Learning legacy - Independentlearninglegacy.independent.gov.uk/.../32-project-brief-ppm.pdf · 2012...
Transcript of Learning legacy - Independentlearninglegacy.independent.gov.uk/.../32-project-brief-ppm.pdf · 2012...
Learning legacyLessons learned from the London 2012 Games construction project
Project BriefChampion Products are examples of tools and formats used by the Olympic Delivery Authority (ODA) in executing its programme. The ODA is publishing these as part of its Learning Legacy in the anticipation that they may be of use to future projects seeking best practice examples of tools and templates that have been used successfully on a large, complex programme.
Purpose of the document, description and how it was usedThe Project Brief was a high level document that outlined the objectives and operational requirements for each project. As the project progressed through the different Royal Institute of British Architects (RIBA) stages of the design process, the brief was developed to form the ‘initial brief’, the ‘design brief’ and the ‘project brief’.
The initial brief was used to set out the initial ODA requirements of the project and informed the development of the design through to the RIBA design stages A/B. It captured the data from the Project Initiation Document and the London Organising Committee of the Olympic Games and Paralympic Games (LOCOG) Venue Requirements and described what the Design team were required to design.
The design brief defined what the next phase of the project should deliver and informed the RIBA stages C/D. It focused on the technical requirements and the measurable criteria defined during design development.
Following completion of the RIBA stages C/D, the project brief was produced which defined the final client’s requirements and refined any inputs and design development from the previous design stages.
At each stage, the briefs were distributed to key project stakeholders and reviewed at a formal client review which ensured that the brief was clear and captured all project requirements.
Benefit to future projectsThis champion product could be used as an example of how to progressively define scope and requirements for large-scale projects.
© 2011 Olympic Delivery Authority. The official Emblems of the London 2012 Games are © London Organising Committee of the Olympic Games and Paralympic Games Limited (LOCOG) 2007. All rights reserved.
The construction of the venues and infrastructure of the London 2012 Games is funded by the National Lottery through the Olympic Lottery Distributor, the Department for Culture, Media and Sport, the Mayor of London and the London Development Agency.
For more information visit: london2012.com/learninglegacy Published October 2011ODA 2011/009
3.1c. 1
FINAL DRAFT NM 240107
Brief Management Introduction This section of the Project Execution Plan sets out the strategy for the management of the remaining Briefs for the Olympic and Paralympic Games and their subsequent Legacy. Authored at end of January 2007 this document marks a point in time when the briefs for the Main Olympic and Paralympic Stadium and the Aquatics Centre have been issued. These briefs and the documentation defined, form the basis for this analysis. The Contents of the PEP The PEP:
Defines the requirements for the briefs with an emphasis on clarity
Reviews the principle stakeholders who contribute to the briefing process
Identifies the reference documentation that informs the briefs
Explains the briefing material that develops from it
Explains of the evolution of the brief through the Project Approvals Process
Outlines the skeleton of a briefing template to support the briefing of the remaining projects
Sets out the next steps for creating briefs that produce consistent delivery by the supply chain to achieve Programme and Project Objectives
Describes how the Brief Coordinator and Brief Management will support the Project Sponsors to ensure that the briefs meet the 2012 Construction Commitments
The Purpose of the Briefs: The briefing process provides the instrument to build alignment across the project. The Briefs allow the ODA to:
Capture and align stakeholder criteria
Define requirements and compliance for fitness for purpose
Define design expectations without being prescriptive
Inform the project team on strategic Assurances and Aspirations
1 .1. 2
For the Delivery Partner and supply chain, the Briefs:
Describe and record the approved project scope and requirements
Define measurable and deliverable criteria
Define the objectives, criteria and specific details to advance the design development and therefore the project delivery
The Brief Management PEP should be read in conjunction with the other PEP’s but specifically the PEP on Project Approvals. Background In a joint statement in the document 2012 Construction Commitments by the Strategic Forum for Construction and its 2012 Task Group, states:
DESIGN QUALITY
• The client will produce a clear brief
before design commences
• Project briefs will specify
performance criteria to encourage
innovation in order to deliver cost-
effective solutions, taking advantage
of opportunities for standardisation,
prefabrication, off-site manufacture
and adopting modern logistics
principles
Figure 1 The 2012 Construction Commitments CLM will support the Project Sponsors to coordinate all future outgoing briefs to meet this commitment. The Stakeholders: The Principal Contributors to the Brief Introduction
Brief Management
3.1c. 3
To understand the drivers of the various briefs it is important to understand who currently contributes to the briefing process. The ODA’s Internal Stakeholders:
Directors
Project Sponsors
Group Heads of cross cutting themes
Sustainability,
Security
Legacy,
Health and safety,
Inclusion
Planning
Utilities
etc As the projects progress, further detailed briefing requirements will be developed from ODA stakeholders on the projects. As the ODA’s policies and procedures are agreed they will be integrated into the briefs giving the performance criteria required to satisfy the 2012 Construction Commitments above. These policies are being jointly developed by the ODA and CLM to ensure their integration is in alignment. External Stakeholders:
External stakeholders include:
LOCOG who are responsible for running the Games their external stakeholders include:
The International Olympic Committee (IOC)
The British Olympic Committee (BOC)
The British Paralympic Association (BPA),
International (IF’s) and National Sporting Federations (NF’s) Other external stakeholders include:
The DFES
The GLA and associated London Boroughs.
