Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower...

62
Kootenai Lower Meander Project Draft Environmental Assessment March 2017 DOE/EA2051

Transcript of Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower...

Page 1: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

KootenaiLowerMeanderProject

DraftEnvironmentalAssessment

March2017

DOE/EA‐2051

Page 2: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai
Page 3: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject2 DraftEnvironmentalAssessment

TableofContents

1  PURPOSE AND NEED FOR ACTION ........................................................................................ 6 1.1  Introduction ........................................................................................................................................... 6 

1.2  Need for Action ..................................................................................................................................... 6 

1.3  Purposes ................................................................................................................................................. 6 

1.4  Background ............................................................................................................................................ 7 

1.5  Public Involvement ............................................................................................................................... 8 

2  PROPOSED ACTION AND ALTERNATIVES .......................................................................... 9 2.1  Proposed Action .................................................................................................................................... 9 

2.2  No Action Alternative ........................................................................................................................ 16 

2.3  Comparison of Alternatives ............................................................................................................... 16 

2.4  Mitigation Measures ........................................................................................................................... 20 

3  AFFECTED ENVIRONMENT AND ENVIRONMENTAL CONSEQUENCES ................. 25 3.1  Soils and Geology ................................................................................................................................ 25 

3.2  Wetlands ............................................................................................................................................... 26 

3.3  Water Resources .................................................................................................................................. 28 

3.4  Fish and Fish Habitat .......................................................................................................................... 32 

3.5  Recreation ............................................................................................................................................. 35 

3.6  Cultural Resources .............................................................................................................................. 37 

3.7  Visual Resources .................................................................................................................................. 39 

3.8  Noise ..................................................................................................................................................... 39 

3.9  Air Quality and Greenhouse Gasses ................................................................................................. 41 

3.10  Public Health and Safety .................................................................................................................... 42 

3.11  Transportation and Utilities ............................................................................................................... 43 

3.12  Socioeconomics .................................................................................................................................... 44 

3.13  Other Environmental Resources ....................................................................................................... 47 

3.14  Cumulative Effects Analysis .............................................................................................................. 47 

4  ENVIRONMENTAL CONSULTATION, REVIEW, AND PERMIT REQUIREMENTS .. 51 4.1  National Environmental Policy Act .................................................................................................. 51 

4.2  Wetlands, Floodplains, and Water Resources ................................................................................. 51 

4.3  Fish and Wildlife ................................................................................................................................. 52 

4.4  Land Use Plan Consistency ................................................................................................................ 54 

4.5  Farmland Protection Policy Act ........................................................................................................ 54 

4.6  Cultural and Historic Resources ....................................................................................................... 54 

4.7  Air Quality ........................................................................................................................................... 55 

4.8  Climate Change ................................................................................................................................... 55 

4.9  Noise ..................................................................................................................................................... 56 

4.10  Hazardous Materials ........................................................................................................................... 56 

4.11  Executive Order on Environmental Justice ...................................................................................... 56 

5  TRIBES, AGENCIES, AND PERSONS CONSULTED ........................................................... 57 5.1  Federal Agencies ................................................................................................................................. 57 

Page 4: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 3

5.2  State Agencies ...................................................................................................................................... 57 

5.3  Tribes ..................................................................................................................................................... 57 

5.4  Local Governments ............................................................................................................................. 57 

5.5  Other ..................................................................................................................................................... 57 

6  REFERENCES .................................................................................................................................. 58 

7  WORKS CITED .............................................................................................................................. 59 

Page 5: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject4 DraftEnvironmentalAssessment

ListofFigures

Figure 1  Lower Meander Project Location ............................................................................................................. 9 

Figure 2  Lower Meander Project Area .................................................................................................................. 10 

Figure 3  Kootenai Lower Meander construction actions, Phase 1 (upstream) ................................................ 11 

Figure 4  Kootenai Lower Meander construction actions, Phase 2 (downstream) .......................................... 11 

Figure 5  Examples of large bank structures in the Kootenai River ................................................................... 13 

Figure 6  Pool excavation actions in the Kootenai River ..................................................................................... 14 

Figure 7  Vegetated brush bank structures under construction at the 2015 Bonners Ferry Islands 

project ............................................................................................................................................... 14 

Figure 8  Staging areas and temporary haul roads .............................................................................................. 15 

Figure 9  Examples of temporary river access road construction ...................................................................... 16 

Figure 10  Peak Flows in the Kootenai River ,1932‐2012 ..................................................................................... 28 

Figure 11  Sediment plume during 2015 Island Construction ............................................................................ 30 

Figure 12  Excerpt from FEMA FIRM Panel 16027 0575 B showing the regulatory floodplain in the 

Lower Meander Project area within Boundary County. ........................................................... 31 

Figure 13   Main public access roads into the project area .................................................................................. 43 

ListofTables

Table 1.  Lower Meander project features by construction phase ...................................................................... 10 

Table 2.  Design details for large bank structures ................................................................................................ 12 

Table 3 Design details for excavated pools ........................................................................................................... 13 

Table 4  Comparison of Alternatives by BPA purposes ...................................................................................... 16 

Table 5  Comparison of Alternatives by Resource Impact1 ................................................................................. 17 

Table 6  Mitigation Measures .................................................................................................................................. 20 

Table 7  Summary of wetlands mapped in the Lower Meander project area .................................................. 27 

Table 8.  Native and non‐native fish species in the Kootenai River likely to inhabit the project area .......... 32 

Table 9.  Common activities and associated noise levels .................................................................................... 40 

Table 10  Demographic Characteristics, 2012........................................................................................................ 45 

Page 6: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 5

AcronymsandAbbreviations

BiOp BiologicalOpinion

BPA BonnevillePowerAdministration

cfs cubicfeetpersecond

dB decibel

dBA A‐weighteddecibel

EA EnvironmentalAssessment

EPA U.S.EnvironmentalProtectionAgency

ESA EndangeredSpeciesList

FCRPS FederalColumbiaRiverPowerSystem

FEMA FederalEmergencyManagementAgency

FIRM FloodInsuranceRateMap

GHG greenhousegas

IDFG IdahoDepartmentofFishandGame

KRHRP KootenaiRiverHabitatRestorationProgram

NEPA NationalEnvironmentalPolicyAct

NHPA NationalHistoricPreservationAct

OHW ordinaryhighwater

SHPO StateHistoricPreservationOffice

Tribe KootenaiTribeofIdaho

U.S.C. UnitedStatesCode

USACE USArmyCorpsofEngineers

USFWS U.S.FishandWildlifeService

Page 7: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject6 DraftEnvironmentalAssessment

1 PurposeandNeedforAction

1.1 IntroductionTheBonnevillePowerAdministration(BPA)proposestoprovidefundingfortheKootenaiTribeofIdaho’s(Tribe)LowerMeanderProject.TheLowerMeanderProjectisoneofseveralprojectsbeingimplementedundertheTribe’sKootenaiRiverHabitatRestorationProgram.ThisprojectwouldbelocatedontheKootenaiRiver0.5to1.0milesabovethetownofBonnersFerry,IdahoandisdesignedtoimprovehabitatconditionsforKootenaiRiverwhitesturgeon,whicharelistedasendangeredundertheEndangeredSpeciesAct(ESA;16U.S.Code[USC]§1531etseq.),andothernativefishbyenhancingislands,sidechannels,restoringstreambanksandcreatingdeeppools.

BPApreparedthisdraftEnvironmentalAssessment(EA)undertheNationalEnvironmentalPolicyAct(NEPA;42USC§4321etseq.)andtheCouncilonEnvironmentalQualityimplementingregulations,whichrequirefederalagenciestoassesstheeffectsthattheiractionsmayhaveontheenvironment.ThisdraftEAwaspreparedtodetermineiftheprojectislikelytosignificantlyaffecttheenvironmentandwarrantpreparinganenvironmentalimpactstatementorwhetheritisappropriatetoprepareaFindingofNoSignificantImpact.

1.2 NeedforActionTheneedfortheProposedActionistorestorefishhabitatfeatureslostordegradedbypastandcurrentlandusepracticesintheKootenaiRiver.TheLowerMeanderProjectisdesignedtomeetthisneedbyrestoringandimprovingKootenaiRiverwhitesturgeonhabitatintherivernearBonnersFerry,Idahobyexcavatingnewpools,enhancingexistingislandsandsidechannels,installinglargewoodstructures,andplantingriparianvegetation.TheKootenaiRivernearBonnersFerry,Idahoisamigratorycorridorfornativefishbutcurrentlyprovidespoorfishhabitatduetoanumberoflimitingfactors,including:lackofnutrients,cover,pools,andinstreamhabitatcomplexity.

1.3 PurposesInmeetingtheneedforaction,BPAseekstoachievethefollowingpurposes:

HelpmitigateforeffectsoftheconstructionandoperationofLibbyDamandtheFederalColumbiaRiverPowerSystem(FCRPS)onfishandwildlifeintheKootenaiRiver,pursuanttothePacificNorthwestElectricPowerPlanningandConservationActof1980(NorthwestPowerAct)(16U.S.C.§839etseq.).

Assistincarryingoutcommitmentsrelatedtothe2006LibbyDamBiologicalOpinionasclarifiedin2008thatdirectstheBPAandUSArmyCorpsofEngineersto“supporttheKootenaiTribeofIdaho’sgood‐faitheffortstoimplementtheKootenaiRiverRestorationProjectMasterPlan.”(USFWS2006,2008)

ImplementBPA’sFishandWildlifeImplementationPlanEnvironmentalImpactStatementandRecordofDecisionpolicydirection,whichcallforprotectingweakstocks,liketheKootenaiRiverwhitesturgeon,whilesustainingoverallpopulationsoffishfortheireconomicandculturalvalue(BPA2003).

Minimizeharmtonaturalorhumanresources,includingspecieslistedundertheESA.

InadditiontoBPA’spurposes,theTribeseekstoachievethefollowingbiologicalobjectives:

IncreasedistributionandabundanceoflargedeeppoolstoprovideholdingandstaginghabitatforKootenaiRiverwhitesturgeonandtoencouragesturgeontomigrateupstreamtohigherqualityspawninghabitatbasedona"poolladder"concept,andtosupportburbotspawning,staging,foraging,andmigration.

Page 8: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 7

Increasetheamountofriparianvegetationinthefloodplaintoimproveprimaryproductionandincreasefoodsourcesofalllifestagesofwhitesturgeon,burbot,bulltrout,kokanee,westslopecutthroattrout,andredbandtrout.

1.4 BackgroundBPAisafederalpowermarketingagencywithintheUnitedStatesDepartmentofEnergy.BPA’soperationsaregovernedbyseveralstatutes,includingtheNorthwestPowerAct.UndertheAct,BPAmustprotect,mitigate,andenhancefishandwildlifeandtheirhabitatsaffectedbythedevelopmentandoperationoftheFCRPS.BPAmustfulfillthisdutyinamannerconsistentwiththeFishandWildlifeProgramdevelopedbytheNorthwestPowerandConservationCouncil(Council).Underthisprogram,theCouncilreviewshabitatimprovement(orrestoration)planssubmittedbyvariousentities,andmakesrecommendationstoBPAaboutwhichfishandwildlifeprojectstofund.

TheTribebegandatacollectionandanalysisofKootenaiRiverhabitatconditionsundertheCouncil’sProgramin2006andcompletedtheKootenaiRiverHabitatRestorationProgramMasterPlan(MasterPlan)in2009(KootenaiTribeofIdaho,2009)(describedinSection1.3.3).In2011,theTribesubmittedaproposaltotheCounciltoimplementspecifichabitatrestorationprojectsconsistentwiththeframeworkpresentedintheMasterPlan.In2012,theCouncil’sIndependentScientificReviewPanelreviewedtheKootenaiRiverHabitatRestorationProgramandthelistofproposedprojects,andrecommendedthatBPAfundtheproposal.

1.4.1 LibbyDamBiologicalOpinion

LibbyDamisontheKootenaiRiverinMontanaapproximately220milesfromitsconfluencewiththeColumbiaRiver.TheUSArmyCorpsofEngineers(USACE)operatesLibbyDamforfloodcontrol,hydropowergeneration,navigation,recreation,fish,andwildlife.Itisamajorupriverstoragedamfortheregion.

TheUSACE,theBureauofReclamation,andBPAhaveconsultedwiththeUSFishandWildlifeService(USFWS)andNationalMarineFisheriesServicetoaddresstheeffectsoftheoperationofFCRPSprojects,includingLibbyDam,onfishlistedundertheEndangeredSpeciesAct(ESA)andtheirdesignatedcriticalhabitat.Damoperationshaveaffectedannualpeakflows,temperature,andsedimenttransportintheKootenaiRiver.In2003,theUSACEbeganalteringdischargesatLibbyDam,onaninterimbasis,tomorecloselymimictheKootenaiRiver’shistoricalflowpatterns,whilestillprovidingfloodcontrol.

InFebruary2006,theUSFWSissuedaBiologicalOpinionontheEffectsofLibbyDamOperationontheKootenaiRiverWhiteSturgeon,BullTroutandKootenaiSturgeonCriticalHabitat(LibbyDamBiOp)(USFWS2006).TheKootenaiRiverwhitesturgeonisoneof18land‐lockedpopulationsofwhitesturgeoninwesternNorthAmerica.ThepopulationofKootenaiRiverwhitesturgeon,afreshwaterfish,hasdeclinedprimarilyduetothechangesinriverflowscausedbytheexistenceofLibbyDamanditsoperations,otherfactorsalsoincludehistoricalover‐harvest,andfloodplaindevelopmentforagriculturalactivities.Damoperationshavereducedannualpeakflowsby50percentanddisruptedthehistoricalriseandfallofwaterlevels.Thishascreatedunnaturalflowfluctuationsandlargelyeliminatedtheriver’sconnectionwithitsfloodplain.

TheLibbyDamBiOpidentifiesgeneralcategoriesofactionsandhabitatimprovementsthatwouldenhanceconditionswheresturgeoncurrentlyspawn,coaxsturgeontospawninupstreamareaswherethereismoresuitablehabitat,andimprovehabitatconditionsassociatedwiththeKootenaiRiver.TherestorationactionsproposedfortheLowerMeanderProjectareconsistentwiththoseidentifiedintheBiOp.

Page 9: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject8 DraftEnvironmentalAssessment

1.4.2 KootenaiRiverRestorationProgramMasterPlan

In2006,BPAprovidedfundingtotheTribetobegindevelopmentofaMasterPlan,andtocontinuewithcriticaldatacollectionandplanningactivities.In2009,theTribecompletedamasterplanforalarge‐scale,ecosystem‐basedriverhabitatrestorationprogram.Thismasterplancalledforrestorationofa55‐milesegmentoftheKootenaiRiver,extendingfromtheconfluenceoftheMoyieandKootenairivers,downstreamtotheCanadianborder.Itprovidesasummaryofhistoricalandexistingconditionsinthe55‐mileprojectarea,andidentifiesspecificphysicalandbiologicalcharacteristicsineachoftheriversegmentsoftheprojectarea.Italsoidentifiedfactorsthatlimithabitatforaquaticspeciesincludingsturgeon,burbot,trout,andothernativefishspecieswithintheprojectarea.Basedonthisinformation,theplanidentifiedrestorationstrategiesandhabitatenhancementstoaddressthelimitingfactorsineachriversegment.

BPA’sfundingallowedtheTribetousethecompletedMasterPlantoidentifyspecifichabitatprojectsintheKootenaiRiverthatwouldenhancehabitatforKootenaiRiverwhitesturgeonasrequiredbytheLibbyDamBiOp.Theseprojectsalsoaddresshabitatandnutrientlimitingfactorsforburbot,troutandothernativefish.

WithfundingprimarilyfromBPA,theTribehasimplementedsixhabitatrestorationprojectsunderthisplanfrom2011to2016upstreamoftheLowerMeanderprojectsiteandoneprojectimmediatelydownstreamofthisproject.TheLowerMeanderProjectwouldbetheeighthprojecttobeimplementedundertheKootenaiRiverHabitatRestorationProgramandisdesignedtoachievethefollowingobjectivesthataddresssite‐specificlimitingfactorsforfishhabitat:

Establishingasequenceofhigh‐quality,deeperpoolsupstreamofBonnersFerrytosupportmigrationofadultKootenaiRiverwhitesturgeontohigherqualityspawninghabitat;

Addingfillandplantingstoexistingislandstopromoteriparianvegetationdevelopmentandfoodwebsupport;

Gradingandplantingerodingriverbankstoestablishsustainableriparianbuffers; Installingbankstructurestoincreasecomplexity,promotebankstabilityandtomaintainpools;

and Installingwoodydebrisstructuresinsidechannelsandalongbankmarginstoimprovehabitat

complexity.

1.5 PublicInvolvementBPAmailedscopinglettersonOctober12,2016tolandowners,Tribes,governmentagencies,andotherpotentiallyaffectedorconcernedcitizensandinterestgroupsthatprovidedinformationabouttheproposalandEAscopingperiod,requestedcommentsonissuestobeaddressedintheEA,anddescribedhowtocomment.ThepublicletterwaspostedonaprojectwebsiteestablishedbyBPAtoprovideinformationabouttheproposalandtheEAprocess(www.bpa.gov/goto/KootenaiMeander).ThepubliccommentperiodbeganonOctober12,2016,andBPAacceptedcommentsontheproposalfromthepublicuntilNovember14,2016.

BPAidentifiedfivetribesthatcouldhaveaninterestintheproposedproject,basedontheirhistoricalorcurrentuseofthelandintheprojectarea:theKalispelTribeofIndians,theCoeurd’AleneTribe,theConfederatedSalishandKootenaiTribes,theSpokaneTribeofIndians,andtheKootenaiTribeofIdaho.BPAprovidedinformationto,andrequestedinformationfrom,thesetribes.

BPAconsideredcommentsitreceivedduringthescopingperiodinthedevelopmentofthisdraftEA.Fourcommentletterswerereceived:threeexpressedsupportoftheproposedprojectandthefourthwasaninquiryregardinganunrelatedissue.Thefulltextofthecomments,includingcopiesofanylettersreceived,isavailableonBPA’swebsiteat:www.bpa.gov/goto/KootenaiMeander.Noneofthecommentsreceivedinscopingresultedinthedevelopmentofadditionalalternatives.

Page 10: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 9

2 ProposedActionandAlternativesThischapterdescribestheProposedActionandtheNoActionAlternative,andcomparesthealternativesbyprojectpurposesandtheirpotentialenvironmentalconsequences.

2.1 ProposedActionTheLowerMeanderProjectislocatedbetween0.5and1.0milesupstreamfromBonnersFerry,Idaho(Figures1and2)andisoneofseveralriverhabitatimprovementprojectsthattheTribehasimplementedsincebeginningrestorationeffortsin2011.Aswiththepreviousprojects,theProposedActionisintendedtoimprovehabitatforjuvenileandadultKootenaiRiverwhitesturgeon,burbot,bulltrout,andothernativefishes.

Figure1.LowerMeanderProjectLocation

Page 11: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject10 DraftEnvironmentalAssessment

Figure2.LowerMeanderProjectArea

TheProposedActioncallsforcreatinglargeexcavatedpoolswithinthemainchanneloftheKootenaiRiver.Severalmid‐channelislandswouldbeenhancedusingmaterialexcavatedfromtheriverbottomtocreatethepools.Materialremovedfromthenorthbankoftheriverwouldalsobeusedtoenhancetheislands.Threestreambankstructureswouldbeconstructedandbankstabilizationmethodswouldbeusedtoreduceerosionandestablishriparianvegetation.Eachoftheseprojectelementsisdescribedinthesectionsthatfollow.

ConstructionoftheLowerMeanderProjectwouldoccurintwophases,duringlatesummer/earlyfallof2017and2018.ThephasingisdesignedtoworkfromupstreamtodownstreamasdisplayedinTable1andFigures3and4.

Table1.LowerMeanderprojectfeaturesbyconstructionphase

ProjectFeature Phase12017

Phase22018

BankStabilization(gradingandbrush‐bankstructures) 2600ft. 2100Ft.

