Lecture 12 - Bracing

42
CVEN4102 Operations and Projects Bracing Instructor: Dr X Shen Date: 22 October 2014

description

Bracing

Transcript of Lecture 12 - Bracing

Page 1: Lecture 12 - Bracing

CVEN4102 – Operations and Projects

Bracing

Instructor: Dr X Shen

Date: 22 October 2014

Page 2: Lecture 12 - Bracing

Dr X Shen©2014

OUTLINE

• Bracing Systems

– Struts

– Rakers

– Tiebacks

• Soil Nailing

• Design of Bracing Systems

2

Page 3: Lecture 12 - Bracing

Dr X Shen©2014

Bracing Systems

• The purpose of the bracing system is to

provide support for and prevent movement

of the retaining elements which are in

direct contact with the soil

• Commonly used bracing systems

– Trench: struts or jacks

– Wider excavation: rakers and tiebacks

3

Page 4: Lecture 12 - Bracing

Dr X Shen©2014

Bracing Systems

• Example:

Timber

Shoring

4

(Courtesy: Nunnally 2011)

(Strut)

Page 5: Lecture 12 - Bracing

Dr X Shen©2014

Bracing Systems

• Wales

– Continuous horizontal members usually

employed in bracing systems

– contacting with the earth-retention system and

transfer the earth loads to the braces

• Main purpose of the wales is to permit the

braces to be placed far enough apart

5

Page 6: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

• Struts

– Most appropriate for narrow excavations

– When installing cross-lot struts, one end is

welded to the wale and the other end stressed

with plates and wedges

– Pipe sections are used for high loads or long

braces

– Cross-lot struts are not feasible for very wide

excavations

6

Page 7: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

7

(Courtesy: SkyscraperPage)

Page 8: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

8

(Courtesy: Pont Cornwall Bridge)

Page 9: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

9

(Courtesy: Mabeyhire)

Page 10: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

• Rakers

– Raker bracing is used for very wide

excavations

– The support for the rakers are installed at the

bottom of the excavation

– Berm: The earth below the raker can be

excavated on a slope to support the sheeting

10

Page 11: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

11

Raker Bracing (Courtesy: Ratay 1996)

Page 12: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

12

(Courtesy: Shorwall)

Page 13: Lecture 12 - Bracing

Dr X Shen©2014

Internal Bracing

13

(Courtesy: RCJ Construction)

Page 14: Lecture 12 - Bracing

Dr X Shen©2014

Tieback Systems

• Tiebacks or Anchors: The structural

system acts in tension and receives its

support in earth or rock

• Tiebacks eliminate obstructions in the

excavation inherent in struts or rakers

14

Page 15: Lecture 12 - Bracing

Dr X Shen©2014

Tieback Systems

• Tieback systems consist of:

– The earth or rock providing ultimate support

– A tension member or tendon transferring the

load from soil-retention system to the earth or

rock, e.g. high strength steel

– A transfer agent transferring the load from the

tendon to the soil or rock

– A stressing unit engaging the tendon and

permitting the tendon to be stressed

15

Page 16: Lecture 12 - Bracing

Dr X Shen©2014

Tieback Systems

16

(Courtesy: Ratay 1996)

Page 17: Lecture 12 - Bracing

Dr X Shen©2014

Tieback Systems

17

(Courtesy: Ground Support PLLC)

Page 18: Lecture 12 - Bracing

Dr X Shen©2014

18

(Courtesy: Geo Structures)

Page 19: Lecture 12 - Bracing

Dr X Shen©2014

Earth Anchors

• Earth anchors are usually installed at a

angle of 10 to 20 degree down from

horizontal

• Advantages: less vertical loads introduced

into the sheeting or soldier piles

• The slight depressed angle aids in

placement of the anchor and grout

19

Page 20: Lecture 12 - Bracing

Dr X Shen©2014

Earth Anchors

20

(Courtesy: Ratay 1996)

Page 21: Lecture 12 - Bracing

Dr X Shen©2014

Earth Anchors

21

Page 22: Lecture 12 - Bracing

Dr X Shen©2014

Rock Anchors

• Rock anchors are used in situations where

excavations extend through soil into rock

• The depressed angle for rock anchors is

about 45 degree

• Great care must be exercised in protecting

the rock face under the vertical members

due to the large vertical loads

22

Page 23: Lecture 12 - Bracing

Dr X Shen©2014

Rock Anchors

23

(Courtesy: Ratay 1996)