Leisure consultants, supporting the ODA with Venue business plans.
Community groups The Reference Documents Introduction
1 .1. 4
The following documents are referenced in preparing the Initial Briefs. Each has been reviewed as part of this PEP, each is introduced, its purpose defined and its contents outlined.
The 2012 Candidate File
The Project Initiation Documents (PID) for the Stadium and Aquatics Centre
The Initial Briefs for the Aquatic Centre for the Stadium and Aquatics Centre
The LOCOG Location Venue Requirements (LVR) for the Stadium and Aquatics Centre
The ODA’s PAO Business Case Templates V1 for the Stadium and Aquatics Centre
PMO’s Guide to Projects The Candidate File Introduction The Candidate File was compiled in 2004 for submission to the IOC as part of London’s bid for the 2012 Olympic and Paralympic Games. It was prepared by several stakeholders including the LDA, the GLA and supporting contributors Purpose To convince the IOC that London should host the 2012 Olympic and Paralympic Games. Contents The Candidate File incorporates:
Schematic plans for the venues
Schedules of accommodation detailing capacities
Venue schedules for the Games.
General data supporting London’s infrastructural capabilities to host the Games. The Candidate File is regarded as the base brief for each of the venues. Any deviations from it need to be agreed with the IOC and with the International Sporting Federations through change control systems established by LOCOG, the document is version controlled. The Project Initiation Document (PID) Introduction
The PID is the first of the business case documents set out in the ODA’s Project Assurance Offices (PAO’s) suite of Project Approval documents which are further defined in the Project Approvals section of the PEP; it is prepared and owned by the ODA’s Project Sponsor.
Purpose The PID defines the:
Brief Management
3.1c. 5
Overall Objectives of the project
Rationale for undertaking the project
End state which defines the state of the project in legacy condition. Contents The PID document is brief in content and set out in a template format, its headings include:
Inclusions/exclusions
Assumptions
Constraints
Milestones/deliverables
Resources
Stakeholders/working groups
Major risks
Dependencies/interfaces
Financial
d off by the ement Board
enables the
Statement of need
Headline definition
of requirements- 2012 Candidate File
- IOC Technical File
-Sports Federation Req’ts
-LVR’s if they exist
PID
Figure 2 The Inputs to the Project Initiation Document. The LOCOG Location Venue Requirements (LVR) Introduction The LVR sets out LOCOG’S technical requirements for each of the Venues in Olympic and Paralympic Mode, it is prepared and owned by LOCOG’s LVR Manager. Purpose
1 .1. 6
The LVR collates data from the Candidate File, the IOC Technical File, International and National Sporting Federation requirements and those of the BPA for the venue together with relevant design standards and guidelines. Contents The document incorporates:
Visions and Objectives
Background information
A schedule of accommodation
A scope of work with Specific and Functional requirements
Schedules of services and utilities
An Overview of Operations
Appendices including venue plans in Games Mode Elements of the LVR text are repeated in the Initial Brief outlined below. The Initial Brief Introduction The Initial Brief is generated and owned by the ODA’s Project Sponsor and the Sponsor’s masterplanning team. It captures the data from the PID and LOCOG’S LVR outlined above. Purpose The Initial Brief sets out the ODA’s initial requirements for the project, it informs RIBA stages A/B of the design process it also aligns with the project process. Contents The Initial Brief contains:
Visions Aspirations and Objectives for the project
Stakeholder requirements
Site Information
Requirements of the Olympic and Paralympics conversion.