LargeBankStructures two structures(structures#1and#2)

onestructure(structure#3)

Side‐ChannelLargeWoodStructures 15structures none

ExcavatedPools Onepool(pool#1) Onepool(pool#2)

IslandEnhancement Threeislands(total20acres)

Threeislands(total6.5acres)

Page 12: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 11

Figure3.KootenaiLowerMeanderconstructionactions,Phase1(upstream)

Figure4.KootenaiLowerMeanderconstructionactions,Phase2(downstream)

Page 13: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject12 DraftEnvironmentalAssessment

2.1.1 LargeBankStructures

Threelargebankstructureswouldbeinstalledtoprovidelargerecirculationzones(eddies)andprotectadjacentbankareasfromerosion.Thetwoupstreamstructureswouldbeconstructedfromtimberpiles,importedgravel/riprap,andwoodydebris.Thethirddownstreamstructurewouldbeconstructedfromimportedcobbleonly.

Forthetwoupstreamlargebankstructures(Structure1,Structure2),timberpileswouldbedrivenintotheriverbedwithapproximatelyfourtosixfeetofeachpileremainingexposed.Largelogswouldbeplacedinbetweentheverticalpilesandthenboltedtosecuretheminplace.Abarriercomposedofwoodandrockwouldbeinstalledattheupstreamendofeachstructurethatwoulddirecttherivertoflowaroundthestructuretoreducetheriskoferosion.Thedownstreamstructure(Structure3)createdusingimportedrockwouldhavemoderatelyslopingsidesandfunctionsimilarlytootherexistinggravelbarfeaturesintheriver.

Vegetatedbrushbankstructures(asdescribedinSection2.1.3.3)wouldbeinstalledbetweenStructures1and2andatthebanktie‐inpointstocreatestabletransitionstotheexistingbankattheupstreamanddownstreamedgesofthelargebankstructures.

DesigninformationforlargebankstructuresisprovidedinTable2.Figure5displaysphotographsofsimilarlargebankstructuresatpreviousrestorationsitesalongtheKootenaiRiver.

Table2.Designdetailsforlargebankstructures

Structure1(upstream)

Structure 2(middle)

Structure3(downstream

BankLength(feet) 180 390 350

ProjectionintoRiver(feet) 100 180 200

Projectionangle(degrees) 25 25 17

Elevation(NAVD88feet) 1756to1765 1756to1764 1757to1758

Distancefromnextstructuredownstream(feet)

900 1,800 N/A

Numberoftimberpiles 52 134 0

Riprap(cubicyards) 1,900 4,800 0

Gravel(cubicyards) 1,400 8,900 0

Cobble(cubicyards) 0 0 6,400

Area(squarefeet) 4,100 20,300 28,200

Volume(cubicyards) 3,300 13,700 6,400

Page 14: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 13

Figure5.ExamplesoflargebankstructuresintheKootenaiRiver

2.1.2 PoolExcavation

PoolswouldbeexcavatedattwolocationsinhopesofprovidingstagingandholdinghabitatforKootenaiRiverwhitesturgeonandtoencouragesturgeontomigratefurtherupstreamtosuitablespawninghabitat.Locationsforpoolexcavationwereidentifiedprimarilybasedontheirexpectedmorphologicsustainabilityandtheiraccessibilitybyland‐basedexcavationequipment.Gravelandsandexcavatedfromthepoolswouldbeusedtoconstructislandsasdescribedbelow.

Eachpoolwouldbeapproximatelyfourtofiveacresand,oncecompleted,wouldbe10to15feetdeeperthantheexistingriverbed(Table3).Tocreatebothpools,approximately120,000cubicyardsofmaterialwouldberemoved.Figure6displaysphotographsofpoolexcavationactivitiesconductedin2015duringconstructionoftheBonnersFerryIslandsProject.

Table3Designdetailsforexcavatedpools

Pool1(Upstream) Pool2(Downstream)

Maximumwidth(feet) 180 300

Length(feet) 1,200 1,000

SideSlopes 5:1 5:1

Area(acres) 4 5

Volume(cubicyards) 51,000 69,000

2.1.3 IslandConstructionandEnhancement

Sixexistingislandswouldbeenhancedusinggravelandsandfromexcavatedpoolsandbankgrading.Thenewislandareaswouldthenbeplantedwithnativeriparianvegetationandalsoreceivefloodplainroughnesstreatments.

Page 15: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject14 DraftEnvironmentalAssessment

Figure6.PoolexcavationactionsintheKootenaiRiver

IslandelevationswouldbesimilartoexistingislandswithintheKootenayLakebackwaterinfluence,upstreamfromtheprojectarea,thatdisplaydesiredvegetationcommunities.Thefloodplainroughnesstreatmentswouldcreateprotectedmicrositesbothforplantedspeciesaswellasnativeseedlingsthatareexpectedtocolonizethenewlyconstructedfloodplainsurfaces.Floodplainroughnesswouldbecreatedusingfurrowsandridgesuptoonefoothighandpartiallyburiedpiecesofwoodandbrush.Theburiedpiecesofwoodwouldbesixtotwelveinchesindiameterandeighttotwelvefeetlongandsmallerbrushuptosixinchesindiameterandeighttotwelvefeetinlength.

2.1.4 BankStabilization

Highbanksandbankswithsteepangleswouldbegradedandloweredtoimprovebankstability,increasethewidthofriparianbuffers,establishfloodplainconnection,andtosetelevationsandslopessuitableforestablishingtreesandshrubs.Existingcarbodiesandothernon‐naturaldebrisusedhistoricallyforerosioncontrolwouldberemoved.Finishedgradeswouldincludefloodplainroughnesstreatmentsasdescribedabove.Approximately18,400cubicyardsofmaterialwouldbeexcavatedinthisprocessinPhase1,and39,800cubicyardsinPhase2.

Vegetatedbrushbankstructureswouldbeinstalledinthere‐gradedbankstoestablishvegetationandprovidestability.Thesestructuresconsistoflayeredbrushandsmalllogsbuiltonasmallriprapfoundationwithlivevegetativecuttingswithinthebrushlayersatelevationsthatareincontactwiththewatertableduringthegrowingseason(Figure7).Approximately2,400linealfeetofthesestructureswouldbeinstalledinPhase1and2,100linealfeetinPhase2.

Figure7Vegetatedbrushbankstructuresunderconstructionatthe2015BonnersFerryIslandsproject

Page 16: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 15

SideChannelLarge‐WoodStructures

Approximately15large‐woodstructureswouldbeinstalledinthesidechannelstoprovidehydrauliccomplexitybetweentheislandsandtocreateaseriesofsmallscourpoolsinthesidechannels.Thestructureswouldbeinstalledingroupsofthreestructuresasshownbythesmall‘X’s’inFigure3.Eachstructurewouldoccupyapproximately400squarefeet(20ft.by20ft.)andwouldbeconstructedfromtimberpilesandlargewoodydebris.Thetimberpileswouldbedrivenintothebedbelowscourdepthtoprovidestability.Largewoodydebriswouldbeboltedtothetimberpilesinavarietyofconfigurationstoresembleanaturalaggregateofrackedlogs.Gravelwouldbeexcavatedfromthelocationoftheexpectedscourpoolandusedtobackfilltheinteriorofthestructure.Overtimethesestructuresmaycollectadditionaldebrisandpromotedepositioninthesidechannels,thuscontributingtofloodplaindevelopment.

2.1.5 AccessandStaging

AccessonthenorthsideoftheKootenaiRiverareaswouldbefromtheDistrict2RoadviaBallParkRoadandaprivateunimprovedroadacrossprivatelandthatisusedasapasture.Atemporarystagingareawouldbeestablishedinthepasture.Temporaryhaulroadswouldbeconstructedtoaccesstheriverbankandstructurelocations(Figures8and9).

Figure8.Stagingareasandtemporaryhaulroads

AccesstothesouthbankwouldbefromCowCreekRoadviaWaterhouseLane.FromWaterhouseLane,accesswouldbeviaaprivateunimprovedroad.Atemporarystagingareawouldbeestablishedandtemporaryhaulroadswouldbeconstructedtoaccesstheriverbank,islandsandpoolexcavationareas(Figures8and9).

Page 17: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject16 DraftEnvironmentalAssessment

Figure9Examplesoftemporaryriveraccessroadconstruction

2.2 NoActionAlternativeUndertheNoActionAlternative,BPAwouldnotfundtheKootenaiRiverLowerMeanderProjectandtheTribewouldnotmakethefishhabitatimprovementstotheKootenaiRiverasproposed.Inaddition,BPAwouldnotusetheprojecttohelpmeetitsfishandwildlifemitigationobligationsundertheNorthwestPowerAct,orfurthersupporthabitatimprovementeffortsidentifiedintheLibbyDamBiologicalOpinion.

2.3 ComparisonofAlternativesThefollowingtwotablescomparetheProposedActionandtheNoActionalternative.Table4comparesthealternativesbythepurposesofthisproject.Table5displaysasummaryoftheeffectsofimplementingeachalternative,withdetailedinformationavailableinChapter3.

Table4ComparisonofAlternativesbyBPApurposes

Purposes ProposedAction NoActionAlternative

SupporteffortstomitigateforeffectsofthedevelopmentandoperationoftheFCRPSonfishandwildlifeinthemainstemColumbiaRiveranditstributariesundertheNorthwestPowerAct.

WouldhelpsupportmitigationeffortscalledforintheNorthwestPowerActbyenhancingfishandwildlifehabitatintheKootenaiRiveraboveBonnersFerry.

WouldnotsupportBPA’seffortstoenhancefishandwildlifehabitatintheKootenaiRiveraboveBonnersFerry.

Seektofurtheraddressobligationsunderthe2006LibbyDamBiOpasclarifiedin2008,whichdirectstheBPAandUSACEto“supporttheKootenaiTribeofIdaho’sgood‐faitheffortstoimplementtheKootenaiRiverRestorationProjectMasterPlan.”

WouldfurtheraddressBPA’sobligationsunderthe2006LibbyDamBiOp.

WouldnotcontributetoBPA’seffortstomeetobligationsspecifiedunderthe2006LibbyDamBiOp.

ImplementBPA’sFishandWildlifeImplementationPlanEISandRODpolicydirection,whichcallforprotectingweakstocks,liketheKootenaiwhitesturgeon,whilesustainingoverallpopulationsoffishfortheireconomicandculturalvalue.

Wouldcontributetoestablishingself‐sustainingpopulationsofKootenaiRiverwhitesturgeonandothernativespeciesintheKootenaiRiverwhichareofculturalvalueandmayprovide

WouldnotfurtheractionstohelpprotectKootenaiRiverwhitesturgeonorothernativefishforeconomicandculturalvalues.

Page 18: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 17

Purposes ProposedAction NoActionAlternative

economicbenefits,whileatthesametimeprotectingESA‐listedfish.

Minimizeharmtonaturalorhumanresources,includingspecieslistedundertheESA.

Proposedmitigationmeasureswouldminimizeharmtonaturalandhumanresources.Approvalsby,andreporting,toregulatoryagencieswouldminimizetheriskofadverseeffectstoESA‐listedspecies.(SeeTable5forasummaryofeffects.)

Withnoconstructionofnewfacilities,therewouldnopotentialtoeffectnaturalandhumanresourcesorshort‐termeffectstonativeESA‐listedspecies;therewouldalsobenoadditionalpotentialforlong‐termKootenaiRiverwhitesturgeonrecoverybenefits.(SeeTable5forasummaryofeffects.)

Table5ComparisonofAlternativesbyResourceImpact1

ResourceAffected EffectsofProposedAction1 EffectsofNoAction

GeologyandSoils Changedtopographyofriverbanksandnearlytriplethesizeofislandsinriver.Short‐termerosion/soillossandsedimentationfromexcavationandtemporaryroadbuilding.Long‐termerosionprotectionfromstabilizedbanksandislandsandimprovedriparianvegetationconditions.Theoveralleffecttogeologyandsoilswouldbelow.

Noneweffectstogeologyandsoils.Riverbankandislandtopographywouldremainunchanged.Ratesandpatternsoferosionwouldlikelycontinuesimilartopresentconditions.

Wetlands Lessthanoneacreofwetlandswouldbepermanentlyimpacted.Therestorationactivitieswouldestablish24acresofnewwetlandsonthenewlycreatedislandsandalongtheriparianareawheretheriverwouldbehydraulicallyconnectedtotheareasofnewplantings.Theeffectswouldbebeneficialandmoderate.

Noneweffectstowetlandsorfloodplains.

WaterResources Nolong‐orshort‐termchangestowaterquantity.Short‐termeffectstowaterqualityareexpectedfromturbidityduringconstructionbutstabilizationofbanksandimprovedriparianvegetationconditionsareexpectedtoreduceerosion/turbidityandimprovedwaterqualityinthelongterm.Riverwouldbechangedhydrologicallybyisland,channelandpoolconstruction,thoughthesefeaturesareexpectedtochangesomewhatwithriverconditionsovertime.Theeffectstowaterresourceswouldbelow.

Theprojectwouldcausea0.15footincreaseinbasefloodelevationswithintheprojectareaandnoincreaseatBonnersFerry,butwouldnotrequireachangeinoperationsatLibbyDamtopreventflooding.

Noneweffectstowaterresourcesintheprojectarea.Waterqualityandhydrologicconditionswouldremainunchanged.

Page 19: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject18 DraftEnvironmentalAssessment

ResourceAffected EffectsofProposedAction1 EffectsofNoAction

Fish Long‐termimprovementinfishhabitat.Shorttermadverseeffectsfrompile‐drivingnoise,turbidity,excavation,rockplacement,andaccidentalhazardousmaterialspillsduringconstructionactivities.Intheshort‐termfishareexpectedtomoveoutoftheconstructionareawhenwoodenpilesaredriven.Long–termincreasesinfishpopulationsfromimprovedhabitatsareexpected.Therewouldthusbealowtomoderateshort‐termandtemporaryeffecttofishpopulationsintheprojectarea.

Noneweffectstofishintheprojectarea.Noshort‐termdisplacementeffects.Nobenefittofishorincreasedpopulationpotentialfromnotimprovingriverbanks,pools,channels,islands,andriparianhabitats.

Recreation Short‐termadverseeffectonfishingopportunitiesduringconstructionactivities.Long‐termbeneficialeffectonfishingopportunitiesfromincreasedfishpopulationsinareaswherehabitathasbeenimprovedforfish.Someeffectsonboatersusingsidechannelswithlargewoodstructuresasthesemaycreateanobstacleneedingavoidance,butwouldalsocreatefishhabitatwithincreasedfishingopportunities.Effectswouldbelow.

Noeffectstoboatingrecreationsinceconstructionactivitieswouldnotoccur.Noadditionofboatingobstacles(largewoodstructures),butnoimprovementinfishingopportunitiesfromincreasedfishpopulations.

CulturalResources

Noknownculturalresourceswereidentifiedintheareasimpacted.

Ifunanticipatedsitesarediscoveredduringconstruction,sitescouldbeaffected;however,stopwork,notification,andmitigationrequirementswouldlessenpotentialeffects.

Noeffectstoculturalresources.

VisualResources Visualchangeswouldincludeanapproximatethree‐foldincreaseinislandsizeswithmorevegetativecoverthanarevisibleatpresentonbothislandsandriverbanks.Largewoodstructuresnotlikelydiscernablefrompublicroadways,butclearlyevidenttoboaters.Effectswouldbelow.

Nochangestolanduseorvisualcharacteroftheriveroritsislandsandbanks.

Noise Piledrivingwouldbetheprimaryeffect,thoughdistancetoBonnersFerryisnearlyonemileaway,largelyattenuatingtheimpact.Approximately30‐daynoiselevelchangewouldbenoticeable,butlikelynotmuchgreaterthanroutinebackgroundnoiseintown.Effectswouldbelow.

NochangestoambientnoiselevelsinprojectareaorinBonnersFerry.

AirQuality,andGreenhouseGasses

Airpollutantsandgreenhousegasesfromvehicleemissionsanddustfromconstructionactivitieswouldbegeneratedduringtheconstructionperiod.Effectswouldbeshort‐term,temporary,andlowbecauseofapplicationofmitigationmeasures.

Noneweffectstoairqualityortheexistingconditionsrelativetogreenhousegas(GHG)emissions.

Page 20: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 19

ResourceAffected EffectsofProposedAction1 EffectsofNoAction

PublicHealthandSafety

Minorincreaseintraffic,potentialforaccidents,anddemandsonlocalemergencyservicesduringconstructionactivities.Introductionoflong‐termboatinghazardsintotheKootenaiRiverthoughthesetypesofriverhazardsareroutineforboatersandmitigationwouldbeimplementedtominimizetheeffectstoboaters.Effectswouldbelow.

Noeffectonpublichealthandsafety.

TransportationandUtilities

Temporaryincreaseintraffic,includinglargeconstructionvehicles,onlocalroadsduringconstruction;thoughnoroutingthroughresidentialareas.Noanticipatedalterationoftrafficpatterns.Effectswouldbelowtomoderate.

Noneweffectstotransportationorutilitiesneartheprojectsite.

Socioeconomics Onlyafewtemporaryjobsprovidedbyconstructionactivity,withnolong‐termemploymentopportunitiesprovided.Noimpactonhousing.Moderateshorttomid‐termbeneficialeconomicimpactfromconstructionspendingandneedforsupplyandhauloflocalgravel,logs,etc.andthemultipliereffectsthroughthelocaleconomy.Noeffecttoenvironmentaljusticepopulations.

Nosocioeconomiceffects.

1TheeffectsdisplayedinthistablepresumetheapplicationoftheMitigationMeasureslistedinTable6.

Page 21: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject20 DraftEnvironmentalAssessment

2.4 MitigationMeasures

Table6liststhemitigationmeasuresthatwouldlessenoravoidpotentialimpactofimplementingtheKootenaiLowerMeanderProject.

Table6MitigationMeasures

EnvironmentalResource MitigationMeasure

GeologyandSoils

Prepareandimplementaplanforerosionandsedimentationcontrolandastormwaterpollutionpreventionplanforconstructionactivitiestominimizeerosionandsoilloss(e.g.,usesiltfences,strawbales,interceptortrenchesorotherperimetersedimentmanagementdevices;maintainasnecessarythroughoutconstruction).

Locatestagingareasinpreviouslydisturbedorgraveledareastominimizesoilandvegetationdisturbance,wherepracticable.

Designandbuildaccessroadsthatminimizedrainagefromtheroadsurfacedirectlyintosurfacewaters,anddirectsediment‐ladenwatersintovegetatedareaswherepossible.

Inspectandmaintainaccessroadsandotherfacilitiesduringconstructiontoensureproperfunctionandnominalerosionlevels.

Reseeddisturbedareas,monitorseedgermination,andimplementcontingencymeasuresasnecessaryuntilareasdisturbedfromconstructionactivityarestabilized.

Existingunimprovedroads,temporaryhaulroadsandthestagingareawouldbegraded,surfacedwithgravelandtreatedfordustcontrol(waterapplication)asneededtosupporthaultrafficduringconstruction.

Wetlands

Identifyclearinglimitsonallconstructiondrawingsandflagas“no‐work”areasbeforeconstruction.

Revegetatedisturbedareas(includingwetlands)withappropriatenativespeciesusingseedmixesthatmeettherequirementsoffederal,state,andcountynoxiousweedcontrolregulationsandguidelines.

Implementmitigationmeasurestocontrolpotentialnoxiousweedinfestationsbefore,during,andafterconstruction.

Page 22: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 21

EnvironmentalResource MitigationMeasure

Implementbestmanagementpracticesduringconstructiontominimizeadverseeffectsonwetlands(e.g.,limitwetlanddisturbanceareas;flagorstakewetlandboundaries;refuelmachineryandstorefuelsawayfromwetlands;developandimplementerosionandsedimentationcontrolplan).

Installsiltfencesandstrawwattlesatculvertlocationsandwetlandareastopreventeffectsfromstormwaterrunoffandconstruction‐relateddisturbance.

