Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted...

21
Strengthening the transmission system in your neighbourhood Leaside to Main Infrastructure Refurbishment Project Partners in Powerful Communities N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:22 PM Page 1

Transcript of Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted...

Page 1: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Strengthening the transmission system inyour neighbourhood

Leaside to Main Infrastructure Refurbishment Project

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:22 PM Page 1

Page 2: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Meet our project team and learn more about:

• The proposed project in your community

• The study area for the project

• The planning and approvals process

• Construction methods

• Next steps and opportunities for your participation

We’re here to listen to your comments or concerns,obtain your feedback and answer your questions.

Welcome to ourPublic Information Centre

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 2

Page 3: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Partners in Powerful Communities

Transmission Lines230,000 volts - 500,000 volts

Generation Step-upTransformer Station

Pole-MountedTransformer

Distribution Lines 27,600 and 13,800 volts

Home Wiring120/240 volts

115,000 voltUnderground Cable

NetworkTransformer Station

Step-downTransformer Station

Junction

Transmission Lines115,000 volts

Hydro OneOntario Power Generation andPrivate Generation Companies

Shared

Toronto Hydro

Hydro One’s Role in DeliveringElectricity to Your Community

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 3

Page 4: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Partners in Powerful Communities

To ensure a continued, reliable supply of electricity tothe area, Hydro One will:

1. Replace two sections of existing underground 115 kilovolt (kV) cable located between:

• Leaside Transformer Station (TS) and Todmorden Junction (JCT) and;

• Lumsden JCT and Main TS

2. Replace existing overhead shield wire, used to protect the line from lightning, located between:

• Todmorden JCT and Lumsden JCT

Proposed Project

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 4

Page 5: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Project Infrastructure

Junction:The point where atransmission line switchesfrom overhead infrastructureto underground cables

Partners in Powerful Communities

Transformer Station:A station with powertransformers and otherelectrical equipmentarranged to transfer powerfrom one voltage level to another

Leaside Transformer Station

Lumsden Junction

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 5

Page 6: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Shield Wire

Partners in Powerful Communities

• Shield wire, also referred to as skywire, is used toprotect our equipment from lightning and does notcarry electricity

Shield Wire

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 6

Page 7: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Partners in Powerful Communities

• Hydro One must refurbish aging transmissioninfrastructure to ensure a continued safe and reliablesupply of power to Toronto Hydro customers in the areaand minimize the risk of future power interruptions

• The existing underground cables were installed inthe1950s and are approaching their end of life

• Replacing the existing overhead shield wire withnew fibre optic wire will enhance Hydro One’s abilityto monitor and control the transmission network

• This project will strengthen and modernize theelectricity grid that powers your city every day

Need for Leaside to Main Project

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 7

Page 8: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Leaside to Main Project Study Area

Partners in Powerful Communities

!!!

!!

!!!

!!

!!

!!

!

!!!

!!

!!

!!

!

!!!

!!

(((

(((((( ((( ((( ((( ((( (((

((((((

(((((( ((( ((( ((( ((( ((( ((( ((( ((( (((

((((((

((((((

((((((

((((((

(((

(((((( ((( ((( ((( ((( (((

((((((

(((((( ((( ((( ((( ((( ((( ((( ((( (((

((((((

((((((

((((((

((((((

(((")

")

")

")

Don River

LEASIDE BRIDGE

DON VALL

EY P

KY

MILLWOOD RD

DANFORTH AVE

MAIN TS

LEASIDE TS

LUMSDEN JCT

TODMORDEN JCT

O'CONNOR DR

PAPE AVE

WO

ODBINE AVE

COXW

ELL AVE

GERRARD ST E

ST CLAIR AVE E

BR

OA

DVI

EW A

VE

KINGSTON RD

DON

MILLS

RD

Legend

0 500250m 1:20,500 [

Roads

Class EA Study Area

") Station or Junction

Proposed Alternate Cable Route

! Existing Underground Cables (115 kV)

((( Existing Overhead Skywire

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 8

Page 9: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Partners in Powerful Communities

Leaside TS to Todmorden JCTUnderground Cable Route

!!!!!!!

!!

!!

!

!!

!!!!!!!!!!!

!

!

"

"

LEASIDE TS

TODMORDEN JCT

0 15075m1:4,000

[

" Station or Junction

! Existing Underground Cables (115 kV)

Proposed Alternate Cable Route

Water

• An alternate underground cable route option between Leaside TSand Todmorden JCT has been identified

• Both the existing and alternate routes will be evaluated through theClass Environmental Assessment process

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 9

Page 10: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Partners in Powerful Communities

Lumsden JCT to Main TSUnderground Cable Route

!!!!

!!

!!

!!

!

!!

!!

!!

!!

!!

!!

!!

!!

!!

!!

!!

!!"