Base case legacy building requirements and business case
Accommodation schedule
Technical requirements
Building engineering
Accessibility and inclusive design
Sustainability requirements
Health and safety requirements
Security requirements
Budget requirements
Appendices with plans and additional supporting data
Brief Management
3.1c. 7
This Initial Brief is version controlled and issued through the ODA’s own document management systems. The Evolution of the Briefs through the Project Approval Process Introduction At the time of writing the current project phase has delivered projects through the PID and to the Initial Brief stage. This PEP identifies three distinct briefing stages through which the briefs evolve over the lifetime of the project. These are also aligned with the project approvals process outlined below. Figure 3 explains the relationship between the Project Approval Process and the evolution the three briefs through the project lifecycle. The interface will maintain momentum of the project through alignment with the approvals process and concise briefing appropriate to the project phase
Initial Brief Design Brief Project BriefProject Initiation
Document (PID)
Brief development
Figure 3 The Brief Process Aligned with the Approval Process The Initial Brief Introduction
1 .1. 8
For the remaining projects it is proposed that the Initial Brief becomes a more streamlined document with less but more concise text. Purpose The Initial Brief informs the RIBA stages A/B design stage and as can be seen from figure 1 provides all the stakeholders and contributors with a description of the project requirements as far as they are defined at this stage. The initial brief should be able to define the project concisely with sufficient detail to enable design team responses which can be appraised from the outset to assess alignment with the core principles of the project and the criteria defined:
Budget compliance
Cross Cutting themes
Sustainability principles
Legacy
Inclusion etc
A clear and demonstrated understanding of the 2012 Commitments
Technical venue requirements
Initial Brief
ODA
LOCOG
PID
Candidate File
ODA Headline Inputs
•Aspirations
•Legacy
•Sustainability
•Business Case
•Master planning Team
• Other stakeholders
•GLA
•DFES
•Boroughs
•Community
LVR,
IOC,
IF’s
NF’s
Figure 4 Inputs to the Initial Brief Contents The contents will be defined with the ODA project Sponsor to a standard template refined from the contents of the current Initial Brief. Indicative contents:
Brief Management
3.1c. 9
Outputs The Initial Brief and the responses to it should enable the ODA and CLM to understand any issues arising from the brief which cannot be satisfied or variances that should be incorporated into the next phase of the project definition. Ownership The Initial Brief will be owned by and be the responsibility of the ODA Project Sponsor. It will be generated by the Master Planning team. Design Brief Introduction The Design Brief should validate the design teams approach from the stage A/B submissions if in compliance and integrate any amendments which the previous project phases have identified as non compliant. Purpose The Design Brief should inform the next design stage; RIBA stages C/D. Its contents will be more focused on compliance with the technical requirements and the measurable criteria defined during design development by the Project Sponsor and the design team and the Delivery Partner. It will ensure alignment with the ODA’s core themes, the project requirements and define what the next phase should deliver. Refer to Figure 2 for its alignment with the Approval Process. Contents The contents of the Design Brief will be defined in partnership with the ODA in order to create a standard template for the remaining projects. Indicative contents:
Design Statements and technical reports from the members of the consultant team demonstrating alignment with the project requirements
The drawings delivered and developed through stages A/B
Specifications
Schedules of Accommodation
Fire and life safety information
Demonstration of the integration of the ODA’s cross cutting themes
Alignment with the 2012 commitments
Cost reports and verification of alignment with cost targets, value and risk management
Landscaping
Construction approach / methodology The inputs to the Design Brief are shown in figure 5.
