Lecture 1-Introduction & Conceptual Bridge Design Consideration
-
Upload
nuruddeen-muhammad -
Category
Documents
-
view
26 -
download
1
description
Transcript of Lecture 1-Introduction & Conceptual Bridge Design Consideration
1 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
LECTURE 1
INTRODUCTION & CONCEPTUAL BRIDGE DESIGN
CONSIDERATION
OBJECTIVE
To provide overview of various bridge types and process involve in
selecting suitable bridge type for a design.
To identify the planning and conceptualization process of the
bridge design.
2 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
1.0 INTRODUCTION
Bridge Engineering is an exciting field of Engineering. Bridges sometimes
offer the only solution for a transportation system to cross rivers, difficult
ground conditions, or reducing conflict points in transportation system by
carrying one mode/traffic over the other (flyovers), etc.
Bridge Engineering goes beyond mere design of the physical bridge
structures, such as deck, abutments, piers and foundations. It covers all
the topics that impact on the safe operation of the bridge throughout its
serviceable life span. The past century is known for the construction of
more bridges prior to the discovery of new technology, material
availability and advancement in bridge engineering. At this stage, bridge
design has evolved from early art forms to a sophisticated science.
Every bridge design must begin with the conceptualisation of the nature
of the bridge. This will involve the planning, obtaining economical span
length for the bridge, the nature of the bridge site / environment, the
bridge loading and as well as the type of bridge to be designed for.
Concrete bridges are undoubtedly the most predominant bridge
construction types in Nigeria today, probably due to the cost and ready
availability of materials for its construction. This means that bridge
designers in the country are constantly faced with the challenges of
designing concrete bridges. And a complete bridge design process
involves series of complex stages, each involving iterative processes of
analysis, synthesis and appraisal.
3 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
1.1. Bridge and its Uses
A bridge is a route designed to provide continuous passage over a river,
valley or any obstacle. On a river, bridge allows traffic and water to flow
pass one another on different levels at the same geographical point, thus
resolving the most difficult problem a road would encounter on its route,
a bridge forms part of the road and owes its origin to the river or any
other obstacle.
Alternatively, a bridge is a continuation of a roadway/railroad, when the
latter takes off from the ground. Bridges are not only for crossing over
river but also over other types of flows, such as traffic routes (like in the
case of Flyovers), or other natural or artificial obstacle( In the case of
viaducts, i.e. bridge constructed over deep valleys which renders the
construction of embankment an expensive solution).
Other function of a bridge can be seen from it economical, social and
advancement of a community, by providing shortest effective
transportation route for commerce between communities. Also, an
aesthetically pleasing architectural bridge structure will serves as a
monumental edifice that will attract tourism, and this is a major concept
adopted in modern bridges today.
1.2. General Planning and Design Consideration
The following factors must not be ignored in bridge engineering:
4 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
The site, as the choice of bridge site affects greatly the choice of
type of bridge structure and the economic span of the bridge.
The stream/river hydrology and hydraulics.
Environmental Impact:
Additional constraints have been added to the bridge planning and
design by increasing demands for an overall ecosystem approach –
environmental impact assessment. This means that in addition to
hydrology and hydraulics, consideration must be given to the
impact of a new bridge crossing on existing vegetation, terrestrial
and aquatic habitat, recreational areas and fishery resources.
Aesthetic, historical and archaeological impacts may also require
attention.
The environmental factors: wind, temperature, humidity, rainfall,
atmospheric pollution level.
The soil characteristics
Bridge loading
In river crossing, navigational restraints, the types of vessels using
the river.
Bridge design data
bridge construction sequence
5 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
2.0 SELECTION OF BRIDGE TYPE
It is very important for every bridge designer to understand the various
bridge types and their attributes for effective selection of suitable bridge
type.
Four main factors are used in describing a bridge. By combining these
terms one may give a general description of most bridge types.
I. Span (simple, continuous, cantilever)
II. Material (stone, concrete, metal, etc.)
III. Placement of the travel surface in relation to the structure
IV. Form (beam, arch, truss, etc.).
Table 2.1 below can be useful as rough guide in selecting bridge deck type
based on economic span range.
6 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
TABLE 2.1
Span Bridge Deck Type
Up to 20m In‐situ reinforced concrete.
In‐situ prestressed post‐tensioned concrete.
Prestressed pre‐tensioned inverted T beams with in‐situ fill.
16m to 30m In‐situ reinforced concrete voided slab.
In‐situ prestressed post‐tensioned concrete voided slab.
Prestressed pre‐tensioned M and I beams with in‐situ slab.
Prestressed pre‐tensioned box beams with in‐situ topping.
