Lecture 3_23Apr SW0[1]

download Lecture 3_23Apr SW0[1]

of 46

Transcript of Lecture 3_23Apr SW0[1]

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    1/46

    Slide 1

    PIPELINES AND SOIL MECHANICS

    Pipeline Ancillary Equipment

    Presented by: Scott Wright PhD BEng (Hons) [email protected]

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    2/46

    Slide 2

    Q: What is pipeline ancillary equipment?

    A: Components of the pipeline system other than the physical pipeline.

    The list of components is wide ranging but we will take a look at:

    Flanges, end fittings and connectors

    Bulkheads

    Coatings

    Insulation

    Anodes

    Protection

    Manifolds

    Valves

    Flow meters

    Controls equipment

    Tie-in spools

    PIPELINE ANCILLARY EQUIPMENT

    When asked to do this lecture I wasnt sure what we should be looking at for pipeline

    ancillary equipment.

    In the end I decided that it should be all components of the pipeline system other than simply

    the physical pipe. In reality there is a wide range of components that make up the pipeline

    system, each of which performs an important role. We will take a look at the most significant

    of these components, including:

    Flanges, end fittings and connectors.

    Bulkheads.

    Coatings.

    Insulation.

    Anodes.

    Protection.

    Manifolds.

    - Valves.

    - Flow meters.

    - Controls equipment.

    Tie-in spools.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    3/46

    Slide 3

    FLANGES

    Flanges provide a pressure containing connection between two parts of the pipeline

    system.

    Flanges are traditionally made by hand either onshore or by diver on the seabed.

    Principally 2 types of flanges:

    API

    ANSI / ASME

    Flanges provide a pressure containing connection between two parts of the pipeline system.

    Flanges are normally made by hand either onshore or by diver on the seabed.

    Principally 2 types of flanges:

    API - provides face to face seal between the flange faces.

    ANSI / ASME Flange faces are separated and interface is provided through the

    gasket.

    In general, API flanges are smaller than ANSI flanges.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    4/46

    Slide 4

    FLANGE ASSEMBLY

    Weld Neck to Weld Neck Connection Weld Neck to Swivel Ring Connection

    Weld Neck StudboltsGasket

    Weld Neck

    Swivel Ring

    Subsea flange connections are normally made using weld neck to weld neck flanges or, where

    the flange connection needs to be made-up Subsea, using weld neck to swivel ring flanges.

    Weld neck flanges consist of a single component comprising a flange with a tapered hub

    section to which the pipe is welded.

    Swivel ring flanges are made up of two components, an inner part and a outer swivel ring.

    The inner part is similar to weld neck flange and is welded to the pipe at the rear of the

    tapered hub. The swivel ring freely rotates around the hub for easy alignment of bolt holes

    during make up. The flange is bolted together through the swivel ring which bears on the

    inner hub.

    Between the flanges there is a metal gasket which provides the pressure retaining seal.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    5/46

    Slide 5

    SMALL FLANGE ALTERNATIVES

    Compact Flanges SPO, Destec

    Hub Clamp Connectors Grayloc, Techlok

    Often size and weight is of particular concern in subsea design. There are a number of

    alternatives to the traditional ANSI and API flanges, the most common being:

    Compact flanges, such as the vector SPO flange and the Destec Compact flange.

    Hub connectors, such as the vector Techlok and the Grayloc connectors.

    Compact flanges are a smaller and lighter proven alternative to conventional ANSI or API

    flanges. Compact flanges are increasingly used in the subsea industry because of their

    smaller sizes, lower weight and guaranteed seal integrity.

    Hub connectors again provide significant size and weight savings. They also provide reduced

    bolting requirements and therefore reduce the time required to make the connection. They are

    often the preferred solution where space, weight and joint integrity are critical and can often

    be found on flexible riser systems.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    6/46

    Slide 6

    FLANGE RATING

    Flanges, indeed many pipeline and piping components, are c lassified by pressure

    rating.

    425.4

    2,500

    255.4153.110268.25119.6ANSI Pressure @ LowTemperature (bar)

    1,500900600400300150ANSI Class

    32

    164

    G

    M

    G

    FPP deff

    ++=

    G = Mean Gasket Diameter

    Pd = System Design Pressure

    F = Tensile Load

    M = Bending Moment

    Peff = Equivalent Flange Pressure Loading

    Kellogs Equation

    20,00015,00010,0005,0003,0002,000API Pressure (psi)

    Flanges are classified by pressure rating. If the flange was subject to no other loads it would

    be capable of retaining this pressure. However, tensile loading and bending moments acts to

    open the flange pair and this reduced the pressure it can withhold.