1 .1. 10
Design Brief
ODA and
Delivery Partner Detail:
•Logistics
•Programme
•Sustainability
•Legacy
•Budget
•Procurement
•LOCOG
Design Stage A/D
Inputs
Figure 5. Inputs to the Design Brief Ownership The Design Brief will be owned and led by the ODA’s Project Sponsor and generated by the appointed design team. Outputs The Design Brief should contribute to the approval process supporting the reviews associated with the Outline Business case and the Full Business Case (OBC and FBC).Completion of Stages C/D will enable the production of the Project Brief at the end of Stage D. The Project Brief Introduction The last step in the evolution of the briefing process is the Project Brief. Purpose The Project Brief should finally define the Client’s Requirements at the end of Design Stage D and refine any inputs and design development from the Design Brief and previous design stages. Contents The contents will be defined with the ODA project Sponsor to a standard template. Indicative contents:
Any inputs arising from OBC and FBC procurement process
The drawings delivered and developed through stages A/D
Brief Management
3.1c. 11
Specifications
Design Statements from the members of the consultant team demonstrating alignment with the defined project criteria / requirements
Calculations
Schedules of Accommodation
Fire and life safety information
Demonstration of the integration of the ODA’s cross cutting themes
Demonstration of alignment with the 2012 commitments
Reports and verification of alignment with cost targets, cross cutting themes e.g. sustainability, inclusion
Life cycle costs
Construction approach / methodology
Landscaping
Other logistical site wide issues
Project Briefs
ODA and Delivery
Partner Detail:
Logistics
Programme
Sustainability
Legacy
Budget
Procurement
LOCOG
Design Stage D
Inputs
Figure 6. Inputs to the Project Brief Outputs By this point in the project cycle, the Project Brief will have developed to capture all the client’s requirements. It should inform any subsequent design stages. Ownership The Project Brief will be owned by the Project Sponsor and be generated by the design team.
1 .1. 12
Next Steps and Verification of the Project Brief Introduction Briefs will be issued at different stages in the project cycle, dependant upon the procurement route, but at whatever stage this release of information occurs the briefs should integrate enough information to meet the 2012 Commitments. The Contractor’s Proposal Procurement through the Design Build process will require the contractor to confirm compliance in the Contractor’s Proposal. The ODA’s Project Sponsor and Delivery team should define the deliverables required from the contractor at this point. The Contractor’s Proposals should confirm that the project to be delivered is in accordance with all the requirements set out in the Project Brief and issued documentation to that date. Contents The indicative contents of the Contractor’s Proposal should be defined by the project team as required deliverables. Indicative contents:
Programme
Cost Analysis
Construction methodologies
Organisational structures
H&S Drawings and other documentation will include:
Developed drawings
Schedules of Accommodation
Services Provision
Other schedules
Lifecycle costings
Submissions will be reviewed by the ODA and the CLM project team, the design team and brief coordinator to ensure compliance. If the design team has been novated the Contractor’s Proposal will be reviewed by the ODA’s technical advisors. Change Control in the Briefing Process The various stages of the brief will be managed through CLM document management version control protocols with tracked changes. CLM’s PMP on Design Management Procedures and Policies presents CLM’s strategy for the control and management of the design teams and information management.
Brief Management
3.1c. 13
CLM: Brief Management Implementation and Objectives Introduction The PEP proposes that the CLM Brief Coordinator manages future briefs into one consolidated data source; this interface is schematically shown in figure 7.
BRIEF CO-ORDINATION
CLM
PID and Business
Case PAO Documents
Budget Brief
ODA
ODA APPROVAL
Security
ODA Brief
Aspiration Vision
2012 Candidate File
LOCOG
Venue Requirements
Environmental
Operation
Sustainability
Legacy
f
Formal Baseline Staged Brief
Issued to Designers
OR Contractors
Sporting
Federations
IOC Technical
File
Accessibility
Policies Procedures Design
Standards etc
Figure 7. The elements of the brief which require coordination. The Brief Coordinator will proactively work with the Project Sponsor and teams to integrate the “cross team” texts concerning sustainability, security, area schedules, services requirements glossaries etc to create a single source, “one time” data collection point. This streamlined approach will integrate the data and removes the risk of redundant material being in the project realm in different locations. It is important that each stakeholder still manages and owns their component of the brief and develops it as necessary, complying with the agreed protocols. LOCOG will retain their own base “stand alone brief” which informs its own procurement paths, the key components of the LVR will be incorporated into the Briefs at the various stages. What the Brief Coordinator will do.