WaterResources

Depositandstabilizeallexcavatedmaterialnotre‐usedinanuplandareaoutsideoffloodplains.

FollowtheIdahoDepartmentofEnvironmentalQuality’sCatalogofStormwaterBestManagementPracticesforIdahoCitiesandCounties(IDEQ,2005)tocreateastormwaterpollutionpreventionplanforconstructionactivities.Useandmaintainthisplanthroughoutconstructiontominimizeerosionandsoilloss(e.g.,usesiltfences,strawbales,interceptortrenchesorotherperimetersedimentmanagementdevices).

Implementmeasurestopreventstockpileerosionduringrainevents(e.g.,surroundpileswithcompostberms,coverpileswithimperviousmaterials,oruseotherequallyeffectivemethods).

Minimizestagingareastothesizenecessarytoconductthework,andlocatethestagingareasinpreviouslydisturbedareasatleast150feetfromtheriverorwetlands.

Createandusea spillprevention,controlandcountermeasuresplantominimizethepotentialforspillsofhazardousmaterial,whichincludesprovisionsforstorageofhazardousmaterials,andrefuelingofconstructionequipmentoutsideofriparianzones,aspillcontainmentandrecoveryplan,andnotificationandactivationprotocols.

Storespillcontainmentkitsateachworksiteandtraintheconstructioncrewsinproperuse.

Page 23: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject22 DraftEnvironmentalAssessment

EnvironmentalResource MitigationMeasure

Washallequipmentbeforemovingittotheprojectsite,tominimizetheintroductionofforeignmaterialsandfluidstotheprojectsite.

Useonlyhydraulicfluidscertifiedasnon‐toxictoaquaticorganismsinequipmentusedtoworkinthewater.

Inspectallequipmenttoensureitisfreeofoil,hydraulicfluid,anddieselfuelleaks.Repairdetectedleaksinthevehiclestagingareabeforethevehicleresumesoperation.Documentinspectionsinarecordthatisavailableforreviewonrequest.

Locatevehiclestaging,cleaning,maintenance,refueling,fuelstorageareas,andsanitaryfacilities,suchaschemicaltoilets,atleast150feetfromtheKootenaiRiverorwetlands.

Cleanallequipmentoperatedinstreambeforebeginningoperationsbelowthebankfullelevationtoremoveallexternaloil,greaseanddirt.Everyday,inspectallpowerequipmentoperatingwithin150feetofthewaterforfluidleaks.

Applytruckdiaperstoanystationarypowerequipment(e.g.,generators)operatedwithin150feetofanystream,waterbodyorwetlandtopreventleaks.

Floatingsiltcurtainsand temporarybermswouldbeusedwherewaterdepthallowsforturbiditymanagement.Practicaleffortswouldbemadetoinstallfloatingsiltcurtainsinlowervelocityareasatthedownstreamendoftheworkareassuchthatconstructionrelatedturbiditycansettleoutinlowervelocitybackwaterareas.Floatingsiltcurtainswouldbeanchoredwith12‐inchdiametertemporarysteelpiles.

Fish

ConductworkbelowtheOrdinaryHighWaterMark(OHWM)fromAugustthroughNovember

OperatemachineryforbelowOHWMconstructionfromthetopofthestreambankalongadjacentuplandareas,totheextentpossible.

Protectexistingriparianandwetlandvegetation

Page 24: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 23

EnvironmentalResource MitigationMeasure

totheextentpossible.

RecreationInstallsignageattheTwinRiversCanyonResortboatlaunchtoinformboatersofrestorationactivitiesandindicatetheirlocation.

CulturalResources

InstallpermanentsignsattheTwinRiversboatramprequestingthatboatersandtubersstayclearoftherestorationareainordertoprotecttherestorationwork.Signswouldalsocontainaneducationalelementtodescribethedifferentprojectlocations,thetypesofstructures,andthebenefitstheyprovideforfish.

Markknownculturalresourcesitesasavoidanceareasonconstructiondrawingsandflagasno‐workareasinthefieldpriortoconstruction.

Protectanyunanticipatedculturalresourcesdiscoveredduringconstructionasfollows:

Stop allwork;coverandprotectthe‘find’inplace.

Notify ProjectManagerandBPAculturalresourcesspecialistimmediately.

Implement mitigationorothermeasuresasinstructedbyBPAculturalresourcespecialist.

VisualResources

Retainexistingvegetation,whenpossible,tovisuallyscreendisturbancecreatedbyconstructionactivities.

Reseedandplantdisturbedareaswithappropriatenativespecies.Controlweedsfollowingconstruction.

NoiseLimitconstructionnoisetonormaldaytimeworkinghours.

PublicHealthandSafety NoMitigationnotrequired

AirQualityandGreenhouseGasses

Confinevehiclefuelingandmaintenancetoapprovedlocations.

Usewatertruckstocontroldustduringconstruction,asneeded.

Ensurethatallvehicleenginesaremaintainedingoodoperatingconditiontominimizeexhaustemissions.

Page 25: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject24 DraftEnvironmentalAssessment

EnvironmentalResource MitigationMeasure

Implementvehicleidlingrestrictions.

Encouragetheuseofthepropersizeofequipmentforeachjob.

Usealternativefuelsforstationaryequipmentattheconstructionsites,suchaspropane,oruseelectricalpower,wherepracticable.

Reduceelectricityuseintheconstructionofficebyusingcompactfluorescentbulbsandturningoffcomputersandotherelectronicequipmenteverynight.

Recycleorsalvagenonhazardousconstructionanddemolitiondebris,wherepracticable.

Keepconstructionactivitiesandequipmentclearofresidentialdriveways,tothegreatestextentpossible.

TransportationandUtilities

Employtrafficcontrolflaggersandpostsignsalongroadswarningofconstructionactivityandmergingtrafficfortemporaryinterruptionsoftraffic,whereneeded.

CoordinatewithBurlingtonNorthernSantaFe

todeterminewhethertheywouldrequireaflaggerbepresentduringconstructiontimestoavoidtrainconflictsordelaysattheunmarkedcrossingoftheBurlingtonNorthernSantaFerailline.

Limitconstructionnoisetodaytimeworkinghours(seeNoise,Section3.8).

Usewatertruckstocontroldustduringconstruction,asneeded(seeAirQuality,Section3.9).

Socioeconomics N/A

Page 26: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 25

3 AffectedEnvironmentandEnvironmentalConsequencesThischapterevaluatesthepotentialeffectsoftheProposedAction,aswellastheNoActionalternative,onhumanandnaturalresources,todeterminewhethereitherhavethepotentialtocausesignificantenvironmentaleffects.Foreachresource,theexistingenvironmentthatcouldbeaffectedbythealternativesandthepotentialenvironmentalconsequencesofthealternativesaredescribed.ManyoftheeffectswouldbeminimizedbytheapplicationofthemitigationmeasureslistedinSection2.4andthediscussionsherepresumetheapplicationofthoseconditions.Discussionofthecumulativeeffects(incrementaleffectsoftheProposedActionwhenaddedtootherpast,present,andreasonablyforeseeablefutureactions)isattheendofthischapter.

3.1 SoilsandGeology3.1.1 AffectedEnvironment

RegionalGeology

TheproposedprojectareaiswithintheBoundaryCountysoilsurveyarea,whichiswithintheNorthernRockyMountainsgeographicprovince.Between100,000and11,000yearsago,theCordilleranicesheet(alargemassofice,alsoknownasacontinentalglacier)coveredmostofthevalleyareasintheregion,leavingonlythehighermountainpeaksexposed.Theseglacialepisodescreatedmuchofthesurfacematerialsandtopographythatexiststoday.Alpineglacierserodedthecraggy,jaggedpeaksandfilledinmountainvalleyswithmoraine(soilandrockdepositedbyglaciers)andoutwash(sandandgravelleftbymeltingwater)deposits.TheicesheetextendedasfarsouthasCoeurd’AleneLake,75milestothesouth.Theglaciersleftthickdepositsofglacialtill(unsortedglacialsediment)andsilt,transportedlargeboulderstothearea,andscouredsomeareas,leavingbedrockexposedatthesurface(USDANRCS,2013).

SeismicFaults

TherearenoknownseismicfaultsinBoundaryCounty.TheBoundaryCountyComprehensivePlanstatesthatthecountyisinSeismicZone2,asdelineatedintheUniformBuildingCode.SeismicZone2indicatesthatamoderatedamageriskcouldbeexperiencedinthisareashouldanearthquakeoccur(BoundaryCounty,2008).

LocalSurfaceSoils

SoilsintheKootenaiRiverfloodplainarecomprisedofsilty,alluvial(materialdepositedbyflowingwater)depositsleftbehindfromfloodwatersthatspreadoverthefloodplainanddepositedsilt,clay,andveryfinesands(USDANRCS,2013).Moreashy,siltyloamsoilsoccuronthegentlyslopingareasborderingtheshoreline,floodplain,andthesteepescarpments.(ToxicitysamplingofriversedimentsisdiscussedinSection3.3,WaterQuality.)

3.1.2 EnvironmentalConsequences–ProposedAction

WithintheareaoftheProposedAction,largeamountsofsoilwouldbemovedandtopographywouldbechanged(loweringpoolelevationsintheriverbed,raisingislandelevations,andgradingofcurrentlyerodingriverbanks).Theworkwouldcausesedimentationanderosionintheshorttermduringconstruction,butthebankgradingandbankstabilizationstructuresandplantingofnativevegetationwouldhelpstabilizesoilmovementinthelongterm.

Thetwopoolstobeexcavatedwouldrequirerelocationof51,000and69,000cubicyardsofgravelandsandfromthemainchanneloftheriver.Thisexcavatedmaterialwouldbedepositedonexistingadjacentgravelbarsandislandstoenhancesixislandsandraisetheirelevationssotheyareableto

Page 27: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject26 DraftEnvironmentalAssessment

supportriparianvegetation.Thenewlycreatedislandsurfaceswouldbestabilizedthroughgradingandcreationoffloodplainroughnesstominimizeerosionandthroughextensiveplantingofnativeriparianvegetation.

Gradingtostabilizeerodingbankswouldresultinsometemporarysoillossduringconstructionbuterosionandsedimentcontrolmeasureswouldbeusedtocontrolandmanagethoseeffects.Overthelongterm,theProposedActionwouldhavebeneficialeffectsonsoils,asbankstabilization,largebankstructures,andmorevegetativelyrobustriparianareaswouldreducetheamountofsoilsexposedtorivercurrents.

About1.25milesoftemporaryaccessroads,wouldbebuilttoallowheavymachinerytoaccessprojectlocationsalongtheriverforexcavation,gravelandsandrelocation,rockandlogplacement,etc.Thesetemporaryroadswouldcompactanddisplacesoilswhileinusebutwouldberemovedandthelandrestoredfollowingconstruction.

Constructioncouldresultinerosioncausedbystormwaterrunofforwindblowndustduringdryconditions.Theseeffectswouldbeminimizedbyimplementingbestmanagementpractices(seeSection2.4).

Althoughimplementationofconstructionbestmanagementpracticesandmitigationmeasureswouldreducethepotentialforshort‐termincreasederosion,someincreasedlevelsoftemporaryerosionandsoillosswouldbeexpectedduringandimmediatelyafterconstruction.Forthelongterm,however,stabilizedandrevegetatedbanksandislandswouldreducethepotentialforerosivelossofsoilresources.TheoverallimpactoftheProposedActiononsoilsandgeologywouldbelow.

3.1.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,therewouldbenoshort‐termsoillossesortopographychangesbecauseconstructionactivitieswouldnotoccur.Theongoingerosionalprocessesoccurringintheriverandonitsbanksandislandswouldcontinue.

3.2 Wetlands3.2.1 AffectedEnvironment

Ingeneral,wetlandfunctionsareseparatedintothreeprimarycategories:waterquality,hydrology,andhabitat(Novitzki,1996).Palustrinewetlandsnexttoriversystemshavethepotentialtoimprovewaterqualitybyfilteringandstoringsediments,processingpollutants,andstoringandcyclingnutrients.Hydrologicfunctionsoftenincludegroundwaterrecharge,floodmoderationandfloodwaterstorage.Wetlandscansupporthighlevelsofprimaryproductivityandprovideuniquehabitatforfishandwildlife(Hruby,2004).Theirabilityandopportunitytoperformanyofthesefunctionsdependslargelyontheirpositioninthelandscape,sizeandcomplexity,adjacentlanduse,andlevelofdisturbance.

Palustrineemergentwetlandsarecharacterizedbyerect,rooted,andnon‐woodyvegetation.Ascrub‐shrubwetlandisdominatedbywoodyvegetationlessthan20feettall(Hruby,2004).

AwetlanddelineationfortheprojectareawasconductedonJuly19,20,and21,2016andfollowedthemethodsforroutinedelineationsinareasgreaterthanfiveacresinsizefromtheCorpsofEngineersWetlandDelineationManual(EnvironmentalLaboratory1987).DatacollectionandwetlandboundarydelineationsfollowedmethodsdescribedinRegionalSupplementtotheCorpsofEngineersWetlandDelineationManual:WesternMountains,Valleys,andCoastRegion(U.S.ArmyCorpsofEngineers2010).WetlanddelineationdatacollectionoccurredonalllocationswithintheLowerMeanderProjectarea(includingthepotentialaccessroutes)andalllocationswerevisitedtoidentifyareaswithwetlandcharacteristics.

Page 28: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 27

Wetlanddelineationsamplingdatawerecollectedtocapturevariationsinvegetationcommunities,landscapepositionandtopography.Datacollectionpointswerelocatedtobepaireduplandandwetlandplots,exceptwheresamplepointsonlydocumenteduplandconditions.

TheOHWMwasidentifiedforwatersoftheU.S.usingguidancefromTitle33oftheCodeofFederalRegulations,Part328“DefinitionofWatersoftheUnitedStates”andtheRegulatoryGuidanceLetternumber05‐05fromtheArmyCorpsofEngineers(2005).

OnthenorthsideoftheKootenaiRiverthereisarelicsidechannel.Thisareawasdelineatedaspalustrineunconsolidatedbottomwetlands.WhilenotpartoftheareatobedisturbedbytheProposedAction,theareawasdelineatedbecauseofitsproximitytotheprojectarea.ThesidechannelisnotconnectedtotheKootenaiRiverbutdoesreceiveoverbankflowsduringhighwaterevents.Palustrineunconsolidatedbottomwetlandsnormallyhaveshallowwaterthroughoutthemostoftheyearandaresurroundedbypalustrineemergentwetlands.Theboundarybetweenthetwowetlandclassesismarkedbyatransitionfromareaswheresurfacewaterexistsyearroundandisdeepenoughtosuppressvegetationgrowthtoareaswithestablishedemergentvegetationcommunities.

WithintheLowerMeanderProject,thereareapproximately11acresofpalustrinescrubshrubwetlandsandabout9.5acresofpalustrineemergentwetlands(Table7).Thereisalsoapproximately7acresofwetlandsclassifiedasamixofscrub/shrubandemergentwetlands.Thevegetationfoundintheemergentwetlandintheprojectareaisdominatedbyeitherwaterknotweedorsedges.Thevegetationfoundwithinthepalustrinescrubshrubwetlandsincludessandbarwillow,yellowwillow,andred‐osierdogwood.

Table7SummaryofwetlandsmappedintheLowerMeanderProjectarea

Wetland Class Existing Area (acres)

Palustrine emergent 9.53

Palustrine emergent/scrub shrub 7.29

Palustrine scrub shrub 10.85

Palustrine unconsolidated bottom 3.13

Total wetland area 30.80

3.2.2 EnvironmentalConsequences–ProposedAction

Theplacementofexcavatedmaterialaroundexistingvegetationonthemid‐channelislandswouldoverlapwiththeedgesofsomeofthedelineatedpalustrinescrubwetlandsresultinginapermanentlossof0.4acresofwetland.Streambankregradingisexpectedtoalsoresultinapermanentlossofapproximately0.2acrespalustrineemergentwetlands.Temporaryeffectsassociatedwithconstructedaccessrouteswouldresultinalossof0.25acresofwetlands,whichwouldberestoredonceconstructioniscompleted.

Inaddition,asaresultoftheProposedActiontherewouldbeanetgainofapproximately24acresoverallofwetlandarearesultingfromthecreationofnewfloodplainandislandsurfacesthatarehydrologicallyconnectedtotheKootenaiRiver.Theareaofpalustrinescrubshrubwetlandwouldbeincreasedontheconstructedislandsasaresultofnaturalrecruitmentandplanting.Theregradedstreambankswouldalsobeplantedandresultinnewpalustrinescrubshrubwetlands.Becauseofthenetincreaseinoverallwetlandarea,theeffectsonwetlandswouldbebeneficial.Theeffectswouldbemoderateoverall.

Page 29: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject28 DraftEnvironmentalAssessment

3.2.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,theexistingwetlandswouldremainunaffectedandtherewouldbenowetlandcreation.

3.3 WaterResources3.3.1 AffectedEnvironment

HydrologicCharacteristics

TheKootenaiRiver(spelled“Kootenay”inCanada)originatesinsoutheasternBritishColumbia(BC).Fromtheheadwaters,itflowssouthintoLakeKoocanusa,whichstraddlestheborderbetweenBritishColumbiaandMontana.LakeKoocanusaisameldingofthewordsKootenai,Canada,andtheUSA.LibbyDam,operatedbytheUSACE,holdstheriverbacktoformtheLakeKoocanusaReservoir.Downstreamofthedam,nearLibby,Montana,theriverturnsandflowswestwardtowardIdaho.NearBonnersFerry,Idaho,theriverturnsnorth,andflowsagainintoBCwhereitentersKootenayLake.FromtheoutletonthewestarmofthelakenearNelson,BC,theriverflowswestward,throughseveralhydropowerfacilities,toitsconfluencewiththeupperColumbiaRivernearCastlegar,BC.

TheKootenaiRiversubbasinencompassesapproximately18,000squaremiles(sevenpercent)oftheColumbiaRiverbasin.Itisthethirdlargestsub‐basinbyarea,andthesecondlargestbyvolumeofwater(KTOI2009).

Historically,theamountofwaterintheKootenaiRiverhasvariedgreatlythroughtheyear.AswithmanyriversintheColumbiaRiverbasin,theKootenaiisfedbymeltingsnow,andtheannualpeakflowsoccurredinthespring.Oncethesnowhadmeltedathigherelevations,hotdrysummerswouldresultindramaticdecreasesinflowsthroughlatesummerintothefall,whenwinterrainswouldresume.FollowingtheconstructionofLibbyDamin1972,peakspringtimeflowshavebeenreducedby50percent,andwinterflowshaveincreasedby300percent(USFWS2006,2008)(Figure10).

Figure10.PeakFlowsintheKootenaiRiver,1932‐2012

Page 30: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 29

FlowsintheKootenaiRiverthroughBonnersFerryarealsoaffectedbyabackwatereffect(reducedwatersurfaceslopewhichcauseslittleornocurrentintheriver)causedbyKootenayLake.KootenayLakeis70milesdownstreamofBonnersFerryandisregulatedbyCorraLinnDam.WhenhighflowsraisethelevelofKootenayLakeduringthespringrunoff,abackwatereffectoccursintheportionoftheKootenaiRiverbetweenKootenayLakeandBonnersFerry.Inmostyears,theupstreamextentofthebackwaterreachesrivermile153nearBonnersFerry.Thisbackwatereffectchangestheslopeofthewatersurface,andconsequently,thevelocityofthewaterpassingthroughtheproposedprojectarea.Whentheamountofwaterintheriverisgreatest,thevelocityofthewaterslowsthroughtheproposedprojectareaandthewatersurfaceelevationincreases.Whentheflowsarelower,andthelakeleveldrops,thevelocityofthewaterthroughtheproposedprojectareaincreases,andwatersurfaceelevationdecreases.

Floodplains

Afloodplainisanareanearariverorastreamthatfloodswhenthewaterlevelreachesfloodstage.The100‐yearfloodplainisusedandisdefinedasanyareadeterminedbytheFederalEmergencyManagementAgency(FEMA)tohaveaonepercentchanceoffloodedduringagivenyear.