    The Kellogs equation can be used as a first pass to assess flange loading. In this equation the

    flanges pressure capacity is apportioned into pressure, tensile and bending moment capacity.

    Detailed flange capacity calculations can be performed using the method in ASME VIII and

    PD5500. Alternatively finite element analysis can be performed with linearised stress checks

    in accordance API 6A or PD5500.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    7/46

    Slide 7

    MECHANICAL CONNECTORS

    Mechanical connectors are typically used in flanged-spool repair applications.

    They can be fitted to pipe ends to provide a flange connection.

    They are proprietary equipment and as a result are more expensive than a traditional welded

    flange solution.

    The pipe end needs to be cleaned and prepared to the connector manufacturers requirements.

    The connector is then slid over the pipe end and tightened. The action of tightening the

    connector activates the gripping and sealing mechanism.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    8/46

    Slide 8

    MERLIN CONNECTOR

    There are some advanced connectors out there like the Merlin connector. Either side of the

    connector is welded to the pipe ends. The pipe ends are then brought together. The annulus of

    the connector is pressurised and the two components are displaced together. The annulus is

    then depressurised and the connection is complete.

    It provides a connection with a high integrity metal to metal seal.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    9/46

    Slide 9

    DIVERLESS CONNECTORS - When is Diverless Technology Required?

    Requirement Set by either

    Water depth

    Safety

    Local Legislation

    Existing kit

    Implication of Water Depth

    Increase in Hydrostatic pressure with depth.

    Toxicity and impact of respiratory gases under pressure on human tissue.

    Fatigue, insomnia, memory loss occur as depth increases >> 300m

    Time to decompress increases

    e.g. For a dive to 530m, takes 8 day to compress, 18 Day to decompress

    Before delving into diverless system requirements, it is worth considering why we would

    adopt a diverless system strategy.

    In general pipelay can be conducted in a variety of water depths up to 2000m without divers

    being required. The primary area that require diver intervention is for the make up of

    connections on tie-in spools or for maintenance (intervention) when something needs to be

    changed out.

    1. Water depth poses a natural limit set by human physiology. Typically saturation divers can

    operate safety to about 300m (1000ft). With increasing depth, the gases and in particular

    oxygen (in air diving) can become toxic which necessitates differing respiratory gas

    combinations depending on depth. At deeper depths, experience has shown that fatigue,

    insomnia and memory loss can occur, although divers have achieved 530m in water and over

    700m in dry decompression chambers. An additional consideration is the time for

    decompression which is limited to approximately 15 meters per day, and this controls the time

    required for decompression.

    2. A second consideration is safety. Intuitively, placing a diver in the water poses a risk.

    Adopting an alternative diverless technique has to be fundamentally safer, although this will

    incur a cost delta which may be significant

    3. There may be local legislative requirement for the work to be done diverless. This is the

    preference in Norway where divers are used only as a last resort for safety reasons.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    10/46

    This can cause some interesting cases where projects straddle the UK-Norway boundary

    where the portion in UK waters has been diver assisted and that in Norwegian waters is

    diverless.

    4. Finally, if tie-in into existing subsea kit there may be little option but to adopt a similar

    philosophy.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    11/46

    Slide 10

    DIVERLESS CONNECTORS - When is Diverless Technology Required?

    Diving Options

    Air Diving: Breathing gas : Normal atmospheric mixture of oxygen and Nitrogen

    Limited to a depth of about 58m (190 ft)

    More commonly being used for

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    12/46

    Slide 11

    DIVERLESS CONNECTORS

    Many different Diverless Connection system on Market

    Fundamentals of each are similar, but differ locall y in design Vetco (GE) : Icarus, HCCS or VCCS system

    Cameron : CVC or CHC system Kvaerner : RTS and BBRTS system FMC : FLYCON, ROVCON, UTIS system

    Diverless Lacks benefit of diver dexterity: Bolted clamp no longer possible

    => Adopt either a clamp or collettype solution Clamp must be deployable by ROV

    Dedicated structure to enable primary location => An alignment structure is required with guide posts

    Method of pulling in either connection required => A dedicated pulling tool required

    Method of inserting seal and cleaning sealing faces if dirty

    All functions must be conductable by ROVThese compromises / enhancements increase the size, weight, complexity and cost of the connection.

    Diverless connection systems are typically classified by the orientation of the connection, i.e.HORIZONTAL OR VERTICAL

    The intention with diverless system is to provide exactly the same level of functionality and

    flexibility as a diver assisted system. However, divers have a major benefit; that being their

    freedom to move and rotate. Any mechanical system trying to provide similar flexibility

    needs to be quite complex and is ultimately expensive. The approach taken is to make the

    seabed installed sections as cheap and simple as possible (essentially just steelwork), with all

    the control and pulling systems located within multi use tying tools.

