LearningMaterial-245

download LearningMaterial-245

of 37

Transcript of LearningMaterial-245

  • 8/12/2019 LearningMaterial-245

    1/37

    Shrikant Deshpande

    Asst Manager (Safety)

    Gammon India Limited

  • 8/12/2019 LearningMaterial-245

    2/37

    Cotton godown

    Blow room / Mixing

    Carding

    Combers

    Draw frames

    Speed frames

    Ring Frame

    Auto coners

    Packing

    Warehouse

  • 8/12/2019 LearningMaterial-245

    3/37

    Cotton comes in thetextile mills in theform of compressedbales which are stored

    in the godown andreleased to the processas and when required Average weight of

    cotton bale is 200 to250 kgDimension of bale is0.75 X0.75X1.25 meter

  • 8/12/2019 LearningMaterial-245

    4/37

    Since the space islimitation so balesare stacked as high

    as roof height.Either manuallyand in few casesmechanically.

  • 8/12/2019 LearningMaterial-245

    5/37

    Accidental falling of bales

    At the time of stackingensure that the stack is inadequate equilibriummeans it should be suchthat when one bale isdisturbed for unloadingthe stack should notcollapse this is usuallyachieved by stacking themin along and across inalternate layers like bricksplaced in the wall

  • 8/12/2019 LearningMaterial-245

    6/37

    Accident by contactwith sharp edges ofthe straps on thebales.

    Fire due to improperwiring

    Smoke in the godowndue to moving of

    forklift Chance s of accidents

    by fork lift

  • 8/12/2019 LearningMaterial-245

    7/37

  • 8/12/2019 LearningMaterial-245

    8/37

    Bales are transported from godown to blowroom either manually , or by means of trolleysor by means of forklifts.

    Blow room consists of Hopper openers

    Bale breakers

    Beaters and condensers

    Feeding unit assembly

  • 8/12/2019 LearningMaterial-245

    9/37

    Through pneumatic line section lumped masscotton in the form of bales is opened , beatenup, torn apart and converted into soft, fluffy

    lap of cotton.

    Here major part is to remove

    Stalk

    Motes

    Some sand

    Dust

    Etc.

  • 8/12/2019 LearningMaterial-245

    10/37

    Transmission machine parts

    Belts

    Pulleys

    Gears

    Shafts

    Revolving

    Beaters Spiced lattices or apron

    Other moving parts

  • 8/12/2019 LearningMaterial-245

    11/37

    Generally blow room consists of units ofhopper openers , bale breakers, beaterscondensers and feeding unit assembly and

    cotton is transferred from one unit to other bypneumatic section. Using these units the lumpmass of cotton in the bales is opened , beatenup, torn apart and converted into a soft fluffy

    lap of cotton. In this process the major part ofimpurities such as bits of leaves, stalk, motessome sand , dust etc get removed from thecotton

  • 8/12/2019 LearningMaterial-245

    12/37

    Sudden opening of cotton bale results intosudden disengage of steel strap and chances ofaccident.

    Since all the machinery consists of belts , pulleys,gears, shafts and they are rotating so as per TheFactories act 1948 all the transmission machineryand other dangerous parts should be made

    inaccessible by proper guards. All gears and toothed wheels which do not

    required frequent adjustment should be fullyenclosed.

  • 8/12/2019 LearningMaterial-245

    13/37

    Suitable and safe belt shifting device andemergency stopping device should be providedto all the machinery.

    On all these machines the beater covers andother openings which provide access to thedangerous parts should be effectivelyinterlocked.

    Opening gibing access to dust chambers shouldbe so fenced that while light is admitted to thechambers access to the beater guard isprevented.

  • 8/12/2019 LearningMaterial-245

    14/37

    Chances of accidents while releasing chokesand removing dirt from under casing of beatersand such opening must be interlock effictively.

    Absence of ladder for reaching on certainpoints of machine may result into falling ofperson.

    Improper housekeeping also may lead toaccident and fire in the cotton textile industry.

  • 8/12/2019 LearningMaterial-245

    15/37

    Carding Machine consists of

    Cylinder

    Doffer

    Licker in

    Calendar roll nip

    Here cotton comes in the form of lap and leavesthe machine as sliver.

    Sliver rope is about an inch in diameter and

    made up of clean while fiber.

  • 8/12/2019 LearningMaterial-245

    16/37

    Accident due to cylinder

    Interlock guard to be provided to the stripping

    door on cylinder. Door cannot be open withoutcylinder stopping and cylinder can not be startwithout securely closing the stripping door.

  • 8/12/2019 LearningMaterial-245

    17/37

    Accident in licker in

    Access to licker in securely closed by panels

    Gauging clearance Clearance between cylinder, licker in or doffer or flat

    is done by using feeler gauges . AT the time of thisactivity following steps to be followed in order to

    prevent accident.

  • 8/12/2019 LearningMaterial-245

    18/37

    1) Stop the machine before using filler gauge andshould never be done when parts of machine is inmotion.

    2) Operator should not remove fluff, lint, frommoving parts of machine specially fromcylinder, licker in doffer and flat.