Prestressed post‐tensioned beams with in‐situ slab.
Steel beams with insitu slab.
30m to 40m Prestressed pre‐tensioned Y U beams with in‐situ slab.
Prestressed pre‐tensioned box beams with in‐situ topping.
Prestressed post‐tensioned I beams with in‐situ slab.
Steel beams with in‐situ slab.
30m to 250m Box girder bridges ‐ As the span increases the construction
tends to go from 'all concrete' to 'steel box / concrete deck'
to 'all steel'.
Truss bridges ‐ for spans up to 50m they are generally less
economic than plate girders.
150m to 350m Cable stayed bridges.
350m to? Suspension bridges.
7 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
Environment (i.e. bridge site) also imposes great varying conditions on the
bridge structure, giving rise to a whole variety of bridge types and shapes.
Bridge designs differ in the way they support loads. These loads include
the weight of the bridges themselves, the weight of the material used to
build the bridges, and the weight and stresses of the vehicles crossing
them.
2.1. Bridge Types
There are basically eight common bridge designs: beam, cantilever, arch,
truss, suspension, cable-stayed, movable, and floating bridges. Each
design differs in appearance, construction methods and materials used,
and overall expense. Some designs are better for long spans. Beam
bridges typically span the shortest distances, while cable-stayed and
suspension bridges span the greatest distances.
Beam Bridges
Beam bridges represent the simplest of all bridge designs. A beam bridge
consists of a rigid horizontal member called a beam that is supported at
both ends, by vertical posts called piers or abutments. Beam bridges are
the most commonly used bridges in highway construction.
Cantilever Bridges
Cantilever bridges are a more complex version of the beam-bridge design.
In a cantilever design, a tower is built on each side of the obstacle to be
crossed, and the bridge is built outward, or cantilevered, from each
tower. The towers support the entire load of the cantilevered arms. The
8 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
arms are spaced so that a small suspended span can be inserted between
them. The cantilevered arms support the suspended span, and the
downward force of the span is absorbed by the towers.
Arch Bridges
Arch bridges are characterized by their stability. In an arch, the force of
the load is carried outward from the top to the ends of the arch, where
abutments keep the arch ends from spreading apart. Arch bridges have
been constructed of stone, brick, timber, cast iron, steel, and reinforced
concrete.
Truss Bridges
Truss bridges utilize strong, rigid frameworks that support these bridges
over a span. Trusses are created by fastening beams together in a
triangular configuration. The truss framework distributes the load of the
bridge so that each beam shares a portion of the load. Beam, cantilever,
and arch bridges may be constructed of trusses.
Suspension Bridges
Suspension bridges consist of two large, or main, cables that are hung
(suspended) from towers. The main cables of a suspension bridge drape
over two towers, with the cable ends buried in enormous concrete blocks
known as anchorages. The roadway is suspended from smaller vertical
cables that hang down from the main cables. In some cases, diagonal
cables run from the towers to the roadway and add rigidity to the
structure. The main cables support the weight of the bridge and transfer
9 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
the load to the anchorages and the towers. Suspension bridges are used
for the longest spans.
Cable-Stayed Bridges
Cable-stayed bridges represent a variation of the suspension bridge.
Cable-stayed bridges have tall towers like suspension bridges, but in a
cable-stayed bridge, the roadway is attached directly to the towers by a
series of diagonal cables. A cable-stayed bridge is constructed in much the
same way as a suspension bridge is, but without the main cables.
Movable Bridges
Movable bridges make up a class of bridge in which a portion of the
bridge moves up or swings out to provide additional clearance beneath
the bridge. Movable bridges are usually found over heavily travelled
waterways.
Floating Bridges
Floating bridges are formed by fastening together sealed, floating
containers called pontoons and placing a roadbed on top of them. A
pontoon typically contains many compartments so that if a leak occurs in
one compartment, the pontoon will not sink. Some floating bridges are
constructed using boats or other floating devices rather than pontoons.
Floating bridges were originally developed and are most widely used as
temporary structures for military operations.
10 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
Combination Bridges
Combination bridges include crossings consisting of several types of
bridges or both bridges and tunnels.
3.0 CHOICE OF BRIDGE SITE
The bridge design of necessity begins with the selection of a site. Choice
of the right location is crucial for the designing and planning of a bridge.
