pipe sizes, tolerances, corrosion allowance, etc.
Bends
Seabed restraint
Protection
Loading
Submerged weight
Mattresses
Pressures & temperatures
Environmental loading (waves and currents)
Tie-in spools are typically designed using a non linear structural, piping or finite element
package.
Involves non-linear analysis for the pipe to seabed friction modelling. Non linear models are
those which cannot be solved in a linear manner, in this instance the tie-in spool loading is
path dependant, i.e. the spool submerged weight needs to be applied to generate the frictional
resistance before any operational loading is applied.
The primary design considerations include:
Geometry The tie-in locations, self loading and pipeline expansion may all
influence and the size and layout of the spool.
Pipe sizes, tolerances, corrosion allowance, etc. the pipe will be modelled with
the correct diameter and wall thickness. It is normal to model the pipe nominal wall
thickness, however fabrication tolerances, corrosion allowances, erosion allowances
bend thinning etc. may need to be taken into account when code checking.
Bends spool bends may be of radius 1.5D (forged long radius elbows), 3D (pulled
induction bends) or 5D (pulled induction bends). If there is a pigging requirement the
bends will have to be 3D or 5D induction bends. The hot induction bending process
induces thinning of the bend wall which should be taken into account in the analysis.
Seabed restraint the interaction between the spool pipe and the seabed provides
resistance to spool movement. This resistance is difficult to accurately predict and a
conservative range is normally analysed.
-
7/23/2019 Lecture 3_23Apr SW0[1]
38/46
Protection the tie-in spools must be protected against dropped objects and fishing
gear interaction.
Loading tie-in spool loading will be dependant on the actual tie-in spool
configuration, but will typically involve:
- Submerged weight of the tie-in spool and any attachments, e.g. coatings,
anodes, flanges, etc. and including contents.
-
Mattresses The application of mattress protection adds weight to the pipe
and introduces another interface between the pipe and the mattress, both of
which act to resist spool movement.
- Pressures & Temperatures (where applicable including pipeline
expansion)
-
Environmental loading from waves and currents
Spool design will be illustrated by a simple example.
-
7/23/2019 Lecture 3_23Apr SW0[1]
39/46
Slide 32
TIE_IN SPOOL EXAMPLE
Diameter = 12 (323.8mm OD)
Wall thickness = 17.5mm (Schedule 80)Material X65
s=7850kg/m3
SMYS=450MPa
E=207GPa
=0.3
=11.710-6 oC-1
Contents density =800kg/m3
Pressure = 300bar
Pipeline end expansion = 1m
Seabed frictional resistance = 0.4 to 0.9
Seawater Density = 1025kg/m3
For simplicity ignore temperature, coatings, protection, tolerances.
25m
10m
90o 5D Radius Bend
The wall thickness is sufficient for pressure containment, i.e. in accordance with PD 8010
t
PDSMYS
272.0 > thin walled theory 20>
t
D
Wall thickness requirement t=300e5323.8/(20.72450e6)=15mm (D/t=21.6 therefore thin
wall approximation is OK)
-
7/23/2019 Lecture 3_23Apr SW0[1]
40/46
Slide 33
TIE-IN SPOOL EXAMPLE
Spool
Pipeline
The basic steps to the analysisare:
Set up model with nodes and
elements.
Add section for pipeline.
Apply geometric and materialproperties.
Set up seabed frictionalresistance.
Apply loads.
Solve.
The basic steps to the tie-in spool analysis are:
Set up model with nodes and elements. The tie-in spool-to-seabed contact is modelled
using friction gap elements. These elements represent the spool-to-seabed interaction
by supporting the pipe on discrete vertical springs, with stiffness equal to the vertical
stiffness of the seabed. The pipe is free to rise off the seabed and, when in contact
with the seabed, is opposed from moving laterally and axially by frictional resistance.
As a result, the model is sub divided into a number of elements to gain an accurate
representation of seabed frictional resistance.
A section of the pipeline is added to remove any artificial end effects caused by over
restraint of the spool.
Apply geometric and material properties.
Set up seabed frictional resistance.
Apply loads.
Solve.
-
7/23/2019 Lecture 3_23Apr SW0[1]
41/46
Slide 34
TIE-IN SPOOL RESULTS
Deflected shape for the lowfriction case (=0.4)
-
7/23/2019 Lecture 3_23Apr SW0[1]
42/46
Slide 35
TIE-IN SPOOL RESULTS BENDING MOMENT
Low friction case (=0.4) High friction case (=0.9)
55kNm 311.2kNm185.1kNm
223.8kNm
The above slide shows the distribution of bending moment around the tie-in spool.
Greatest moment is generated in the tie-in spool bend for the high friction case, i.e. that which
provides greatest resistance to spool movement. However, because of the greater resistance,
bending moment drops off with distance from the bend. In the low friction case more moment
is transferred back to the restraint on the left hand side. This could be a flange connection to,
for example, a manifold which you wouldnt want subject to such a large bending moment.
-
7/23/2019 Lecture 3_23Apr SW0[1]
43/46
Slide 36
In the high friction case (=0.9) maximum loading occurs in the spool bend. This corresponds
to:
Effective axial force = -64 kN
Bending Moment = 311.2 kNm
Calculate the PD 8010 equivalent stress utilisation ratio
where fd=0.96 and
TIE-IN SPOOL RESULTS EXERCISE
SMYSfUR
d
equ
=
222 3 ++= lhlhequ
-
7/23/2019 Lecture 3_23Apr SW0[1]
44/46
Slide 37
TIE-IN SPOOL RESULTS
0.824
Of course the good thing about computer programs is that it does it for you
-
7/23/2019 Lecture 3_23Apr SW0[1]
45/46
Slide 38
TIE-IN SPOOL RESULTS
We will use an 11 API flange for our 12 tie-in spool. Use the Kellogs equation to determine
whether this flange should be rated 5k (5000psi=345bar) or 10k (10,000psi=690bar).
Note our design pressure is 300bar and a 11 API flange uses a SBX 158 gasket with a meangasket diameter of 328.9mm.
-
7/23/2019 Lecture 3_23Apr SW0[1]
46/46
Slide 39
TIE-IN SPOOL RESULTS - BEND ANGLE
60o
25m
1.06460o
0.94270o
0.87480o
0.82490o
PD 8010 URBend Angle
Someone in the last lecture asked why routing aimed at achieving 90obends on the tie-in
spools. I have re-analysed the tie-in spool with the same leg lengths but varied the angle
between 60oand 90
o. The table here shows increased PD8010 utilisation ratios, and thus
stress, at the spool bend.