Lean Construction Leadership_David Trent

download Lean Construction Leadership_David Trent

of 26

Transcript of Lean Construction Leadership_David Trent

  • 8/2/2019 Lean Construction Leadership_David Trent

    1/26

    Lean Construction Leadership

    David Trent

    Director - Project Controls

  • 8/2/2019 Lean Construction Leadership_David Trent

    2/26

    Words to remember

    Albert Schweitzer Example is not the main thing in influencing others, it is the

    only thing.

    General George S. Patton:

    Never tell people how to do things. Tell them what to doand they will surprise you with their ingenuity.

    2

  • 8/2/2019 Lean Construction Leadership_David Trent

    3/26

    Traditional Project Leadership

    Value Stream Managers-Project Managers

    Supervisors Lead Hands

    Team Leaders-Lead Hands

    Direct Workers

    3

  • 8/2/2019 Lean Construction Leadership_David Trent

    4/26

    Lean Leadership

    Value Stream Managers-Project Managers

    Direct Workers

    Team Leaders-Lead Hands

    Supervisors- Lead Hands

    4

  • 8/2/2019 Lean Construction Leadership_David Trent

    5/26

    The Human Condition

    Four things contribute to a project:

    Resources (Material, Space, People)

    Prerequisites (Work, Material, Design/Specifications)

    Directives (Agreements, Decisions, Instructions)

    External Conditions (Weather, Geotechnical, Regulatory)

    We must consider the Human aspect of the first three

    Concerns or Interests

    Reliability and Trust

    Integral part of the Flow of the project

    5

  • 8/2/2019 Lean Construction Leadership_David Trent

    6/26

    Lean Construction

    6

  • 8/2/2019 Lean Construction Leadership_David Trent

    7/26

    What is Lean Construction Anyway?

    Lean Construction is

    customer focused (nay, driven) organisation

    Identification and elimination of waste

    Standardised processes/work steps

    Appropriate measurement, analysis, and action

    Reliable, sustainable flow of work

    Cultural Change

    7

  • 8/2/2019 Lean Construction Leadership_David Trent

    8/26

    Waste

    Henry Ford -

    The easiest waste, and the hardest to correct is the waste of time,

    because wasted time does not litter the floor like wasted material

    8

  • 8/2/2019 Lean Construction Leadership_David Trent

    9/26

    Why

    Seven Wastes OverproductionWhy put in cable tray for something that

    isnt needed for weeks when others are waiting for it in another

    work area. This is the worst form of waste and leads to theother six.

    Waiting Standing around because you need somethingbefore you can start/continue working on your task.

    Conveyance Unnecessary movement of equipment, partsand tools.

    Processing Performing unnecessary work.

    Inventory Too much or not enough are both wastes.

    Motion Unnecessary movement of people

    Correction Rework for any reason

    9

  • 8/2/2019 Lean Construction Leadership_David Trent

    10/26

    Five Big Ideas

    COLLABORATE, REALLYCOLLABORTE.

    INCREASE

    RELATEDNESS

    PROJECTS ASNETWORKS OFCOMMITMENT

    OPTIMIZE

    THE WHOLE

    TIGHTLYCOUPLELEARNINGW/ACTION

    Acknowledgements: Sutter Health

    10

  • 8/2/2019 Lean Construction Leadership_David Trent

    11/26

    Three Linked Opportunities

    Acknowledgements: Greg Howell - LCIWill Lichtig - LCI

    11

  • 8/2/2019 Lean Construction Leadership_David Trent

    12/26

    Learning Loops

    DesignCriteria

    Purposes

    ProcessDesign

    Design

    Concepts

    DetailedEngineering

    Product

    Design

    Construction

    Fabrication &Logistics

    Commissioning

    Operations &Maintenance

    Modifications

    ProjectDefinition

    Design Procure Construct Operate &Maintain

    Production Control

    Work Structuring

    Adapted from: Greg Howell - LCI

    Will Lichtig - LCI

    Continuous Learning

    12

  • 8/2/2019 Lean Construction Leadership_David Trent

    13/26

    What are your drivers? What do you measure?

    The push for footage How much of your production is show pipe?

    How often do you have to revisit a work face to

    finish a task?

    What is your real percentage of re-work?

    On what is your reward system based?

    How often do you consider the next craft in the

    work sequence and what they require?

    13

  • 8/2/2019 Lean Construction Leadership_David Trent

    14/26

    Measurement and Metrics

    90% of measuring the value of Lean Construction is in use

    today. Earned Quantities/Planned Quantities

    Recordable/Lost Time Injury Rates

    Quality metrics (weld reject rates and non-conformances)

    Rework Etc.

    The other 90% is unique to Lean Construction

    Last Planner Planned Percent Complete (PPC)

    The difference is moving away from Project Control toProduction Control.

