Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show...
Transcript of Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show...
![Page 1: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/1.jpg)
Lake Hodges Bicycle and P d t i B id St t R tPedestrian Bridge Status Report
Susan Carter, Deputy DirectorSan Dieguito River Park Joint Powers AuthoritySan Dieguito River Park Joint Powers Authority
Bill Prey, Construction EngineerSANDAG
February 13, 2008
![Page 2: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/2.jpg)
![Page 3: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/3.jpg)
![Page 4: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/4.jpg)
Stress Ribbon Bridge
![Page 5: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/5.jpg)
StressStress--Ribbon Bridge ConstructionRibbon Bridge Construction
![Page 6: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/6.jpg)
Bridge LayoutBridge Layout
![Page 7: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/7.jpg)
Bridge Typical SectionsBridge Typical Sections
![Page 8: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/8.jpg)
Project Purpose Project Purpose
Provide bicyclists and pedestrians a Provide bicyclists and pedestrians a commuting and recreational route for crossing Lake Hodges and the San crossing Lake Hodges and the San Dieguito River Valley Provide recreational users access to Provide recreational users access to the network of trails on both sides of the lake without using an automobileg
8
![Page 9: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/9.jpg)
DesignDesign
Design by T Y Lin InternationalDesign by T Y Lin International“Stress ribbon” bridge 1 000 ft long1,000 ft longThree spansPrecast concrete deckPanels 14 ft wide x 10 ft long x 16 in thick
9
![Page 10: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/10.jpg)
DesignDesign
Panels strung on cables anchored Panels strung on cables anchored using rock anchorsPanels "stressed“ to create a rigid Panels stressed to create a rigid deck Concrete panels produce a thin bridge Concrete panels produce a thin bridge profile from the side
10
![Page 11: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/11.jpg)
LAKE HODGES BICYCLE AND PEDESTRIAN BRIDGE FUNDING(Phase 1 and Phase 2)
1. $3,061,000 Federal Transportation Enhancement (TE) funds (w/ Caltrans District 11)
2. $1,500,000 State River Parkway Bond Act funds (Prop 13)
3. $625,000 State River Parkway Bond Act funds (Prop 40)
4. $500,000 SANDAG FY 2004 and 2005 TransNet Bicycle Program funds
5. $2,000,000 Federal TE funds (SANDAG regional, March 2006)
6. $1,875,000 SANDAG FY 2009 TransNet Bicycle, Pedestrian and Neighborhood Safety funds
(March 2007)
k d f d ( l )7. $347,000 State River Parkway Bond Act funds (Prop 40, July 2007)
8. $9,908,000 Total Available Funding Phase 1 and Phase 2
11
![Page 12: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/12.jpg)
LAKE HODGES BICYCLE AND PEDESTRIAN BRIDGE BUDGET (Phase 1 and Phase 2)
Expenditures
To Date
Forecast
To Complete
Line Item
1. $70,000 $70,000 Project Administrationj
2. $401,913 $401,913 Environmental
3. $798,187 $816,599 Design
4. $249,800 $438,995 Construction Management
5. $2,107,978 $2,107,978 Construction Phase 1
6. $3,397,059 $6,710,205 Construction Phase 2
7. - ($229,171) Change Orders Phase 2
8. - - Remaining Project Contingency
9. $7,024,937 $10,316,519 Total Budget Phase 1 and Phase 2
![Page 13: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/13.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Forecast to Complete: $10 316 519Forecast to Complete: $10,316,519Available Funding: $9,908,000Current Shortfall: $408 519Current Shortfall: $408,519Options:
Addi i l i h Additional cost saving changes Grants and donationsA b hiAssess membershipMortgage reconstructed facility
![Page 14: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/14.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Phase 1Phase 1Constructed South AbutmentContractor – FCI Constructors IncContractor FCI Constructors, Inc.Amount - $2,107,978Completed - May 15, 2007Completed May 15, 2007
![Page 15: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/15.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Phase 2 Phase 2 Constructing Bridge, Piers and North AbutmentContractor – FCI Constructors, Inc.Amount - $6,679,275, ,Began - September 16, 2007Scheduled Completion – March 16, 2009
![Page 16: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/16.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Phase 2 Phase 2 51% complete$3 4 million of $6 7 million earned $3.4 million of $6.7 million earned 37.5% of working days expended4.5 months of 12 month working time 4.5 months of 12 month working time expended
![Page 17: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/17.jpg)
“EXAMPLE” CONSTRUCTION PROGRESS CURVE
100
708090
405060
102030
00 10 20 30 40 50 60 70 80 90 100
Percent of Time
![Page 18: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/18.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Phase 2 Phase 2 Constructed temporary trestleCompleted driving piling for bridge piersCompleted driving piling for bridge piersCompleted driving sheet pilingInstalled internal bracing for cofferdamsInstalled internal bracing for cofferdamsBegan pumping water from cofferdams
![Page 19: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/19.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Phase 2 Phase 2 Constructed north abutment retaining wall and abutmentShop drawings for precast concrete deck approved, except for minor detailsRock anchor fabrication underwayNo construction mid March to mid S t bSeptember
![Page 20: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/20.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Phase 2 remaining work Phase 2 remaining work Construct bridge piersDrill and place rock anchorsDrill and place rock anchorsCast and place bridge deck panelsStress bridge deck elementsStress bridge deck elementsInstall handrail and lightingRemove temporary trestlep yCleanup and demobilize
![Page 21: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/21.jpg)
Lake Hodges Bicycle and Pedestrian Bridge Status ReportPedestrian Bridge Status Report
Phase 2 Construction Change Orders Phase 2 Construction Change Orders transfer phase 1 work into phase 2 contract $21,420$ ,Reduction in quantity of driven piling $5,925 Potential redesign bridge railPotential redesign lighting systemPotential to allow work in nesting season
![Page 22: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/22.jpg)
CONSTRUCTION TRESTLE
![Page 23: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/23.jpg)
COFFER DAM FOR PIER CONSTRUCTION
![Page 24: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/24.jpg)
![Page 25: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/25.jpg)
DRIVING PILES FOR PIERS
![Page 26: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/26.jpg)
![Page 27: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/27.jpg)
NORTH ABUTMENT CONSTRUCTION
![Page 28: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/28.jpg)
![Page 29: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/29.jpg)
![Page 30: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/30.jpg)
![Page 31: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/31.jpg)
![Page 32: Lake Hodges Bicycle and Pd ti Bdi Stt R tPedestrian Bridge ... Hodges Bridge/Phase Two/Slide Show L… · Pd ti Bdi Stt R tPedestrian Bridge Status Report Susan Carter, Deputy Director](https://reader034.fdocuments.us/reader034/viewer/2022042318/5f079b9e7e708231d41dd51d/html5/thumbnails/32.jpg)
Lake Hodges Bicycle and P d t i B id St t R tPedestrian Bridge Status Report
Susan Carter, Deputy DirectorSan Dieguito River Park Joint Powers Authoritywww.sdrp.org
Bill Prey, Construction EngineerSANDAG
February 13, 2008