FEMAusesfloodinsuranceratemaps(FIRM)toidentifytheareaswiththepotentialtoflood.FortheproposedprojectthemostrecentFIRMmapshowingfloodplainsinthisareawasissuedAugust2,1982andshowstheprojectareaiswithinthe100‐yearfloodplain(FEMA,1982b).

Theareajustdownstreamoftheprojectarea,wheretheKootenaiRiverpassesthroughBonnersFerry,isprotectedfromfloodingbylevees.Intheareasprotectedbylevees,abasefloodelevation,ratherthanafloodplainarea,isusedtodeterminefloodrisk.Likethe100‐yearfloodplain,thebasefloodelevationistheheightthathasaonepercentchanceorgreateroffloodinginagivenyear.ThebasefloodelevationwithintheCityofBonnersFerryis1,768feetatthedownstreamend,and1,769feetattheupstreamend.TheUSACEoperatesLibbyDamandmanagesflowsintheKootenaiRiver,tominimizethepotentialforflooding.

3.3.2 EnvironmentalConsequences–ProposedAction

Theinstallationofthethreelargebankstructuresalongthenorthbankwouldprovideerosionprotectionbydeflectingriverflow.Theselargewoodandriprapstructureswouldalsoprovideareaswithslowerflowsandrecirculationeddies.Theuseofriverbottommaterialfrompoolexcavationtocreatenewislandswouldcreatenewareasofshallowwateralongtheshoresoftheseislandsthatwouldslowwatervelocitiesinareaswhereadeeperchannelandfasterwaterexistcurrently.

Poolsustainabilityattheprojectsitewouldbeinfluencedbyrivergeometry(meanderradiusandwidth‐depthratio),transitorybackwaterconditions,andtheflowpartitioningbetweenthemainstemandsidechannels.Thepotentialforpoolfillingwasminimizedtothedegreepossibleinprojectdesign,buttheexcavatedpoolswouldlikelyfilloverthenextfewyears.Poolscreatedbythethreelargebankstructurescouldforminthesameareabutthesizeandlocationofthosenewpoolsareuncertain.

Theside‐channellargewoodstructureswouldcreatehydrauliccomplexityinthesidechannelsbetweentheislands.Thestructureswouldpromotedevelopmentofbedformdiversitybyestablishingaseriesofsmallscourpools.Overtime,thesestructuresmaycollectadditionaldebrisandpromotedepositioninthesidechannels,thuscontributingtofloodplaindevelopment.

ConstructionactivitiesinandadjacenttotheKootenaiRiverwouldgeneratetemporaryandlocalizedincreasedturbidity.However,previoussamplestakenintheKootenaiRiverareashowthattheriverbottommaterialiscomprisedpredominantlyofgravelandsand(95‐97percent)withverylittlesiltorfinematerial(3‐5percent)(RiverDesignGroup,2012).Becauseofthesmallamountoffinematerialinthesediment,turbidityintheriverduringconstructionwoulddissipatequickly.Figure11showsthe

Page 31: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject30 DraftEnvironmentalAssessment

addedsedimenttotheKootenaiRiverduringislandconstructionattheBonnersFerryIslandlocation.Thesedimentplumestayedinanarrowbandalongonesideoftheriveranddissipatedwithin0.6milesdownstreamofthesourceofthesediment.

Stormwaterrunofffromtemporarily‐disturbedconstructionandstagingareascouldalsocontributesedimentladenwatertotheriverandincreaseturbidity.Erosionandsedimentcontrolmeasureswouldbeusedduringallconstructionactivitiestopreventdischargesfromconstructionsitestotherivertothemaximumextentpracticable.

Figure11.Sedimentplumeduring2015IslandConstruction

TheuseofhazardousmaterialsorsubstancesduringconstructionoftheProposedActionhasthepotentialtoresultinthecontaminationofsurfacewaterorgroundwater.Constructionequipmentcontainspetroleumproducts,suchasgasoline,dieselfuel,motoroil,andhydraulicfluid,andotherhazardousfluids,suchasanti‐freeze.Equipmentleakagemayleadtothereleaseofsmallquantitiesofthesesubstancesintotheenvironment.Theimplementationofaspillprevention,controlandcountermeasureplanandBMPswouldreducethepotentialforleaksorspillsofhazardousmaterialsfromequipmentduringconstruction.Releasesofhazardoussubstancestotheenvironmentmayalsooccurifexistingsitesofcontaminationareencounteredduringconstruction.Asdescribedabove,thesedimentanalysisconductedintheprojectareashowedlowlevelsofcontaminantsbuttheywerewithinallowablelevels(Bartonetal.2012).

Page 32: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 31

PlantingsassociatedwiththeProposedActionwould,whenmature,provideabeneficialeffectonwatertemperaturebycreatingadditionalshadealongtheriver.

Insummary,riverhydraulicswouldbechangedinlocalizedareasintheprojectarea.Constructionactivitieswouldresultintemporaryandlocalizedsedimenteffectsonsurfacewaterquality,thoughtheseeffectswouldbemitigatedbytheapplicationofbestmanagementpracticesandmitigationmeasures(seeSection2.4).Overthelong‐term,reducedstreambankerosionandturbiditywouldresultfromthecreationofnewriparianhabitatareasalongtheregradedriverbanksandnewenhancedislands.Thus,theeffectsoftheProposedActiononwaterresourceswouldbelow.

InaccordancewitharequestfromtheUSACE,ananalysiswasconductedoftheproject’spotentialtoincreasefloodingintheprojectareaaswellasareasdownstreamwithinBonnersFerrythatisregulatedbyUSACE.TheanalysisincludedthecumulativeeffectsofallthecompletedandproposedKRHRPprojectsintheBraidedReach.Modelingresultsoftheeffectsofa;theKRHRPprojectsshowlessthan0.15feetofincreasetowatersurfaceelevationsatBonnersFerry(ZoneAE)forthe100‐yearfloodeventand0.2feetforthe10‐yearfloodevent.TheseincreasesweredeterminedtobetheresultoftheBonnersFerryIslandsProjectthatwascompletedin2016.WhentheBonnersFerryareaswasanalyzedtodeterminetheeffectsoftheLowerMeanderProject,noadditionalincreaseinwaterseeninthewatersurfaceelevationforeitherthe100‐yearor10‐yearfloodevents.ModelingofpotentialchangesofwatersurfaceelevationchangeswithintheLowerMeanderprojectareashowedanincreaseoflessthan0.1feetforboththe10‐yearand100‐yearfloodevents.Basedontheseresults,theProposedActionwouldnotnotablyincreasetheBonnersFerryfloodelevationstoadegreethatwouldrequirechangesintheUSACE’swatermanagementactivitiesatLibbyDamforfloodregulationoperations(RiverDesignGroup,Inc.,2017).

Figure12.ExcerptfromFEMAFIRMPanel160270575BshowingtheregulatoryfloodplainintheLowerMeanderProjectareawithinBoundaryCounty.

3.3.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,therewouldbenochangesinriverhydrology,noconstruction‐relatedturbidity,andnochangeinbasefloodelevationsinBonnersFerry.Ongoingshorelineerosionwouldcontinuetocontributetosomesedimentationintheriver.

Page 33: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject32 DraftEnvironmentalAssessment

3.4 FishandFishHabitat

3.4.1 AffectedEnvironment

Fish

Numerousnativefishspeciesincluding,bulltrout,westslopecutthroattrout,ColumbiaRiverredbandtrout,kokanee,burbot,andKootenaiRiverwhitesturgeonexistintheKootenaiRiver,inorneartheproposedprojectarea.Noanadromousfish(fishthatlivepartoftheirlifeintheocean,thenreturntotherivertospawn,e.g.salmonandsteelhead)populationsoccupytheKootenaiRiver.Table8showsalistoffishspeciesintheKootenaiRiver.

Table8.Nativeandnon‐nativefishspeciesintheKootenaiRiverlikelytoinhabittheprojectarea

Commonname ESAstatus IdahoStatestatus

Whitesturgeon Endangered Endangered

Burbot None Endangered

Bulltrout Threatened Threatened

Westslopecutthroattrout None Gamefish

RedbandRainbowtrout None Gamefish

Kokaneesalmon None Gamefish

Mountainwhitefish None Gamefish

Redsideshiner None Unprotectedwildlife

Peamouthchub None Unprotectedwildlife

Northernpikeminnow None Unprotectedwildlife

Largescalesucker None Unprotectedwildlife

Slimysculpin None Unprotectedwildlife

Longnosesucker None Unprotectedwildlife

Torrentsculpin None Unprotectedwildlife

Rainbowtrout None Gamefish

BrownTrout None Gamefish

Brooktrout None Gamefish

Bluegill None Gamefish

Pumpkinseed None Gamefish

SmallmouthBass None Gamefish

LargemouthBass None Gamefish

NorthernPike None Gamefish

Yellowperch None Gamefish

Blackbullhead None Gamefish

Page 34: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 33

TwofishspecieslistedundertheESAmayexistintheprojectarea:theKootenaiRiverwhitesturgeon(endangered),andtheColumbiaRiverbulltrout(threatened)(USFWS2013).

JuvenileandadultKootenaiRiverwhitesturgeonliveyear‐roundintheKootenaiRiverdownstreamofBonnersFerry(USFWS,2006,2008).JuvenilesturgeoncanbefoundallyearlongupstreamofBonnersFerry,butadultsturgeonarefoundinfrequentlypastBonnersFerry.Aboutone‐thirdofKootenaiRiverwhitesturgeoninspawningconditionarebelievedtomigrateupstreamtotheBonnersFerryareaannually(MaythroughJuly),butfewremaintheretospawn(USFWS2013).

TheKootenaiRiverisoneof22designatedbulltroutrecoveryunitsintheColumbiaRiverBasin,andhasbeendesignatedascriticalhabitat.FieldstudiesshowthatadultbulltroutexistintheIdahoportionofthemainstemKootenaiRiverinverylowdensities.Bulltrouthavetwolifehistorystrategies:migratoryorresident.Migratoryformsmovebetweenlakesormainstemriverstosmalltributariestospawn.Residentformsremaininthesmalltributariesallyearlong.MigratoryformsofbulltroutintheKootenaiRiverusethemainstemKootenaiRiverasamigratorycorridortoaccessthesmalltributaries,locatedupstreaminMontana,inJuneandJuly.AfterspawninginsmalltributariesinSeptemberandOctober,theymovedownstreamintodeeppoolsinthemainstemKootenaiRiverorKootenayLakeinlateOctoberandNovember.

FishHabitat

Humanactivitysincetheearly1900shascausedsignificantlossesinriparianandwetlandareasalongthelowerKootenaiRiver,negativelyaffectingfishhabitatintheKootenaiRiver(USEPA,2004).Someofthemostseriouseffectstofishhabitathavecomefromthefollowingactivities:

Waterimpoundmentanddiversion Riverdiking Floodcontrolandchannelization Damconstructionandoperation Wetlanddrainingandassociatedreductionofnativespeciesdependentonwetlands(including

beavers) Livestockgrazing Urbanandsuburbandevelopment Landclearingforagriculture Roadbuilding Recreation

Theseactivitiescausedriparianandriverinehabitatlossanddegradationthatimpairedkeyecologicalfunctions,includingsedimentfiltering,streambankbuilding,waterstorageandaquiferrecharge,dissipationofstreamenergy,primaryproductivity,andnutrientretention.ThedegradationofthesekeyecologicalfunctionshascausedthelossofaquatichabitatsthatareimportantforthesurvivalofthenativefishfoundintheKootenaiRiver(USEPA2004).

Intheprojectarea,landusepracticesincludinggrazing,bankarmoring,gravelmining,dikeconstructionandvegetationclearinghavealteredriverbank,floodplainandvegetationconditions.Inaddition,theprojectareaisaffectedbythealteredmagnitudeandtimingofflowsreleasedfromLibbyDamlocatedupstream,andbyatransientbackwaterconditioncreatedbyKootenayLakelocateddownstreaminCanada.Multiplevegetatedislandshavedevelopedintheprojectarea,thoughvegetationdevelopmentonthemhasbeenslowduetointensebrowsepressurefromwildlife,thealteredflowconditions,andlowsupplyofsedimentandwoodydebris.

Aquatichabitatlimitingfactorsinthisreachincludealackofcover,complexity,andpools.BasedonmonitoringdatafromtheIdahoDepartmentofFishandGameandUniversityofIdahograduatestudies,

Page 35: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject34 DraftEnvironmentalAssessment

thissectionoftheKootenaiRiverisusedprimarilyasamigratorycorridorfornativefish(Zelch2003).Nativefishhavealsobeendocumentedinthenearbyenhancedoff‐channelandside‐channelhabitatcreatedbytheKootenaiTribe’sNorthSideChannelsproject.InfrequentKootenaiRiverwhitesturgeonusehasbeendocumentedinthisreachbutnospawninglocationshavebeenidentified(USFWS2013).JuvenileKootenaiRiverwhitesturgeonappeartobemovingthroughthisreach.

3.4.2 EnvironmentalConsequences–ProposedAction

AlthoughtheProposedAction’sactivitiesareintendedtoimprovefishhabitatconditionsoverthelongterm,short‐termadverseeffectstofishandfishhabitatmayoccurbecauseofconstructionactivities.TheProposedActioncouldtemporarilyaffectfishbyincreasingturbidity,generatingnoisefrompiledrivingandgeneralconstructionactivities,andbydisturbanceandinjuryfromrockplacement.

In‐waterworkwouldoccurbetweenlateAugustandearlyNovember,pertheworkwindowidentifiedbyIDFGandUSFWS,andtheperiodoflowestseasonalflowsintheKootenaiRiver.TheworkwindowfortheprojectwasestablishedsothatconstructionwouldoccurwellafterthespawningperiodforKootenaiRiverwhitesturgeon,andtoensurethatadultKootenaiRiverwhitesturgeonwouldnotbeintheareaduringprojectimplementation.Evenatsuchlowflows,becauseofthesizeoftheworkareaandthedepthandvelocityofthewater,worksiteisolationanddewateringwouldnotbepractical.Consequently,dewateringisnotproposed,andpoolexcavation,bankgrading,andbankstructureinstallationwouldoccurinwetconditions.Inaddition,siltcurtainsarenotfeasiblebecauseofthewaterdepthandvelocity–anymaterialusedtocaptureorslowwatersufficientlytoallowturbiditytosettleoutwouldbequicklyover‐topped.However,becausetheriverbottommaterialispredominantlygravelandsandwithverylittlesiltorfinematerialtoremainsuspendedinthewatercolumn,turbidityintheriverduringconstructionwoulddissipatequickly.

Floatingsiltcurtainsandtemporarybermswouldbeusedatthedownstreambankstabilizationareaandislandcreationareabecausewatervelocityintheseareasisexpectedtobelowenoughtoallowconstruction‐relatedturbiditytosettleout.Floatingsiltcurtainswouldbetemporarilyanchoredwithone‐inchdiametersteelpiles.Temporaryhaulroadswouldbeusedasbermstodirectflowaroundtheworkareasandreduceflowvelocityintheworkareas.Floatingsiltcurtainswouldnotbeusedintheupstreamareasbecausewaterdepthandvelocitythereisexpectedtobetoogreattoallowconstruction‐relatedturbiditytosettleout.

Becauseoftheamountofin‐waterworknecessarytoimplementtheProposedAction,othereffectstofishhabitatcouldoccur,suchasaccidentalhazardousmaterialspillsorfluidleaksfromconstructionequipment.TheuseofBMPswouldreducethelikelihoodofanyexposuretoaquaticorganismsshouldaspilloccur(seeSection2.4.).

ImplementationoftheProposedActionwouldrequiredrivingtimberpilesintotheriverbedtocreatetwoofthethreeproposedpool‐formingstructuresalongthenorthbankandfifteenside‐channellarge‐woodstructuresinthesidechannels.Thetwoupstreampool‐formingstructureswouldrequireapproximately52piles(Structure1)and134piles(Structure2)foratotalof186piles.Eachpilewouldbe30to50feetlong,and12to18inchesindiameter.Thefifteenside‐channelstructureswouldrequire150piles(10pileseach).Drivingeachpileintotheriverbedwouldrequireabout380impacthammerstrikesallowingforabouteightto10pilestobeinstalledperday.Atthisrate,installationofpilesintotheriverbedwouldtakeabout30to40workdays.

Thelevelofimpacttofishfromthispile‐drivingisbasedonthesoundexposurelevel,whichisdeterminedbytheloudnessanddurationofthenoise,andthedistancefishwouldbefromthenoise.Fisharealsoaffectedbytheaccumulatedsoundexposurelevel.Theaccumulatedsoundexposurelevelthatafishwouldexperienceiscalculatedbyusingthenumberofhammerstrikesduringaone‐dayworkperiod(assumingtherewouldbeabreakofatleast12hoursbetweenworkperiods)minusthe

Page 36: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 35

amountofsoundenergyabsorbedbythewater.Theaccumulatedsoundexposurelevel,perworkperiod/day,determinesthelevelofeffecttofishfromtheexposuretoprolongednoise(USFWS2013).

Duringinstallationofthelargebankstructures,thesoundpressurelevelswouldlikelyexceedthephysicalinjurythresholdforbulltroutandKootenaiRiverwhitesturgeon.AccumulatedsoundexposurelevelswouldalsoreachthethresholdforadversephysicaleffectstobothbulltroutandKootenaiRiverwhitesturgeon,extending420feetfromthepilebeingdriven.BulltroutandKootenaiRiverwhitesturgeonupto705feetawayfrompiledrivingactivitieswouldlikelybebehaviorallyaffected(moveawayfromthenoise)bynoisegeneratedbydrivingpiles(USFWS2013).

Althoughitispossiblethatbulltroutwouldbeintheprojectareaduringconstruction,theyareinlowabundance,andthehabitatareaavailableinthelowerKootenaiisquitelargecomparedtotheareathatwouldbetemporarilyaffectedbyelevatednoiselevelsduringconstruction.Additionally,theprojectareaiscurrentlycharacterizedasdegradedhabitat,whichmakesitunlikelythatbulltroutwouldbepresentatall.Inaddition,becausebulltrouttypicallymigrateatnight(HowellandBuchannan,1992),itisunlikelythattheywouldbepassingthroughtheprojectareaswhenpiledrivingisoccurring.Therefore,theeffectsonbulltroutfromnoisegeneratedbypiledrivingwouldbelow.

Sturgeonarenotexpectedtoremaininthevicinityofpiledrivingforanytimelongenoughtobemorethantemporarilyaffectedbypiledrivingnoise.Thehabitatispoortobeginwith,sofewareexpectedtobepresent,andthosemovingthroughwouldbeexpectedtoremainforonlybriefperiodsoftime‐notlongenoughfortheaccumulatedsoundexposurelevelstocauseharm.Therefore,theeffectsonKootenaiRiverwhitesturgeonfromnoisegeneratedbypiledrivingwouldbelow.

Otherfishspecieswouldlikelybepresentintheprojectareaduringconstruction(Table9)andwouldalsobeaffectedbytheshort‐termandtemporaryconstructionactivities.Thelargesteffecttofishwouldbetheirshorttermdisplacementfromoccupiedhabitatsfromthenoisegeneratedbypiledriving.Thoughadjacenthabitatsareavailableforthemtodisplaceinto,thosehabitatsarelikelyalreadyoccupiedbyotherfish.Thissetsupacompetitivescenariothatputsindividual,likelysmallerorweaker,fishathigherriskfromincreasedexposuretopredationorsomeadverseenvironmentalfactorsuchastemperature,flow,preyscarcity,etc.fortheperiodoftimetheyaredisplacedandexposed.However,thenumbersoffishimpactedwouldlikelybelow,asfishhabitatinthisareaislimitedandofpoorqualityandfishpopulationsherearethusanticipatedtobelow.Therewouldthusbealowtomoderateshort‐termandtemporaryeffecttofishintheprojectarea.