    Considering a comparison with a typical bolted flange assembly, the following applies:

    1.

    Firstly, bolting a flange is quite a complex operation for a machine. It is easier to

    use a clamp with tapered faces, or a collet type connector (see next slide) which

    simplifies make up.

    2. Ends need to be located within a certain range to enable clamping of both halves.

    This requirement dictates the need to positively locate the spools relative to one

    another which is done using retrievable guideposts.

    3. Generally, the guidepost provides only course initial alignment. A tie-in tool is then

    used to clean the connecting faces. To facilitate pull-in, pull-in forces need to be

    transferred between each side of the connection and this requires a dedicated pull in

    structure. As the forces involved can be large, the tie-in structure itself can be huge.

    Once in position the tie-in tool inserts a seal ring, pulls both halves of the connectors

    together and makes up the clamp. All these functions are controlled by a work class

    ROV operated form the surface.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    13/46

    A large range of diverless connection system current exist essentially each sub sea

    equipment supplier has their own unique system which are all unique. However, ultimately

    they may be broken down into the orientation of the connector : either Horizontal or Vertical

    and the type of connector used : Collet or clamp type connector.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    14/46

    Slide 12

    DIVERLESS CONNECTORS - Collet And Clamp Connectors

    Collet Clamp

    Collet (Left) and Clamp (Right) Connectors

    The collet connectors has a number of latching fingers (shown in black) and a movable

    securing ring (shown in yellow) which is positioned around the pipe hub (gray). In this

    diagram the connector is closed with the yellow securing ring engaged.

    When the yellow hub is retracted, the fingers open and this allow a mating hub to mate

    against the hub within the clamp. The yellow locking ring is then engaged causing the latches

    to close and secure the mating hub together. To reverse the operation, the locking ring is

    retracted and the fingers open.

    The clamp connector operates by means of a 3 piece clamp assembly attached to an ROV

    operable trunnion which opens and closes the clamp assembly. The inner surface of the

    clamps and the external profile of the hubs are profiled that once the hubs are located with a

    certain capture tolerance, the clamp forces both hubs together to form a seal. The yellow disk

    is the sealing gasket.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    15/46

    Slide 13

    DIVERLESS CONNECTORS - Horizontal Tie-in System

    Make up: Metrology conducted and spool fabricated on

    shore to fit. Landing bucket and inboard connector pre-

    attached to structure

    Spool lowered from Vessel and ROV used toensure stab-in pins lands within Landingbucket (primary alignment)

    Tie-in tool lowered from Vessel and slidesdown V shaped receptacles over bothconnectors.

    ROV controls stroking operation from top Both halves pulled together, ROV engages

    Collet clamp and conducts back seal test. Tie-in tool removed.

    Considerations Low connection height required, typically 1.5m

    minimum Low height allows protection from Fishing and

    dropped objects However, larger probably of stirring seabed

    with ROV di rt in connector Spool needs to be made short to allow fit-up

    => Spool prestressed during pull-in

    Landing bucketattached to structure(Primary alignment)

    In board Connector onStructure

    Outboard hub withcolletconnector

    Tie-in Tool (lands overeither half and strokes

    halves together andmake up collet)

    Tie in spool withStabinpin in Funnel

    A Cameron Horizontal Connector tie-in system is shown above. The Landing bucket and

    inboard connectors are preinstalled on the structure during the structure fabrication.

    Once the structure and pipeline is installed metrology is conducted to determine the

    finalised length of the tie-in spool, within a permissible tolerrance. Metrology is required as

    all subsea structures can only be installed to a certain level of accuracy typically within +/-

    2m.

    One the metrology measure is known, the spool is fabricated with the outboard half of the

    connector attached, pressure tested, rigged for lifting and shipped offshore for installation.

    Each outboard connection has a vertical stab-in pin which is used for primary location of the

    connector. In the figure above, this is located within the landing bucket and is not visible.

    Both sets of hubs are separated by a known distance which is large enough to allow any

    protection covers to be removed and to facilitate seal ring insertion / cleaning of the mating

    surfaces.

    The tie-in tool is then deployed and lands over both hubs. The yellow ring around the hub is

    the reaction structure onto which the Tie-in tool lands and reacts against to pull both halves

    together.

    In the present case, a collet type connector is shown. The orange ring is pulled down over the

    fingers to secure both halves of the clamp together and complete the tie-in procedure.