    14

  • 8/2/2019 Lean Construction Leadership_David Trent

    15/26

    The Last Planner System

    Last Planner System

    System of commitments

    6-12 week look-ahead (from material management through thehands at the workface, plus all interfacing disciplines)

    Work face planning (one crews work for one (or two) weekperiod)

    Elimination of restraints and going right to work without delay forthe entire week

    The focus is on ensuring reliable flow of work from onetask to the next, minimizing the seven wastes.

    Accept the fundamental reality of constant change andcontinuously re-planning throughout a project

    Improved Safety Performance!

    15

  • 8/2/2019 Lean Construction Leadership_David Trent

    16/26

    Case 1

    Refiner in Mid-US (first implementation of

    Last Planner ) Refinery shutdown

    Two shifts of 12 hours each, 7 days per week

    Over 1million direct man-hours

    All float consumed by engineering/design/material issues 9.5% improvement in labor productivity

    Complete schedule recovery

    Safety performance best ever for a shutdown at this facility

    Acknowledgements: Pete Glynn - LIS

    16

  • 8/2/2019 Lean Construction Leadership_David Trent

    17/26

    Case 2

    Canadian Hydrocarbon Grassroots Construction

    Two nearly identical projects with same Owner and CM

    One used Workface Planning (Last Planner) and one did not(until later)

    Acknowledgements: COAA

    17

  • 8/2/2019 Lean Construction Leadership_David Trent

    18/26

    Background

    Workface Planning

    (Last Planner)?

    Job A (Used) Job B (Did not use)

    Engineering Same Same

    Sub-ContractorExperience

    Less More

    Project Size More Less

    Labour Availability More Less

    Planners 12 1

    Contract Reimbursable Lump Sum

    18

  • 8/2/2019 Lean Construction Leadership_David Trent

    19/26

    Background

    Workface Planning

    (Last Planner)?

    Job A (Used) Job B (Did not use)

    Schedule On time On time

    Predictability On S curve Major Deviations

    Hours On Budget 3X Budget

    Rework Same Same

    Progress Reporting Accurate Hit and Miss

    Productivity 2X greater Baseline

    Scaffolding Same Same

    19

  • 8/2/2019 Lean Construction Leadership_David Trent

    20/26

    Results

    JOB A Productivity increased for all contractors

    Piping productivity doubled Electrical productivity increased by 50% Scaffolding costs greatly reduced

    All contractors believed the increased planning resulted inimproved productivity

    All contractors believed the Workface Planning was introducedtoo late on the project

    Unnecessary scaffolding take downs were virtually eliminated

    Recommendations were made to implement Workface Planningon subsequent projects

    Job B was converted to a cost reimbursable job and immediatelyimplemented Workface Planning (Last Planner) to recoverschedule.

    20

  • 8/2/2019 Lean Construction Leadership_David Trent

    21/26

    Lean Behaviors(5 fundamental concepts)

    Perfection Identify theValueStream

    SpecifyValue

    Pull

    Flow

    Acknowledgements: M.L. Emiliani1998

    21

    B C

  • 8/2/2019 Lean Construction Leadership_David Trent

    22/26

    Key Differences Between Lean and Current Forms of Project

    Management

    Aspect Lean Construction Current Form

    Control Make things happen Monitoring results

    Performance Maximize value/minimizewaste

    Optimizing eachactivity/task

    Project Delivery Focus on Discovery andDevelopment

    Transactional and DecisionMaking base

    Value Continuously re-defined bythe Customer

    Defined by Customer atoutset of job

    Coordination Pull - reliable/continuousflow of work

    Push (schedule driven) -using original plan

    Decision making Bottom up Top down

    22

  • 8/2/2019 Lean Construction Leadership_David Trent

    23/26

    Going Lean

    The Construction Industry Institute surveyed Lean

    Construction Practitioners and found that there are five

    major principles, on which each team must focus:

    Customer Focus

    Culture/People

    Workplace Organisation/Standardisation

    Waste Elimination

    Continuous Improvement and Built-In Quality

    *The Construction Industry Institute, based at The University of Texas at Austin, is a consortium of more than 100

    leading owner, engineering-contractor, and supplier firms from both the public and private arenas.

    Acknowledgement - CII

    23

  • 8/2/2019 Lean Construction Leadership_David Trent

    24/26

    Create the culture Be the Directional Manager

    Standardize Processes

    Continuous Improvement Focus

    Embrace Uncertainty

    Lead Change

    LEADERSHIP

    24

  • 8/2/2019 Lean Construction Leadership_David Trent

    25/26

    What is YOUR Standard Work?

    Daily Meetings (15 minute stand-ups)

    Move from focus on results to focus on process

    Insist on Continuous Improvement

    Visual Controls insist on the right metrics

    Ask, dont Tell

    25

  • 8/2/2019 Lean Construction Leadership_David Trent

    26/26

    Start with what goes wrong!!!

    We learn best from our mistakes

    Be quick about root cause analysis, remedy options, andimplementing improvements

    Measure value and keep/lose changes tried as appropriate

    26