Asaresultoftheproject,however,fishhabitatwouldbeimprovedandexpanded.TheProposedActionwouldcreatehabitatconditionsconsistentwithwhatonceexistednaturallyintheKootenaiRiversystembuthassincebeenlostduetohuman‐causedchangestothebasin.Theseimprovementswouldprovidehighercarryingcapacitythanbeforeformultiplespeciesandalllifestages,andthelong‐termoutcomeswouldbebeneficial.

3.4.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,therewouldbenodisturbancetofishduetoconstructionactivitiesandpoorhabitatconditionsforKootenaiRiverwhitesturgeon,burbot,bulltrout,andothernativefishspecieswouldremainandpossiblyworsen.

3.5 Recreation3.5.1 AffectedEnvironment

TheKootenaiRiverisawide,slow‐movingriverinthereachesaboveandbelowtheprojectareaandthusholdslittleattractionforkayakersandrafterswhopreferthefasterwaterfoundupstreamoftheprojectarea.Itsuseisprimarilybyrecreationalboatersandanglersastheriversupportscutthroat

Page 37: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject36 DraftEnvironmentalAssessment

andrainbowtroutaswellasmountainwhitefishandotherspecies.FishhabitatqualityhasbeenimprovingduetotheTribe’shabitatrestorationeffortsandsoitsattractionforfishandanglersisincreasing.In2009,theestimateoftroutpermilehadincreasedfrom50fishpermiletoalmost300fishpermile(RyanHardy,perscom,2016).

Theriverisrelativelyinaccessiblefromshoresincemostshorelineisinprivateownership.Thereissomeevidenceoflimitedprivateshorelineusebuttherearenopublicaccesssitestotheriverwithintheprojectarea.ThenearestboatrampsarelocatedfourmilesupstreamattheTwinRiversResortandtwomilesdownstreamattheSearchandRescueBoatRamp.BoatslaunchedatthislocationwouldtravelthroughtheprojectareaandtakeoutattheBoundarySearchandDiveRescueboatramplocatedonthesouthbankoftheKootenaiRiver,offRiversideDrivedownstreamofBonnersFerry.Approximately200boatslaunchfromTwinRiverseachyear(RexHoisington,personalcommunication,Dec2016).SomeoftheseboatsmotorupstreamintotheKootenaiRiverCanyon;theremainderfloatdownstreamtoBonnersFerry.

3.5.2 EnvironmentalConsequences–ProposedAction

BecausetheKootenaiRiverisregularlyusedforrecreationalboating,theimplementationoftheproposedprojecthasthepotentialtoaffectrecreation,bothduringconstructionandfromthelong‐termpresenceoflargewoodstructuresonthebankorinthesidechannels.

Theinstallationoflargebankandinstreamwoodstructuresalongthebanksandwithinthechannelscouldposeadangertoboaters,kayakers,andtubers.Theselogstructureswouldextendintothecurrentoftheriverandcouldcreatethepotentialforsnaggingordamagingpassingboatsorthatpeoplefloatingoninnertubescouldbebeinginjuredorentrainedbytheswirlingcurrentscreatedbythestructures.

ConstructionoflargebankandlargewoodstructuresintheprojectareawouldoccurbetweenlateAugustandearlyNovemberin2017and2018.Duringconstruction,someequipmentwouldbeinorneartheriverthuscreatingthepotentialforaboatinghazard.Thispotentialislikelytobelowbecauseofthelongsightlinesthatwouldallowboaterstoseetheconstructionactivitiesbeforereachingthearea.AlsotheTribewouldpostsignsattheTwinRiversResortboatlaunchnotifyingboatersoftheconstructionactivityandtoremainaware.

Becauseofhighflowsandcoldwater,themajorityoftheboatingthroughtheprojectareaoccursbetweenJulyandSeptemberwhenflowsrangefrom20,000cfsinJulytolessthan10,000cfsinSeptember.Atthelowestflows,thelargebankstructureswouldextendapproximately200feetoutintothemainchanneloftheriver,leaving200‐300feetofchannelwidthforboaterstonavigate.Intheside‐channelsestablishedbetweenthenewlyconstructedislands,fifteenlargewoodstructureswouldbecomestationaryobjectsthatrecreationalboaterswouldneedtoavoid.Atlowflows,therewouldbeapproximately100feetofchanneltonavigatearoundthestructures,thoughthemajorityofboatersareexpectedtoremaininthemainchannelandnotenterthesidechannelsatall.Inaddition,thestructureswouldmimictheappearance,function,andeffectsonflowofsimilarnaturalfeaturesoccurringalongmajorwaterwaysliketheKootenaiRiver.Flowsareexpectedtobedeflectedawayfromthestructuresandtowardtheunobstructedareasoftheriver,andexperiencedriverfloatersroutinelyusesuchflowstoavoidriverobstacles.Oncecompleted,therecreationeffectswouldbelowbecausethestructureswouldbevisibletoboatersapproachingfromupstreamandtherewouldbeampletimeandspacewithwhichtonavigatethroughthearea.

Temporaryconstruction,transportation,andstagingactivitiesalongthebanksandislandsareexpectedtohavenoeffectonrecreationastheseareasarenotaccessibletothepublicandarenotusedrecreationally.

Page 38: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 37

Long‐termimprovementinfishingopportunitiesareanticipatedasfishpopulationsrespondtoimprovedhabitatconditions.AsrecentlyasSeptember2016,aSpokane,Washingtonnewspaper(Landers2016)citedtheseongoinghabitatimprovementsintheKootenaiRiverasboostingfishpopulationsandincreasingfishingopportunities.

3.5.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,norestorationactionswouldbeimplementedandtherewouldbenoeffect(positiveornegative)onrecreationactivitiesontheKootenaiRiver.

3.6 CulturalResourcesCulturalresourcesarethingsandplacesthatshowevidenceofhumanoccupationoractivityrelatedtohistory,architecture,archaeology,engineering,andculture.Historicproperties,asdefinedby36CFR800(theimplementingregulationsoftheNationalHistoricPreservationAct[NHPA],54USC306108)areasubsetofculturalresources.Thissubsetconsistsofanydistrict,site,building,structure,artifact,ruin,object,workofart,ornaturalfeatureimportantinhumanhistorythatmeetsdefinedeligibilitycriteriafortheNationalRegisterofHistoricPlaces(NRHP).

TheNHPArequiresthatfederalagenciesinventoryandevaluateculturalresourcesforeligibilityforlistingintheNRHP,andevaluateandconsidereffectsoftheiractionsontheseresources.FederalagenciesevaluateculturalresourcesforeligibilityintheNRHPusingspecificcriteria,includinganexaminationoftheculturalresource’sage,integrity(oflocation,design,setting,materials,workmanship,feelingandassociation),andsignificanceinAmericanculture,amongotherthings.AculturalresourcemustmeetatleastonecriteriontobeeligibleforlistingintheNRHP.HistoricpropertiesincludeprehistoricresourcesthatpredateEuropeancontactandsettlement.

3.6.1 AffectedEnvironment

EthnographicOverview

TheprojectareaiswithinthetraditionalterritoryoftheKtunaxa(Kootenai)Nation,andspecifically,theLowerKootenaipeople.TheKootenaiTribeofIdahoispartoftheKtunaxaNation.TheLowerKootenaipeopletraditionallyoccupiedtheKootenaiRivervalleys,andthesurroundingareas,fromwhatarenowLibbyandJennings,Montana,toKootenayLakeinBritishColumbia.

AfewLowerKootenaiwouldaccompanytheUpperKootenaionsnowshoes(beforetheyhadhorses),toareaseastoftheRockyMountainsontheiryearlybison‐huntingexpeditions(Brunton,1998).OneofthestopsalongtheKootenaiRiverwheregroupswouldfindresourceswasatthemouthoftheMoyieRiver,nowthesiteoftheKootenaiTribe’sTwinRiversCanyonResortandTwinRiversSturgeonandBurbotHatchery(onaportionoftheKootenaiTribe’sreservation).

SomeoftheKootenai,especiallytheLowerKootenai,wouldjoinlargetribalgatheringsatKettleFalls,fortheJulyandAugustrunsofChinook,coho,andsockeyesalmon(KennedyandBouchard,1998).BirdhuntingwasessentialtotheLowerKootenaiandsought‐afterspeciesincludedcranes,ducks,gulls,sprucegrouse(knownasfoolhens),andgeese.

TheKootenaiTribeofIdahoreliedheavilyonthelocalfisheryincludingsturgeon(whichtheircanoesweremodeledafter)andburbotaswellasothernativefish.Inthesummerandfall,theycollectedberries,fallroots,seeds,andvariousplants,andhuntedfordeer,elk,caribou,andmoose.Theyalsohuntedortrappedbeaver,muskrat,mountaingoats,bear,lynx,wolf,andotheranimalsfortheirhidesand,occasionally,forfood.

Page 39: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject38 DraftEnvironmentalAssessment

HistoricalOverview

DavidThompson,aBritish‐Canadiansurveyorandfurtrader,wasthefirstnon‐Indiantoexplorethearea.In1807,ThompsontravelleduptheKootenaiRiverfromKootenayLakeinsoutheasternBritishColumbia.HestoredcanoesnearBonnersFerryandtraveledonhorsebackuptheMoyieRivervalley,totheareathatisnowCranbrookandFt.Steele,B.C.(TyrellJ.B.,1916).

Followingtheearlyexplorationoftheregionbyfurtraders,thediscoveryofgoldcausedthefirstsustainedrushofEuro‐AmericansettlerstonorthernIdaho.Thisinspiredtheconstructionofatransportationsystemsufficienttocarrypeopleandgoods.Aftertheinitialrushofprospectorsbroughtdevelopmentofmorestablecommunities,interestturnedtorockmines.This,inturn,requiredaregionaltransportationsystemtobringthemassiveequipmentthatthemillsandsmeltersrequired(Ostrogorskyetal,1991).

In1882,workerscompletedthetranscontinentalNorthernPacificRailroad.ItspannednorthernIdaho,northoftheClarkForkRiver,aroundthenorthsideofLakePendOreille,alongthenorthsideofthePendOreilleRiver.There,itcrossedjustaboveAlbeniFalls,andthenwentsouthwestfromNewporttoSpokane,Washington.

In1893,JamesJ.HillcompletedhisGreatNorthernRailroad,whichranfromDuluth,Minnesota,toSeattle,Washington,bywayoftheKootenaiRiverandBonnersFerry.TherailwayrouteinnorthIdahocrossedtheKootenaiRiveratBonnersFerry,ransouthtocrossLakePendOreilleatSandpoint,andcontinuedacrosstheRathdrumPrairietoSpokane.TheSpokaneInternationallinefollowedin1905,crossingtheKootenaiRiveratBonnersFerry,andconnectingSpokanewiththeCanadianPacificRailway(BonnerCountyHistoryBookCommittee,1991).

Railroadsopenedtheareatolarge‐scalelogging,mining,andagriculturaldevelopment.Thisgaverisetosmallcommunitiesandlumbermillsalongtheirroutes.SmalltownsincludingAddie,MeadowCreek,Snyder,andMoyieSpringsinIdaho,dependedontherailroadforsuppliesandcommunication.

3.6.2 EnvironmentalConsequences–ProposedAction

BasedonthereviewofarchaeologicalsiterecordsandculturalresourcesurveyreportsonfileattheIdahoStateHistoricPreservationOfficeandnineteenth‐centurymapscreatedbytheGeneralLandOffice,twopreviouslyrecordedarchaeologicalsiteswithintheprojectareawereidentified.

ApedestrianandsubsurfacesurveywasconductedonNovember16,2016andfinishedNovember19,2016.RonAbraham,KootenaiTribeofIdahoTribalCouncilman,observedthefieldwork.Duringthepedestriansurvey,twonewarchaeologicalsiteswereidentified.OneofthesiteswaspreviouslydeterminedeligibleforlistingintheNRHP;however,thesiteremainsarelocatedoutsideoftheconstructionfootprintthusdirectimpactstoitwouldnotoccur.ThesecondsitewaspreviouslyidentifiedanddeterminednoteligibleforlistingintheNRHP(Dampf,Perrin,&Tarman,2014).Thus,thepotentialfortheproposedactiontoeffectculturalresourcesislow.

Thoughthepotentialforadditionalundiscoveredsitestobefoundduringconstructionislow,aprotocolformanaginganinadvertentdiscoverywouldbedevelopedandfollowedthatwouldpreventorlessenpotentialeffectstositesifdiscoveredduringconstructionactivities.

3.6.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,becausenorestorationactionswouldbeimplemented,therewouldbenopotentialforeffectsonculturalresources.

Page 40: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 39

3.7 VisualResources3.7.1 AffectedEnvironment

Thevisualcharacteroftheprojectareaisdominatedbythenaturalfeaturesoftheriverandthehuman‐alteredfeaturesofagriculturalareasandprivatehomesites.

Theriver’sfeaturesincludethebroad,nearlyquartermile‐wideKootenairiversurface,willow‐shruborwoodedriparianislandsandriverbanks,andexposedgravelandsandbars.Theagriculturalandhomesitefeaturesalongtheriverincludeplowedorcultivatedhayfields,farmhouses,outbuildings,barns,andfarmroadsandequipment.

TheprojectareaisvisibletoonlyasmallsectionoftheelevatedresidentialnortheasternsectionofBonnersFerryeastofUSHighway95/2andsouthofCowCreekRoad;andtotheriver‐levelresidencesimmediatelyeastoftheKootenaiRiverInn.TheprojectareaisnotvisiblefromtheKootenaiRiverInn.

TheprojectareawouldbeclearlyvisiblefromtheCowCreekRoadinplacesasitiselevated30to50feetabovetheriver.Thisroadfollowstheriverupstreamandisbetween0.35and0.65milesfromtheprojectareaatvariousspots,thustheprojectareawouldbemiddlegroundtobackgroundviewing.Noneoftheprojectareaisinforegroundornearmiddle‐groundviewingdistance.

3.7.2 EnvironmentalConsequences–ProposedAction

BuildingtheProposedActionwouldcauseseveralchangestothevisuallandscape.Thenewandenhancedislands(anearlythree‐foldincreaseinsize),bankgradingandstabilization,andlargewoodstructureswouldbevisiblefromCowCreekRoadandthebluffsouthofthemaindowntownarea,andbyrecreationalboaters.Whilevisible,theywouldlikelynotbethatnoticeabletomostviewersduetotheirdistanceaway(generallyoverone‐halfmile).Noneofthelargebankstructureswouldbeclearlydiscernabletoanyoneotherthanboatersontheriverorthetwoprivateresidencesnearthesouthbankoftheriver.

ConstructionactivitiesfromAugusttoNovemberin2017and2018mightbevisible,butnotclearlydiscernablebecauseofdistance.Constructioneffectsonvisualresourcesfromlocationsthepublicmightbepresentwouldbetemporaryandlow.

Duringandafterconstructioniscompleted,thehabitatstructuresandenhanced/newislandswouldbevisibletoboatersandthefewresidentsadjacenttotheprojectsite.Overtime,asnewvegetationestablishesandmatures,thesitewouldresemblenaturalfeaturesthatoccuralonglargerivers,andwouldbeconsistentwiththeexistinglandscape.Consequently,thelong‐termeffectsonthevisualresourceswouldbelow.

3.7.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,norestorationactionswouldoccurintheKootenaiLowerMeanderprojectarea.TheviewsoftheKootenaiRiverbothfromlandandwaterwouldstillchangeovertimeastheshorelineandexistingislandserode,cutbanksshift,andastheriverredepositsmaterials.

3.8 Noise3.8.1 AffectedEnvironment

Forthepurposesofthisanalysis,noiseisanysoundthatisloud,disruptive,unexpected,orotherwiseundesirable.EnvironmentalnoiseiscommonlyquantifiedintermsofA‐weighteddecibels(dBA);anoverallfrequency‐weightedsoundlevelthatapproximatesthefrequencyresponseofthehumanear.Table9containsexamplesofcommonactivitiesandtheirassociatednoiselevelsindBA.

Page 41: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject40 DraftEnvironmentalAssessment

Table9.Commonactivitiesandassociatednoiselevels

Source/Location SoundLevelThresholdofHearing 0dBALibrary 35dBAChicagoSuburbs–nighttime minimum40dBASmallTown/QuietSuburb 47‐53dBAPrivateBusinessOffice 50dBALightTrafficat100ftAway 50dBAAverageResidence 50dBALargeRetailStore 60dBAAccountingOffice 60dBABoston‐InsideHouseonMajorAvenue 68dBAAverageTrafficonStreetCorner 75dBAInsideSportsCar(50mph) 80dBALosAngeles‐¾milefromJetLanding 86dBAInsideNewYorkSubwayTrain 95dBALoudAutomobileHorn(at1m) 115dBA

Source:EPA1974

Theabilitytoperceiveanewnoisesourceintrudingintobackgroundconditionsdependsonthenatureoftheintrudingsound,andthebackgroundsound.Forsituationswherethenatureofthenewsoundissimilartothebackgroundsound(e.g.,newtrafficnoiseaddedtobackgroundtrafficnoise),anoiseof3dBAisjustnoticeable,achangeof5dBAisclearlynoticeable,andachangeof10dBAisperceivedasdoublingthesoundlevel(orhalving,ifthesoundisreduced).Forsituationswherethenatureofthenewintrudingsoundisdifferentfrombackgroundsound(e.g.,constructionnoiseinanotherwisequietsetting),thenewsound(includingsporadic“clanks”fromconstructionequipment)canbeeasilyperceived,evenifitonlyraisestheoverallnoiselevelbylessthan1dBA.

Therearenearbyresidentsandthoserecreatinginorneartheprojectareathatwouldbesusceptibletonoiseeffects.ExistingnoisesourcesincludetrafficalongUSHighway95/2andCowCreekRoad,traintrafficontheBurlingtonNorthernSantaFerailwaylineimmediatelysouthoftheprojectarea,theUnionPacificrailwaywestoftheprojectarea,andsawmilloperationssouthoftheprojectarea.

BackgroundnoiselevelsinsmalltownssuchasBonnersFerryaretypicallyaround45dBAduringthedayand35dBAatnight(EPA,1974).Thetraingeneratesintermittent,loudsoundsasitpasses.Noisegeneratedbyanindividualtraindependsonthetraintype,length,speed,andwhetherthetrainusesitswarningwhistle.Trainssoundtheirwarningwhistleatthe“at‐grade”vehiclecrossings,liketheoneonOakStreetinBonnersFerry,towarnmotoristsoftheon‐comingtrain.Atadistanceof100feet,atrain‐warningwhistlecangeneratemaximumnoiselevelsofabout100to105dBA.Trainenginestypicallygeneratemaximumnoiselevelsofapproximately80to85dBA,whiletraincarsgeneratenoiselevelsofabout70to75dBA.

3.8.2 EnvironmentalConsequences–ProposedAction

Theprimaryeffectfromconstructionactivitiesforthisprojectwouldcomefromthenoiseofpiledriving.Animpactpile‐drivinghammerisalargepiston‐likedevicethatisusuallyattachedtoacrane.Mostimpactpiledriverhammershaveaverticalsupportthatholdsthepileinplace,andaheavyweight,orram,movesupanddown,strikingananvilthattransmitstheblowoftheramtothepile.Thenoisefromanimpactpile‐drivinghammercomesfromtheimpactofthetoolagainstmaterial.Theselevelscanvarydependingonthetypeandconditionofthematerial.Noiselevelsat50feetfromimpact

Page 42: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 41

pile‐drivinghammercanrangefrom80to110dBA.ThenearestresidencetotheprojectareaisonthesouthbankoftheKootenaiRiverandmorethan1,000feetawayfromwherepiledrivingwouldoccur.

Thetwoupstreamlargebankstructureswouldrequireapproximately186piles,30to50feetlong,and12to18inchesindiameter.Thefifteenside‐channelstructureswouldrequire150piles(10pileseach).Drivingeachpileintotheriverbedwouldrequireabout380impacthammerstrikes.Workerswouldlikelyinstalleightto10pilesperday,andwouldthusbedrivingpilesintotheriverbedforapproximately34to42daysMondaythroughSaturday,7:30AMto6PM.

