KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7...

41
Reconstruction of the Historic BNSF Br. 482.1 Temple Overman (HNTB) & Cory Duerr (KNA) KU Structures Conference March 7, 2019

Transcript of KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7...

Page 1: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

Reconstruction of the Historic BNSF Br. 482.1Temple Overman (HNTB) & Cory Duerr (KNA)

KU Structures Conference

March 7, 2019

Page 2: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

OUTLINE

Project Overview Bridge Elements Phase Changeouts Construction Highlights and Lessons

Learned− Mass Concrete− Accelerated Bridge Construction− Construction Quantities

2

Page 3: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

PROJECT LOCATION

3

PROJECT OVERVIEW

BNSF Bridge 482.1

W. Memphis, AR Memphis, TN

Page 4: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

PROJECT TIMELINE

4

November 2015 to October 2017 Historic Flooding

PROJECT OVERVIEW

Page 5: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

FORMER LAYOUT

5

Chief Engineer: George S. Morison Open for traffic on May 12, 1892 First bridge across the Lower Mississippi

PROJECT OVERVIEW

Page 6: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

NEW LAYOUT

6

PROJECT OVERVIEW

2,711’-9” Total Length With Spans From 72’-6” to 191’-0”Constructed On Alignment

Page 7: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

OLD APPROACH

7

PROJECT OVERVIEW

Page 8: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

NEW APPROACH

8

PROJECT OVERVIEW

Page 9: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

PEDESTRIAN BRIDGE

9

PROJECT OVERVIEW

Page 10: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

HYBRID SUBSTRUCTURE

10

BRIDGE ELEMENTS

Column Diameters: 7’ to 10’ Drilled Shaft Diameters: 8’ to 10’

Page 11: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

HYBRID SUBSTRUCTURE

11

BRIDGE ELEMENTS

Page 12: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

HYBRID SUBSTRUCTURE

12

Hybrid Drilled Shaft/Micropiles

BRIDGE ELEMENTS

Page 13: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

HYBRID SUBSTRUCTURE

13

BRIDGE ELEMENTS

8 Micropiles in 10’ Shafts, 4 Micropiles in 8’ Shafts. 280 total production micropiles.

Page 14: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

SUPERSTRUCTURE

14

BRIDGE ELEMENTS

DPG spans w/ steel or composite concrete deck 6 Span Lengths

− 72’-6”, 77’-2”, 88’-2”, 176’-6”, 178’-1”, 191’-0”

Page 15: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

SUPERSTRUCTURE

15

BRIDGE ELEMENTS

Page 16: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

PHASE I CHANGEOUT November 10-11, 2016

16

Spans 1 – 7 Replaced 748’

PHASE CHANGEOUTS

Page 17: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

17

Spans 8 – 15 Replaced 708’

PHASE CHANGEOUTS PHASE II CHANGEOUT

February 20-21, 2017

Page 18: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

18

Spans 16-23 Replaced 708’

PHASE III CHANGEOUT April 3-4, 2017

PHASE CHANGEOUTS

Page 19: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

19

Spans 24-27 Replaced 548’

PHASE IV CHANGEOUT August 28-30, 2017

PHASE CHANGEOUTS

Page 20: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

20

Mass ConcreteCONSTRUCTIONHIGHLIGHTS & LESSONS LEARNED

Page 21: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

21

ACI 207.1R-05 - Guide to Mass Concrete (Reapproved 2012)“Mass concrete is any volume of concrete with dimensions large enough to require that measures be taken to cope with the generation of heat from hydration of the cement and attendant volume change to minimize cracking.”

BNSF West Memphis Approach Specification defined Mass Concrete as.

“Mass concrete placement shall be defined as any pour in which the concrete being cast has dimensions greater than or equal to 6’ in three different directions.”

Mass Concrete DefinitionCONSTRUCTION Mass Concrete

Page 22: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

22

CTL Group (John Gajda) Analyzed Materials & Temperature Control Methods

− Maximum Temperature, Minimum Temperature, Temperature Differential

Time vs. Effort− Proper Preparation of Concrete = Cooling Tubes Not Required− Temperatures Needed Monitored 3x to 4x Longer Without Cooling

Tubes

PlanningCONSTRUCTION Mass Concrete

Page 23: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

23

Ready Mix Plant− Aggregate stored under canopies & sprinkled with 34°F water− Concrete was mixed using 50-75% of its water content from

ice− Remaining makeup water was added at 34°F

Concrete Preparation & CoolingCONSTRUCTIONMass Concrete

Page 24: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

24

Onsite Preparations− Decision was made to use cooling tubes

− Cooling tubes were used on all substructure placements except Pier 27 footing

− As a comparison Pier 3 with cooling tubes completed thermal cure in 5 Days; Pier 27 without cooling tubes completed thermal cure in 27 Days

− Water was cycled through Frac Tanks− Up to 5 Frac tanks were used− Water was flushed anytime it exceeded 80°F

Concrete Preparation & CoolingCONSTRUCTION Mass Concrete

Page 25: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

25

Trouble Shooting the Plan− Kraemer had to cancel the first mass concrete pour after the first 3

trucks showed up too hot to place.− Some inspection showed that some parts of our plan were not being

followed as closely as we would have liked.− We found that when temperatures and humidity was high we needed

to place all of our concrete at night.

Warmer was Better (for the Schedule)− Once the concrete was placed at an appropriate temperature it was

found that we were able to have the concrete out of thermal monitoring much sooner, because the likelihood of the temperature differential exceeding its maximum was much less apt to occur.

Trouble Shooting Mass ConcreteCONSTRUCTION Mass Concrete

Page 26: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

26

Accelerated Bridge Construction

Precast Concrete Elements Temporary Jump Spans Extended Pier Cap Beams Pier 27 Construction Deck Truss Removal Span Roll-Ins

CONSTRUCTIONHIGHLIGHTS & LESSONS LEARNED

Page 27: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

27

Precast Concrete ElementsABC

Page 28: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

28

Temporary Jump Spans

Transition from New Ballast Deck to Existing Open Tie Deck

ABC

Page 29: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

29

Extended Pier Cap BeamsABC

Page 30: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

30

Extended Pier Cap BeamsABC

Page 31: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

31

Pier 27 ConstructionABC

Page 32: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

32

Pier 27 ConstructionABC

Page 33: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

33

Pier 27 ConstructionABC

Page 34: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

34

Deck Truss RemovalABC

Page 35: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

35

Deck Truss RemovalABC

Page 36: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

36

Span 2 & 3 Roll-Ins

Phase I Changeout− 2 ~ 176.5’ Spans Rolled Transversely 17’-6.75”

ABC

Page 37: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

37

Span 2 & 3 Roll-InsABC

Page 38: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

38

ABC Span 26 & 27 Roll-Ins

Span 27 rolled transversely 23’-8” and longitudinally 3’-8” Span 26 rolled transversely 23’-8”

Page 39: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

39

ABC Span 26 & 27 Roll-Ins

Page 40: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

CONSTRUCTION QUANTITIES

40

Total Concrete Quantity ≈ 16,000 CY Total Rebar Quantity ≈ 3 million lbs Structural Steel Quantity ≈ 8.2 million lbs

CONSTRUCTIONHIGHLIGHTS

Page 41: KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7 Replaced 748’ PHASE CHANGEOUTS. 17 Spans 8 – 15 Replaced 708’ PHASE CHANGEOUTS.

QUESTIONS?

41