    Commissioning Procedure for Khabat PP 132kV SwitchyardProtection Equipment Tests

    TOTAL 12 PAGES

    (Including Cover)

    PROJECT NAME : Khabat Thermal Power Plant Units 1&2 Purpose

    ☐ For Information☒ For Review

    ☐ For Approval

    ☐ For Construction

    ☐ As-Built

    DOCUMENT NO. : KP-00+++-TZ782-V0015

    TITLE : Commissioning Procedure for Khabat PP  132kV Switchyard Protection Equipment Tests

    OWNER : Ministry of Electricity (MOE) of Kurdistan Regional Government

    A 29.04.2015 First Issue DE EÖ AY YÖ

    Rev.No.

    DATE DESCRIPTIONPREPARED CHECKED REVIEWED APPROVED

    GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

    Owner 

    Ministr y of Electrici ty (MOE)of Kurdistan Regional Government

    Contractor 

    POSCO ENGINEERING

    & CONSTRUCTION CO., LTD.

    Main Subcontractor 

    GAMA POWER SYSTEMS

    ENGINEERING & CONTRACTING,INC.

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    2/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 1/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    Khabat Thermal Power Plant Units 1&2 Project132kV Air Insulated Switchgear 

    COMMISSIONING PROCEDURE FOR 132kV

    SWITCHYARD PROTECTION EQUIPMENT TESTS

    DOCUMENT NO: KP-00+++-TZ782-V0015

    SUBCONTRACTOR: SIEMENS

    GAMA REVIEW

    DisciplineSuperintendent

    HSE Manager QA/QC Manager Site Manager  

    Name

    Date

    Sign

    Remarks:Any such review or consent by GAMA, shall not relieve the Subcontractor, in any case or for any reason whatsoever,from any obligation, liability or responsibility arising out of or in connection with the Contract, including without being

    limited thereto, to the responsibility for errors, omissions, discrepancies and non-compliances. Within this context, thisdocument shall not prevail over or amend the Contract, or relieve the Subcontractor from any of its duties, obligations,responsibilities or liabilities under the Contract.Anything presented herein by the Subcontractor shall in no eventi) excuse the Subcontractor’s non-performance under the Contract, or ii) entitle him to a variation under the Contract or an adjustment to the Contract Price.

    SUBCONTRACTOR

    Rev.No.

    Date Description*Prepared

    byHSE

    Manager QA/QC

    Manager Site

    Manager Project

    Manager 

    A 29.04.2015 132kV SwitchyardSteel Erection

    Works

    DenizEREN

    - - - EyyüpÖZBAY

    DOCUMENT HISTORY:

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    3/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 2/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    Rev.

    No. Date

    Remarks

    (Reason for Revision)

    A 29.04.2015 First Issue

    * Descript ion:

    Document issue purpose

    - First Issue

    - For Information

    - For Review

    - For Approval (or Issued for Construction)

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    4/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 3/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    CONTENT

    1.0 OBJECTIVE ........................................................................................................................ 4

    2.0 ACCEPTANCE CRITERIA .................................................................................................. 4

    3.0 TEST AND COMMISSIONING PROCEDURE ..................................................................... 4

    4.0 TEST AND COMMISSIONING SCHEDULE ........................................................................ 6

    5.0 PREREQUISITES............................................................................................................... 6

    6.0 PRECAUTIONS AND NOTES ............................................................................................ 6

    7.0 TEST EQUIPMENT ............................................................................................................ 6

    8.0 RESTORATION ................................................................................................................. 6

    9.0 REFERENCES ................................................................................................................... 6

    10.0 APPENDIX ......................................................................................................................... 7

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    5/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 4/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    1.0 OBJECTIVE

    To provide instructions for electrical testing of Protection Equipments before putting

    into service. It included visual inspection of the Protection Cubicle’s for proper 

    installation and cleanness, to verify the correct operation and to verify equipments meet

    the acceptable requirements.

    2.0 ACCEPTANCE CRITERIA

    This procedure applies to the following testing for Protection System.

