LCLS-IISC Parameters
description
Transcript of LCLS-IISC Parameters
LCLS-IISC ParametersTor Raubenheimer10/1/2013
LCLS-II - Linac and Compressor Layout for 4 GeV
CM01 CM2,3 CM04 CM15 CM16 CM35
BC1270 MeV
R56 = -65 mmIpk = 60 A
Lb = 0.40 mmsd = 1.4 %
BC21550 MeV
R56 = -65 mmIpk = 1000 A
Lb = 0.024 mmsd = 0.50 %
GUN0.75 MeV
LH98 MeV
R56 = -5 mmIpk = 12 A
Lb = 2.0 mmsd = 0.006 %
L0j 0
V0 97 MV
L1j =-26°
V0 =235 MV
HLj =-170°
V0 =40 MV
L2j = -28°
V0 = 1448 MV
L3j = 0
V0 = 2460 MV
LTU4.0 GeVR56 = 0
Ipk = 1000 ALb = 0.024 mmsd 0.02 %
100 pC; Machine layout 26SEP2013; Bunch length Lb is FWHM
3.9GHz
Linac
V(MV)
j(deg)
Acc. Grad.
(MV/m)
No. Cryo
Mod’s
No. Cav’s
Spare Cav’s
Cavities per
Amplifier
L0 97 * 14.6 1 8 1 1
L1 235 -26 15.1 2 16 1 1
HL -40 -170 - 3 (3.9GHz) 12 0 12?
L2 1448 -28 15.5 12 96 6 32?
L3 2460 0 15.7 20 160 10 32?
* L0 phases: (-40, -52, 0, 0, 0, 13, 33), with cav-2 at 20% of other L0 cav’s.
Start from 10A APEX beamIncludes 2-km RW wake
Paul Emma
LCLS-II Overview 3
Operating modes
1.0 - 18 keV (120 Hz)1.0 - 5 keV (100 kHz)
0.2-1.2 keV (100kHz)4 GeV SC Linac
•Two sources: high rate SCRF linac and 120 Hz NCu LCLS-I linac
•North and south undulators always operate simultaneously in any modeUndulator
SC Linac (up to 100kHz) Cu Linac (up to 120Hz)
North 0.25-1.2 keV
South 1.0-5.0 keV up to 18 keVhigher peak power pulses
Cu Linac
• Concurrent operation of 1-5 keV and 5-18 keV is not possible
4
Preliminary Operating Parameters
LCLS-II Overview
Preliminary LCLS-II Summary Parameters v0.7 8/30/13
North Side Source South Side Source
Running mode SC Linac SC Linac Cu Linac
Repetition rate up to 1 MHz* up to 1 MHz* 120 Hz
Electron Energy 4 GeV 4 GeV 14 GeV
Photon energy 0.25-1.2 keV 1-5 keV 1-20 keV
Max Photon pulse energy (mJ) (full charge, long pulse)
up to 2 mJ* up to 2 mJ* up to10 mJ
Peak Spectral Brightness (10 fs pulse) (low charge, 10pC)
3.9x1030 ** 12x1030 ** 247x1030 **
Peak Spectral Brightness(100fs pulse) (full charge, 100pC)
3.0x1030 ** 6.9x1030 ** 121x1030 **
* Limited by beam power on optics **N_photons/(s*mm^2*mrad^2*0.1% bandwidth)
5Insert Presentation Title in Slide Master
High Level Schedule
6Insert Presentation Title in Slide Master
More Immediate Schedule
1. Mid-October Workshop to review design, cost and
schedule with collaborators
2. Late November FAC review of the draft CDR
3. Mid-December Director’s Review for CD1 Review
4. Early-February CD1 Lehman Review
7Insert Presentation Title in Slide Master
Assumed Beam Parameters
The assumed emittance of 0.43 at 100 pC is roughly 25% larger than
the LCLS-II baseline. It is more conservative than the NLS or the
scaled NGLS values (the latter are consistent with the LCLS-II baseline)
however a gun has not yet been demonstrated that achieves the
desired emittances. Reduced emittances will decrease gain lengths.