    A fundamental consideration with a horizontal system is that as a gap is required, the spool

    must be made short to ensure fit. During the stroking operation the spool is prestressed into

    position and stresses must be assessed to ensure these are within permissible limits.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    16/46

    Horizontal connectors can be positioned approximately 1.5m above seabed. However, the

    lower the connector, the larger the possibility that ROV will sir up dirt that may foul the

    sealing surface, which may require the connection to be remade. A back seal test facility is

    typically provided to give an indication that the seal is good.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    17/46

    Slide 14

    DIVERLESS CONNECTORS - Vertical Tie-in System

    Make up: Metrology conducted and spool fabricated on

    shore to fit. Spool configured in W or M configuration to

    allow expansion Inboard connector pre-attached to structure

    Spool with pull-in tool preinstalled droppedfrom vessel and landed over Inboard Hubs.

    Tie-in tool secured and pull-in operationbegun

    Both halves pulled together, ROV engagesCollet clamp and conducts back seal test.

    Tie-in tool removed.

    Considerations Spool generally span between connection

    points Height of connection typically>3m

    Reduces potential for dirt in connection fromROV operations.

    Height causes a concern where Fishing anddropped objects are a problem. More difficultto protect.

    Spool made of exact length => Spool doesnot become pre-stressed during tie-in

    Inboard Hub onStructure

    M-shaped Spools

    Combined alignmentand tie-in tool

    The vertical system is similar to the horizontal system except orientated in the vertical plane

    which causes the assembly to be much taller and more snagable where fishing interaction is

    likely.

    The tie-in spool is usually orientated vertically and configured in a U or W shape to allow

    expansion. Metrology is conducted and the spool is fabricated and shipped to site for

    installation. One key difference from the horizontal system, is that as both end are landed at

    the same time, there is no need for the spool to be fabricated short. Additionally, gravity helps

    to locate either end. The pulling and latching of the collet connector is conducted similar to

    the process described for the vertical connector.

    Vertically connectors are typically used where fishing interaction is not likely. The assistance

    of gravity in make up means they can be more lightweight (primarily as friction loads do not

    apply).

    As such they can be positioned at a higher elevations relative to the seabed and are less likely

    to be subject to fouling from dirt stirred up by the ROV fans.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    18/46

    Slide 15

    DIVERLESS CONNECTORS - Horizontal vs Vertical Connectors?

    Considerations

    Seabed Conditions

    No defined seabed in some deeper water developments

    Gradual change in density from water to soil

    Concern to ensure connecting surfaces are clean

    Vertical connector position 5-6m above seabed provide an advantage.

    Fishing interaction

    Where fishing interaction is a threat, 5 to 6m high spools are not practical.

    Typically adopt horizontal connection where fishing interaction is likely

    Typically horizontal connections used < 500m, vertical > 500m

    The decision to use horizontal or vertical connectors depends primarily on the seabed

    conditions and the level of fishing interaction.

    In many West African developments, there is no defined hard seabed, but rather a gradual

    change from water to soil. Additionally many of these area are not fished. Thus vertical

    connectors are extensively used. In Norway, seabed tend to be either sand or gravel and are in

    regions / water depths where fishing interaction remains a possibility. Horizontal connectors

    are favoured as they are more squat and thereby easier to protect.

    In general, vertical connectors are typicially, but not exclusively, used for very deep water

    applications water depths in excess of 500m. Horizontal connectors are used for depth less

    than this.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    19/46

    Slide 16

    BULKHEADS

    Pipe-in-Pipe End Bulkhead

    Where number of pipes terminate at the ends of pipeline bundles, pipe-in-pipe pipelines or

    caissons, a bulkhead will be provided to provide mechanical connection between the inner

    pipes and the carrier pipe. A bulkhead normally comprises a large steel connection that ties all

    of the pipes to the carrier pipe. This connection needs to be designed to accommodate the

    different axial loads within each inner pipe and the carrier pipe. The analysis is normally

    performed using finite element solid modelling with the results assessed in accordance with

    PD5500, API 6A or ASME VIII.

    This slide shows a solid finite element model of a pipe-in-pipe bulkhead. Only half of the

    assembly is modelled as it takes advantage of a symmetrical boundary along the pipe centre

    line. On the left the entire model is shown with the flange, bulkhead and adjoining sections of

    pipe. On the right only the bulkhead is shown. The colours indicate the level of stress within

    the bulkhead.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    20/46

    Slide 17

    BULKHEADS

    Bundle and Caisson Riser Bulkheads

    Unlike a pipe-in-pipe system, bundles or caisson riser systems may have a number of internal

    pipes. Examples of such cases are illustrated here. The bulkhead generally comprise a thick

    connecting plate with nibs that increase in wall thickness as the bulkhead approaches. This

    assists in reducing high stresses caused by a the stiffness discontinuity between the pipe and

    the bulkhead.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    21/46

    Slide 18

    COATINGS

    The pipeline may be coated for a number of reasons, typically:

    Submerged weight and stability

    External corrosion protection

    Insulation

    Corrosionprotection

    coating

    Concreteweight coating

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    22/46

    Slide 19

    COATINGS EXTERNAL CORROSION

    External corrosion is controlled by a combination of:

    Corrosion resistant coating

    Cathodic protection (sacrificial anodes)

    Typical corrosion resistant coatings include:

    Fusion Bonded Epoxy

    Thermoplastics polypropylene and polyethelene

    Elastomers Neoprene rubber (polychloroprene)

    Thermally Sprayed Aluminium

    Asphalt Enamel

    Wraps

    Each coating has an associated breakdown factor

    3 layer PP

    External corrosion protection is controlled via a combination of:

    Corrosion resistant coating

    Cathodic protection

    Both are necessary as coating systems are not 100% reliable and it is not practical to provide

    anodes to protect the entire bare steel pipeline over its design life.

    Typical corrosion resistant coatings include:

    Fusion Bonded Epoxy(FBE) is an epoxy based powder coating that is sprayed onto

    a rotating pipe. The name 'fusion-bond epoxy' is due to resin cross-linking and the

    application method, which is different from a conventional paint. The resin and

    hardener components in the dry powder FBE stock remain unreacted at normal

    storage conditions. At typical coating application temperatures, usually in the range

    of 180 to 250 C, the contents of the powder melt and transform to a liquid form. The

    liquid FBE film wets and flows onto the steel surface on which it is applied, and soon

    becomes a solid coating by chemical cross-linking, assisted by heat. This process is

    known as fusion bonding.

    Thermoplastics, typicallypolypropylene and polyethelene which are extruded onto a

    rotating pipe

    Elastomers Polychloroprene is normally hot-bonded to the steel using a

    vulcanization process in a steam autoclave. This process both cures the rubber and

    bonds it to the steel. Polychloroprene provides tough, durable protection for pipelines

    and risers with excellent resistance to water take-up, hydrocarbons and ozone.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    23/46

    Polychloroprene can also be applied as a field joint coating on site being cured using

    heated electrical tapes.

    Thermally Sprayed Aluminium (TSA). A sprayed coating that is suitable for

    relatively high temperatures. It has high thermal conductivity which makes it useful

    for cooling and heating spools.

    Asphalt Enamelis a plant applied durable coating based on modified bitumen

    (asphalt).

    Wraps. These are not commonly used but may be suitable for field joints.

    Selection of coating type will be based on:

    Cost

    Operating temperature each coating system is only suitable for a certain

    temperature range

    Installation method

    Thermal requirements (U-value)

    Other coatings insulation or concrete weight coating.

    Location of coating plant

    Etc

    Coating layers may be combined. The picture in this slide shows a 3 layer polypropylene

    coating which is a very common pipeline coating. It is a multilayer coating composed of three

    functional components, a high performance fusion bonded epoxy (FBE) followed by a

    copolymer adhesive and an outer layer of polypropylene which provides one of the toughest,

    most durable pipe coating solutions available.

    Each coating system has an associated breakdown factor. This provides a measure of

    protection offered to the pipeline by the coating and is thus used when assessing the cathodic

    protection requirements. The coating breakdown factor accounts for coating damage and

    water ingress. A break down factor of 0 means 100% electrically insulating whereas a break

    down factor of 1 indicates that the coating has no protective properties.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    24/46

    Slide 20

    INSULATION

    Pipeline may require insulation for flow assurance requirements.

    Pipeline insulation may be provided by:

    External wet insulating coating

    Soil

    Dry insulation, pipe-in-pipe system

    Wet insulation systems

    Solid polypropylene or polyurethane

    Syntactic coatings

    In oil production pipelines, wax deposition on the pipe wall may occur if the fluid

    temperature becomes too low, leading to a local constriction of the bore. Also, the viscosity of

    oil rises as the temperature falls, resulting in reduced flowrate. In gas production pipelines,

    hydrates (ice-like material) may form under high pressure conditions if the temperature falls

    too low and water is present in the product. Hydrates can block a pipeline and are difficult

    and costly to remove. Insulating a gas pipeline prolongs the period between shut-in and the

    fluids reaching the hydrate formation temperature and this can help to avoid the requirement

    to de-pressurise the system. An alternative to insulating a pipeline transporting wet gas is to

    continuously inject a hydrate inhibitor such as MEG into the product. Normally hydrate or

    wax survival times of 24 hours are targeted following a shutdown event.

    Pipeline may require insulation to maintain the required flow rate and prevent wax and

    hydrates forming. Flow assurance predicts the thermal insulation requirement and a coating

    system is selected to achieve this.

    Pipeline insulation may be provided by:

    External wet insulating coating.

    Soil. If the pipeline is buried the surrounding soil provides thermal insulation.