But above all, safety considerations that govern the technical, functional,
economic, efficiencies, and expeditiousness, and authentic requirements
are very important, it is necessary for a bridge and each of its components
to be safe, durable, reliable, and stable. This is usually checked by using
current specifications. But not all questions of durability, reliability, and
stability may be answered by analysis. Therefore in some cases it is
necessary to provide special measures such as testing the performance of
the structure and examining its behaviour under maximum loading on
site. Occasionally an unusual structural form may be subjected to wind
tunnel test. When in doubt seek a second opinion. The site for road or
rail bridge crossing will be restricted to certain reaches of the river
through constraints imposed by the alignment of the road or rail. The
choice of site must of necessity avoid costly river works.
The choice of site for a bridge must start with desk study using maps,
aerial photographs and Satellite imageries; followed by site inspection –
(reconnaissance survey). The bridge site is not chosen in isolation; it is
chosen to harmonize with the transportation-desired alignment.
Sometimes transportation alignment dictates and generally governs the
11 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
selected site. However the following information should be taken into
consideration in the choice of bridge site:
The river channel regime, that is, whether it has a wide flood plain
or whether it is incised with little or no flood plain.
The stability of channel. It is necessary to determine whether the
river is statically stable, dynamically stable or unstable. A
meandering river may during flood change its course. This is
precisely the case with the Owena River Bridge at Okitipupa in
Ondo State during the 1964 flood. The river changed its course and
the bridge was no longer perpendicular to the river but in line with
the river flow. The road embankments were completely washed
off.
The river flow pattern. It is necessary to find out whether the
channel migration is active.
Range of water levels, low and high-water levels and frequency of
occurrence.
Range of discharges, particularly flood discharges and their
frequency of occurrence.
Width of waterways, width of flood plain, meander length and
width.
Type and grade of river bed material.
Type of material composing the river bands.
Location of any rock outcrops or other hard points in the channel
boundaries that may act like bridge substructures to cause a form
of local scour.
12 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
3.1. Factors Affecting Design
Economical aspects in fixing spans of a bridge:
Let a = length of one span
n = total number of spans
L = total length of bridge
L = na ... ... (1.01)
Let F = cost of one pier
P = cost of superstructure per metre of span
(is proportional to length of span)
P = ka (k = cost coefficient)
Let Q = cost of superstructure per span
Q = Pa = ka x a
Q = ka² ... ... (1.02)
Let C = total cost of bridge excluding abutments
C = nQ+F (n-1) ... (1.03)
but n = L/a
Substituting for n in equation (1.03)
C = L/a [Q + F (L/a-1)]
Substituting for Q = ka² in equation (1.03)
C = L/a [ka² + F (L/a -1)]
= kLa + F (L/a-1) ... (1.04)
C is minimum when dc/da = 0
Differentiating equation (1.04)
dc/da = kL- FL/a² = 0 = KLa² – FL = 0
∴ F = ka²
From equation (1.02)
F = Q
The span is economical when the cost of pier equals the cost of one span
of the superstructure.
13 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
4.0 HYDRAULIC CONSIDERATIONS
4.1. Basic Hydraulic Requirements
For a bridge crossing, there are two basic hydraulic requirements that the
bridge crossing must seek to satisfy:
A suitable location and alignment from the perspective of the river
characteristic, traffic and the environment.
The capability of the bridge opening and embankments to pass the
design discharge, and to withstand severe flood or debris
conditions without compromising the serviceability and structural
integrity of the bridge or adversely affecting the environment.
4.2. Bridge Location (Hydraulic/Environmental Aspects)
Where the location of a proposed bridge is not fixed by other
considerations, the following considerations should be used as guide in
selecting the location for the bridge and the route.
I. The choice of bridge location is generally determined by economics
balanced with environmental considerations. In crossing a flood
plain, the most economical solution that combines bridge opening
and the most economical embankment height must be determined.
II. Environmental factors cannot be ignored in the selection of bridge
location. The interaction of the route and bridge location must be
carefully evaluated in order not to adversely affect a fragile
ecosystem.
III. Location of existing utilities must not be ignored especially in the oil
producing areas. The integrity and normal operation of these
utilities must be ensured.
14 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
IV. Stream characteristics and geomorphology sometimes vary within
the river under consideration for crossing sites. Stable river reaches
that do not require elaborate channel control works are preferred.
V. The alignment of the bridge and the location of the waterway
opening should fit so far as possible the existing river alignment and
the location of the principal channel. However in some situations
where the alignment route dictates, channel modification may be
necessary to provide a reasonable maintainable crossing. In the
case of meandering streams, they are sometimes modified by
channel diversion. Where streams are alternating single-and
multiple-channel reaches, single-channel locations are normally
preferable.
VI. Bridges are usually located on straight reaches of the river avoiding
sharp bends. However where the bends provide stable channels,
there is no reason why the bridge should not be located there; as it
may offer the shortest total length of the bridge. In unstable rivers,
the outer banks at bends are often particularly unstable to bank
erosion. If the bend location is adopted, the banks should be
stabilized.
