LEAN ENERGYDr Johan Wollin
20th June 2018
Volvo Construction Equipment
Part of Volvo Group
14000 employees
6.7 B Euro company
Three construction brands in the Volvo Group
Joint venture
Terex Trucks
Manufacturer of
rigid and articulated
trucks
Volvo
Leading premium brand offering a wide
range of construction equipment
SDLG
Leading Chinese
construction brand
Industrial footprint consisting of 14 plants
TO BECOME THE WORLD LEADER IN SUSTAINABLE TRANSPORT SOLUTIONS
We are committed to be a climate leader within the global construction equipment industry
1. Increased
machine fuel
efficiency
5. Host the
Construction
Climate Challenge
3. Industry
standardization
leadership
6. Production site
energy efficiency
2. Advanced
technology
development
7. Supply chain
energy efficiency
4. Eco Operator
training & Customer
site optimization
Starting at the base… Step 1 – Energy conservation (never ends…)
Renewable energy
Energy Efficiency
Energy Conservation
What does that mean?
Energy
conservationEnergy efficiency
Renewable
energy
• Turn off non-essencial
equipment
• Turn on non-essencial
equipment later and turn it
off earlier
• Use existing equipment in a
smarter way
• Use right sized equipment
• Invest in energy recovery
• Invest in more energy
efficient equipment
• Buy green electricity
• Switch energy
sources away from
CO2 emitting ones
• Investigate own
energy production
A culture building strategy
Low cost
2013-2015
Idle electricity
2016+
Production energy
Renewable
energy
Self funded
Culture and behavior
Why start with idle electricity?
Reduce cost for future improvements
Project management using ”Idle electricity A3”
How to measure success?
Target: Reduce relative idle electricity to less than 15% before end of 2015
Production electricity (kWh’s during 10 production hours)
Idle electricity (kWh’s during 10 idle hours)Relative idle
electricity % =
Clear KPI with stretched target
Able to compare plants
Re-calculate back to kWh
Need a measurement system (internal or external)
Pareto thinking to prioritize and focusEnergy intensity of 0.54%
Energy cost per unit reduced 24%
Idle electricity use reduced by > 50%
Waste elimination without investment using Lean tools
• Waste hunts
– Night walks with management
– Reinforced end of shift routines
– Energy treasure hunts (2-3 days workshops)
• Timers, motion sensors and twilight sensors
• Building control system for light and ventilation
• Etc. etc.
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
kW
h
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
kW
hResults – Before vs. After
June w26 2015 (before)
November w48 2015 (after)
Monday Tuesday Wednesday Thursday Friday Saturday Sunday Monday
Step 2 – Energy efficiency
Renewable energy
Energy Efficiency
Energy Conservation
We have saved 41 GWh’s of energy
Target of 40 GWh’s 2014 to 2020 is equivalent to 2% annual reduction
Third party audit by Ecofys / Navigant
WWF A3
41 GWh
Step 3 – Renewable energy
Renewable energy
Energy Efficiency
Energy Conservation
Road map examples and result
Non-energy benefits (NEB)
MOTIVATION
COSTQUALITY
PRODUCTIVITY / RELIABILITY
SAFETY
Less working
on height with
LED lights due
to their longer
life expectancy
Optimized
machining to
reduce time
and same time
improve
surface quality
Detailed
understanding
of the
production
process enable
optimization of
cycle times
Running oil
separator only
when
machining
increase filter
chance
frequency
Celebrating
achievements
together and
motivate for
continuous
improvements
in other areas
Non-energy benefits (NEB)
NEB = 2.5 x Energy cost reduction
Hall et. al. 2003
Summary
• Total electricity use reduced by > 20 %
• Idle electricity use reduced by > 50 %
• 5 M Euro cost avoidance 2017 compared to 2014
• Total energy savings of 41 GWh
• Many “Non-Energy Benefits” (NEB’s)
• Energy cost per unit reduced by 24%
Learning
• Just do it!
• Push responsibility out on the shop floor and harness ideas
• Communicate in an easy to understand format (A3)
• Get sense of urgency by external driver (WWF)
• Don’t invest until low cost improvements have been attempted
• Share success stories and best practice widely
Questions?