    Dry insulation, pipe-in-pipe system.

    External wet insulations generally comprise of:

    Solid polypropylene or polyurethane

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    25/46

    Syntactic coatings. Plastic or glass microspheres are mixed with the polymer to

    enhance its thermal insulation properties. Syntactic polyurethane (SPU

    polyurethane mixed with plastic or glass microspheres).

    Overall heat transfer coefficients or U-values as low as 2.5 W/m2K can be achieved using an

    external wet insulation system.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    26/46

    Slide 21

    DRY INSULATION - PIP

    Pipe-in-pipe systems comprise of two pipes with dry insulation in the annulus:

    The insulation may be:

    Polyurethane foam

    Rockwool

    More sophisticated material, such as:

    - Aerogel

    - Izoflex

    - Wacker

    Centralisers required to maintain pipe concentricity

    As a contingency water stops may be provided.

    A pipe in pipe system consists of 2 pipes one inside the other. The outer or carrier pipe

    provides a dry annulus around the inner pipe. This enables the use of dry insulation which is

    far more effective than wet insulation. Sometimes a vacuum can be provided in the annulus to

    improve the thermal insulation. Overall heat transfer coefficients or U-values as low as 0.5

    W/m2K can be achieved with pipe-in-pipe systems.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    27/46

    Slide 22

    ANODES EXTERNAL CORROSION

    External corrosion is controlled by a combination of:

    Corrosion resistant coating

    Cathodic protection (sacrificial anodes)

    Cathodic protection involves the use of galvanic sacrificial bracelet anodes attachedto the pipeline at intervals along its length.

    Anodes are electrically connected to the stee l pipeline.

    Typical galvanic anode materials include:

    Aluminium

    Zinc

    Magnesium

    External corrosion is controlled by a combination of:

    Corrosion resistant coating

    Cathodic protection (sacrificial anodes)

    External corrosion is covered within the materials module of the course and is therefore not

    covered herein.

    Corrosion is an electro-chemical process that involves the passage of electrical currents.

    Cathodic protection involves the use of galvanic sacrificial bracelet anodes attached to the

    pipeline at intervals along its length.

    Galvanic anode systems employ reactive metals as anodes that are directly electrically

    connected to the steel being protected. The difference in natural potentials between the anode

    and the steel, as indicated by their relative positions in the electro-chemical series, causes a

    positive current to flow in the electrolyte solution (surrounding water) from the anode to the

    steel. Thus, the whole surface of the steel becomes more negatively charged and becomes the

    cathode. The anode (anodic reaction) corrodes as it passes electrons to the cathode (steel

    cathodic reaction) which does not corrode.

    The metals commonly used, as sacrificial anodes are aluminium, zinc and magnesium.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    28/46

    Slide 23

    PROTECTION

    Pipelines and spools require protection from f ishing gear and dropped objects.

    Untrenched pipeline sections and spools are often provided with additional protection.This typically takes the form of:

    Concrete mats

    Concrete tunnels Protection frames

    Rockdump

    Pipelines exposed to a significant possibility of impact from dropped objects, fishing gear or

    any other type of harmful interface, must be shown to be capable of retaining their integrity

    and operability should such an event occur.

    A dropped object assessment is normally performed to assess the potential, based on the

    frequency of offshore lifts, of various dropped objects and the probability of these objects

    impacting the subsea facilities. Tie-in spools are not normally buried and are often located

    adjacent to offshore facilities, where there is an increased risk of dropped object impact.

    Surface laid pipelines and spools that are located in areas of frequent fishing activity must be

    shown to be capable of surviving interference from the various types of trawl gear that they

    are likely to encounter. DNV RP F111 gives guidance on these calculations for trawl gear

    pull-over, impact and hooking.

    Pipelines smaller than 16 inch diameter are usually trenched and buried for mechanical

    protection in the UKCS (united Kingdom Continental Shelf).

    Concrete weight coatings, applied primarily for stability, are considered to offer some impact

    protection to pipelines.

    Untrenched pipeline sections and spools are often provided with additional protection. This

    typically takes the form of:

    Flexible concrete mattresses

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    29/46

    Concrete protection tunnels

    Protection frames

    Rockdump

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    30/46

    Slide 24

    CONCRETE MATTRESSES

    Concrete mattresses typically dont absorb a great deal of energy but rather spreads the

    energy so that it doesnt act as a knife edge impact.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    31/46

    Slide 25

    PROTECTION STRUCTURES

    Concrete Tunnels

    Tie-in spools are typically protected using flexible concrete mattresses. Where this provides

    insufficient protection or the spool cannot have mattresses protection, for instance elevated

    free draining spools, protection structures may be adopted.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    32/46

    Slide 26

    ROCKDUMP

    Rock may be used for protection or to restrain the pipeline. As protection it may be used

    along the entire pipeline length or more normally at crossings and trench transitions.