Peak current is consistent with higher energy beams and BC’s
NLS NGLS LCLS-IISC
Beam energy [GeV] 2.25 2.4 4
Bunch charge [pC] 200 300 100
Emittance [mm-mrad] 0.3 0.6 0.43
Energy spread [keV] 150 150 keV 300 keV
Peak current [kA] 0.97 0.5 1
Useful bunch fraction [%] 40 50 50
8Insert Presentation Title in Slide Master
Example of Injector: APEX
9
Example of Litrack fromAPEX Simulation
100pC20A peak currentSlice emittance 0.2-0.25 umProjected emittance ~ 0.35 um
better current/energy profile
Charge =100pCR56@BC1=-38.5mmR56@BC2=-54.7mmL1 phase =-21.7 degreeL2 phase =-29.2 degreeL3 phase =-2 degree3rd HC phase =-158 degreeL1voltage =211 MVL2 voltage =1.54GV3rd HC Voltage=47MV
Lanfa Wang
10Insert Presentation Title in Slide Master
SCRF Linac
Roughly 400 meters long including laser heater at ~100
MeV, BC1 at ~300 MeV and BC2 at 1000-2000 GeV. Long
bypass line starting at Sector 10 BSY.
Based on 1.3 GHz TESLA
9-cell cavity with minor
mods for cw operation
11
1.3 GHz 8-cavity cryomodule (CM)
• It is proposed to use an existing cryomodule design for the 4-GeV
LCLS-II SRF linac.
• CM is roughly 13 meters for 8 cavities plus a quadrupole package
• The best-fit is the EU-XFEL cryomodule
• Modifications are required for LCLS-II• (The CEBAF 12 GeV upgrade module must also be considered)• (The ILC CM is similar but has several important differences and is
not as well suited for CW application)
• 100 cryomodules of this design will be built and tested by the
XFEL by 2016 Global industrial support for this task
• One XFEL ~prototype CM was assembled and tested at Fermilab• (Fermilab assembled an ILC cryomodule and has parts for another)\
12
Linac Parameters
v0.9 2013-08-30
Linac parameters
Energy 4 GeV
Cavity Gradient 16 MV/m
Cavity Q_0 2E+10
Operational temperature 1.8 deg_K
rate 1E+06 Hz
Average current 0.3 mA
Beam power 1.2 MW
Cryogenics power 3.0 MW
Total SC RF AC Power 3.4 MW
SC Layout
1.3 GHz Cryomodules 34 (+1 spare) count
1.3 GHz Voltage 4.2 GV
1.3 GHz Cavities 264 count
1.3 GHz Rf power/cavity 7 kW
1.3 GHz Cavities/klystron 32 count
1.3 GHz SSA 24 count
1.3 GHz Cryomodules/klystron 4 count
1.3 GHz Dist. Between klystrons 57 m
1.3 GHz Klystron avg. power 3.0E+05 W
1.3 GHz Klystron (10% margin) 8
1.3 GHz Mod V 50 kV
1.3 GHz Mod A 10 A
1.3 GHz Sector-pair RF AC power 1.32E+06 W
1.3 GHz Cryomodule spacing 13 m
3.9 GHz cryomodules 3 count
3.9 GHz Voltage 60 MV
3.9 GHz Cavities 12 count
3.9 GHz Cavities/klystron 4 count
L0 length 8 m
L1 RF length 16 m
LC length (3.9 GHz) 4 m
L2 RF length 96 m
L3 RF length 144 mTotal Linac length; not incl BC1 BC2 405 m
13
Linac View in SLAC Tunnel
SLAC Linac
(11 wide x 10 feet high)
(3.35 x 3.05 m)
x
14
First 800 m of SLAC linac (1964):
Cryoplant placement and construction
350 m
Injector Length
15
Geometry downstream of SC linac
LCLS2SC bypass
Plan view
Elevation view
old LCLS2 linac
LCLS2SC bypass
120 Hz
100 kHz
old LCLS2 linacdump
fast kicker
100 kHz
9/26/2013 -- Y. Nosochkov
16
LCLS2SC bypass (from sec-21) to dump
9/26/2013 -- Y. Nosochkov
bypass
LTU dogleg + V-bend diagnostic undulator
dump
extension
17Insert Presentation Title in Slide Master
Assumed FEL Configuration
• High rep rate beam could be directed to either of two undulators
HXR or SXR bunch-by-bunch
• 120 Hz beam could be directed to the HXR at separate times
• The SC linac would be located in Sectors 0-10 and would be
transported to BSY in the 2km long Bypass Line. It would use a
dual stage bunch compressor.
