LARP Accelerator Systems: Progress Highlights and Goals of the Meeting

24
LARP LARP Accelerator Systems: Accelerator Systems: Progress Highlights and Goals of the Meeting Vladimir Shiltsev bnl - fnal- lbnl - slac US LHC Accelerator Research Program

description

US LHC Accelerator Research Program. bnl - fnal- lbnl - slac. LARP Accelerator Systems: Progress Highlights and Goals of the Meeting. Vladimir Shiltsev. Events since Port Jeff. LTVAC formed at Port Jeff (10/25/06) Executive Committee (10/31/06) LTV lab-LARP parity, LARP focus on juniors - PowerPoint PPT Presentation

Transcript of LARP Accelerator Systems: Progress Highlights and Goals of the Meeting

Page 1: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

LARPLARPAccelerator Systems:Accelerator Systems:Progress Highlights

and Goals of the MeetingVladimir Shiltsev

bnl - fnal- lbnl - slacUS LHC Accelerator Research Program

Page 2: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 2

Events since Port Jeff

• LTVAC formed at Port Jeff (10/25/06)• Executive Committee (10/31/06)

– LTV lab-LARP parity, LARP focus on juniors• US-CERN meeting (11/13/06):

– PJAS status to LTV to be further investigated– 5-yr plan and new tasks prioritization

• DoE mini-Review in Dec’06:– “… it is clear that LARP is developing exceedingly

well, and its managers and membership should be congratulated for their outstanding progress and achievements”

• FY’07 CR troubles (RHIC Run 7 off/on Mar’07)• FY’07 semi-annual report to DoE (03/25/07)

Page 3: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 3

Accelerator Systems Budget

2304k$ out of 3611k$=64%half-way thru

FY07

Instrum 77%Commiss 64%Collimat 54%Physics 48%

Page 4: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 4

This meeting and beyond• At the meeting we are to hear (among all)

about financial issues and needs of all the tasks• LARP AS contingency 200k$ - to be distributed

after the meeting• Initial planning for FY’08 to take place at the

meeting– Input on hard deliverable schedules– LTVAC, L2 tasks– New initiatives

• To be finalized after the meeting – “gang of 5+1”– exec committee– DoE Review June 5-6 at FNAL

Page 6: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 6

Instrumentation: Tune&Coupling FB

Success at RHIC and Tevatron

Success at SPSApr’06 Oct’06

Oct’06: successful Final Design Review of at BNL

Now: LHC system test at RHIC, Q’, later – LHC 450 GeV eng run

Page 7: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 7

Instrumentation: Luminosity Monitors

LUMI Prototype to be compared to RHIC ZDC

Two LUMINOSITY detectors under construction

Now: RHIC Run 7 with gold to test of complete systemLater: integration at LHC

Page 8: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 8

Collimation: Rotating Collimators

Significant design improvement

200mm Cu mandrel w/ coil after brazing

200mm collimator brazed

…will hear more progress at the meeting

960 mm Cu mandrel

Page 9: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 9

Physics: BBLR wires – ready for RHIC test

wires (2.5m long) with strong-back (-profile) 7 support points

Now: wire commissioning and experiments Code benchmarking

2 wires installed in RHIC Yellow and Blue rings

Page 10: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 10

Commissioning

• 5 hardware commissioners now at CERN• LTVAC identified / qualified LARP members

from Accel Systems to spend >~3 mos. at LHC

– All labs, incl. CERN, represented– All areas of Accel Sys represented

• At the Collab Mtg: – Endorsements plans, remainder of FY07– Provide recommendations (first pass) for travels

in FY08 to L0/L1• Visit LHC@FNAL (opened in Feb) !

Page 11: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 11

LHC@FNAL

Page 12: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 12

LARP AS : Focus on Junior Physicists

• They are active in all tasks:– Rama Calaga (Toohig Fellow), Mei Bai (Commiss.), Guillaume

Robert-Demolaize (Collim. , 1/2 by RHIC), Natalia Prado de Abreu (Physics, 1/2 by RHIC), Yun Luo (Commiss) – at BNL

– Ryoichi Miyamoto (AC dipole), Andreas Jansson (Schottky), H.J.Kim (IR), Arden Warner (Commiss) - at Fermilab

– Jean-Francois Beche (Lumi) – at Berkeley

• We are actively looking for new ones: – Toohig Fellows– 1 Research Associate for Lumi (Wainer Vandelli, Piza) – 1 RA for Rotating Collimator (Javier Resta Lopez)– 2 from SLAC to take part in commissioning

Page 13: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 13

Collaboration/Coordination with CERN

• Remarkable progress in 2006: – closer contacts established– “driving forces on both sides” model:

•Luminosity monitors: A.RATTI and R.JONES•Schottky detectors: R.PASQUINELLI and F.CASPERS•Tune & Coupling FB: P.CAMERON and R.JONES•AC Dipole: S.KOPP and H.SCHMICKLER•HW Commissioning: M.LAMM and R.BAILEY•Beam Commissioning: M.SYPHERS and M.LAMONT•Collimation: T.MARKIEWICZ & R.ASSMANN

Page 14: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 14

Collaboration with CERN in FY07

• Better coordination of all activities in FY07: – H.Schmickler/AB in LARP LTV Advisory Committee – O.Bruning/AB to be liaison to LARP IR,e-cloud work– J.P.Koutchouk/AT to be liaison to LARP beam-beam compensation

projects (long-range & head-on lenses)• More collaborative work:

– Even more visible LARP presence at CERN for• Installation and commissioning of LARP instruments • Participation in the next round of SPS studies• 2 more Hardware/IR Commissioners to come • First LARP Beam Commissioners - later in 2007