Assumingmaximumconstruction‐generatednoiselevelof110dBAat50feetandanaverageexteriororinteriorstructuralattenuationof15dBA,inhabitantsofresidenceswithinapproximately2,000feetoftheconstructionareasandmaterialyardscouldexperienceincreasesinambientnoiselevelsofgreaterthan10dBA.Ifconstructionactivitiesweretooccurduringthemorenoise‐sensitiveperiodsoftheday(i.e.,eveningandnighttimehours),resultantincreasesinambientnoiselevelscouldresultinsleepdisruptiontooccupantsoftheseresidentialdwellings.Becausetheprojectwouldrestrictconstructiontodaytimehours,effectsfromconstruction‐generatednoisewouldbemoderatebutshorttermfornearbyresidences.

ForallothergeneralconstructionactivitiesintheLowerMeanderProjectareas,noisegeneratedduringconstructionwouldlikelybeonlyslightlyhigherthanexistingbackgroundlevels.Becauseofthelownoiselevelsandtheshortdurationoftheconstructionperiod,noiseeffectsduringconstructionwouldbelow.

3.8.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,norestorationactionswouldbeimplementedintheKootenaiRiverLowerMeanderProjectareaandtherewouldbenoeffectsfromconstruction‐relatednoise.

3.9 AirQualityandGreenhouseGasses3.9.1 AffectedEnvironment

Existing,localizedsourcesofairpollutantsinthestudyareaincludevehiclesonstateandlocalhighways,dieseltrainlocomotives,agriculturalactivities,andindustriallanduses,suchastimbermills.BoundaryCountyis“inattainment”withtheNationalAmbientAirQualityStandardsundertheCleanAirAct.Being“inattainment”meansthattheconcentrationsofairpollutantsintheareaarehistoricallybelowthelimitsdescribedintheNationalAmbientAirQualityStandardswhichcontaincriteriathattheEnvironmentalProtectionAgency(EPA)usestodetermineairqualitybasedonwhatkindofcontaminants,andhowmuchofthem,areinanairsampleforagiventimeperiod(IDEQ,2016).

3.9.2 EnvironmentalConsequences–ProposedAction

AirpollutantemissionswouldbegeneratedduringtheconstructionoftheProposedAction.Ifthepollutantsoccurinsignificantamounts,theycouldposeapublichealthhazard,especiallyforpeoplewithrespiratoryailments.Theemissionscouldreducevisibilityonroads,highways,andinscenicareastothedetrimentofpublicsafetyorenjoyment.Inaddition,vehicleemissionsandcombustionoffossilfuelsduringprojectoperations,aswellasduringconstruction,couldemitgreenhousegases.

Thepollutantsthatcouldincreasebecauseofprojectconstructionarecarbonmonoxide,ozone,andparticulatematter(dust).Dustcouldbecreatedduringconstructionbyvehiclestravellingonunpavedsurfacesandfromground‐disturbingactivities.Thereisnoresidentialareacloseenoughtotheconstructionsitestobeaffectedbyconstructionactivitydust–thenearestisoveramileaway.However,dusteffectswouldbelowbecausetheywouldonlyoccurduringconstruction(AugustthroughNovemberof2017and/or2018),wouldbetemporary,andwouldoccurinlocalizedareas.Consequently,airqualityeffectsduringconstructionwouldbelow.

Page 43: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject42 DraftEnvironmentalAssessment

Emissionsfromconstructionvehicleswouldcontributegreenhousegasestotheatmospherethroughgasolineanddieselcombustionmotors.

Greenhousegas(GHG)emissionswereestimatedbasedontheapproximatenumberofvehiclestobeusedduringprojectconstruction,andtheapproximatedistancethosevehicleswouldtravelduringtheconstructionperiod.FortheProposedAction,workerswouldhaveanestimated30vehicleroundtripsperdayatthesiteduringtwo,threemonthconstructionperiods(2017and2018).Theestimatedgreenhousegasemissionsforthesetwoconstructionperiodswouldbe383metrictonsofcarbondioxide(CO2).Whileallemissionsofgreenhousegasescontributetoglobalgreenhousegasconcentrationsandclimatechange,thetotalCO2emissionsfromtheproposedprojectwouldbelowcomparedtoemissionsfromothercontributors.

3.9.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,norestorationactionswouldbeimplementedintheKootenaiLowerMeanderprojectareaandtherewouldbenoeffectonairqualityandnoemissionsofGHGs.

3.10 PublicHealthandSafety3.10.1 AffectedEnvironment

TheProposedActionislocatedinaruralsettingonprivatepropertiesonwhichtheownersconductresidential,ranchingandotheractivitiesthatarenottypicallyregardedaslikelysourcesoftoxicorhazardoussubstances.Publichealthandsafetyriskspresentatandnearthesitesaretypicalofthoseforruralareaswithlimiteddevelopment,includingeventssuchastrafficaccidents,weather‐relatedtravelhazards,wildfires,floodsandmedicalemergencies.Numerousfederal,stateandlocalgovernmentjurisdictionsprovidelawenforcement,fireprotection,emergencymedicalandrelatedpublichealthandsafetyservicesintheBonnersFerryarea.

3.10.2 EnvironmentalConsequences–ProposedAction

Workaroundwaterisinherentlydangerous,andriskofdrowningwouldincreasebecauseworkermobilitywouldberestrictedwhileequipmentisoperating.Riskofinjurytoworkerscomesfromtheuseofheavyequipment,workingnearhigh‐voltagelines,workinginwater,andbeingexposedtohazardousmaterialssuchasfuelsduringtemporaryroadconstructionandearthwork,andplacementofstructures.Constructionactivity,however,wouldbeconductedsubjecttostandardBPAcontractrequirementsforworkersafety;accesstotheconstructionsitesandtravelonlocalroadswouldbemanagedtominimizesafetyrisksfornon‐projecthumanactivityintheprojectarea,andconstructionactivitieswouldmeettheguidelinesforuse,handling,storage,anddisposalofhazardoussubstances.

Futureneedsforlawenforcement,fireprotection,emergencymedical,andrelatedpublichealthandsafetyserviceswouldremainwithinthecapacityoftheexistingserviceproviders.Therewouldbenoimpactfromtheseactivitiesonthecontinueddeliveryofthoseservices.

Largewoodstructuresintroducealong‐termpotentialboatinghazardatmultiplelocationswithintheriverintheprojectarea.Projectdesignsforthesefeatureswouldprovideadequatetimeandspaceforboaterstoavoidthestructures.Also,theTribehasinstalledsignageattheTribally‐ownedTwinRiversCanyonResortboatlaunchtoinformboatersoftherestorationactivitiesalongtheriverandindicatingtheirlocation.

Becauseprojectactivitieswouldbeconductedincompliancewithapplicablelaws,regulations,andguidelines;andtherewouldbenoeffectsonpublichealthandsafetyservices,theeffectoftheProposedActiononpublichealthandsafetywouldbelow.

Page 44: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 43

3.10.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,norestorationactionswouldbeimplementedintheKootenaiLowerMeanderprojectarea,andtherewouldbenoeffectonpublichealthandsafety.

3.11 TransportationandUtilities3.11.1 AffectedEnvironment

PublicandPrivateRoadsaffected

Theprojectareaisaccessibleonlybyprivatefarmroads.ThenearestpublicroadsaretheCowCreekRoadandWaterfrontLanetothesouthandtheDistrict2Road(CountyRoad60)andBallParkRoadtothenorthandwest.PrivatefarmroadsthatconnecttothesepublicroadswouldbeimprovedandusedforconstructionaccessasdiscussedinSections2.1.5and2.1.6.Figure8displaystheexistingandproposedtemporaryaccessroads.Figure13displaysthetransportationinfrastructureinandneartheprojectarea.

Figure13Mainpublicaccessroadsintotheprojectarea

Page 45: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject44 DraftEnvironmentalAssessment

RailroadsandPublicUtilities

TheBurlingtonNorthernSantaFeraillineparallelstheKootenaiRiveralongitsouthernbank,andapproximately42trainsusethisraillineperday.TheUnionPacificraillinecrossesDistrict2Roadonthenorthsideoftheriverandisusedbyapproximatelyeighttrainsperday.

Therearenomajorutilitycorridorswithinoradjacenttotheprojectarea,thoughthereisalocaldistributionpowerlinethatcrossestheriverimmediatelydownstreamoftheprojectarea,andburiedlocalpowerlinesupslopeof,butnotwithin,thebankstabilizationsworkareasinphase2(seeFigure4).

3.11.2 EnvironmentalConsequences–ProposedAction

TheProposedActionwouldtemporarilyincreasetrafficfromvehiclescarryingconstructionmaterialstoandfromtheprojectareasites.Largeconstructionequipmenttravelingtotheprojectareasmayalsoperiodicallyblocktraffic,causingshort‐termdelaysforothervehicles.

ConstructionvehicleswouldberequiredtocrosstheunmarkedlevelcrossingoftheBurlingtonNorthernSantaFeraillineonWaterfrontLane.Becausethiscrossingisunmarked,aBurlingtonNorthernSantaFeflaggermayneedtobepresentduringallconstructiontimestoavoidtrainconflictsordelays.TrafficwillalsocrosstheUnionPacificrailwayonthenorthsideoftheriveratDistrict2Road.Thisisapublicmarkedcrossingsowouldnotrequireaflagger.

BoththeDistrict2RoadandtheCowCreekRoadarereadilyaccessiblefromHwy2.ConstructiontraffictravelingalongthesouthbankoftheKootenaiRiveronCowCreekRoadwouldpassthroughseveralsmallresidentialareas.Whileconstructionwouldtemporarilyincreasetraffic,theeffectwouldbeminorcomparedwithexistingroadwayuse,andisnotexpectedtosubstantiallyaltertrafficoperationsonthelocalroads.Althoughlargeconstructionvehiclesandtruckscontainingmaterialscouldcausetrafficdelays,thosedelayswouldbebriefandinfrequent.Therefore,transportationeffectsduringconstructionatbothlocationswouldbelowtomoderate.

3.11.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,restorationactivitiesintheKootenaiLowerMeanderProjectareawouldnotoccur;therefore,therewouldbenoeffectontransportation.

3.12 Socioeconomics3.12.1 AffectedEnvironment

BoundaryCounty,Idaho,isthestudyareaforsocioeconomics.

PopulationandHousing

BoundaryCounty'sscenery,recreationalopportunities,qualityoflifeandexpandingjobmarketdrewmanynewresidentsinthe1980sand1990s.Theeconomicdownturnin2001slowedeconomicandpopulationgrowthofthecountywithgrowthresumingin2005aspopulationandemploymentexpandedacrossthestate.Thecounty’slowerhousingcostsandrurallifestyledrewsomepeoplefromneighboringBonnerCounty.From2005to2015,thecounty’spopulationgrew10percentfrom10,303to11,318whileIdaho'spopulationgrew16percentandtheU.S.populationgrew9percent.(IdahoDept.ofLabor2016)

About90percentofthecountyisforestedsomostofthepeopleliveintheKootenaiRiverValley.BonnersFerryhadapopulationof2,549andMoyieSpringshadapopulationof717in2015.(IdahoDept.ofLabor2016)

Page 46: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 45

Table10DemographicCharacteristics,2012

BonnersFerry BoundaryCounty StateofIdaho

TotalPopulation 2,543 10,972 1,567,582

MinorityPopulation 146(5.7%) 574(5.2%) 171,095(10.9%)

Low‐IncomePopulation 23.9(+/‐7.9) 16.1(+/‐3.8) 15.0%(+/‐0.3)

EmploymentandIncome

Agriculture,forestryandrelatedenterpriseshavehistoricallybeentheeconomicmainstaysinBoundaryCountybutotherindustriessuchastransportation,wholesaling,retailing,servicebusinesses,andgovernmentalserviceareincreasingintheircontributiontothecounty’seconomy.Healthcare,manufacturingandretailplayanincreasinglyimportantrole(IdahoDept.ofLabor2016).

Agriculture'simportanceincreasedinthe1980swhenAnheuser‐BuschbegangrowinghopsatElkMountainFarms,andseveralornamentaltreenurseriesandChristmastreefarmsopened.WiththechangeinownershipfromAnheuser‐BuschtotheBelgium‐basedIn‐Bevcompany—formingAnheuser‐BuschInBev,ElkMountainFarmscutbackproductionandremainsinflux.(IdahoDept.ofLabor2016)

In1986,theKootenaiTribeopenedtheKootenaiRiverInn,contributingtothecounty'stourismsectorpotential.Inthe1990s,theTribeaddedacasinoandmostrecentlyexpandedthehotel.ThecountyalsobenefitsfromeconomicactivityatitstwoportsofentryontheCanadianborder—PorthillandEastport.Importsincreased24percentatthetwoportsthroughthedepthsoftherecessionandexportsincreased37percentfrom2009to2011.BonnersFerry,namedbytouristsasIdaho’s“friendliestcity,”hasmademajorimprovementstoitsdowntowntoattractmorevisitors(IdahoDept.ofLabor2016).

BoundaryCountyhasbeensuccessfulindiversifyingandexpandingitseconomywiththenumberofprivate‐sectoremployersinBoundaryCountyincreasingby13.4percent(374to424)sincetheyear2000.Theindustriescreatingthemostnewbusinesseswerehealthcare,professional,andbusinessservices(IdahoDept.ofLabor2016).

About4,288peopleage16andoverhadjobsinsomecapacityinBoundaryCountyin2012(USCensus,2012).Theunemploymentrateinthestudyareain2012was5.6percent.In2012,per‐capitapersonalincomeinthestudyareawas$18,298(USCensus,2012).BoundaryCountygovernmentandBoundaryCommunityHospitalarethelargestemployers;andIdahoForestGroupandWelcoarethelargestprivateemployers(IdahoDepartmentofLabor,2017).

EnvironmentalJustice

ExecutiveOrder12898directsfederalagenciestoidentifyandaddress“disproportionatelyhighandadversehumanhealthorenvironmentaleffectsofitsprograms,policies,andactivitiesonminoritypopulationsandlow‐incomepopulations”(collectively,environmentaljusticepopulations)(59FederalRegister7629[February11,1994]).ThisexecutiveorderdirectsagenciestoanalyzetheeffectsofpotentialactionsonminorityandlowincomecommunitiesthroughtheNationalEnvironmentalPolicyActreviewprocess(CouncilonEnvironmentalQuality,1997).

Todeterminepotentialeffects,federalagenciesidentifygeographicareaswhereethnicandracialminoritiesexceed50percentofthepopulation,inadditiontogeographicareaswherethepercentageoftheethnicandracialminoritypopulationis“meaningfullygreater”thanthepercentageinthesurroundingarea.Low‐incomepopulationsarepopulationsthatareatorbelowthepovertyline,asestablishedbytheU.S.DepartmentofHealthandHumanServices.

Page 47: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject46 DraftEnvironmentalAssessment

InBonnersFerry,4.7percentofthepopulationisconsideredaminority.InBoundaryCounty,3.6percentofthepopulationisconsideredaminoritypopulation.InthestateofIdaho,5.4percentofthepopulationisconsideredaminoritypopulation(USCensus,2012).

TheU.S.CensusBureauusesasetofdollarvaluethresholdsthatvarybyfamilysizeandcompositiontodeterminethepovertylevel.Between2008and2012inBonnersFerry,23.9percentofpeoplehadincomesbelowthepovertylevelBoundaryCountyascomparedto16.1percentofthepopulationofBoundaryCountyand13.6percentofthestatewidepopulation(USCensus,2014).

3.12.2 EnvironmentalConsequences–ProposedAction

PopulationandHousing

BecausestagingandconstructionfortheproposedactionwouldoccurbetweenJulyandNovemberin2017and2018,thedurationofworkwouldlikelynotbelongenoughtoinduceanypermanentchangestopopulationinthestudyarea.Constructionwouldrequireapproximately20workers,withtheworkforcecomingfrombothinsideandoutsideBoundaryCounty.WorkersfromoutsideBoundaryCountywouldlikelyresidetemporarilywithintheprojectvicinityandhaveanindiscernibleeffectontheoverallpopulationofthestudyarea.Theworkersfromoutoftheareawouldrequiretemporarylodginginthelocalarea.Constructionworkerswouldlikelyoccupyrecreationalvehicleparksandhotelsormotels.Thereisexpectedtobesufficienttemporarylodgingtoaccommodatethissmallincreaseindemandovertheconstructionperiod.Therefore,thepotentialforeffectsonpopulationandhousingfromconstructionwouldbelow.

EmploymentandIncome

Asdiscussedabove,thetemporaryincreaseinjobsduringconstructionwouldrepresentaverysmallproportionofthecurrentworkforceinthestudyarea.Therefore,thetemporaryeffectonthelabormarketinthestudyareawouldbelow.Forthosepeoplewhogetconstructionjobs,especiallyiftheyarecurrentlyunemployed,theindividualeffectwouldbepositive.ConstructionoftheProposedActionisexpectedtocostapproximately$7million.Thiscostwouldincludeexpendituresonmaterialsandequipment,andlabor–someofwhichwouldbespentlocallyinthestudyarea.Theselocalexpenditureswouldhavemultipliereffectswithintheeconomy,asworkersandbusinessesreceivingincomewouldre‐spendsomeofthemoneylocally,theworkersandbusinessesthatreceivethatmoneywouldre‐spendsomelocally,andsoon.Thesedirectandindirectexpenditureswouldrepresentasmallproportionofthetotalannualincomeinthestudyarea,sotheeffectwouldbetemporaryandlow.

EnvironmentalJustice

Noresidentialorconcentratedhumanuseareasneartheprojectsitewouldbeaffectedbyconstructionnoise,dust,orairqualityreductions.Humanhealthandthelivingconditionsofanycommunitywouldbeunaffected,includingthosewhereenvironmentaljusticemightbeofconcern.

Asdescribedabove,constructionoftheProposedActionwouldhavealowbutpositivetemporaryimpactontheeconomyintheaffectedarea,withmultipliereffectslikelybenefittingmanytoasmalldegreeandadverselyaffectingnone.Thus,constructionoftheProposedActionwouldlikelyhavenoadverseordisproportionateeffectsonminorityorlowincomepopulations.

3.12.3 EnvironmentalConsequences–NoAction

UndertheNoActionalternative,restorationactionsintheKootenaiLowerMeanderProjectareawouldnotoccur;therefore,theeffectsrelatedtoconstructionwouldnothappen.Short‐termcontributionstothelocaleconomywouldnotoccur.Noothereffectsonsocioeconomicsorenvironmentaljusticehavebeenidentified.

Page 48: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 47

3.13 OtherEnvironmentalResources

3.13.1 Wildlife

Effectsonwildlifewouldbelow.VegetationremovalalongthenorthbanksoftheKootenaiRiveratSites1and2wouldmodifysomehabitat,butallofthiswouldbereplacedwithnative‐speciesplantings.Thisisexpectedtoincreasethevalueofthehabitatforthespeciescurrentlyusingtheseareas.Theindividuals,however,wouldlikelybetemporarilydisplacedduringconstructionactivities,,inthatprocess,butmayreturnorbereplacedbyotherindividualsofthesametypesofspeciesastheplantingsmatureovertime,andareabletosupportgreaternumbersofanimals.

Theproposedrestorationofin‐riverandriparianhabitatsalongtheKootenaiRiverwouldlikelybenefitnativewildlifespeciessuchasbeaver,muskrat,otter,mink,andvariousspeciesofbirds.TheprojectwouldhavenoeffectonESA‐listedwildlifespeciesbecausetheprojectareaisoutsidemanagementareasordesignatedcriticalhabitatforthreeESA‐listedwildlifespeciesknowntooccurinBoundaryCounty:grizzlybear,woodlandcaribou,andCanadalynx.StagingandconstructionwouldoccurbetweenJulyandNovember,whichisoutsideofthenestingperiodformigratorybirds.