    Rockdump may also be used for intermediate supports on uneven seabeds. Its use is typically

    restricted to geographic regions where rock is readily available.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    33/46

    Slide 27

    SUBSEA STRUCTURES - MANIFOLDS

    A manifold is a subsea structure housing:

    Pipework

    Valves

    Controls Equipment

    Chemical injection and distribution facilities

    Metering

    for the control and operation of the Subsea field.

    A manifold is a subsea structure that houses:

    Pipework

    Valves

    Controls equipment

    Chemical injection and distribution facilities

    Metering

    for control and operation of the Subsea field.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    34/46

    Slide 28

    MANIFOLD DESIGN

    Design Activities

    Structural analysis

    Transportation

    Installation

    Inplace

    - Hydrodynamic Loading

    - Foundations

    - Impact / Fishing Gear Interaction

    Pipe Stress Analysis

    Controls Equipment DesignCodesandStandards

    Designing a manifold for the system requirement involves:

    Structural analysis.The principal purpose of the structure is to protect the

    equipment within its envelope. As a result, the structure needs to be suitably designed

    for all functional and accidental loads that it may be exposed to throughout its design

    life.

    Pipe stress analysis.The pipework within the structure should be suitable for the

    design operating conditions as well as any functional and accidental loads that it may

    be expose to during its design life.

    Controls equipment.The controls equipment covers all electrical, hydraulic and

    chemical systems that are required for operation of the subsea field. All control

    signals are normally provided through a subsea umbilical which terminates within the

    manifold. The controls may then be distributed around the manifold, to the trees, to

    other developments, etc. through a subsea distribution unit (SDU), also housed within

    the manifold.

    Shown here is the 8 slot Callanish manifold from the Britannia Satellites development. The

    top picture shows the integrated pipework and structure model used for the design and the

    bottom picture shows the 3D model of the manifold.

    The scale of the manifold is illustrated by the diver standing at the bottom corner. The

    structure is the size of a reasonably large building approximately 15m long 6m wide

    6.5m high.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    35/46

    Slide 29

    MANIFOLD INSTALLATION

    This slide illustrates the Callanish manifold being installed it doesnt look the size of a

    building

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    36/46

    Slide 30

    TIE-IN SPOOLS

    Tie-in spools connect one part of the subsea system to another.

    Typically rigid single pipe and, if required, are designed in a configuration to

    accommodate pipeline end expansion.

    Commonly configured in a Z shape.

    Expansion

    Manifold

    Tie-in Spool

    Pipeline

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    37/46

    Slide 31

    TIE-IN SPOOL DESIGN

    Tie-in spools are typically designed using a non linear structural, piping or finite element

    package.Involves non-linear analysis for the pipe to seabed friction modelling.

    Design considerations:

    Geometry

    Pipe sizes, tolerances, corrosion allowance, etc.

    Bends

    Seabed restraint

    Protection

    Loading

    Submerged weight

    Mattresses

    Pressures & temperatures

    Environmental loading (waves and currents)

    Tie-in spools are typically designed using a non linear structural, piping or finite element

    package.

    Involves non-linear analysis for the pipe to seabed friction modelling. Non linear models are

    those which cannot be solved in a linear manner, in this instance the tie-in spool loading is

    path dependant, i.e. the spool submerged weight needs to be applied to generate the frictional

    resistance before any operational loading is applied.

    The primary design considerations include:

    Geometry The tie-in locations, self loading and pipeline expansion may all

    influence and the size and layout of the spool.

    Pipe sizes, tolerances, corrosion allowance, etc. the pipe will be modelled with

    the correct diameter and wall thickness. It is normal to model the pipe nominal wall

    thickness, however fabrication tolerances, corrosion allowances, erosion allowances

    bend thinning etc. may need to be taken into account when code checking.

    Bends spool bends may be of radius 1.5D (forged long radius elbows), 3D (pulled

    induction bends) or 5D (pulled induction bends). If there is a pigging requirement the

    bends will have to be 3D or 5D induction bends. The hot induction bending process

    induces thinning of the bend wall which should be taken into account in the analysis.

    Seabed restraint the interaction between the spool pipe and the seabed provides

    resistance to spool movement. This resistance is difficult to accurately predict and a

    conservative range is normally analysed.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    38/46

    Protection the tie-in spools must be protected against dropped objects and fishing

    gear interaction.

    Loading tie-in spool loading will be dependant on the actual tie-in spool

    configuration, but will typically involve:

    - Submerged weight of the tie-in spool and any attachments, e.g. coatings,

    anodes, flanges, etc. and including contents.