"

LUMSDEN JCT

MAIN TS

0 300150m1:6,000

[" Station or Junction

! Existing Underground Cables (115 kV)

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 10

Page 11: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Partners in Powerful Communities

Todmorden JCT to Lumsden JCTShield Wire Replacement

(((

(((((( ((( ((( ((( ((( (((

((((((

((((((

((( ((( ((( ((( ((( ((( ((( ((( ((((((

((((((

((((((

((((((

(((((("

"

Don R

iver

Massey Creek

Taylor Creek

LUMSDEN JCT

TODMORDEN JCT

0 400200m1:10,000

[" Station or Junction

((( Existing Overhead Skywire

Water

• Existing shield wire will be replaced with fibre optic wire, capable ofmonitoring and controlling high voltage equipment

• Shield wire replacement is not subject to the Environmental AssessmentAct, but is included in the scope of this project

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 11

Page 12: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Environmental Features Map

Partners in Powerful Communities

"

"

"

"

Don River

Massey Creek

Taylor Creek

LEASIDE BRIDGE

MILLWOOD RD

MAIN TS

LEASIDE TS

LUMSDEN JCT

TODMORDEN JCT

Toronto and Region Conservation Authority

DO

N V

ALL

EY P

KY

DON VALL

EY P

KY

O'CONNOR DR

DANFORTH AVE

PAPE AVE

WO

ODBINE AVE

COXW

ELL AVE

LAIRD DRBAYVIEW

AVEGERRARD ST E

ST CLAIR AVE E

VICTORIA PA

RK AVE

BR

OA

DVI

EW A

VE

DON M

ILLS RD

Leaside to Main Infrastructure RefurbishmentProject - Natural Features Map

["(((

!

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 12

Page 13: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

• The replacement of underground transmission cablesis subject to the provincial Environmental AssessmentAct, and is being planned in accordance with theprocess outlined in the Class Environmental Assessment(Class EA) for Minor Transmission Facilities (1992)

• The Class EA process is an effective way of ensuringthat minor transmission projects that have apredictable range of effects are planned and carriedout in a environmentally acceptable manner

• As part of the Class EA consultation process, a draftEnvironmental Study Report (ESR) will be available fora public review and comment period once studies arecomplete

Approvals Process

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 13

Page 14: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

• If no concerns are expressed during the public reviewand comment period, a final ESR will be filed with theOntario Ministry of the Environment and ClimateChange (MOECC)

• If concerns are expressed during the review andcomment period, Hydro One will attempt to resolvethem to complete the Class EA process

• If Hydro One cannot satisfy all of the concerns raisedduring the review period, a written request (Part IIOrder) asking for a higher level of assessment(Individual Environmental Assessment) can besubmitted to the MOECC

Class Environmental Assessment

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 14

Page 15: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

What does the Class EA Process Consider?

Partners in Powerful Communities

The Class EA process will identify potential project effectsrelated to:

• Business and residential property owners

• Planned land uses and existing infrastructure

• Terrestrial and aquatic resources

• Environmentally sensitive areas

• Archaeological and heritage resources

• Recreational resources

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 15

Page 16: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Measures to reduce, prevent or mitigate potentiallyadverse environmental effects during design, constructionand operation could include:

• Controlling noise, mud, dust, traffic disturbances and other nuisance effects during construction

• Protecting cultural heritage resources

• Minimizing soil erosion and compaction

• Minimizing effects on terrestrial and aquatic resources

• Environmental management during construction and operation

Please share your comments and feedback with us!

Environmental Mitigation Measures

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 16

Page 17: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Replacing the Underground Cable

Partners in Powerful Communities

• Existing cables will be replaced with cross linkedpolyethylene (XLPE) cables, encased within concrete ducts

• Modern XLPE cables are easier to install and do notcontain insulating oil

• Duct banks will be approximately 10 feet deep by 4 feet wide (3 m x 1.2 m)

• Surface trenching and installation of concrete duct will occur in short sections

Example of trenching Cross LinkedPolyethylene Cable

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 17

Page 18: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

• Crews will manually climb towers to pull new shieldwire

• Temporary roads may be required for vehicle accessto tower structures

Replacing the Shield Wire

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 18

Page 19: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

• Some vegetation may need to be removed toundertake construction activities

• During the Class EA, we will work with interestedparties to ensure that adverse effects to vegetationand other natural features are avoided or mitigatedwhere feasible

• A Biodiversity Initiative will be implemented tocompensate for effects to the natural environment

Biodiversity

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:18 PM Page 19

Page 20: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Timeline

Partners in Powerful Communities

December 2015

January 2016

February 8 & 10,2016

Spring 2016

May/June 2016

June - August 2016

August 2016

End of 2016, contingenton the outcome of the

Class EA process

Briefing for City of Toronto elected officials

Class Environmental Assessment initiated

Public Information Centre #1Introduction to project

Community Walks in the project areas

Public Information Centre #2

Notice of Completion & Draft Environmental Study Report

available for a 45-day review period

Final Environmental Study Report filed with the Ministry of the

Environment and Climate Change

Anticipated start of construction

PU

BLIC

AN

D S

TAK

EH

OLD

ER

CO

NS

ULTA

TIO

N

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 5:00 PM Page 20

Page 21: Leaside to Main Infrastructure Refurbishment Project · Step-up Transformer Station Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Home Wiring 240 volts 115,000

Thank you for joining us at this Public Information Centre.

Please join our project mailing list and complete a commentform before you go.

To share concerns or request information call or email us at:

Telephone: 416-345-6799

Email: [email protected]

www.HydroOne.com/Projects/LeasidetoMain

Your input is important to us

Partners in Powerful Communities

N6667_Leaside to Main Panels Feb 2016_Clarington Panels 16-02-01 3:22 PM Page 21