1 .1. 14
The Brief Coordinator will manage and coordinate the briefs to:
Support the Project Sponsor and Design Group
Add clarity, making them a single data source
Build the alignment of briefs for the remaining projects
Support the business case and the ODA Approval Process
Deliver Assurance and expedite the project process
Incorporate lessons learned from the briefs prepared to date
Ensure compliance with the 2012 commitments By:
Working collaboratively with LOCOG, the ODA’s Project Assurance Group Project and the ODA’s Project Sponsors and Design Group ,
Coordinating input from the ODA’s Project Sponsors and Stakeholders
Coordinating input from the CLM teams
Coordinating input from the Design teams
Coordinating and developing standard outline / content templates to capture input from assurance and the teams defined above
Maintaining momentum through the Project Approval Process through the delivery cycle
Achieving target dates for the delivery of the briefs Figure 8 graphically represents the briefing sequence and its relationship with the RIBA stages A-D. Clearly the stage at which the brief passes to the contractor will depend upon the procurement route chosen, the briefs should therefore be able to “standalone” and define the project at any given stage. The ODA and CLM are currently defining the best procurement paths for the various projects.
Brief Management
3.1c. 15
Candidate File
ODA SPONSOR
Project Initiation
Document PID
LOCOG BRIEFING
Location Venue Requirements
LVR
DESIGN BRIEF
From Various Stakeholders
Procurement Options
Dependant upon route
INITIAL BRIEF
IOC Technical
Manual
ODA /
Stakeholder / Sponsor
Sign off
OPRG
ODA
APPROVALS PROCESS
SOC – Strategic Outline Case
OBC – Outline Business Case
FBC – Full Business Case
with Tender Figures
Sporting
Federations
Briefing Material
PROJECT BRIEF
RIBA
C
RIBA
A/B
RIBA
D
OD
A A
PP
RO
VA
LS
PR
OC
ES
S
PR
OC
UR
EM
EN
T O
PT
ION
S / C
ON
TR
OLS
CL
M B
RIE
F C
OO
RD
INA
TIO
N
OD
A O
PR
G S
TA
KE
HO
LD
ER
SIG
N O
FF
Figure 8 The Briefing Sequence. Brief Coordinator Interfaces During February The Brief Coordinator will implement a series of individual and joint meetings with: the ODA’s design team leaders, the ODA’s appointed Design Advisor, Project Sponsors, LOCOG team members and CLM discipline heads to agree this integrated briefing approach which can then be adopted for the remaining projects. The Brief Coordinator will work with the ODA during February to determine the refinements to the contents of the briefs and introduce the contributors to the process further defining the timeframes and milestones for brief development in alignment with the various project programmes. This work will support the design procurement processes defined elsewhere in the CLM’s Procurement PEP and the competition briefing process for the Handball, Velopark projects and for other temporary and permanent buildings. Clarity of the briefing process at the outset will speed the competition and procurement process and improve the post evaluation project start up at Stage C. The coordinated brief will build cross team / cross project communication and speed the integration of the various contributing team members. Measurement of Success. The success of the Brief Management Process can be measured by:
1 .1. 16
Delivery of the briefs in accordance with the agreed project milestones
Delivering clear and concise briefs which meet the ODA’s 2012 commitments at each project milestone
Assessing the integration of team input
The creation of a coordinated “one time” data source which can standalone at each project phase
Summary and Conclusion In order for the ODA to meet its commitments outlined and signed up to in the document “2012 Construction Commitments” to design quality, clear briefing is essential. The Brief Management PEP sets out the current brief making process and the next steps in the Briefing Process which will define the remaining projects through the PAO’s Approvals Cycle. The PEP describes a coordinated process to maintain project momentum and compliance through the approvals process. Structured and coordinated Brief Management will achieve the ODA’s committed targets. It will ensure consistent delivery by the supply chain to meet the objectives of the Programme and the Project. Reference Documents
PMO Guide to Projects
Project Initiation Document
LOCOG’s Stadium LVR
The ODA’s Initial Brief The “Living Stadium”
LOCOG’s Stadium LVR
The ODA’s Initial Brief Aquatics Centre
CLM’s Programme Management Plan Project Approvals
Creating Excellent Buildings A Client Guide First Edition 2003
Good Buildings Need Good Briefing RIBA Publications