Lawrence Livermore National Laboratory - Parallel Programming
Lawrence Livermore National Laboratory Building 111
description
Transcript of Lawrence Livermore National Laboratory Building 111
Lawrence Livermore National Laboratory
Building 111
Mike Holda
Lawrence Berkeley National Laboratory(510) 486-6358 or (209) 835-8150,
LLNL Building 111
• Originally designed as the Experimental Physics Building
• Built in 1966• Seven stories, 107,000
square feet • Now used as
administrative offices & research support space
LLNL Building 111Original HVAC and Lighting
Equipment
• Two 225 ton Carrier electric chillers– 1.0 + kW/ton efficiency, CFC-11 refrigerant
• Two gas-fired hot water boilers for heating• Two constant volume air handling systems
– For east wing, south wing & interior – Bypassed VAV air handlers and VFD motors
• Fluorescent light fixtures with T-12 lamps
LLNL Building 111Project Scenario
• 23-year-old inefficient chillers in need of overhaul– using CFC refrigerants, 1.0+ kW/ton
• Poor air quality and building comfort– Air system was out of balance– Economizers stuck open
• High temperature hot water reheat system with supply temperature reset (didn’t work)
• Less efficient T-12 lamps– Lighting levels unnecessarily high in hallways– Substantial unoccupied time with lights left on
LLNL Building 111Project Challenges
• Fragmented funding for projects– In-House Energy Management funding for measures
with simple paybacks of < 10 years
• Work presented here was actually done in Three separate projects– Chiller replacements– Lighting retrofits– HVAC System Improvements
LLNL Building 111 System Solutions
• (2) Chillers replaced– (2) new 200 ton chillers, one chiller
redundant
• New VAV’s & VFD’s added to air system with zone level control– 250 zones– Economizer controls
• New T-8 lighting, occupancy sensors, LED exit signs
LLNL Building 111Chiller Replacement
• Done in 1994• New McQuay centrifugal chillers
• 0.65 kW/ton• R-134a• 200 tons• Expected to save 151,400 kWh per year
LLNL Building 111Air System Improvements
• Done in 1996• Converted fixed balancing dampers
– To variable/automatic actuating dampers – Used exist pneumatic controls– Could not afford new VAV boxes– Air flow controlled in each zone – Variable volume terminal boxes hooked up to
existing zone heater thermostats
• New VFD to control fan motors on east, west, south & interior system
• Economizer controls
LLNL Building 111Lighting Improvements
• Done in 1995• Delamped fixtures
– Overlit building, especially in corridors– Reduced number of lamps per fixture from 3 to 2, or 6 to 3, or
8 to 4
• Replaced existing T-12 lighting – New T-8 fluorescents, electronic ballasts
• LED fixtures replaced incandescent and fluorescent exit signs
• Occupancy sensors used to turn off lights in offices, corridors, etc.
LLNL Building 111Electrical Energy Savings
0
50000
100000
150000
200000
250000
300000
350000
400000
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
kWh
1993 Actual 1994 Actual Sim. Existing Sim. Retrofit
LLNL Building 111Integrated Economics
ProjectInvestment
Cost($)
AnnualElectricitySavings(kWh)
AnnualGas
Savings(therms)
AnnualEnergySavings
($)
PaybackPeriod(years)
ChillerReplacements
$ 290,000 151,389 --- $ 6,358 45
Lighting, Exit Signs,Occupancy Sensors
$ 80,000 124,665 (2,400) $ 4,636 17
HVAC SystemImprovements
$ 400,000 817,289 96,045 $62,973 6.3
Total $ 770,000 1,093,343 93,645 $ 73,967 10.4
• Measures with lower paybacks reduce the overall project payback period
LLNL Building 111Financing Structure
• In-House Energy Management Funds from US DOE used for: – Chiller Replacements– Lighting retrofits– HVAC System improvements
• Appropriations from US DOE, no financing charges
LLNL Building 111Project Timeline
0 6 12 18 24 30 36
construction
procurement
design
funding received
construction
design
funding received
construction
procurement
design
funding received
Months
Chiller Replacement
Lighting Work
HVAC Systems
Jul 93 Jan 94 Jul 94 Jan 95 Jul 95 Jan 96 Jul 96
LLNL Building 111Project Results
• Saved over $73,000 annually on utility bills – ~40% of total bill
• New chillers without CFC’s– use R-134a, an HFC
• Improved air quality & comfort• Increased efficiency of HVAC System
LLNL Building 111Lessons Learned
• Projects not planned & executed together• Reduced cooling load not accounted for in
new chiller sizing• Incremental funding with lots of paperwork
and hassles• Super-ESPC’s developed to address these
problems