    -

    Mattresses The application of mattress protection adds weight to the pipe

    and introduces another interface between the pipe and the mattress, both of

    which act to resist spool movement.

    - Pressures & Temperatures (where applicable including pipeline

    expansion)

    -

    Environmental loading from waves and currents

    Spool design will be illustrated by a simple example.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    39/46

    Slide 32

    TIE_IN SPOOL EXAMPLE

    Diameter = 12 (323.8mm OD)

    Wall thickness = 17.5mm (Schedule 80)Material X65

    s=7850kg/m3

    SMYS=450MPa

    E=207GPa

    =0.3

    =11.710-6 oC-1

    Contents density =800kg/m3

    Pressure = 300bar

    Pipeline end expansion = 1m

    Seabed frictional resistance = 0.4 to 0.9

    Seawater Density = 1025kg/m3

    For simplicity ignore temperature, coatings, protection, tolerances.

    25m

    10m

    90o 5D Radius Bend

    The wall thickness is sufficient for pressure containment, i.e. in accordance with PD 8010

    t

    PDSMYS

    272.0 > thin walled theory 20>

    t

    D

    Wall thickness requirement t=300e5323.8/(20.72450e6)=15mm (D/t=21.6 therefore thin

    wall approximation is OK)

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    40/46

    Slide 33

    TIE-IN SPOOL EXAMPLE

    Spool

    Pipeline

    The basic steps to the analysisare:

    Set up model with nodes and

    elements.

    Add section for pipeline.

    Apply geometric and materialproperties.

    Set up seabed frictionalresistance.

    Apply loads.

    Solve.

    The basic steps to the tie-in spool analysis are:

    Set up model with nodes and elements. The tie-in spool-to-seabed contact is modelled

    using friction gap elements. These elements represent the spool-to-seabed interaction

    by supporting the pipe on discrete vertical springs, with stiffness equal to the vertical

    stiffness of the seabed. The pipe is free to rise off the seabed and, when in contact

    with the seabed, is opposed from moving laterally and axially by frictional resistance.

    As a result, the model is sub divided into a number of elements to gain an accurate

    representation of seabed frictional resistance.

    A section of the pipeline is added to remove any artificial end effects caused by over

    restraint of the spool.

    Apply geometric and material properties.

    Set up seabed frictional resistance.

    Apply loads.

    Solve.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    41/46

    Slide 34

    TIE-IN SPOOL RESULTS

    Deflected shape for the lowfriction case (=0.4)

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    42/46

    Slide 35

    TIE-IN SPOOL RESULTS BENDING MOMENT

    Low friction case (=0.4) High friction case (=0.9)

    55kNm 311.2kNm185.1kNm

    223.8kNm

    The above slide shows the distribution of bending moment around the tie-in spool.

    Greatest moment is generated in the tie-in spool bend for the high friction case, i.e. that which

    provides greatest resistance to spool movement. However, because of the greater resistance,

    bending moment drops off with distance from the bend. In the low friction case more moment

    is transferred back to the restraint on the left hand side. This could be a flange connection to,

    for example, a manifold which you wouldnt want subject to such a large bending moment.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    43/46

    Slide 36

    In the high friction case (=0.9) maximum loading occurs in the spool bend. This corresponds

    to:

    Effective axial force = -64 kN

    Bending Moment = 311.2 kNm

    Calculate the PD 8010 equivalent stress utilisation ratio

    where fd=0.96 and

    TIE-IN SPOOL RESULTS EXERCISE

    SMYSfUR

    d

    equ

    =

    222 3 ++= lhlhequ

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    44/46

    Slide 37

    TIE-IN SPOOL RESULTS

    0.824

    Of course the good thing about computer programs is that it does it for you

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    45/46

    Slide 38

    TIE-IN SPOOL RESULTS

    We will use an 11 API flange for our 12 tie-in spool. Use the Kellogs equation to determine

    whether this flange should be rated 5k (5000psi=345bar) or 10k (10,000psi=690bar).

    Note our design pressure is 300bar and a 11 API flange uses a SBX 158 gasket with a meangasket diameter of 328.9mm.

  • 7/23/2019 Lecture 3_23Apr SW0[1]

    46/46

    Slide 39

    TIE-IN SPOOL RESULTS - BEND ANGLE

    60o

    25m

    1.06460o

    0.94270o

    0.87480o

    0.82490o

    PD 8010 URBend Angle

    Someone in the last lecture asked why routing aimed at achieving 90obends on the tie-in

    spools. I have re-analysed the tie-in spool with the same leg lengths but varied the angle

    between 60oand 90

    o. The table here shows increased PD8010 utilisation ratios, and thus

    stress, at the spool bend.