L-11 HydropowerConcepts & Simulation
-
Upload
manuel-suero -
Category
Documents
-
view
218 -
download
0
Transcript of L-11 HydropowerConcepts & Simulation
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 1/53
Hydrologic Engineering Center
HydropowerConcepts
How Does Hydropower Affect
Reservoir Simulation?
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 2/53
Topic Objective:
To know the basic hydropower concepts andhow they affect reservoir system analysis.
Power Definitions
Power Demand
Types of Hydropower projects
Computing power release
Reservoir hydropower simulation
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 3/53
Definitions
Work = Force × Distance (ft-lbs. or N-m)
Power = Rate of doing work
Referred to as Capacity (to do work)
Electric Capacity given in Kilowatts orMegawatts (KW or MW)
1 Kilowatt = 1,000 N-m/sec = 737.56 ft-lbs./sec
Energy = Work = Power * Time
Electric Energy given in Kilowatt-hours orMegawatt-hours (KWH or MWH)
Work accomplished, but not how fast!
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 4/53
Nature of Power Demand
Demand for Power must be exactly met
Supply == Demand at all times
Surplus supply must have a use. You can’t storepower on the grid.
Shortages have severe consequences!
Supply based on Maximum (Peak) Demand
Demand varies:
During day
Days of week
Seasonally
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 5/53
Load Curve
Load: demand for
power
Load Curve: Graph of
load changing with
time
Typical Weekly Load:
Sunday low
Nights low
Mid-day peak or
Morning/Evening peak
– varies seasonally
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 6/53
Demand vs. % of time(Same weekly demand)
Shows usage of powerresources
Shows % time required
Base = 100%
Peak < 5%
Value depends on
alternative resources
Load –Duration
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 7/53
Base Load - the minimum load in a period oftime.
Base Load Plant – a power plant that runs at
a constant capacity to carry base load Peak Load - the maximum load in a period of
time.
Peaking Plant - operates to provide powerduring maximum load periods
Load Characterization
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 8/53
Plant Factor
Plant Factor - the fraction of the day during whichthe plant ran at capacity
Plant Factor = 6 hrs of generation at 100% capacity
= 6/24 x 100/100 = .25 or 25%
Plant Factor - the fraction of capacity the plant ranat to meet load ( Avg. Load / Capacity ) Plant Capacity = 60,000 kW
Avg. Load = 8,750 kW
Plant Factor = 8,750 / 60,000 = 15%
If the Plant ran at Capacity to meet this load, it wouldoperate 15% of the time
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 9/53
Load carrying ability of a hydropower plantduring the “Critical Period”
Critical Period (for hydropower) - when thelimitations of hydroelectric power supplydue to water conditions are most criticalwith respect to system load requirements
Drought period (or low water availability)
coincident with..
High demand
Dependable Capacity
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 10/53
Dependable (Firm) Energy
Energy associated with Dependable Capacity
Electric energy which is intended to have
assured availability to the customer to meet
all or any agreed upon portion of his load
requirements
Assured availability usually means that no
shortages will be tolerated
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 11/53
Separate benefits for energy & capacity Energy … power generated
Capacity … ability to generate
Primary Power benefits for dependablecapacity and firm energy Energy based on kW-Hrs on demand
Capacity based on availability at critical period
Secondary Power benefits for energyproduced during high flow periods Secondary value usually much lower
Value of Energy and Capacity
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 12/53
Storage Reservoirs
All or part of the reservoir pool is allocatedto power
For generation – a power pool
To maintain head – buffer or operating inactive
Releases made to meet Energy demand
Power storage used when flow is low
Headwater varies with pool
Tailwater dependent on flow
Primary and Secondary energy are outputs
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 13/53
Run-of-River Reservoirs
Headwater essentially constant
Tailwater dependent on flow
Energy is a function of flow (in & out)
Energy is Secondary with lower value
Often downstream from storage reservoir
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 14/53
Storage – Peaking Reservoirs
Peaking Power operates for short interval
High releases during generation
Minimum Releases during non-power
periods Releases impact downstream system
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 15/53
Power demand function of pool level
Firm energy from minimum power pool topower rule curve
Higher energy produced when above powerrule curve
Provides more energy when water supply ishigh
Storage – Power Guide Curve
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 16/53
Firm Energy Computations
Computed for the Critical Period.