VII. The hydraulic effects of existing nearby bridges and other
infrastructure should be carefully considered especially the effect
on the proposed bridge hydraulics. In the case of complex
combinations, numerical or physical hydraulic modelling is
sometimes used to evaluate current patterns.
VIII. When planning a major new bridge, overall watershed-planning
issues should be addressed through consultation with all
15 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
stakeholders involved in the basin. Future plan for Dam
developments or other works could affect the choice of the
location. Consideration should be given to factors such as climate
change and land-use change that might result in increased flows,
increased settlement yield, and morphologic changes to the river.
4.3. Design Discharge and High Water Levels
Criteria
The fixing of the design discharge and design high water ideally should be
based on the cycle cost of the project, i.e. the initial capital cost and the
operational maintenance costs (which should include costs associated
with road closures due to flooding). There has to be appropriate balance
between capital cost and operating/maintenance costs depending greatly
on the scale of the planned structure and integrity of use.
The design discharge and design high water levels depend on the flood
return period T.
Various countries fixed the flood return period for estimating design
discharge and design high water levels. The British mostly consider 100-
year return period. The U.S. guidelines (Richardson and Davis 1995)
recommend that the return period of the super-flood should be in the
order of 500 years. In the absence of reliable estimate for the return
period, a discharge equal to 1.7 times the 100-year is suggested.
16 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
Design Discharge
The design discharge corresponding to the return period T is computed
based on statistical frequency analysis of stream flow data. However the
result of the frequency analysis is not necessarily the final value of the
design discharge. It is sometimes advisable to review or adjust T-year
value as derive from frequency analysis, or use other methods of analysis,
in order to take account of the following factors:
Climate change
Land-use changes in the catchment area (past and potential future)
Possible changes to the operating rules for existing reservoir
Planned upstream or downstream reservoirs
Possible flow diversions into or out of the river
Possible influences on other riparian water users
Criteria used for existing nearby bridges
Past occurrence of catastrophic flood.
Design High Water Level
For open-water river conditions, the high water level corresponding to the
design discharge may be estimated from documented stage-discharge
relationships or from open channel hydraulics computations.
In some cases, discharge data may be scarce but a record of annual
maximum water levels (stages) may be available. In such a case, design
high water level may be derived from frequency analysis of the stage
data. If the data are for open-water floods only, the corresponding design
discharge may be estimated from hydraulic computations.
17 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
4.4. Height of Bridge
Sometimes the route profile may control the height of the bridge. But for
most bridges, especially major bridges, the elevation of the underside of
the superstructure is normally determined by the design high water level
plus appropriate freeboard or clearance. The following factors should be
taken into account when considering clearance:
The maximum expected height of waves, where not included in the
design high water level
Wind set up and storm surge in coastal waters, lakes and reservoirs,
where not included in the design high water level
Elevation of the water at light bends in high velocity streams
Projection of logs and other floating debris
Statutory navigational requirements
Consideration should also be given to the susceptibility of the
superstructure to the impact by debris and to the hydraulic forces
that would be generated.
4.5. Hydraulic Design Procedures
Before sealing the preliminary design and estimate for a new bridge and
approach roads, it is advisable to go through a systematic process for
checking the various items of hydraulic design as discussed above. Figure
4:1 sets out this process in the form of a linear flow chart. At various
stages the consequences of a choice can be assessed against previous
choices and adjusted if necessary.
18 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
FIG. 4.1: Flow chart with suggested procedure for bridge hydraulic studies
19 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
1. Initial Conception of Project
Hydraulic factors should be given priority consideration when a road
project is conceived, because they have important bearing on initial
design and route location. For example the relative cost of alternative
routes may depend on the cost of drainage structures. Also the
environment traversed by the route may greatly influence choice. For
example, one route might cross an environmentally sensitive wetland
while the other may pass through a favourable and stable environment
2. Basic Data Collection
After the choice of alternative routes, all available information pertaining
to the hydraulic study should be assembled and reviewed and
arrangements should be made for collection of additional information if
necessary.
3. Selection of Design Values
The hydraulic capacities of existing structures and channels should be
evaluated using assembled office and field information. Using hydraulic
analysis and other considerations, values may then be determined for
design discharge and high water level etc. as discussed above. Other
constants such as permissible backwater effects, clearance and statutory
navigational requirements should be examined.
4. Selection of Bridge Location and Waterway Opening
The selection of bridge location is not only controlled by hydraulic factors
but by such other factors as road alignment, slope stability, nature of
20 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
foundation materials, and assessment of economic and other
consequences of alternative choices.
