Lab # 2
-
Upload
kelly-kirk -
Category
Documents
-
view
20 -
download
0
description
Transcript of Lab # 2
Creating a Task List
TaskTasks are the most basic building blocks
of any project
Task represent the work to be done to accomplish the goals of the project
Task describe project work in terms of sequence, duration and resource requirements
TaskEach task has a unique ID number, but it
does not necessarily represent the order in which task occur
By default the task start date is the same as the project start date and the one day for the duration
Task DurationTask duration is the amount of time you
expect it will take to complete the task
You can work with task duration on the scale of hours, days and weeks (m,h,d,w,mo)
The question mark in the duration field indicates that the duration is an explicit estimate
Task Duration8/80 rule suggests that task duration
between 8 hours and 80 hours are generally sized to a manageable duration
Milestone Milestones are significant events that are
either reached within the project or imposed itself
It represented as task with zero duration
Summary taskIt is helpful to organize groups of closely
related tasks that represent a major portion of the project’s work into phases
For the summary task you can’t edit it’s duration , start date or other calculated value directly
Top- Down & Bottom– Up PlanningTop- Down Planning from general to specific
Bottom– Up Planning from specific to general
Linking tasksSequence: is the second task must occur later
than the first task
Dependency: is the second task can occur only if the first task is completed
Predecessor successor
Linking tasksFinish-to- start FS
Start- to- start SS
Finish-to- finish FF
Start-to- finish SF
Documenting taskYou can record additional information about
task in a note
There are three types of note : task notes, resource notes and assignment notes