3.13.2 Vegetation

Effectsonuplandvegetationwouldbelow.Scatteredlimitednumbersoftreesandshrubswithinstreambankgradingareaswouldberemovedduringconstruction;however,existingnativevegetationwillbepreservedtothegreatestextentpossible.Whereconstructionrequiresremovalofnativevegetation,effortswillbemadesalvageandtransplantappropriatespecieswherefeasible.Plantingnativevegetationonover21acresofimprovedislandsandapproximately8acresofstreambankswouldfullymitigatetheremovalofthisminoramountofexistingvegetation.

3.13.3 LandUse

Effectsonlandusewouldbelow.TheconstructionwouldoccurinthemainchanneloftheKootenaiRiverandcausenochangestolanduse.Somelandcurrentlyusedforagricultureandpasturewouldbeusedfortemporaryaccessandstagingareasbutthoselanduseswouldcontinueduringconstruction,andnopermanentchangeintheiruseisproposed.

3.14 CumulativeEffectsAnalysisCumulativeeffectsarethosethatcouldoccurwhenconsideredinadditiontootherpast,present,andreasonablyforeseeablefutureactionsregardlessofwhatagency(federalornon‐federal)orpersonundertakessuchotheractions.Currentactionsarethoseprojects,developments,andotheractionsthatareunderwaybecausetheyareeitherunderconstructionoroccurringonanongoingbasis.Reasonablyforeseeablefutureactionsgenerallyincludethoseactionsformallyproposedorintheplanningstages.Cumulativeeffectscanresultfromindividuallyminorbutcollectivelysignificantactionstakingplaceoveraperiodoftime.

PastactionsthathaveaffectednaturalandhumanresourcesalongtheKootenaiRiverinIdahoincludetheconstructionofLibbyDam,timberharvest,diking,agriculture,roaddevelopment,commercialandresidentialdevelopment,andmining.Since2011,theTribehasimplementedaquaticandriparianhabitatrestorationprojectsalongtheKootenaiRiverintendedtobenefitnativefishandwildlifespecies,focusinginparticularontherecoveryofKootenaiRiverwhitesturgeonandburbot.TheTribehasalsoimplementeduplandrestorationactionsalongtheKootenaiRiver’shistoricalfloodplainandtributaries.

Page 49: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject48 DraftEnvironmentalAssessment

Indeterminingthepresentandreasonablyforeseeableactionswiththepotentialtocontributetocumulativeeffects,whencombinedwiththeeffectsofthealternatives,BPAconsideredotherplanningefforts,large‐scaleprojects,orrestorationactionsalongtheKootenaiRiverbelowLibbyDamthatwouldbelikelytoresultineffectsthatcouldinteractcumulativelywiththosefromtheproposedproject.

TimberharvestingactivitiescontributesedimenttotheriversandstreamsthatflowintotheKootenaiRiver.TheKootenaiRiverbelowLibbyDamflowsthroughtheThreeRiversRangerDistrictoftheKootenaiNationalForestinMontanaandtheBonnersFerryRangerDistrictoftheIdahoPanhandleNationalForestinIdaho.TherearenotimbersalesbeingconsideredineitheroftheserangerdistrictsthatwouldresultineffectstotheKootenaiRiver(USFS,2014a,2014b).Privatetimbersalescouldoccurthatcouldresultineffectstowetlands,vegetation,andwaterquality.

TheU.S.ForestService’sCollaborativeForestLandscapeRestorationProgram(CFLRP)providesfundingforcollaborative,science‐basedecosystemrestorationofpriorityforestlandscapes.Pastpracticeshavedegradedforesthealthandincreasedfirerisk.TheKootenaiValleyRestorationInitiativehasreceivedCFLRPfundingtoimplementrestorationactionsonU.S.ForestServicelandsthatfocuson:

Reforestation Pre‐commercialThinning PrescribedBurning InvasivePlantManagement CulvertUpgrades FishPassageCulvertReplacements RoadDecommissioning RoadMaintenance

3.14.1 SoilsandGeology

Thepast,present,andreasonablyforeseeablefutureactionsthatcouldcumulativelyaffectsoilsandgeologyarehabitatrestorationactionsandcontinuedhydroelectricdamoperationsaswellasland‐disturbingoperationssuchasroadconstruction,agriculture,commercialandresidentialdevelopment,andmining.

TheProposedActionmaycumulativelyaffecterosion‐preventingvegetationandwetlandsduringconstructionbecausetherewouldbeotheractionsimpactingvegetationandwetlandsduringthesamegeneraltimeframeasthisproject.TheProposedAction,whenconsideredwithpast,present,andfuturehabitatrestorationprojectsintheKootenaiBasinbelowLibbyDamwouldcontributetopreventingsoillossovertimebyreestablishinghealthynativevegetationalongtheriverandintheadjacentuplands.Environmentaldesignfeatures/mitigationmeasuresdescribedinSection2.4wouldensurethatnegativecumulativeeffectsfromtheprojectonsoilsandgeologywouldbelow.

3.14.2 Wetlands

BecausetheProposedActionwouldresultinanoverallincreaseinwetlandareaandimprovedwetlandfunctionsforthelongterm,theProposedActionwouldnotcontributetothecumulativeeffectsofthelossofwetlandsalongtheKootenaiRiverthathaveoccurredovertime.ImplementationofthemitigationmeasuresdescribedinSection2.4wouldensurethenegativeshort‐termcumulativeeffectsonwetlandswouldbelow.

Page 50: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 49

3.14.3 WaterResources

Thepast,present,andreasonablyforeseeablefutureactionsthatcouldcumulativelyaffectwaterresourcesarehabitatrestorationactionsandcontinuedhydroelectricdamoperationsaswellasland‐disturbingoperationssuchasroadconstruction,agriculture,commercialandresidentialdevelopment,andmining.

AsdiscussedinSection3.3.2,waterqualityeffectsfromtheProposedActionwouldbelowandofshortdurationduringconstruction,andwouldlikelyimprovewaterqualityfromthebankstabilization,riparianplantings,anderosioncontrolelementsoftheproject.Thus,whenaddedtopast,present,andreasonablyforeseeablefutureactions,thecumulativeeffectsoftheProposedActiononwaterresourceswouldbelow.

3.14.4 FishandFishHabitat

Thepast,present,andreasonablyforeseeablefutureactionsthathaveaffected,andarecontinuingtocumulativelyadverselyaffectfishandfishhabitatincludecontinuedhydroelectricdamoperationsaswellasland‐disturbingoperationssuchasroadconstruction,agriculture,commercialandresidentialdevelopment,andmining.Thesecumulativeactionshavedegradedhabitatforsturgeon,burbot,bulltrout,andotherspeciesandaretheprimarydriversforthiscurrentaction.ThecumulativeeffectofKootenaiRiverfishhabitatrestorationactionsintherecentpasthavebenefittedfishtosomedegree,butthecumulativeeffectsoftheadverseactionslistedabovecontinuetodepressfishpopulations.

TheProposedActionwouldhaveshort‐termadverseeffectsonfishandfishhabitat(asdiscussedinSection3.4)yetprovidelong‐termbenefitsfromtheincreasedhabitatquantity,diversity,andcomplexity.Thisactionwouldcontinuethetrendoftherecentpasttowardimprovedfishhabitatandincreasedfishpopulations,andthoughnotexpectedtoreversethecumulativeimpactofthehistoricaladverseactionsdiscussedabove,thecumulativeeffectonfishandfishhabitatwouldbelow.

3.14.5 Recreation

Pastandpresentactionssuchas,hydroelectricdamoperations,roadconstruction,agriculture,mining,andcommercialandresidentialdevelopment,havenothadasignificantcumulativeimpactonrecreationaluseofthisriverbeyondthelossoffishingopportunitiesresultingfromreducedfishhabitatandfishpopulations.

TheProposedActioncontributestothereversaloflostfishingopportunitiesbyimprovingfishhabitatandinthelongterm,increasingfishpopulations.Thoughtheprojectwouldcreatelong‐termobstacles(largewoodstructures)thatrecreationalriverusersmustnavigate,projectdesignsforthesefeatureswouldprovideadequateavoidancetimeandspaceforboaters.Thisprojectwouldcontributepositivelytothisriver’srecreationattractionthroughthepotentialfutureimprovementinfishingopportunities.Therefore,theProposedAction’soverallcumulativeeffecttorecreationwouldbelow.

3.14.6 CulturalResources

Culturalresourcesintheprojectareahavelikelybeencumulativelyaffectedbypast,present,andcurrentdevelopmentactivities.Mosteffectshavelikelyoccurredasaresultofinadvertentdisturbanceordestructionfromland‐disturbingoperationssuchasroadconstruction,agriculture,mining,andcommercialandresidentialdevelopment.

ImplementationofthemitigationmeasuresdescribedinSection2.4wouldreducethepotentialforconstructionactivitiestocontributeincrementallytothecumulativeeffectsonunknownculturalresources.Intheeventthatpreviouslyundiscoveredculturalresourcesareencountered,potentialeffectswoulddependonthelevelandamountofdisturbance,andtheeligibilityoftheresourceforlistingintheNRHP.

Page 51: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject50 DraftEnvironmentalAssessment

3.14.7 VisualResources

Thecurrentvisualcharacteroftheprojectareaisthecumulativeresultofpastandpresentlandusesandhuman‐causedchangesintheKootenaiRiver.WhilethisprojectisintendedtochangetheKootenaiRivertoimprovefishhabitat,theelementsandscaleofthatchangearestillconsistentwiththeexistingcharacterofthislargemeanderingriver.Therefore,thecumulativeeffectonthevisualcharacterofthisareawouldbelow.

3.14.8 Noise

WhiletheProposedActionwouldcauseatemporaryincreaseinnoiselevels,therewouldbenolongtermorpermanentsourceofnewsoundintroducedintothisareabythisproject.Thesoundscapethatexistsnowwouldnotbechangedinthelongterm.Thisprojectwouldmakenocumulativepermanentcontributiontonoiselevelsinorneartheprojectarea.

3.14.9 AirQuality

Ongoingvehicularuse,agriculturalactivities,andcommercialandresidentialfacilitiesintheanalysisareaallcontributetoambientairpollutantemissions.Theseexistingsourcesofpollutantswouldcontinuetooccur.WhiletheProposedActionwouldcontributeasmallamounttopollutantlevelsduringconstruction,whencombinedwithpast,presentandreasonablyforeseeablefutureactionsintheaffectedarea,theseactionsarenotexpectedtoviolateNationalAmbientAirQualityStandardsand,therefore,cumulativeeffectsonairqualitywouldbelow.Therewouldbenolongterm,orpermanentsourcesofpollutantemissionsfromthisproject.

AlllevelsofgreenhousegasemissionsplayaroleincontributingcumulativelytoglobalGHGconcentrationsandclimatechange.However,giventhelowemissionscausedbythetemporaryconstructionoftheProposedAction,itscumulativecontributiontoglobalgreenhousegasconcentrationsisconsideredlow.

3.14.10 PublicHealthandSafety

TheProposedActionmayintroduceaminoramountofroadwaytravelriskonpublicroadsandhighwaysasheavyequipmentismovedinandout,butitmakesnopermanentorlongtermchangeinanyroadwaytravel,utility,orcommunicationfeaturethatwouldaffectpublicsafetyorthedeliveryoflawenforcement,fireprotection,oremergencyresponsecapabilitiescurrentlyavailable.

Theinstallationofside‐channellargewoodstructures,however,mayconstituteaslightincreaseinrisktoboatersafetysincetheyarepermanentandmid‐streaminthesechannels.Thiswouldcontributecumulativelytowhateverexistingboatersafetyhazardsarepresentontheriver.Thisadditionalrisk,however,isconsideredtobelowandthusthecumulativeeffectofthisprojectonpublichealthandsafetyislow.

3.14.11 TransportationandUtilities

TheProposedActionwouldcauseminimaltemporaryincreasesintrafficduringconstruction,butitmakesnochangestotheexistingtransportationorutilityinfrastructure,normodifiesanyenvironmentalfeaturethatwouldputtheseexistinginfrastructuresatrisk.Thisprojectdoesnotrequireapowersource,anddoesnoteffectexistingtransportationandutilityinfrastructure.Thisprojectwouldhavenocumulativeeffectontransportationorutilityinfrastructureordemands.

3.14.12 Socioeconomics

TheProposedActionwouldprovideaverysmallandshorttermcontributiontothelocaleconomy,withverylittletemporaryandnolong–termeffectonpopulation,housing,employment,andincome.Increasedrecreationalanglingoverthelonger‐termcouldprovidesomeeconomicbenefits.Because

Page 52: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 51

thepositiveeffectsoftheProposedActionwouldbetemporaryandlow,itwouldhavealow,effectonpopulationandhousing,employmentandincome,andnoeffectonenvironmentaljusticepopulations.

4 EnvironmentalConsultation,Review,andPermitrequirements

4.1 NationalEnvironmentalPolicyActBPApreparedthisEApursuanttoregulationsimplementingNEPA(42U.S.C.4321etseq.),whichrequirefederalagenciestoassesstheeffectstheiractionsmayhaveontheenvironment.NEPArequirespreparationofanEISformajorfederalactionssignificantlyaffectingthequalityofthehumanenvironment.BPApreparedthisdraftEAtodetermineiftheProposedActionwouldcreatesignificantenvironmentaleffectsthatwouldwarrantpreparinganEnvironmentalImpactStatement,orifaFindingofNoSignificantImpactisjustified.

4.2 Wetlands,Floodplains,andWaterResourcesAspartoftheNEPAreview,U.S.DepartmentofEnergyNEPAregulationsrequiretheassessmentofeffectsonfloodplainsandwetlands,andtheevaluationofalternativesforprotectionoftheseresourcesinaccordancewithCompliancewithFloodplain/WetlandsEnvironmentalReviewRequirements(10CFR1022.12)andExecutiveOrders11988(FloodplainManagement)and11990(ProtectionofWetlands).AnevaluationofeffectsoftheprojectonfloodplainsandwetlandsisdiscussedinSection3.2,Wetlands,andSection3.3,WaterResources,ofthisEA.

SeveralsectionsoftheCleanWaterAct(33USC1251etseq.)andtheIdahoStreamChannelProtectionAct(Title42,Chapter38,IdahoCode)addresswetlandandwaterwaymanagement,regulation,andprotection.TheTribewouldsubmitaJointPermitApplicationtotheUSACEandIdahoDepartmentofWaterResourcesbeforeconstruction.Theapplicableregulationstotheprojectarediscussedbelow.

4.2.1 CleanWaterActSection401

AfederalpermittoconductanactivitythatcausesdischargesintonavigablewatersisissuedonlyaftertheStateofIdahocertifiesthatexistingwaterqualitystandardswouldnotbeviolatedifthepermitwereissued.DEQwouldreviewtheproject’sSection402andSection404permitapplicationsforcompliancewithIdahowaterqualitystandardsandgrantcertificationifthepermitscomplywiththesestandards.

4.2.2 CleanWaterActSection402

ThissectionauthorizesNationalPollutantDischargeEliminationSystempermitsforthedischargeofpollutants,suchasstormwater.TheEPA,Region10,hasageneralpermitfordischargesfromconstructionactivities.TheTribeanditscontractorwouldfileNoticesofIntentforcoverageunderthisgeneralpermit,andwouldprepareastormwaterpollutionpreventionplantoaddressstabilizationpractices,structuralpractices,stormwatermanagement,andothercontrols.

4.2.3 CleanWaterActSection404

WhendredgedorfillmaterialdischargesintowatersoftheUnitedStates,includingwetlands,itrequiresauthorizationfromtheUSACEinaccordancewiththeprovisionsofSection404oftheCleanWaterAct.TheTribewouldworkwiththeUSACEtogetaSection404permitforfillplacedinwetlandsandwatersoftheUnitedStates,andworkwithDEQtogetSection401waterqualitycertification(see

Page 53: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject52 DraftEnvironmentalAssessment

Section4.2.1).Sections3.3,Wetlands,and3.4,WaterResources,ofthisEAdescribepotentialeffectsonwetlandsandotherwaters.

4.2.4 IdahoStreamChannelProtectionAct

TheIdahoStreamChannelProtectionActrequiresprotectionofstreamchannelsofthestateandtheirenvironmentagainstalterationtoprotectfishandwildlifehabitat,aquaticlife,recreation,aestheticbeautyandwaterquality.IdahoDepartmentofWaterResourcesissuesaStreamChannelAlterationpermitbeforeanyworkisdonewithinthebedsandbanksofacontinuouslyflowingstream.TheTribewillsubmitaJointPermitapplicationtotheUSACEandIdahoDepartmentofWaterResourcesbeforeconstruction.

4.3 FishandWildlife4.3.1 EndangeredSpeciesAct

TheESA(16USC1531etseq.)establishesanationalprogramfortheconservationofthreatenedandendangeredspeciesoffish,wildlife,andplants,andthepreservationoftheecosystemsonwhichtheydepend.TheUSFWSadministerstheESAforterrestrialspeciesandsomefreshwaterfishspecies,whileNationalMarineFisheriesServicehasjurisdictionoveranadromousfishandmarinespecies.Section7(a)oftheESArequiresfederalagenciestoensurethattheactionstheyauthorize,fund,andcarryoutdonotjeopardizethecontinuedexistenceofanyendangeredorthreatenedspeciesorresultinthedestructionoradversemodificationofcriticalhabitat.Section7(c)oftheESAandotherfederalregulationsrequirethatfederalagenciesprepareabiologicalassessmentaddressingthepotentialeffectsoftheiractionsonlistedorproposedendangeredspeciesandcriticalhabitats.

In2013,BPApreparedaprogrammaticbiologicalassessmentandsubmittedittoUSFWS(MeridianEnvironmental,Inc.,2013).ThisprogrammaticbiologicalassessmentevaluatedtheeffectstoKootenaiRiverwhitesturgeon(endangered)andColumbiaRiverbulltrout(threatened),andtheirdesignatedcriticalhabitatassociatedwiththeTribe’sproposaltoimplementtheir2013‐2015RestorationProgram.The2013‐2015RestorationProgramincludesprojectsidentifiedintheKootenaiTribe’sKootenaiRiverHabitatRestorationProgram,whichidentifiedspecifichabitatprojectsintheKootenaiRiverthatwouldenhancehabitatforKootenaiRiverwhitesturgeonasrequiredbytheLibbyDamBiOp.TherestorationactionsdescribedinthisEAareinthesameactionareaandimplementthesametypesofactionswiththesameobjectivesasthoseevaluatedinthebiologicalassessmentandevaluatedbytheUSFWSforthelargerrestorationprogram.CommunicationswithUSFWSledtoanagreementthattheLowerMeanderProjectevaluationunderESAsection7isadequatelycoveredinthe2013consultation.

TheUSFWSissuedabiologicalopiniononJuly30,2013withthedeterminationthatimplementingtheKootenaiRiverHabitatRestorationProgramisnotlikelytojeopardizethecontinuedexistenceoftheKootenaiRiverwhitesturgeonoritscriticalhabitat.ThebiologicalopinionprovidedanincidentaltakestatementtoauthorizethepotentialincidentaltakeofKootenaiRiverwhitesturgeonthatmayoccurduringconstructionactivities,andstatedthatnoreasonableandprudentmeasuresnortermsandconditionswerenecessary,inadditiontothosemeasuresincorporatedintotheprogram'sdescription,tofurtherminimizesuchincidentaltakeofKootenaisturgeon.ThebiologicalopinionalsoconcurredwithBPA'sdeterminationof"mayaffect,notlikelytoadverselyaffect"bulltroutandbulltroutcriticalhabitat.

Page 54: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 53

InadditiontoKootenaiRiverwhitesturgeonandbulltrout,BPAdeterminedthatfourterrestrialspeciesarelistedasthreatenedorendangeredunderthefederalESAinBoundaryCounty,Idaho.

Basedonthescope,timing,andlocationoftheproposedprojectsintheKootenaiRiver,BPAhasdeterminedthattheProposedActionwouldhavenoeffectonwoodlandcaribou(endangered),grizzlybear(threatened),Canadalynx(threatened),orNorthAmericanwolverine(proposedthreatened).