5. Waterway Design Proposal
Key information on hydraulic parameters and proposed waterway
geometry should be summarized for use by the structural engineers. Such
information may include length and height requirements, critical water
levels, estimated depth of scour, arrangement of channel control works
and approaches, and other relevant data such as borings, and wave
lengths. Any hydraulic constraints on span layout and on details of piers,
etc should be noted.
6. Selection of Span Arrangement and Foundation Type
The economic span of a bridge at any location is dictated by the
foundation materials and they are governed by structural and foundation
considerations. There has to be close collaboration between the
hydraulic engineer and the structural engineer in arriving at a compromise
design if necessary. This may involve modifying the waterway design
proposal, since choice of span lengths and foundation geometry to meet
other conditions may affect allowable scour and the size of the waterway
opening. In some cases potential for debris blockage may be an
important consideration when selecting span arrangements.
Consideration should also be given to the potential effects of likely
construction works and procedures on scour, backwater and channel
processes in the general vicinity of the bridge. As a rough guideline, the
general vicinity refers to a length of at least 10 channel widths on either
side of the bridge.
21 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
7. Preliminary Drawings
General arrangement plans and profile of the river and the selected road
alignment should show sufficient length of the river to enable an
appreciation of the river’s silent features and their relationship to the
bridge. Air photo-mosaic plans or satellite imagery are most useful in this
respect: Critical water bed and subsoil levels should be indicated on the
drawings and an accompanying report.
8. Review, Approval and Adoption of Project Proposal
The complete project design proposal (which may involve alternatives)
should be checked for compliance with the basic hydraulic requirements
discussed above. Environmental Impact assessment should be carried out
at this stage, seeking approval from the appropriate authorities and
localities.
9. Performance Evaluation and Feedback
The hydraulic performance of bridges in service should be reviewed
periodically. Items to be considered include flood levels, scour problem,
damage or problems related to debris, erosion of riverbanks and channel
control works, environmental consequences and changing of river
morphology and behaviour. If changes to the catchment area are
apparent, such as increase urbanization, deforestation, mass wasting,
etc., it may be prudent to review the hydrology and hydraulics to ensure
that an acceptable level of safety and reliability persists.
22 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
5.0 LOADING CONSIDERATIONS
Bridges unlike buildings are designed to carry moving loads and are
sometime overloaded. Bridges are designed to interact with the
environment, with the river which they cross, the soil which carries them,
their self-weight, imposed dead weights and the moving live loads (see
Fig. 5:1).
FIG. 5.1: Bridge loads and load distribution
The predominant loads on bridges are gravity loads due to self weight and
that of moving traffic using the bridge and its dynamic effects. Others
loads includes wind, earthquakes, snow, temperature etc.
Bridge loading and their applications in bridge design will be
demonstrated in the subsequent lectures.
23 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
6.0 CONSTRUCTION SEQUENCE
To produce a buildable bridge, the designer must have a good
appreciation of the site conditions and of modern construction
technology. The way a bridge is built affects to a greater extent the
moments and shears generated in the structure.
The construction method assumed in the design should always be on the
drawings while any special constraints which the design would impose on
alternative methods of construction clearly stated in the drawings
6.1. Method of Construction
To a large extent, the method of construction will be dictated by the
nature of obstacle to be crossed.
Below is an example of typical bridge stages of construction
Stage 1: Piling
Stage 2: Casting of pile cap
Stage 3: Casting of abutment walls, pier columns
Stage 4: Casting of part of capping beam, plinth, laying of bearings
and precast beams
Stage 5: Laying of precast beams and precast planks
Stage 6: Casting of part of capping beam up to top of precast beam
Stage 7: Casting of In-situ concrete slab
Stage 8: Compaction of backfilling behind abutment
Stage 9: Placement of precast parapet & casting of inner kerb and
approach slab
Stage 10: Laying of walkway pipe, casting of lean concrete
Stage 11: Laying of bituminous surfacing within carriageway
Stage 12: Stone pitching around abutment
24 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
Discussion
25 | P a g e
ACEN 3 DAY TECHNICAL TRAINING ON INTRODUCTION TO THE DESIGN OF SHORT SPAN BRIDGES
REFERENCE
I. Etteh.E.I.I, (Unpublished); Introduction to Bridge Design Volume 3.
II. Parke and Hewson,(2008); ICE Manual of Bridge Engineering, Second
Edition,
III. Ryall, M.J. et al (Edited), 2000; Manual of Bridge Engineering, Institution
of Civil Engineers, UK