    1) Visual Check of Protection Equipments

    2) Protection Cubicle Mechanical and Electrical Functional Tests

    3.0 PROCEDURE

    3.1 VISUAL CHECK

    The system is checked with mentioned items below visually.

    3.1.1 Missing Equipment

    The devices and equipments that are shown on the drawings are checked to be

    mounted 

    3.1.2 Cable Connections

      Power and control cable connections are checked according to drawings

    3.1.3 Earthing of Panel

      Panel should be earthed from the earthing busbar or earthing terminal

    3.2 CUBICLE ELECTRICAL AND MECHANICAL FUNCTIONAL TEST

     The systems is functionally tested with mentioned items below as electrical and mechanical.

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    6/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 5/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    3.2.1 Mechanical Checks of Cubicle

      The panels are checked that its door and moving parts are operating well

    3.2.2 Polarity of DC Voltage

     Before energising the system, firstly the terminal connections are checked. After 

    supplying DC voltage to relevant system, it should be sure that the polarity is

    correct by measuring on L(+) and L(-) terminals.

    3.2.3 Internal Functional Test

    Internal circuitry of panel is checked to be working, regarding the drawings.

    3.2.4 External Functional Test

    Signals between panels, CB Commands and other equipments of the system isverified according to drawings.

    3.2.5 Relay Software Download and Interlocking Conditions

    Prepared relay settings file is downloaded to device. Inputs and Outputs are

    checked by connection to relay. Interlocks over the relay (CFC etc.) are checked,

    regarding the drawings.

    3.2.6 Secondary Voltage-Current Injection

    All measurements of current and voltage circuits are observed with secondaryinjection.

    3.2.7 Simulation of Protection Functions

    Protection relays are tested for trip limits by simulation of fault conditions. Trip

    signals are also observed. (Omicron156/256 or eqv. is used.)

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    7/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 6/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    4.0 TEST AND COMMISSIONING SCHEDULE

    According to updated time schedule, which is submitted separately.

    5.0 PREREQUISITIES

    1) Protection Panel should be installed.

    2) External cable connections should be completed.

    3) AC and DC power should be prepared.

    4) Panel Grounding should be completed.

    6.0 PRECAUTIONS AND NOTES

    The following shall be done in order to made safe prior to starting of Protection

    Equipment testing

    1) Equipments which is related with Protection system should be mounted and 

    tested before starting Protection Equipment tests.

    2) Warning types shall be installed around the HV Switchyard’s in order to provideunauthorized access to testing area.

    7.0 TEST EQUIPMENT

    Testing equipments with necessary test certificates will be informed later.

    8.0 RESTORATION

    In case of necessity for processing on the commissioning tests, some revision could be done on

    secondary drawing by informing responsible designer.

    9.0 REFERENCE

    · Electrical Single-Line Diagrams

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    8/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 7/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    10.0 APPENDIX

    APPENDIX A – PROTECTION PANEL CHECKLIST

    EQUIPMENT IDENTIFICATION

    FACILITY UNIT NO. JOB NO. SHEET

     ____ OF ____

    SYSTEM EQUIPMENT NAME/NUMBER

    Rated Voltage: Feeder Name: Frequency:

    TEST EQUIPMENT

    NAME OF MANUFACTURER SERIAL NUMBER:

    CALIBRATION DUE DATE PANEL TYPE:

    TEST RESULTS

    Test results are attached.

    REMARKS

    SYSTEM COMMISSIONING ENGINEER DATE APPROVED DATE

    Control&Tests Status Notes

    1 Earthing connection completed?

    2 Cable connections completed?

    3 Terminals labelled?

    4 Polarity of DC Contol Voltage

    5 Functional Test of Control Circuit

    6 Measurement Devices

    7 Alarms and Indications

    8 Interlocking Conditions

    9 Local&Remote control

    10 Voltage Circuit control

    11 Current Circuit Control

    12 Functional Test of Protection RelaySee attached Test Protocol.

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    9/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 8/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    APPENDIX B- LINE DISTANCE PROTECTION RELAY TEST REPORT

