• Summary of year’s activities– Forsyth/Wiens Recoveries– Cascadia Construction and TRM Deployment (testing)– Staffing
• Upcoming plans/schedule– Cascadia deep deployment (2011)– Mariana deployment (2012)– Chile deployment (2012)– Cascadia recoveries/turnaround (2012)
• Development– Completed/ongoing projects– Future projects
![Page 2: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/2.jpg)
Forsyth Recoveries (S of Shatsky)
Site Depth, m Acoustics Release Data
14 6002 Good No release
12 5788 Good 1 wt dropped after ~2h 244/370
9 5933 Good 1 wt dropped after ~2h 150/370
8 6007 Good Normal release 372/372
5 5994 None
2 5752 None
Faulty burnwires: Sites 9, 12, 14?
Sites 2, 5: implosion or early release ?
![Page 3: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/3.jpg)
Wiens Lau Recoveries
• 21 of 22 recovered• 13 had OBMs
• OK performance,• Some bad channels
• Depth restriction 5000 m• No low-pressure leaks
![Page 4: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/4.jpg)
Inventories (instruments and people)
• ~29 standard OBS (5 TCs; 24 L4s)• 30 (20 TRM; 10 standard) in Cascadia fleet (considerable overlap in design)
• People: 3 core, 5 peak– Engineer Gassier– Engineer Koczynski– Technician Oletu– Technicians Stolzmann, Brusa
![Page 5: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/5.jpg)
Cascadia Construction/Deployment
2 test cruises in LI Sound (battery issues; instrument survived 3’ drop)Corrosion test in LI sound
Made decision early 2011 to add popup buoys
Construction:
Possible TRM delays became apparent ~ April/May
Steel supplier/coater overwhelmed (19 tons in 900 pcs)
Estimated 5+ instruments ready for deployment cruise
10 standard Cascadia OBSs on track for October 2011
![Page 6: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/6.jpg)
New standard OBS
![Page 7: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/7.jpg)
TRM OBS
![Page 8: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/8.jpg)
Cascadia Deployment
15 delivered for cruise
![Page 9: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/9.jpg)
TRM Deployment Cruise July, 2011
15 deployed9 with popups
Heave challenges
1 TRM fell
1 tilted
1 recovered
Some had temperaturesensors
Major fishing collaboration
![Page 10: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/10.jpg)
TRM Recovery
![Page 11: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/11.jpg)
2011-12 Activities
• Cascadia Standard deployment, October 2011• Mariana experiment (Wiens) Jan/Feb 2011
– 10 standard OBSs– 5 moored instruments– Temperature sensors ?
• Chile experiment (Trehu) April/May 2011– 10 standard OBSs– Flowmeters
• Cascadia Recoveries/Turnaround [All summer…]
![Page 12: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/12.jpg)
Completed Development
• Switched to Trillium Compact leveling system in Al tube
• TRMs developed and built• OBS dataloggers redesigned: batteries separated• APG dataloggers incorporated into OBSs• TRM deployment/recovery approaches
![Page 13: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/13.jpg)
2011-12 Development Directions
• New FPGA for APG logger• Atomic clocks• TRM tweaks• Mariana moored instruments• Adding SIO flowmeters to standard OBSs • Incorporate broadband sensor• New OBS datalogger• Deep OBS
![Page 14: LDEO IIC 2010-11](https://reader038.fdocuments.us/reader038/viewer/2022102801/568147ee550346895db52589/html5/thumbnails/14.jpg)
Issues
• Confidence has increased (5 years)• But… recognize need to consolidate.
• Last year, working flat-out. May be false economy given per-instrument and data costs.
• Data: Backlog is critical problem. First Forsyth
experiment site to DMC yesterday.