Energy produced during the period ofmaximum drawdown is determined
Annual Firm Energy is based on the sum ofminimum energy produced in each timeperiod of the calendar year.
Dependable Capacity is the capacity associated
with Firm Energy.
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 17/53
Power Equation
Power = weight of a discharge “falling” adistance
Power (kW) = [Q * w * h * e] / 737.56
Q = discharge in cfs
w = weight of water in lbs./ft3
h = net head in feet (Total h - Hydraulic losses)
e = efficiency of generator & turbine units
737.56 ft-lbs./sec = 1 Kilowatt
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 18/53
Q = 737.56 (kW) / (w * h * e)
if, e = constant 0.86
w = 62.4 lbs./ft3
Q = 13.74 ( kW / h )
h = Headwater - Tailwater - Losses
Headwater, Tailwater, & Loss depend on Q
Iterative solution is required
Calculation of Power Release
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 19/53
Power Release Determination:Instantaneous
Assume net Head Initial estimate based on end of previous period or
iteration
Compute Q, based on capacity (kW)
Determine Tailwater for Q
Calculate net Head, based on headwater,tailwater and losses
Compute new discharge using net Head Repeat until net Head remains the same
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 20/53
Compute Average Q for period
Compute ending Storage Outflow = Qpower + Losses + Evaporation
Determine ending Elevation Calculate avg. Headwater for period
Repeat until average Q remains the same
Power Release Determination:Period Average
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 21/53
Leakage & Seepage
Evaporation - dependent on release
Fish Ladders
Navigation Locks
Water Supply withdrawals
Station use: cooling, power,
Minimum releases during non-generationperiods
Water Lost to Hydropower
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 22/53
Hydropower Limits
Penstock Flow Capacity – can’t release morethan penstock can carry
Turbine Capacity – can’t release more than theturbine can discharge
Generator Overload Capacity – can’t generatemore than maximum capacity
Variable efficiency – maximum efficiency exists
in a narrow range of head and discharge
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 23/53
References
Estimate of National Hydroelectric Power Potentialat Existing Dams, USACE, July 1977
Hydroelectric Power Evaluation, Federal PowerCommission, FPC P-35, March 1968
Hydropower, EM 1110-2-1701, 31 Dec 1985
Potential for Increasing the Output of ExistingHydroelectric Plants, USACE, HEC July 1981
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 24/53
Hydrologic Engineering Center
Hydropower Simulation
HEC-ResSim
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 25/53
Objectives
To know how to:
Add a Power Plant to a reservoir and define Power
Plant Data
Add Hydropower Rules to the system
Control Release Allocation to outlets
Review the hydropower output options
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 26/53
Hydropower Data
Physical Data
Add Power Plant
Define Power Plant Data Outlet Capacity
Power Capacity
Efficiency
Losses
Station Use
Hyd. losses
Add Tailwater Elevation
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 27/53
Add a Power Plant
Add Power Planta) Use component-specific menu
b) Use right-click shortcut menu
P Pl D O l
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 28/53
Power Plant Data-OutletCapacity
Physical Powerhouse
Capacity
Elevation vs Flow
Limits Flow for power
generation
Considerations:
“Best Gate”
“Full Gate”
P Pl t D t P
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 29/53
Power Plant Data-PowerCapacity
Select Capacity tab in Power Plant dialog
Enter the Installed Capacity (MW).