    EQUIPMENT IDENTIFICATION

    FACILITY UNIT NO. JOB NO. SHEET

     ____ OF ____

    SYSTEM EQUIPMENT NAME/NUMBER

    VT Ratio: Frequency: Line Length(km): CT Ratio:

    TEST EQUIPMENT

    NAME OF MANUFACTURER SERIAL Number:

    CALIBRATION DUE DATE Protective Relay:

    RELAY SETTINGS

    Relay settings and selectivity study can be added to this section

    Function tests Status Notes

    1 Line Differential Protection Test

    2 Synchrocheck Function Test Test

    3   Dİstance Protection Function Test

    4 Backup Protection Test

    5 Fault Locator 

    6 Switch on to Fault Function Test

    7 Auto Reclose Function Test

    TEST RESULTS

    Test results are attached.

    REMARKS

    SYSTEM COMMISSIONING ENGINEER DATE APPROVED DATE

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    10/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 9/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    APPENDIX C- OVERCURRENT PROTECTION RELAY TEST REPORT

    EQUIPMENT IDENTIFICATION

    FACILITY UNIT NO. JOB NO. SHEET

     ____ OF ____

    SYSTEM EQUIPMENT NAME/NUMBER

    VT Ratio: Frequency: Line Length(km): CT Ratio:

    TEST EQUIPMENT

    NAME OF MANUFACTURER SERIAL Number:

    CALIBRATION DUE DATE Protective Relay:

    RELAY SETTINGS

    Relay settings and selectivity study can be added to this section

    TEST RESULTS

    Test results are attached.

    REMARKS

    SYSTEM COMMISSIONING ENGINEER DATE APPROVED DATE

    No Control &Tests Status Explanation

    1 Output Check

    2 Input Check

    3 50/51/67, Phase Time Overcurrent

    4 50N/51N/67N, Neutral Time Overcurrent

    5 49, Thermal Overload

    6 46, Unbalance Load Protection

    7 75TC, Trip Circuit Supervis ion

    8 Ossilographic Fault Records

    9 CFC

    10 Event Log, Trip Log

    11 Measurement Check (P,Q,pf,Energy)

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    11/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 10/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    APPENDIX D – BUSBAR AND BREAKER FAILURE PROTECTION RELAY TEST

    REPORT

    EQUIPMENT IDENTIFICATION

    FACILITY UNIT NO. JOB NO. SHEET

     ____ OF ____

    SYSTEM EQUIPMENT NAME/NUMBER

    VT Ratio: Frequency: Line Length(km): CT Ratio:

    TEST EQUIPMENT

    NAME OF MANUFACTURER SERIAL Number:CALIBRATION DUE DATE Protective Relay:

    RELAY SETTINGS

    Relay settings and selectivity study can be added to this section

    Busbar ProtectionTest Settings Operational Sett ings

    Current Time Current Time

    Idiff>

    Idiff>>

     Busbar Protection Function Tests

    Feeder No

    Test I (A) Trip Time (ms)Phase L1

    Trip Time (ms)Phase L2

    Trip Time (ms)Phase L3

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    Breaker Failure ProtectionTest Settings Operational Sett ings

    Current Time Current Time

    Iq>

    Iq>>

  • 8/17/2019 KP-00+++-TZ782-V0015-Rev A-protection equipment comm procedure.pdf

    12/12

    COMMISSIONING PROCEDURE FOR 132kV SWITCHYARD PROTECTIONEQUIPMENT TESTS

    Page: 11/11 Doc. No: KP-00+++-TZ782-V0015 Date:29.04.2015

    Dok. No: KP-00+++-TZ782-V0015, Rev. No: A

    Breaker Failure Protection Function Tests

    Feeder No

    Test I (A) Trip Time (ms)Phase L1

    Trip Time (ms)Phase L2

    Trip Time (ms)Phase L3

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    TEST RESULTS

    Test results are attached.

    REMARKS

    SYSTEM COMMISSIONING ENGINEER DATE APPROVED DATE