  • 8/12/2019 LearningMaterial-245

    19/37

    In this process cotton in

    the form of ribbon lapsis combed in short

    length of about 6mmby a series of needlesplaced on revolvingcylinders. . The fiberbecome longer,straighter and brighteras compare to those in

    card sliver.

  • 8/12/2019 LearningMaterial-245

    20/37

    To provide guard to the unguardedtransmission parts and other gears

    To provide interlock arrangement in order to

    avoid contact with cylinder needles. To provide interlock guard to the nipper knife

    in order to avoid dropping of nipper knife.

  • 8/12/2019 LearningMaterial-245

    21/37

    Sliver from comber andcarding machine arepassed through series of

    rollers which draw thesliver and render thefiber more parallel andblending and mixing

    also accomplished.

  • 8/12/2019 LearningMaterial-245

    22/37

    Head stock gears.

    Provide interlock arrangement to head stockgears such that machine can not be started

    without cover and covers can not be liftedwithout stopping the machine.

    Calendar gears to be guarded properly.

    Avoid jam to calendar rollers.

  • 8/12/2019 LearningMaterial-245

    23/37

    Sliver is converted into roving in this process,sliver through two sets of rollers into a thicksoft roving and also impart strength to it bytwisting before the roving is wounded on the

    bobbins.

  • 8/12/2019 LearningMaterial-245

    24/37

    A) Gears.

    There are large numbers gears which needsfencing on these machine

    Lifter rack and pinion should be well guardedso that access to the nip is prevented bothwhen rack lifts and fall.

    B) Flyers Injury by hitting the flyer at the time of

    removing fluff and cleaning work.

    Inter locking to be provided at the rotating

    zone of flyers.

  • 8/12/2019 LearningMaterial-245

    25/37

    Roving converted into yarn in this process,

  • 8/12/2019 LearningMaterial-245

    26/37

    Accident while piecing broken ends, operatorsusually hold the bobbin at its bottom endbetween their left hand fingers to stop it.

    Chances of accidents due to sharp edges onbobbin come in contact with fingers causesaccident.

    1) Provide finger caps

    2) Educate workers to hold the runningbobbins

    3) Provide stopping mechanism such as breaks

    for individual spindles.

  • 8/12/2019 LearningMaterial-245

    27/37

    Falling of bobbins from creel tops: - Whilecreeling average Indian workers may not reachto the bobbin holder easily and they tstep on

    the railing which expose them to the serioushazards.

    Accidents at the time of handling of Knife.

    To remove fluff or waste yarn on rollers operators do

    use knife. And improper use of knife result intoserious cut injury to fingers.

  • 8/12/2019 LearningMaterial-245

    28/37

    Sharp edges of damaged cans Cutting of bale hoop iron band by chisel and

    hammer may results into injury, proper baleopener should be used.

    Maximum material is handled in the boxes andon the trolley so remove jams on the wheels ofthe trolley on regular intervals to avoid falling

    of trolley and material boxes to be kept inproper manner.

    Wheels of trolleys provided with breaks inorder to blocked them at the time of loading

    and unloading.

  • 8/12/2019 LearningMaterial-245

    29/37

    Over loading of trolleys , boxes and treys to beavoided.

    material to be stored in proper and allocated

    position.

  • 8/12/2019 LearningMaterial-245

    30/37

    Nails from bales

    Hoop iron strip

    Ring travelers

    Bobbins on the floor may create hazard andperson may fall

    Damaged floor may fall trolleys and cans at thetime of material shifting

    Cans trolleys kept haphazardly on the floor sochances of striking against these objects.

  • 8/12/2019 LearningMaterial-245

    31/37

    Maintain good housekeeping

    Regular maintenance of electrical equipmentsand periodic checkup is necessary

    Risk of overheating of bearings can reduced byproviding efficient lubrication.

    Day to day monitoring and maintenance of all

    moving parts Smoking to be prohibited

    Electrical equipments must comply IndianStandard and maintained in safe working

    condition

  • 8/12/2019 LearningMaterial-245

    32/37

    Metal detection and diversion system at blowroom

    CO2 Flooding system at beaters and carding

    section Provision fire doors to maintain sepretion of

    two departments

    Fire extinguishers Fire hydrant system

    Smoke detection and alarm system

  • 8/12/2019 LearningMaterial-245

    33/37

    Noise

    Cotton dust

    Exposure to chemicals

    Exposure to UV rays

    Working in Humid atmosphere

  • 8/12/2019 LearningMaterial-245

    34/37

    Pre employment and periodical mediaclcheckup

    Colour blindness checkup

    Noise induced hearing loss Lung function test

  • 8/12/2019 LearningMaterial-245

    35/37

    Ear plug

    Nose mask

    Safety shoes

    Goggles for specific jobs

    Hand gloves

    Etc

  • 8/12/2019 LearningMaterial-245

    36/37

    Safety policy

    Recruitment of safety officer

    Safety committee

    Accident reporting investigation and analysissystem

    Safety audit , inspection and followup for

    action taken. Identification of unsafe acts and conditions

    Safety training and education

    Safety campaign etc..

  • 8/12/2019 LearningMaterial-245

    37/37

    Thank you