BecausetheKootenaiRiverHabitatRestorationProgramwasexpectedtobeimplementedoverseveralyearswithatimelinethatwassubjecttochange,theUSFWStreatedtheESAconsultationinasemi‐programmaticway.ThismeansthattheUSFWSdeterminationisbasedonanagreementthatBPAwillinformallyconsultwiththeUSFWSbeforetheimplementationofeachphaseofrestoration.Asaresult,BPAhasreviewedtheproposalfortheKootenaiRiverLowerMeanderProjectinrelationtotheinformationpresentedintheoriginalbiologicalassessment,consideringanynewinformationavailable,andmadeadeterminationthattheeffectsuponESA‐listedspeciesandcriticalhabitatarewithinthetypeandscopeofeffectsaddressedwithinthisopinion.OnFebruary22,2017BPArequestedconfirmationfromtheUSFWSthattheproject’seffectsonbulltroutanditsdesignatedcriticalhabitat,andKootenaiRiverwhitesturgeonanditsdesignatedcriticalhabitatareidenticaltothetypeandscopeofeffectsaddressedintheoriginalbiologicalassessmentandopinion.USFWSconfirmedthatthespecificproject’seffectsareconsistentwiththebiologicalassessmentandopinion.

4.3.2 FishandWildlifeConservationActandFishandWildlifeCoordinationAct

TheFishandWildlifeConservationActof1980(16USC2901etseq.)encouragesfederalagenciestoconserveandpromoteconservationofnon‐gamefishandwildlifeandtheirhabitats.TheFishandWildlifeCoordinationAct(16USC661etseq.)requiresfederalagencieswithprojectsaffectingwaterresourcestoconsultwithUSFWSandthestateagencyresponsibleforfishandwildliferesources.TheanalysisinSection3.5,FishandFishHabitat,ofthisEAindicatesthattheProposedActionwouldhavelowtomoderateshort‐termadverseeffectsonfishandfishhabitat,withimplementationofappropriatemitigation;withthegoalofprovidinglong‐termhabitatbenefits.BPAandtheTribehaveconsultedwithUSFWSregardingpotentialeffectsoftheprojectonESA‐listedfishandwildlifespeciesandwillimplementthemitigationmeasuresincludedinthebiologicalassessmentandanyothermeasuresthatUSFWSrequires.TheUSFWSandIDFGhavebeennotifiedoftheprojectandwillbesentcopiesoftheDraftandFinalEA.

4.3.3 MigratoryBirdTreatyActandFederalMemorandumofUnderstanding

TheMigratoryBirdTreatyActof1918,asamended,implementsvarioustreatiesandconventionsbetweentheUnitedStatesandothercountries,includingCanada,Japan,Mexico,andRussia,fortheprotectionofmigratorybirds(16USC703–712).Undertheact,taking,killing,orpossessingmigratorybirds,ortheireggsornests,isunlawful.Theactclassifiesmostspeciesofbirdsasmigratory,exceptforuplandandnonnativebirdssuchaspheasant,chukar,graypartridge,housesparrow,Europeanstarling,androckdove.

BPA(throughtheU.S.DepartmentofEnergy)andUSFWShaveamemorandumofunderstandingtoaddressmigratorybirdconservationinaccordancewithExecutiveOrder13186(ResponsibilitiestoFederalAgenciestoProtectMigratoryBirds).ThisorderdirectseachfederalagencytakingactionsthatcouldnegativelyaffectmigratorybirdstoworkwiththeUSFWStodevelopanagreementtoconservethosebirds(DOEandUSFWS,2013).Thememorandumofunderstandingaddresseshowbothagencies

Page 55: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject54 DraftEnvironmentalAssessment

canworkcooperativelytoaddressmigratorybirdconservation,andincludesspecificmeasurestoconsiderimplementingduringprojectplanningandimplementation.

TheanalysisinSection3.14.1Wildlife,ofthisenvironmentalassessmentindicatesthattheprojectwouldhaveloweffectsonbirds,includingmigratorybirds.Theprojectmayhaveshort‐termadverseeffectsonafewnestingbirdsbecauseafewtreeswouldberemoved.ButstagingandconstructionactivitieswouldbeconductedbetweenJulyandNovember(outsidethenestingperiodformigratorybirds),andriparianhabitatswouldbeexpandedandimproved,providingmorehabitatinthefuturethanisthereatpresent.

4.3.4 BaldEagleandGoldenEagleProtectionAct

TheBaldEagleandGoldenEagleProtectionAct(16USC.668–668d)addressestakingorpossessingofandcommerceinbaldandgoldeneagles,withlimitedexceptions.TheActonlycoversintentionalactsoractsin“wantondisregard”ofthesafetyofbaldorgoldeneagles.

Baldandgoldeneaglesmaytemporarilyusetheproposedprojectarea,butnonestingsitesorlongtermoccupancyhasbeenobserved.Becausetheprojectwouldnotinvolveknowingtakeorotheractsinwantondisregardofbaldorgoldeneagles,itsimplementationwouldnotviolatetheprovisionsoftheBaldEagleandGoldenEagleProtectionAct.

4.4 LandUsePlanConsistencyAsindicatedinSection3.14.3,constructionactivitieswouldoccurinthemainchanneloftheKootenaiRiverandresultinnochangestolanduse.Also,therewouldbenochangeinlandusefromtemporaryaccessroadconstructionandstagingofmaterials.

4.5 FarmlandProtectionPolicyActTheFarmlandProtectionPolicyAct(7USC4201etseq.)directsfederalagenciestoidentifyandquantifyadverseeffectsoffederalprogramsonfarmlands.ThisactminimizesthenumberofFederalprogramsthatcontributetotheunnecessaryandirreversibleconversionofagriculturallandtonon‐agriculturaluses.ThereisnoprimefarmlandinthesitesaffectedbythisprojectandtheProposedActionwouldnotpermanentlyconvertanyareaofagriculturallandtonon‐agriculturaluses

4.6 CulturalandHistoricResourcesLawsandregulationsgovernthemanagementofculturalresources.Aculturalresourceisanobject,structure,building,site,ordistrictthatprovidesirreplaceableevidenceofnaturalorhumanhistoryofnational,state,orlocalsignificance,suchasNationalLandmarks,archaeologicalsites,andpropertieslisted(oreligibleforlisting)intheNRHP.Culturalresourcerelatedlawsandregulationsinclude:

AntiquitiesActof1906(16U.S.C.431–433), HistoricSitesActof1935(16U.S.C.461–467), Section106oftheNHPA(16U.S.C.470etseq.),asamended, ArchaeologicalDataPreservationActof1974(16U.S.C.469a–c), ArchaeologicalResourcesProtectionActof1979(16U.S.C.470aa‐mm),asamended, NativeAmericanGravesProtectionandRepatriationAct(25U.S.C.3001etseq.), ExecutiveOrder13007IndianSacredSites,and AmericanIndianReligiousFreedomActof1978(42U.S.C.1996,1996a).

Page 56: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 55

Section106oftheNHPArequiresfederalagenciestoconsidertheeffectsoftheiractionsonhistoricproperties.TheNHPAprovidestheSection106processthatenablesagenciestoassesseffectsonhistoricpropertiesalongwithparticipationfrominterestedandaffectedpartiessuchastribes,andthenavoid,minimize,ormitigatetheseeffects.Historicpropertiesmaybeprehistoricorhistoricsites,includingobjectsandstructuresthatareincludedinoreligibleforinclusionintheNRHP.Historicpropertiesalsoincludeartifactsorremainswithinhistoricsitesandpropertiesoftraditionalandculturalimportancetotribes.

Tothisend,BPAhasprovidedinformationabouttheProposedActionto,andrequestedinformationfromnumerousagencies,onthelevelandtypeofproposedidentificationandevaluationeffortsoftheprehistoricresources.AgenciesconsultedincludetheIdahoStateHistoricPreservationOffice,theConfederatedSalishandKootenaiTribes,Coeurd’AleneTribeofIdaho,KalispelTribeofIndians,theSpokaneTribeofIndians,andtheKootenaiTribeofIdaho.

4.7 AirQualityTheCleanAirAct,asamended(42U.S.C.7401etseq.),requiresstatesandtheEPAtocarryoutawiderangeofregulatoryprogramsintendedtocomplywithNationalAmbientAirQualityStandards.InIdaho,boththeEPAandIdahoDepartmentofEnvironmentalQualityareresponsibleforairquality.BecausetheProposedActionwouldoccurinanareathatisinattainmentwiththeairqualitystandards,andbecausenostationarysourcesofairemissionswouldresult,constructionassociatedwiththeProposedActionareexemptedfromstateregulation.AirqualityeffectsfromconstructionwouldbelowandmitigatedasdiscussedinSection2.4.

4.8 ClimateChangeGasesthatabsorbinfraredradiationandpreventheatlosstospacearecalledgreenhousegases(GHGs).ModelspredictthatatmosphericconcentrationsofallGHGswillincreaseoverthenextcentury,buttheextentandrateofchangeisdifficulttopredict,especiallyonaglobalscale.AsaresponsetoconcernsoverthepredictedincreaseofglobalGHGlevels,variousfederalandstatemandatesaddresstheneedtoreduceGHGemissions,includingthefollowing.

TheCleanAirActisafederallawwithregulationstocontrolemissionsfromlargegenerationsourcessuchaspowerplants;limitedregulationofGHGemissionsoccursthroughtheNewSourceReviewpermittingprogram.

TheEPA’sFinalMandatoryReportingofGreenhouseGasesRule(40C.F.R.98)requiresreportingofGHGemissionsfromlargesources.Undertherule,suppliersoffossilfuelsorindustrialGHGs,manufacturersofvehiclesandengines,andfacilitiesthatemit25,000metrictonsormoreperyearofGHGsmustsubmitannualreportstotheEPA(CEQ,2010).

ExecutiveOrders13423(StrengtheningFederalEnvironmental,Energy,andTransportationManagement)and13514(FederalLeadershipinEnvironmental,EnergyandEconomicPerformance)requirefederalagenciestomeasure,manage,andreduceGHGemissionsbyagency‐definedtargetamountsanddates.

GHGemissionswouldbebelowEPA’smandatoryreportingthresholdof25,000metrictonsormoreperyearfortheproposedproject(383metrictonsofCO2equivalentsforthetwo‐monthconstructionperiods).TheeffectoftheProposedActiononGHGconcentrationswouldbelow,asdiscussedinSection3.9,AirQuality,ofthisEA.

Page 57: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject56 DraftEnvironmentalAssessment

4.9 NoiseTheNoiseControlActof1972(42USC4901etseq.)setsforthabroadgoalofprotectingallpeoplefromnoisethatjeopardizestheirhealthorwelfare.TheActfurtherauthorizesfederalagenciestocarryouttheprogramswithintheircontroltofurtherthispolicy.Idahodoesnothavestatewideregulationslimitingnoiseemissionsfromcommercialfacilities.Similarly,neitherBoundaryCountynortheCityofBonnersFerryhasanoisecontrolordinancethatlimitsnoiseemissions.Thenoiseeffectsfromtheprojectwouldbetemporaryandmoderateforpeoplewithin2,000feetofconstruction,andlowtononeforthosefartherthan2,000feetfromprojectactions.AsdescribedinSection3.8,theprojectwouldhavetemporarylowtomoderatenoiseeffects,andmitigationwouldfurtherreducenoiseeffects.

4.10 HazardousMaterialsSeveralfederallawsrelatedtohazardousmaterialsandtoxicsubstancespotentiallyapplytotheproject,dependinguponthequantitiesandtypesofhazardousmaterialsbeingused.

4.10.1 TheSpillPrevention,Control,andCountermeasuresRule

TheSpillPreventionControlandCountermeasuresRule(40CFRPart112)includesrequirementstopreventdischargesofoilandoil‐relatedmaterialsfromreachingnavigablewatersandadjoiningshorelines.Itappliestofacilitieswithtotalabovegroundoilstoragecapacity(notactualgallonsonsite)ofgreaterthan1,320gallons,andfacilitieswithbelow‐groundstoragecapacityof42,000gallons.Thisprojectdoesnotproposeon‐sitestorageofoiloroil‐relatedmaterials.

4.10.2 ComprehensiveEnvironmentalResponse,Compensation,andLiabilityAct

TheComprehensiveEnvironmentalResponse,Compensation,andLiabilityAct(42USC9601etseq.)providesfundingforhazardousmaterialstraining,emergencyplanning,preparedness,mitigationimplementation,response,andrecovery.Eligibleindividualsincludepublicofficials,emergencyserviceresponders,medicalpersonnel,andothertribalresponseandplanningpersonnel.Nohazardousmaterialssitesarelocatedwithintheprojectarea.

4.11 ExecutiveOrderonEnvironmentalJusticeInFebruary1994,thePresidentreleasedExecutiveOrder12898,FederalActionstoAddressEnvironmentalJusticeinMinorityandLow‐IncomePopulations.Thisorderdirectsfederalagenciestoidentifyandaddress,asappropriate,disproportionatelyhighandadversehumanhealthorenvironmentaleffectsofitsprograms,policies,andactivitiesonminorityandlowincomepopulations.TheProposedActionwouldnotcausedisproportionatelyhighandadverseeffectsonminorityandlow‐incomepopulations.(seeSection3.12,Socioeconomics).

Therearenoresidentialorconcentratedhumanuseareasneartheprojectsitesuchthatoff‐siteconstructioneffectssuchasnoise,dust,orairqualityreductionsmightimpacthumanhealthortemporarilyimpactlivingconditionsofanycommunity,includingthosewhereenvironmentaljusticemightbeofconcern.Also,constructionactivitieswouldhavealowbutpositivetemporaryimpactontheeconomyintheaffectedareawithmonetarymultipliereffectslikelybenefittingmanyandadverselyaffectingnone.Thus,constructionoftheProposedActionwouldlikelyhavenoadverseordisproportionateeffectsonminorityorlowincomepopulations.

Page 58: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 57

5 Tribes,Agencies,andPersonsConsulted

Thoseconsultedorreceivingnoticeofdocumentavailabilityincludelocal,state,andfederalagencies,publicofficials,andtribesintheprojectvicinity.Specificindividualswerecontactedtogatherinformationanddataabouttheprojectareaandapplicablerequirements,aspartofconsultation,orforpermitapplications.

5.1 FederalAgencies U.S.EnvironmentalProtectionAgency U.S.ArmyCorpsofEngineers U.S.FishandWildlifeService,SpokaneOffice

5.2 StateAgencies IdahoDepartmentofEnvironmentalQuality IdahoDepartmentofFishandGame StateofIdahoHouseandSenatemembersforDistrictsencompassingtheprojectarea IdahoStateHistoricPreservationOffice MontanaFishWildlifeandParks

5.3 Tribes KootenaiTribeofIdaho

5.4 LocalGovernments BoundaryCounty BonnersFerry,Idaho

5.5 Other BurlingtonNorthern–SantaFeRailroad

Page 59: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProject58 DraftEnvironmentalAssessment

6 References

BPA.2003.FishandWildlifeImplementationPlanEnvironmentalImpactStatement.Availableathttp://efw.bpa.gov/environmental_services/Document_Library/Implementation_Plan/.WebsiteaccessedMarch3,2016.

EIA(EnergyInformationAdministration).2009.EnergyandtheEnvironment.GreenhouseGasesBasics.Availableat:http://tonto.eia.doe.gov/energyexplained/index.cfm?page=environment_about_ghg.WebsiteaccessedMarch3,2016.

IdahoDepartmentofLabor.2016.WorkforceTrends.InformationprovidedbyBureauofEconomicAnalysis.September2016.https://labor.idaho.gov/publications/lmi/pubs/BoundaryProfile.pdf

IPCC(IntergovernmentalPanelonClimateChange).2007.ClimateChange2007,WorkingGroupI:ThePhysicalScienceBasis.Chapter2:ChangesinAtmosphericConstituentsandRadioactiveForcing:AtmosphericCarbonDioxide.Availableat:http://www.ipcc.ch/publications_and_data/ar4/wg1/en/ch2.htmlAccessedMarch3,2016

Landers,Rich(2016,September22).KootenaiRiverimprovementsputshineonfallfishing.TheSpokesman‐Review.Outdoors.Availableathttp://www.spokesman.com/stories/2016/sep/22/kootenai‐river‐improvements‐put‐shine‐on‐fall‐fish/

NMFS(NationalMarineFisheriesService).2011.AnadromousSalmonidPassageFacilityDesign.NMFSNorthwestRegion.PortlandOregon.

U.S.CensusBureau.2010.P2:HispanicorLatino,andNotHispanicorLatinobyRace–Universe:TotalPopulation.2010CensusRedistrictingData(PublicLaw94‐171).Availableonlineat:http://factfinder.census.gov/.AccessedonJuly29,2015.

U.S.CensusBureau.2015.StateandCountyQuickFacts.Availableonlineat:http://quickfacts.census.gov/qfd/index.html.AccessedonMarch3,2016.

U.S.DepartmentofHealthandHumanServices.2013.2013PovertyGuidelines.Availableonlineat:http://aspe.hhs.gov/poverty/13poverty.cfm.AccessedonMarch3,2016.

USFWS.2013.BiologicalOpinionforKootenaiRiverHabitatRestorationProgram,KootenaiRiver,Idaho.FWSRef.01EIFW00‐2013‐F‐0278.NorthernIdahoFieldOffice.Spokane,Washington

Zelch,K.2003.AggradingalluvialfansandtheirimpactonfishpassageintributariesoftheKootenaiRiver,IdahoandMontana.UnpublishedMastersthesis,UniversityofIdaho,Moscow,ID.

Page 60: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

LowerMeanderProjectDraftEnvironmentalAssessment 59

7 WorksCitedBrunton,B.(1998).Kootenai.InPlateau.InJ.editedbyDewardE.Walker,HandbookofNorthAmerican

Indians,Vol.12(pp.pp.223–237).Washington,D.C.:SmithsonianInstitution.

EnvironmentalLaboratory.(1987).CorpsofEngineersWetlandsDelineationManual,TechnicalReportY‐87‐1.Vicksburg,Miss.:U.S.ArmyEngineerWaterwaysExperimentStation.

Hruby,T.(2004).WashingtonStateWetlandRatingSystemforWesternWashington,Revised..Olympia,WA:WashingtonStateDepartmentofEcology.

IdahoDepartmentofEnvironmentalQuality(IDEQ).(2016).Attainmentv.Nonattainment.RetrievedDecember12,2016,fromIdahoDepartmentofEnvironmentalQuality:http://www.deq.idaho.gov/air‐quality/monitoring/attainment‐versus‐nonattainment/

IdahoDepartmentofLabor.(2017).WorkforceTrends.RetrievedfEBRUARYFebruary,2017,fromIdahoDepartmentofLaborpUBLICATIONS:https://labor.idaho.gov/

KootenaiTribeofIdaho.(2009).KootenaiRiverHabitatRestorationProjectMasterPlan:AConceptualFeasibilityAnalysisandDesignFramework.BonnersFerry,ID.

Novitzki,R.,Smith,R.,&Fretwell,J.(1996).Restoration,creation,andrecoveryofwetlands:wetlandfunctions,values,andassessment.InNationalWaterSummaryofWetlandResources,USGSWaterSupplyPaper2425.FretwellJD,WilliamsJS,RedmanPJ,editor.

RiverDesignGroup.(2012).KootenaiRiverBonnersFerryIslandsProjectSedimentEvaluationFramework.Whitefish,Montana.

RiverDesignGroup,Inc.(2017).PreliminaryFloodRiskAnalysisResultsforLowerMeanderProject.Whitefish,Montana.

UnitedStatesArmyCorpsofEngineers.ERDC/ELTR‐10‐3.Vicksburg,.(2010).RegionalSupplementtotheCorpsofEngineersWetlandDelineationManual:WesternMountains,Valleys,andCoastRegion(Version2.0).Vicksburg,MS:U.S.ArmyEngineerResearchandDevelopmentCenter.

Page 61: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai
Page 62: Kootenai Lower Meander Project - BPA.gov...Idaho’s (Tribe) Lower Meander Project. The Lower Meander Project is one of several projects being implemented under the Tribe’s Kootenai

BONNEVILLE POWER ADMINISTRATION

DOE/BP-4792 March 2017