• A dechirper might be used to further cancel energy spread for
greater flexibility in beam parameters
• The high rep rate beam energy would be 4 GeV and the HXR
would fill the LCLS hall with ~144 m while the SXR would be <75
m so that it could be fit into ESA
• Both undulators would need to support self-seeding as well as
other seeding upgrades
18Insert Presentation Title in Slide Master
Undulator Requirements
Requirements:
1. SXR self-seeding operation between 0.2 and 1.3 keV
in ESA tunnel (<75 meters) with 2.5 to 4 GeV beam
2. HXR self-seeding operation between 1.3 and 4 keV in
LCLS tunnel (~144 meters) with 4 GeV beam
3. HXR SASE operation up to 5 keV with 4 GeV beam
4. Primary operation of SXR and TXR at constant beam
energy large K variation
5. HXR operation comparable to present LCLS with 2 to
15 GeV beam
Baseline Tuning Range
With overhead
LCLS-IISC Undulator Options
20
X-ray pulse energy at High Rate
Results assume full beam and are somewhat optimistic
LCLS-IISC Undulator Options
21
Comparison of HXR with LCLS performance at 120 Hz (1)
26 mm HXR covers 0.5 keV at ~2.5 GeV to ~30 keV at 15 GeV
LCLS-IISC Undulator Options
22
Comparison of HXR with LCLS performance at 120 Hz (2)
26 mm HXR provides lower pulse energy than 30 mm LCLS but much shorter l
LCLS-IISC Undulator Options
23
Options for HXR: SCU or 30 mm period (2)
Example of a 30 mm period hybrid undulator below. Nearly recovers LCLS
performance (reduction due to slightly larger gap with VG undulator) however the
maximum photon energy at high rate, i.e., 4 GeV is now 4.3 keV not 5 keV as
with 26 mm period and 5 keV would require 4.4 GeV beams.
LCLS-IISC Undulator Options
24Insert Presentation Title in Slide Master
SuperrConducting Undulator options
An SCU has a number of benefits:
1. Would attain comparable performance as LCLS even
while achieving 5 keV at 4 GeV at high rate by operating
with high K
2. Would allow shorter SXR period to reduce SXR beam
energy and gain length to ensure space in ESA while still
covering full wavelength range at constant energy.
25
Potential Areas of Collaboration with Partner Labs
SLAC LBNL FNAL JLAB ANL Cornell Wisconsin
Injector X X X
Undulator X X
SC linac prototype X X X
SC Linac X X
SC cryo line X X
Cryo plant X X
LLRF X X X X
RF systems X
Beam Physics X X
Instruments/Detectors
X X
PM/Integration X
Installation X X X
Commissioning X
LCLS-II Overview
26Insert Presentation Title in Slide Master
Points of Contact
27Insert Presentation Title in Slide Master
CDR Writing
• Must keep the document concise – it is a conceptual design
1. Executive Summary (Galayda)
2. Scientific Objectives (TBD)
3. Machine Performance and Parameters (Raubenheimer)
4. Project Overview (Galayda)
5. Electron Injector (Schmerge)
6. Superconducting Linac Technologies (Ross,Corlett)
7. Electron Bunch Compression and Transport (Raubenheimer, Emma)
8. FEL Systems (Nuhn)
9. Electron Beam Diagnostics (Frisch, Smith)
10. Start-to-End Tracking Simulations (Emma)
11. Photon Transport and Diagnostics (Rowen)
12. Experimental End-Stations (Schlotter)
13. Timing and Synchronization (Frisch)
14. Controls and Machine Protection (Shoaee, Welch)
15. Conventional Facilities (Law)
16. Environment, Safety and Health (Healy)
17. Radiological Issues (Rokni)
18. Future Upgrade Options (Galayda)