LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind...
-
Upload
dwight-matthews -
Category
Documents
-
view
216 -
download
0
Transcript of LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE EU Sune Strøm, Danish Wind...
LEAD TIME AND PROCEDURAL BARRIERS FOR WIND PARK DEVELOPMENT ACROSS THE
EUSune Strøm, Danish Wind Industry Association &
Emilien Simonot, Spanish Wind Energy Association
Tuesday, 20th April
European study of lead time and barriers regarding administrative and grid connection processes• Objective of the project
– Obtain precise information on the administrative and grid access barriers that obstruct wind energy investment
– Give recommendations to the EC on how to overcome the identified barriers and shorten the lead times
• Data for the project has been collected through a survey where developers from 22 countries have responded representing 3,900 MW onshore and 1,800 MW offshore of new capacity connected in the period from 2006 – 2009, primarily 2008
• The results reflects the process of obtaining the needed permits and connections faced by the developers
0
20
40
60
80
100
120
140
160
180Month Total lead time
C&SE: Central & Southeastern European countries: Austria, Bulgaria, Hungary & RomaniaB&N: Baltic & Nordic countries: Estonia, Finland, Latvia, Lithuania & Sweden
Patience is a key competence for being a wind power developer throughout Europe!
EU-27 mean: 55 month
EIA, spatial plans and environmental issues are the main barriers together with insufficient grid capacity
0% 20% 40% 60% 80% 100%
Complying with spatial plans
Scope for EIA
Approval of EIA
Fulfilling technical requirements
Answering comments from NGO's
Lawsuits against the project
Concession for energy production
Approval of modifications
EU-27, onshore
Serious threats Caused a delay
0% 20% 40% 60% 80% 100%
Too high expenses to other issuesOverload by inactive projects
Undetermined cable routeInsuffiecient grid capacity
Too high connection expensesSpatial planning
Enviromental conditionsPolitical reasons
Insecure/ instable frameworkPublic resistance/ law suitsNegative political changes
Inacceptable authority demands
Oth
eris
sues
Grid
issu
esAdm
inis
trat
ive
issu
esEU-27, onshore
Non finalized projects stuck due to
0% 20% 40% 60% 80% 100%
Complying with spatial plans
Scope for EIA
Approval of EIA
Fulfilling technical requirements
Answering comments from NGO's
Lawsuits against the project
Concession for energy production
Approval of modifications
EU-27, offshore
Serious threats Caused a delay
Social acceptance and positive attitude are also crucial for a wind farm project
• 30% of all stuck projects seem to be stuck (partly) due to public resistance and/or law suits against the project
• In some countries almost all stuck projects seem to have got stuck to a great extent due to public resistance and/or law suits against the project
• More than 20% of the connected wind farms in EU-27 experienced delays and/or serious threats caused by law suits or answering questions from NGO’s
1
2
3
4
5
Attitude of the authorities(1: Very negative - 5: Very supportive)
C&SE: Central & Southeastern European countries: Austria, Bulgaria, Hungary & RomaniaB&N: Baltic & Nordic countries: Estonia, Finland, Latvia, Lithuania & Sweden
10%
42%
45%
3%
EU-27, onshore
Planning Early development
Maturation Construction
Share knowledge, fight myths and extend the grid in combination with the “good” decision-making process
• The planning authorities need to be ready with both long term spatial planning and efficient planning and decision-making process for the individual wind farm applications, including the requirements of EIA’s
• The TSO’s and DSO’s need to extend and enforce the grid taken the potential wind power development into consideration
• Establish the “good” process of decision-making by creating a well-defined process pinpointing e.g. the opportunities and framework for interaction between the local citizens, NGO’s etc. and the authorities/TSO’s/DSO’s
• Make public access across the EU-27 to environmental studies for wind farms and experiences regarding “good” practice for the decision-making process regarding both the wind farm development and grid connection/extension
The lead time is not all – the decision-making process also depends on transparency, attitude, deadlines etc.
1
2
3
4
5
Overall performance(1: Bad performance, 5: Best performance)
C&SE: Central & Southeastern European countries: Austria, Bulgaria, Hungary & RomaniaB&N: Baltic & Nordic countries: Estonia, Finland, Latvia, Lithuania & Sweden
Partners in the Wind Barriers:
EWEA, Dorina Iuga (project manager): [email protected] Wind Energy Association, Andrea Kirsci: [email protected] Polish Wind Energy Association, Jacek Tukaj: [email protected] Spanish Wind Energy Association, Emilien Simonot: [email protected] Wind Industry Association, Sune Strøm: [email protected]
Austrian Wind Power: Günther Clauss, [email protected] DONG Energy: Charlotte Boesen, [email protected] Iberdrola Renewables: Matilde Gonzales Balaca: [email protected]
Thank you for your attention
The Wind Barriers partners welcome you to join our side eventThursday, 22 April, 14:00 – 18:00Room D, Hall 4
Sune Strøm, EconomistDanish Wind Industry [email protected]+45 33 73 03 32+45 22 62 22 40