Page 24: Lecture 12 - Bracing

Dr X Shen©2014

Rock Anchors

24

Page 25: Lecture 12 - Bracing

Dr X Shen©2014

Drilling and Grouting Anchors

• Key factors for selecting the equipment:

– The type of soil to be drilled through

– The depth to the supporting stratum

– The level of groundwater

25

Page 26: Lecture 12 - Bracing

Dr X Shen©2014

Drilling and Grouting Anchors

• Drilling equipment: truck or crane mounted

drills

• Most common materials used to transfer

the loads from the tendon to the soil or

rock are concrete, grout and epoxy glue

26

Page 27: Lecture 12 - Bracing

Dr X Shen©2014

Drilling and Grouting Anchors

27

(Courtesy: vwj.org)

Page 28: Lecture 12 - Bracing

Dr X Shen©2014

28

(Courtesy: Lifetime Developments)

Page 29: Lecture 12 - Bracing

Dr X Shen©2014

How to Choose A Bracing System

• Key Factors:

– Geotechnical conditions

– Excavation geometry

– Cost and time of installation

– Possible consequence to structures or utilities

outside of the excavation due to deflections of

retaining structure

29

Page 30: Lecture 12 - Bracing

Dr X Shen©2014

Soil Nailing

• Soil nailing is an earth retention technique using grouted tension-resisting steel elements (nails) that can be designed for permanent or temporary support

• The walls are generally constructed from the top down

• An array of soil nails are installed in a grid that functions to create a stable mass of soil

30

Page 31: Lecture 12 - Bracing

Dr X Shen©2014

Soil Nailing

• Advantages:

– Rapid and economical in the right soil

– Least disruptive to excavations

• Soil nailing requires an unusual amount of

hand work, craftsmanship and

geotechnical knowledge to construct

31

Page 32: Lecture 12 - Bracing

Dr X Shen©2014

Soil Nailing

32

Page 33: Lecture 12 - Bracing

Dr X Shen©2014

Soil Nailing

33

(Courtesy: Geo Structures)

Page 34: Lecture 12 - Bracing

Dr X Shen©2014

Soil Nailing

34

(Courtesy: Gunform)

Page 35: Lecture 12 - Bracing

Dr X Shen©2014

Soil Nailing

35

(Courtesy: Earthwork)

Page 36: Lecture 12 - Bracing

Dr X Shen©2014

Earth Pressure

36

(Courtesy: OSC Shoring Manual 2011)

- Horizontal stress

- Unit weight of soil

- Earth pressure coefficient

- Lateral earth load

- Depth of wall

Page 37: Lecture 12 - Bracing

Dr X Shen©2014

Lateral Earth Pressure for Braced Wall

37

H - Exposed height of

anchored wall

D - Embedded depth

Trapezoidal Shaped Apparent Earth Pressure Distribution

Page 38: Lecture 12 - Bracing

Dr X Shen©2014

Cohesionless Soils

38

Single Braced/Tieback Walls

𝜎𝑎 - Maximum ordinate

T - Horizontal anchor

force

P - Total lateral load

𝜎𝑎 = 1.3𝑃

23

𝐻

𝑃 =1

2𝛾𝐻2𝐾𝑎

Page 39: Lecture 12 - Bracing

Dr X Shen©2014

39

Page 40: Lecture 12 - Bracing

Dr X Shen©2014

Design Procedures

1. Determine the earth pressure coefficients

2. Convert the active earth pressure above the excavation line to a trapezoidal earth pressure

3. Take moments about the tieback to calculate embedment depth D

4. Set summation of forces equal to zero in horizontal direction to calculate tieback/brace force T

40

Page 41: Lecture 12 - Bracing

Dr X Shen©2014

Example

• Draw the pressure

loading diagram with

each load indicated

41

Anchor tie rod

9 m

D

3 m

Water Table

Sand

Sand

γdry = 16.8 kN/m3

ϕ' = 32°

γsat = 18.9 kN/m3

ϕ' = 32° γwater = 9.8 kN/m3

20°

Water Table2 m

1 m

Earth Pressure Coefficient

𝐾𝑎 = 𝑡𝑎𝑛2 45 −∅′

2

𝐾𝑝 = 𝑡𝑎𝑛2 45 +∅′

2

Page 42: Lecture 12 - Bracing

Dr X Shen©2014

42

Questions?