Lean 6 Sigma

17

Transcript of Lean 6 Sigma

Page 1: Lean 6 Sigma
Page 2: Lean 6 Sigma

Introduction

Page 3: Lean 6 Sigma

Introduction

Page 4: Lean 6 Sigma

The Lean 6σ Concept

DEFINE MEASURE ANALYZE IMPROVE CONTROL

Page 5: Lean 6 Sigma

Lean 6σ Road map

• What is your Problem ??

• Is it really ….

• Why is that important

• How is it related to Business Objectives?

• What factors contribute to those Objectives?

• Solution to the problem to meet those objectives

Page 6: Lean 6 Sigma

Problem DefinitionDEFINE

Page 7: Lean 6 Sigma

Problem DefinitionDEFINE

Page 8: Lean 6 Sigma

Problem DefinitionDEFINE

Rework in components

• A large number of components had to be reworked.

Time Management

• Majority of the time is spent in non value added process such as personnel movement, Photostat copying, etc.

Page 9: Lean 6 Sigma

Data Collection

Rework in components

• In the month of June, 1695 components were inspected • Of the 1695 components, 98 components were reworked.

Time Management

• A value stream map revealed that on an average, a component requires 135 min for inspection of which 25 minutes is the value added time required while the remaining ‘non-value added’ time was spent on movement of inspection personnel, arranging the component, cleaning the component etc

• If an error is made in measurement, the entire time is wasted.

MEASURE

Page 10: Lean 6 Sigma

Analysis of the ProblemANALYZE

Page 11: Lean 6 Sigma

Analysis of the ProblemRework in components

• Error in reading the value on the micrometer scale

• Usually the error is 0.5mm or 5mm

• 0.5mm is interpreted wrongly based on the position of the thimble scale on the main scale (E.g. 5.78mm is interpreted as 5.28mm)

• 5mm is interpreted wrongly based on the anvils chosen for the measurement (E.g. 195mm is interpreted as 190mm because of the operator making the mistake of adding up the reading)

ANALYZE

Page 12: Lean 6 Sigma

Analysis of the ProblemANALYZE

Page 13: Lean 6 Sigma

VSM of Inspection processANALYZE

Page 14: Lean 6 Sigma

Poka-Yoke for Measurement

• An ideal mistake-proofing method is to cross check the reading with a Vernier caliper to ensure that a reading error was not made

• It is not time consuming and avoids any repeatability of inspecting the component once again

IMPROVE

Page 15: Lean 6 Sigma

Controlling error in Measurement & Managing time

• To prevent recurrence of errors, a separate column in the inspection report is made where the Vernier caliper/pie-tape readings can be noted adjacent to the micrometer reading.

• To Manage time, during any process, say for example dismantling of any equipment, the assembly section can offer the equipment for inspection so that inspection and dismantling can be carried out parallel rather than in series.

• Using formats (with drawing readings/tolerances)for commonly dismantled assemblies and keeping instruments ready can reduce time by 25%

CONTROL

Page 16: Lean 6 Sigma

Cost Analysis

Cost of inspection/ hr (average)

• Previously , cost incurred is Rs. 157 per hour (considering a M10 employee earning Rs.450000 PA)

• i.e Rs 354 for Inspecting (for 135 min)

• After Poka-yoke, a 25% of cost is reduced i.e, Rs 265 per hour

Page 17: Lean 6 Sigma