KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7...
Transcript of KU Structures Reconstruction of the Historic BNSF Br. 482...November 10-11, 2016 16 Spans 1 – 7...
Reconstruction of the Historic BNSF Br. 482.1Temple Overman (HNTB) & Cory Duerr (KNA)
KU Structures Conference
March 7, 2019
OUTLINE
Project Overview Bridge Elements Phase Changeouts Construction Highlights and Lessons
Learned− Mass Concrete− Accelerated Bridge Construction− Construction Quantities
2
PROJECT LOCATION
3
PROJECT OVERVIEW
BNSF Bridge 482.1
W. Memphis, AR Memphis, TN
PROJECT TIMELINE
4
November 2015 to October 2017 Historic Flooding
PROJECT OVERVIEW
FORMER LAYOUT
5
Chief Engineer: George S. Morison Open for traffic on May 12, 1892 First bridge across the Lower Mississippi
PROJECT OVERVIEW
NEW LAYOUT
6
PROJECT OVERVIEW
2,711’-9” Total Length With Spans From 72’-6” to 191’-0”Constructed On Alignment
OLD APPROACH
7
PROJECT OVERVIEW
NEW APPROACH
8
PROJECT OVERVIEW
PEDESTRIAN BRIDGE
9
PROJECT OVERVIEW
HYBRID SUBSTRUCTURE
10
BRIDGE ELEMENTS
Column Diameters: 7’ to 10’ Drilled Shaft Diameters: 8’ to 10’
HYBRID SUBSTRUCTURE
11
BRIDGE ELEMENTS
HYBRID SUBSTRUCTURE
12
Hybrid Drilled Shaft/Micropiles
BRIDGE ELEMENTS
HYBRID SUBSTRUCTURE
13
BRIDGE ELEMENTS
8 Micropiles in 10’ Shafts, 4 Micropiles in 8’ Shafts. 280 total production micropiles.
SUPERSTRUCTURE
14
BRIDGE ELEMENTS
DPG spans w/ steel or composite concrete deck 6 Span Lengths
− 72’-6”, 77’-2”, 88’-2”, 176’-6”, 178’-1”, 191’-0”
SUPERSTRUCTURE
15
BRIDGE ELEMENTS
PHASE I CHANGEOUT November 10-11, 2016
16
Spans 1 – 7 Replaced 748’
PHASE CHANGEOUTS
17
Spans 8 – 15 Replaced 708’
PHASE CHANGEOUTS PHASE II CHANGEOUT
February 20-21, 2017
18
Spans 16-23 Replaced 708’
PHASE III CHANGEOUT April 3-4, 2017
PHASE CHANGEOUTS
19
Spans 24-27 Replaced 548’
PHASE IV CHANGEOUT August 28-30, 2017
PHASE CHANGEOUTS
20
Mass ConcreteCONSTRUCTIONHIGHLIGHTS & LESSONS LEARNED
21
ACI 207.1R-05 - Guide to Mass Concrete (Reapproved 2012)“Mass concrete is any volume of concrete with dimensions large enough to require that measures be taken to cope with the generation of heat from hydration of the cement and attendant volume change to minimize cracking.”
BNSF West Memphis Approach Specification defined Mass Concrete as.
“Mass concrete placement shall be defined as any pour in which the concrete being cast has dimensions greater than or equal to 6’ in three different directions.”
Mass Concrete DefinitionCONSTRUCTION Mass Concrete
22
CTL Group (John Gajda) Analyzed Materials & Temperature Control Methods
− Maximum Temperature, Minimum Temperature, Temperature Differential
Time vs. Effort− Proper Preparation of Concrete = Cooling Tubes Not Required− Temperatures Needed Monitored 3x to 4x Longer Without Cooling
Tubes
PlanningCONSTRUCTION Mass Concrete
23
Ready Mix Plant− Aggregate stored under canopies & sprinkled with 34°F water− Concrete was mixed using 50-75% of its water content from
ice− Remaining makeup water was added at 34°F
Concrete Preparation & CoolingCONSTRUCTIONMass Concrete
24
Onsite Preparations− Decision was made to use cooling tubes
− Cooling tubes were used on all substructure placements except Pier 27 footing
− As a comparison Pier 3 with cooling tubes completed thermal cure in 5 Days; Pier 27 without cooling tubes completed thermal cure in 27 Days
− Water was cycled through Frac Tanks− Up to 5 Frac tanks were used− Water was flushed anytime it exceeded 80°F
Concrete Preparation & CoolingCONSTRUCTION Mass Concrete
25
Trouble Shooting the Plan− Kraemer had to cancel the first mass concrete pour after the first 3
trucks showed up too hot to place.− Some inspection showed that some parts of our plan were not being
followed as closely as we would have liked.− We found that when temperatures and humidity was high we needed
to place all of our concrete at night.
Warmer was Better (for the Schedule)− Once the concrete was placed at an appropriate temperature it was
found that we were able to have the concrete out of thermal monitoring much sooner, because the likelihood of the temperature differential exceeding its maximum was much less apt to occur.
Trouble Shooting Mass ConcreteCONSTRUCTION Mass Concrete
26
Accelerated Bridge Construction
Precast Concrete Elements Temporary Jump Spans Extended Pier Cap Beams Pier 27 Construction Deck Truss Removal Span Roll-Ins
CONSTRUCTIONHIGHLIGHTS & LESSONS LEARNED
27
Precast Concrete ElementsABC
28
Temporary Jump Spans
Transition from New Ballast Deck to Existing Open Tie Deck
ABC
29
Extended Pier Cap BeamsABC
30
Extended Pier Cap BeamsABC
31
Pier 27 ConstructionABC
32
Pier 27 ConstructionABC
33
Pier 27 ConstructionABC
34
Deck Truss RemovalABC
35
Deck Truss RemovalABC
36
Span 2 & 3 Roll-Ins
Phase I Changeout− 2 ~ 176.5’ Spans Rolled Transversely 17’-6.75”
ABC
37
Span 2 & 3 Roll-InsABC
38
ABC Span 26 & 27 Roll-Ins
Span 27 rolled transversely 23’-8” and longitudinally 3’-8” Span 26 rolled transversely 23’-8”
39
ABC Span 26 & 27 Roll-Ins
CONSTRUCTION QUANTITIES
40
Total Concrete Quantity ≈ 16,000 CY Total Rebar Quantity ≈ 3 million lbs Structural Steel Quantity ≈ 8.2 million lbs
CONSTRUCTIONHIGHLIGHTS
QUESTIONS?
41