Euclid Creek Pump Station - Lakeshore Boulevard Relief Sewer Project
Community MeetingMay 16, 2013
![Page 2: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/2.jpg)
EXISTING INFRASTRUCTURE
EUCLID CREEK PUMP STATION
LAKESHORE BLVD. INTERCEPTOR
![Page 3: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/3.jpg)
FLOODING COMPLAINTS MADE TO CLEVELAND’S DIVISION OF WATER POLLUTION CONTROL FROM 2009 TO MARCH 2012
![Page 4: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/4.jpg)
Euclid Creek Tunnel OverviewLAKESHORE BLVD. RELIEF SEWER
![Page 5: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/5.jpg)
Benefits
• Reduced CSO discharges to Euclid Creek and Lake Erie– Today: 40– When complete: ≤ 2
• To handle “5-year, 6-hour storm”• Reduced basement flooding
![Page 6: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/6.jpg)
Alignment Facts
• By the numbers:– 4890’ sewer from Triangle Park to intersection of
Lakeshore Blvd. & Rosecliff Ave.• Diameter: 27” to 66”
– 1230’ sewer from East Park Dr. to Dorchester Dr.• Diameter: 24”
– 330’ sewer along Crestland Rd.• Diameter: 18”
Construction largely in public right-of-way.
![Page 7: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/7.jpg)
KEY:--- Lakeshore Blvd. Relief Sewer--- Euclid Creek Tunnel
EUCLID CREEK PUMP STATION
![Page 8: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/8.jpg)
Construction Facts
• New Shaft (4-1A) Constructed– 22’ excavation diameter, 16’ finished diameter– 70’ deep
![Page 9: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/9.jpg)
New Shaft Construction
![Page 10: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/10.jpg)
Construction Facts, cont.
• Triangle Park New Shaft by Pump Station– Trenchless sewer construction– 70’ deep– No impact to Louis Stokes Bridge
![Page 11: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/11.jpg)
Trenchless Construction (a.k.a. Microtunneling)
![Page 12: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/12.jpg)
Construction Facts, cont.
• Lakeshore Blvd. from New Shaft Rosecliff Ave.– Open cut construction– 15’-25’ deep
• New Shaft Crestland Rd.– Open cut construction in westbound (north)
lanes of Lakeshore Blvd. – Parallel to existing Lakeshore Blvd. Interceptor
![Page 13: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/13.jpg)
Construction Facts, cont.
• Crestland Rd. Rosecliff Ave.– Open cut construction in eastbound (south)
lanes of Lakeshore Blvd.– Existing Lakeshore Blvd. Interceptor replaced by
new Lakeshore Blvd. Relief Sewer
![Page 14: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/14.jpg)
Open Cut Construction
![Page 15: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/15.jpg)
EXISTING LAKESHORE BLVD.
INTERCEPTOR
NEW LAKESHORE BLVD. RELIEF SEWER
New Relief Sewer vs. Existing Interceptor Sewer
![Page 16: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/16.jpg)
EXISTING LAKESHORE BLVD.
INTERCEPTOR
NEW LAKESHORE BLVD. RELIEF
SEWER
New Relief Sewer vs. Existing Interceptor Sewer
• Regulators will divert wet weather from existing interceptor to new relief sewer– Marcella Rd., Neff Rd. & Harland Ave.
![Page 17: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/17.jpg)
Who is the Contractor?
• McNally/Kiewit ECT JV (Euclid Creek Tunnel contractor) will perform trenchless work– Triangle Park to EC Pump Station– Start date: Summer 2013– Duration: 18 months
• Advertise remainder of project fall 2013– Lakeshore Blvd., East Park Dr. & Crestland Rd.– Start date: Early 2014– Duration: 18 months
![Page 18: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/18.jpg)
LBRS 4-1A
CSO 239
TREN
CH
LESS
SEW
ER
LAKESHORE BLVD. INTERCEPTOR
OPEN CUT
SEWER
![Page 19: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/19.jpg)
PROFILE OF RELIEF SEWER AT TRANSITION FROM OPEN CUT TO TRENCHLESS CONSTRUCTION
ECPS/LBRS CONTRACT
ECT CONTRACT
SOIL
BEDROCK
![Page 20: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/20.jpg)
MAINTENANCE OF TRAFFIC DURING CONSTRUCTION OF SHAFT 4-1A
![Page 21: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/21.jpg)
Anticipated Construction Schedule
• July 2013 January 2015– Trenchless construction from Triangle Park to
new shaft by pump station– Contractor: McNally/Kiewit ECT JV
• March 2014 September 2015– Open cut construction on Lakeshore Blvd.,
East Park Dr. & Crestland Rd.– Contractor: TBD
![Page 22: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/22.jpg)
Euclid Creek Pump Station Renovations
• New roof, gutters and downspouts• Improved site drainage• New driveway• New pumps and piping system• New HVAC system• New interior stairwells• New interior paint
![Page 23: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/23.jpg)
Post-Construction Features
• Lakeshore Blvd. resurfaced from Louis Stokes Bridge to Rosecliff Ave.
![Page 24: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/24.jpg)
Stay Informed
• Blog– EuclidCreek.blogspot.com
• Collinwood Observer– Ads and articles
• Semi-Monthly Newsletter– E-mail distribution– [email protected] to be added to the list
![Page 25: Lakeshore boulevard relief sewer presentation](https://reader036.fdocuments.us/reader036/viewer/2022062705/55636043d8b42a2f508b4dc3/html5/thumbnails/25.jpg)
How to Reach Us
Social Mediafacebook.com/yoursewerdistrict@neorsd | @wallywaterdrop
Customer Service (216) 881-8247
Emergencies: NEORSD ECT Field Office(216) 268-5469
Ryan Sullivan, [email protected] Elting, [email protected]