LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind...

9
LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind Energy Association Tuesday, 20 th April

Transcript of LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind...

Page 1: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE

EUSune Strøm, Danish Wind Industry Association &

Emilien Simonot, Spanish Wind Energy Association

Tuesday, 20th April

Page 2: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

European study of lead time and barriers regarding administrative and grid connection processes• Objective of the project

– Obtain precise information on the administrative and grid access barriers that obstruct wind energy investment

– Give recommendations to the EC on how to overcome the identified barriers and shorten the lead times

• Data for the project has been collected through a survey where developers from 22 countries have responded representing 3,900 MW onshore and 1,800 MW offshore of new capacity connected in the period from 2006 – 2009, primarily 2008

• The results reflects the process of obtaining the needed permits and connections faced by the developers

Page 3: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

0

20

40

60

80

100

120

140

160

180Month Total lead time

C&SE: Central & Southeastern European countries: Austria, Bulgaria, Hungary & RomaniaB&N: Baltic & Nordic countries: Estonia, Finland, Latvia, Lithuania & Sweden

Patience is a key competence for being a wind power developer throughout Europe!

EU-27 mean: 55 month

Page 4: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

EIA, spatial plans and environmental issues are the main barriers together with insufficient grid capacity

0% 20% 40% 60% 80% 100%

Complying with spatial plans

Scope for EIA

Approval of EIA

Fulfilling technical requirements

Answering comments from NGO's

Lawsuits against the project

Concession for energy production

Approval of modifications

EU-27, onshore

Serious threats Caused a delay

0% 20% 40% 60% 80% 100%

Too high expenses to other issuesOverload by inactive projects

Undetermined cable routeInsuffiecient grid capacity

Too high connection expensesSpatial planning

Enviromental conditionsPolitical reasons

Insecure/ instable frameworkPublic resistance/ law suitsNegative political changes

Inacceptable authority demands

Oth

eris

sues

Grid

issu

esAdm

inis

trat

ive

issu

esEU-27, onshore

Non finalized projects stuck due to

0% 20% 40% 60% 80% 100%

Complying with spatial plans

Scope for EIA

Approval of EIA

Fulfilling technical requirements

Answering comments from NGO's

Lawsuits against the project

Concession for energy production

Approval of modifications

EU-27, offshore

Serious threats Caused a delay

Page 5: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

Social acceptance and positive attitude are also crucial for a wind farm project

• 30% of all stuck projects seem to be stuck (partly) due to public resistance and/or law suits against the project

• In some countries almost all stuck projects seem to have got stuck to a great extent due to public resistance and/or law suits against the project

• More than 20% of the connected wind farms in EU-27 experienced delays and/or serious threats caused by law suits or answering questions from NGO’s

1

2

3

4

5

Attitude of the authorities(1: Very negative - 5: Very supportive)

C&SE: Central & Southeastern European countries: Austria, Bulgaria, Hungary & RomaniaB&N: Baltic & Nordic countries: Estonia, Finland, Latvia, Lithuania & Sweden

10%

42%

45%

3%

EU-27, onshore

Planning Early development

Maturation Construction

Page 6: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

Share knowledge, fight myths and extend the grid in combination with the “good” decision-making process

• The planning authorities need to be ready with both long term spatial planning and efficient planning and decision-making process for the individual wind farm applications, including the requirements of EIA’s

• The TSO’s and DSO’s need to extend and enforce the grid taken the potential wind power development into consideration

• Establish the “good” process of decision-making by creating a well-defined process pinpointing e.g. the opportunities and framework for interaction between the local citizens, NGO’s etc. and the authorities/TSO’s/DSO’s

• Make public access across the EU-27 to environmental studies for wind farms and experiences regarding “good” practice for the decision-making process regarding both the wind farm development and grid connection/extension

Page 7: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

The lead time is not all – the decision-making process also depends on transparency, attitude, deadlines etc.

1

2

3

4

5

Overall performance(1: Bad performance, 5: Best performance)

C&SE: Central & Southeastern European countries: Austria, Bulgaria, Hungary & RomaniaB&N: Baltic & Nordic countries: Estonia, Finland, Latvia, Lithuania & Sweden

Page 8: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

Partners in the Wind Barriers:

EWEA, Dorina Iuga (project manager): [email protected] Wind Energy Association, Andrea Kirsci: [email protected] Polish Wind Energy Association, Jacek Tukaj: [email protected] Spanish Wind Energy Association, Emilien Simonot: [email protected] Wind Industry Association, Sune Strøm: [email protected]

Austrian Wind Power: Günther Clauss, [email protected] DONG Energy: Charlotte Boesen, [email protected] Iberdrola Renewables: Matilde Gonzales Balaca: [email protected]

Page 9: LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind Industry Association & Emilien Simonot, Spanish Wind.

Thank you for your attention

The Wind Barriers partners welcome you to join our side eventThursday, 22 April, 14:00 – 18:00Room D, Hall 4

Sune Strøm, EconomistDanish Wind Industry [email protected]+45 33 73 03 32+45 22 62 22 40