Lean Construction Leadership_David Trent
Transcript of Lean Construction Leadership_David Trent
-
8/2/2019 Lean Construction Leadership_David Trent
1/26
Lean Construction Leadership
David Trent
Director - Project Controls
-
8/2/2019 Lean Construction Leadership_David Trent
2/26
Words to remember
Albert Schweitzer Example is not the main thing in influencing others, it is the
only thing.
General George S. Patton:
Never tell people how to do things. Tell them what to doand they will surprise you with their ingenuity.
2
-
8/2/2019 Lean Construction Leadership_David Trent
3/26
Traditional Project Leadership
Value Stream Managers-Project Managers
Supervisors Lead Hands
Team Leaders-Lead Hands
Direct Workers
3
-
8/2/2019 Lean Construction Leadership_David Trent
4/26
Lean Leadership
Value Stream Managers-Project Managers
Direct Workers
Team Leaders-Lead Hands
Supervisors- Lead Hands
4
-
8/2/2019 Lean Construction Leadership_David Trent
5/26
The Human Condition
Four things contribute to a project:
Resources (Material, Space, People)
Prerequisites (Work, Material, Design/Specifications)
Directives (Agreements, Decisions, Instructions)
External Conditions (Weather, Geotechnical, Regulatory)
We must consider the Human aspect of the first three
Concerns or Interests
Reliability and Trust
Integral part of the Flow of the project
5
-
8/2/2019 Lean Construction Leadership_David Trent
6/26
Lean Construction
6
-
8/2/2019 Lean Construction Leadership_David Trent
7/26
What is Lean Construction Anyway?
Lean Construction is
customer focused (nay, driven) organisation
Identification and elimination of waste
Standardised processes/work steps
Appropriate measurement, analysis, and action
Reliable, sustainable flow of work
Cultural Change
7
-
8/2/2019 Lean Construction Leadership_David Trent
8/26
Waste
Henry Ford -
The easiest waste, and the hardest to correct is the waste of time,
because wasted time does not litter the floor like wasted material
8
-
8/2/2019 Lean Construction Leadership_David Trent
9/26
Why
Seven Wastes OverproductionWhy put in cable tray for something that
isnt needed for weeks when others are waiting for it in another
work area. This is the worst form of waste and leads to theother six.
Waiting Standing around because you need somethingbefore you can start/continue working on your task.
Conveyance Unnecessary movement of equipment, partsand tools.
Processing Performing unnecessary work.
Inventory Too much or not enough are both wastes.
Motion Unnecessary movement of people
Correction Rework for any reason
9
-
8/2/2019 Lean Construction Leadership_David Trent
10/26
Five Big Ideas
COLLABORATE, REALLYCOLLABORTE.
INCREASE
RELATEDNESS
PROJECTS ASNETWORKS OFCOMMITMENT
OPTIMIZE
THE WHOLE
TIGHTLYCOUPLELEARNINGW/ACTION
Acknowledgements: Sutter Health
10
-
8/2/2019 Lean Construction Leadership_David Trent
11/26
Three Linked Opportunities
Acknowledgements: Greg Howell - LCIWill Lichtig - LCI
11
-
8/2/2019 Lean Construction Leadership_David Trent
12/26
Learning Loops
DesignCriteria
Purposes
ProcessDesign
Design
Concepts
DetailedEngineering
Product
Design
Construction
Fabrication &Logistics
Commissioning
Operations &Maintenance
Modifications
ProjectDefinition
Design Procure Construct Operate &Maintain
Production Control
Work Structuring
Adapted from: Greg Howell - LCI
Will Lichtig - LCI
Continuous Learning
12
-
8/2/2019 Lean Construction Leadership_David Trent
13/26
What are your drivers? What do you measure?
The push for footage How much of your production is show pipe?
How often do you have to revisit a work face to
finish a task?
What is your real percentage of re-work?
On what is your reward system based?
How often do you consider the next craft in the
work sequence and what they require?
13
-
8/2/2019 Lean Construction Leadership_David Trent
14/26
Measurement and Metrics
90% of measuring the value of Lean Construction is in use
today. Earned Quantities/Planned Quantities
Recordable/Lost Time Injury Rates
Quality metrics (weld reject rates and non-conformances)
Rework Etc.
The other 90% is unique to Lean Construction
Last Planner Planned Percent Complete (PPC)
The difference is moving away from Project Control toProduction Control.