Select the Variable Capacity option
Installed Capacity with Overload factor
Enter the Overload Factor Function of Reservoir Elevation
Function of Reservoir Storage
Function of Release
Function of Operating Head
P Pl t D t Pl t
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 30/53
Power Plant Data-PlantEfficiency
Select Efficiency tab in Power Plant dialog
Select the Efficiency Method option Constant
Function of Reservoir Elevation
Function of Release Function of Operating Head
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 31/53
Power Plant Data-Station Use
Select Station Use tab in Power Plant dialog
Select the Station Use Method option Constant
Function of Release
Station use is not available for power generation
P Pl t D t H d li
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 32/53
Power Plant Data-HydraulicLosses
Select Hyd. Losses tab in Power Plant dialog
Select the Hydraulic Losses Method option Constant (feet/meter)
Function of Release (Release vs. loss)
Hydraulic Loss is subtracted from Gross Head in power
computations.
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 33/53
Add Tailwater Elevation
Add Tailwatera) Use component-specific menu
b) Use right-click shortcut menu
Tailwater
Tailwater appears in tree below theselected component
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 34/53
Define Tailwater Elevation
Select Tailwater
Enter data
Constant Elevation
Downstream Control
Rating Curve
If multiple data,
higher controls
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 35/53
Hydropower - Power Guide Curve
Hydropower - Schedule
Hydropower - System Schedule
Hydropower - Time-series Requirement
Hydropower Operation Rules
Hydropower Power Guide
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 36/53
Create the rule
Select the top and bottom zones
of the power pool
Hydropower-Power GuideCurve
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 37/53
Complete thetable to define
the rule
% Storage vs.
% Plant Factor
Power Generation
Pattern
Power Guide Curve
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 38/53
Power Generation Pattern
Pattern applies all year
Weekly Pattern
Seasonal Variation
Specify weekly Pattern for:
All Week
Weekdays & Weekends
Each Day
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 39/53
Power Generation Pattern
Seasonal Variation
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 40/53
Create the rule Requirement varies
Monthly
Seasonally
Specified as:
Plant Factor
Daily MWH
Weekly MWH
Monthly MWH
Starting day of week Week belongs…day
Period to satisfy the
requirement
Hydropower-Schedule
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 41/53
Hydropower Schedule
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 42/53
Hydropower-System Schedule
d i i
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 43/53
Hydropower-Time Series
R l All i Wh ?
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 44/53
Release Allocation-What?
What is Release Allocation? Which outlets should release first, next, and so on
Balanced approach
Evenly weighted (e.g., 50:50 split (default))
Unevenly weighted (e.g. 60:40 split)
Sequential approach
Hydropower reservoirs often direct any release to thepower plant first
Other outlets release water when the power plant
reaches capacity Release Allocation is an “operations” option
Define the priority (or order) to the available outlets
R l All ti H ?
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 45/53
Release Allocation – How?
Operations Tab in Reservoir Editor Use Specified Release Allocation
Specify Allocation Type
Balanced
Specify the component weighting
Sequential
Specify the component order
P O t t O ti
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 46/53
Reports
Power Summary
Plots Options
Plot
Plot Power
User Plots
Power Output Options
P S R t
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 47/53
Power Summary Report
P Pl
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 48/53
Power Plot
U D i d Pl t E l
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 49/53
User Designed Plot Example
Bring up thedefault plot
Open the “SelectPlot Variables”
menu
User Designed Plot Example
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 50/53
User Designed Plot Example
Save Custom Plots for reuse
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 51/53
Save Custom Plots for reuse
Summary
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 52/53
Summary
In the Reservoir Editor, Physical Tab… Add Power Plant
Define Power Plant Parameters
Add Tailwater
In the Reservoir Editor, Operations Tab… Add Hydropower Rule to an Operating Zone Specify Hydropower Requirements
Specify Release Allocation Type
Analyze results with plots and reports
Questions?
7/23/2019 L-11 HydropowerConcepts & Simulation
http://slidepdf.com/reader/full/l-11-hydropowerconcepts-simulation 53/53
Questions?