– Joint eCloud Clearing workshop @CERN (Mar’07)– Joint LHC beam-beam&IR workshop at SLAC, Jun’07

• Org’d by A.Chao & W.Fischer; to review experiments& simulations

Page 15: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 15

FY07 AS Priorities & Goals1. Lumi-Monitors: construct, install, start commissioning2. Tune&Coupling FB: deliver design, participate in

installation and commissioning3. Schottky: participate in installation and commissioning 4. Hardware Commissioning: execute the plan (5-7 people)5. Beam Commissioning: develop detailed Long Term

Visitors TV plan for FY08+ by ~mid-FY076. Other tasks: execute Task Sheet’s Plans7. “5+1”: develop FY08 plan (incl. new tasks) by ~June’07

Hard Deliverable

Hard Deliverable

Hard Deliverable

Page 16: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 16

This Meeting

• This is “large” meeting to address:– Plan execution, achieved milestones, finances– Expected schedule/cost changes in FY07– Plans for FY08 and beyond

• It is the meeting to report/discuss– Technical achievements, in detail– Difficulties of any kind– Status of collaboration affairs (US labs, CERN)

• Very important– Open discussion of new proposals (Thur PM)– Welcome new people joining us

• from SLAC• from various Fermilab groups

Page 17: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 17

New Initiatives

• Collider Instrumentation– BBQ-based Quadrupole Monitor – Synch light based diagnostics

• Physics– LHC Crystal Collimation Scheme– LHC Electron Lenses – Modeling of LLRF Limitations on LHC Performance

• LHC Injectors– The Low-Energy Transverse Emittance Project – Super-Ferric Fast Cycling Injector in the SPS Tunnel – LHC injectors Upgrades, space-charge effects

Page 18: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 18

Consideration Process• “Group of 5+1” to meet right after to recommend

on support of proposals • General requirements:

– Interesting subject, development should push up the state of the accelerator physics and technology in the US

– Of interest for LHC– Collaboration of >1 Lab, Universities welcome– Not at expense of current unfinished tasks– Right time and budget scale

• Final approval by LARP Executive Committee

Page 19: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 19

Summary:• Remarkable progress since last LARP meeting:

– Instrumentation tasks, Hardware commissioning– Rotating collimator design, Beam-beam wires, etc– Greatly improved LARP-CERN communication

• Priorities in FY’07: – instrumentation tasks, – commissioning

• LTV Advisory Committee started: – focus on junior researchers

Page 20: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 20

Back up slides

Page 21: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 21

AP: New Proposals vs Existing Tasks

• Electron cloud (200k$/yr): – very high priority for the LHC, a lot of interest from US

projects, now attacking e-p interaction simulations (new territory)

• IR Optics and Beam-Beam Simulations (270k$/yr):– Making important contribution to LHC Upgrade work (12

talks in Valencia), plugs US into the LHC Upgrade consideration process as a pratner, develops software tools of particular importance for the LHC and generic importance for US colliders (beam-beam lifetime)

• Beam-beam wires (150k$/yr):– Very positive development at CERN (there will be wires,

space reserved), effective CERN-LARP collaboration, experiment at RHIC greatly enhances advanced accelerator R&D in the US, little funds after FY’07

Page 22: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 22

Instrumentation Tasks in FY’07 and FY’08

• Schottky & Luminosity Monitors, Tune Feedback : – Are or will be constructed and installed in FY07 – LARP will support their commissioning (via Commissioning task)

in FY’07 and – in larger scale - in FY’08 (including 450 GeV run)• AC Dipole:

– Just started, significant design progress expected in FY07 will determine funds needed in FY08

• Being discussed:– Longitudinal Density Monitors, Crab Cavities, ODR monitors

• Funds in FY08 will depend on situation with higher priority tasks, e.g., commissioning of existing instruments (TBD after collaboration meeting in April’07)

Page 23: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 23

New Physics Initiatives • Crystal Collimator (~50k$ 1st year):

– waiting for Tevatron results with new bent crystal, not much encouragement from CERN, competes with Rotating Collimator for Phase II• Superferric LER or (S)PS (~100k$ 1st yr):

– LER is “dead”, Super Ferric (S)PS+ m.b. considered later – depends on CERN plans, no strong inter-Lab team in the US• Hollow electron beam as proton/ion primary collimator

(~50-100k$ 1st year): – Some interest at CERN, initial considerations to take place in FY07

technical considerations possible • Electron lens for beam-beam compensation (300 k$ 1st yr, ~600+ k$/yr x 4 yrs):

– Preparatory theory work not done, some limited interest at CERN, working collaboration may be formed in FY07 – encouraging TEL results (doubles p-lifetime)

• NB: before funding other things, we need complete current commitments (Instruments) as the highest priority

Page 24: LARP Accelerator Systems: Progress Highlights  and Goals of the Meeting

04/18/2007 LARP Collaboration Meeting 24

LHC Software at Fermilab (LAFS)

• Motivation: make vast Tevatron accelerator controls experience available to the LHC operation team

• Goal: to develop a suite of software products to enable Fermilab accelerator physicists to make key contributions to the beam commissioning of the LHC

• A modest team (~3-5 FTE’s or 10 people) of computer professionals, operational experts, and accelerator physicists to make a substantial contribution to the LHC

• LAFS is part of LHC@FNAL– Head – D.McGinnis – reports to E.Gottschalk– Three groups:

• RBA (Role Based Access) – S.Gysin• Sequencer – J.Patrick• SDA – Sequenced Data Acquisition – E.McCrory

• Collaborative agreement FNAL/CERN is signed by S.Holmes (last week) now at CERN

• Relationship to LARP : – Complementary:– LARP input via LHC@FNAL Integration Task Force LHC subgroup