14
-
8/2/2019 Lean Construction Leadership_David Trent
15/26
The Last Planner System
Last Planner System
System of commitments
6-12 week look-ahead (from material management through thehands at the workface, plus all interfacing disciplines)
Work face planning (one crews work for one (or two) weekperiod)
Elimination of restraints and going right to work without delay forthe entire week
The focus is on ensuring reliable flow of work from onetask to the next, minimizing the seven wastes.
Accept the fundamental reality of constant change andcontinuously re-planning throughout a project
Improved Safety Performance!
15
-
8/2/2019 Lean Construction Leadership_David Trent
16/26
Case 1
Refiner in Mid-US (first implementation of
Last Planner ) Refinery shutdown
Two shifts of 12 hours each, 7 days per week
Over 1million direct man-hours
All float consumed by engineering/design/material issues 9.5% improvement in labor productivity
Complete schedule recovery
Safety performance best ever for a shutdown at this facility
Acknowledgements: Pete Glynn - LIS
16
-
8/2/2019 Lean Construction Leadership_David Trent
17/26
Case 2
Canadian Hydrocarbon Grassroots Construction
Two nearly identical projects with same Owner and CM
One used Workface Planning (Last Planner) and one did not(until later)
Acknowledgements: COAA
17
-
8/2/2019 Lean Construction Leadership_David Trent
18/26
Background
Workface Planning
(Last Planner)?
Job A (Used) Job B (Did not use)
Engineering Same Same
Sub-ContractorExperience
Less More
Project Size More Less
Labour Availability More Less
Planners 12 1
Contract Reimbursable Lump Sum
18
-
8/2/2019 Lean Construction Leadership_David Trent
19/26
Background
Workface Planning
(Last Planner)?
Job A (Used) Job B (Did not use)
Schedule On time On time
Predictability On S curve Major Deviations
Hours On Budget 3X Budget
Rework Same Same
Progress Reporting Accurate Hit and Miss
Productivity 2X greater Baseline
Scaffolding Same Same
19
-
8/2/2019 Lean Construction Leadership_David Trent
20/26
Results
JOB A Productivity increased for all contractors
Piping productivity doubled Electrical productivity increased by 50% Scaffolding costs greatly reduced
All contractors believed the increased planning resulted inimproved productivity
All contractors believed the Workface Planning was introducedtoo late on the project
Unnecessary scaffolding take downs were virtually eliminated
Recommendations were made to implement Workface Planningon subsequent projects
Job B was converted to a cost reimbursable job and immediatelyimplemented Workface Planning (Last Planner) to recoverschedule.
20
-
8/2/2019 Lean Construction Leadership_David Trent
21/26
Lean Behaviors(5 fundamental concepts)
Perfection Identify theValueStream
SpecifyValue
Pull
Flow
Acknowledgements: M.L. Emiliani1998
21
B C
-
8/2/2019 Lean Construction Leadership_David Trent
22/26
Key Differences Between Lean and Current Forms of Project
Management
Aspect Lean Construction Current Form
Control Make things happen Monitoring results
Performance Maximize value/minimizewaste
Optimizing eachactivity/task
Project Delivery Focus on Discovery andDevelopment
Transactional and DecisionMaking base
Value Continuously re-defined bythe Customer
Defined by Customer atoutset of job
Coordination Pull - reliable/continuousflow of work
Push (schedule driven) -using original plan
Decision making Bottom up Top down
22
-
8/2/2019 Lean Construction Leadership_David Trent
23/26
Going Lean
The Construction Industry Institute surveyed Lean
Construction Practitioners and found that there are five
major principles, on which each team must focus:
Customer Focus
Culture/People
Workplace Organisation/Standardisation
Waste Elimination
Continuous Improvement and Built-In Quality
*The Construction Industry Institute, based at The University of Texas at Austin, is a consortium of more than 100
leading owner, engineering-contractor, and supplier firms from both the public and private arenas.
Acknowledgement - CII
23
-
8/2/2019 Lean Construction Leadership_David Trent
24/26
Create the culture Be the Directional Manager
Standardize Processes
Continuous Improvement Focus
Embrace Uncertainty
Lead Change
LEADERSHIP
24
-
8/2/2019 Lean Construction Leadership_David Trent
25/26
What is YOUR Standard Work?
Daily Meetings (15 minute stand-ups)
Move from focus on results to focus on process
Insist on Continuous Improvement
Visual Controls insist on the right metrics
Ask, dont Tell
25
-
8/2/2019 Lean Construction Leadership_David Trent
26/26
Start with what goes wrong!!!
We learn best from our mistakes
Be quick about root cause analysis, remedy options, andimplementing improvements
Measure value and keep/lose changes tried as appropriate
26