LABOUR CONTRACT AGREEMENT
This Contract of Agreement is made and entered on this day of 9th September 2015 between M/s K.KARTHIK S/O V.Karunanidhi residing at No: 3/2 , V.M.STREET,2 ND LANE ROYAPETTAH,CHENNAI.600014 (hereinafter referred to as (“the Owner”) of the ONE PART AND Mr.C.H.NAGESH having his office and establishment situated at M/S Nageswari construction. No: 26/14,Pallapan Street, Chennai-600 005 (hereinafter referred to as “The Labour Contractor”) of the OTHER PART.
WHEREAS the “Owner” K.KARTHI is is on the look out for a suitable “Labour Contractor” who can undertake/render services for the housing construction in respect of construction the job and the labour contactor of other part agreed to construct the house site situated at Plot No: 3,C B I COLONY, Medavakkam, Chennai-600100 as per the terms and conditions given below
-2- AND WHEREAS the”OWNER” agreed to supply all raw materials to site in appropriate time
AND WHEREAS the”Labour Contractor” has agreed to undertake the said job on the terms of RS.290/- (Ruees Two hundred and ninety only) per square foot of whatever the plinth area constructed. Rate include arranging of labour,civil construction equipment such as column boxes , all centering materials,scafolfings and all masonry tools. Total area constructed will be measured after completion of building taken to account and the conditions set out hereunder:
A. To construct as per Drawing and Details of the job to be given:
B. Rate include complete labour contract to construct the above said premises with all civil work such as all masonry, R.C.C work (Such as Roof,columns,Plinth and roof beams ect.,), Brick walls, plastering of wall,staicase head room, include staircase, sunshades and necessary R.C.lofts
Additional Workswith extra LABOUR The Labour Contractor will be paid for the bellow said job
a) Constructing R.C.C underground Sump @ Rs.07/- per litreb) Constructing underground Septic Tank @ Rs.05/- per litrec) Weathering course over terrace @ Rs.40/- per square footd) Construction of Compound walls Rs.120/- per Running foote) Construction of Parapet wall at terrace floor Rs.60/-per running foot. (applicable only for
construction of ground floor. This will free of cost If the construction goes first floor) The “LabourContractor” has accepted and agreed and herein confirms that he shall abide and is willing to execute the work assigned to him in accordance with the terms and conditions of this Contract of this Agreement
Chennai9.10.2015
SIGNED Owner of the building
SIGNED Labour contractor