Konrad Decision-making Tools in Construction Management (2)

download Konrad Decision-making Tools in Construction Management (2)

of 76

Transcript of Konrad Decision-making Tools in Construction Management (2)

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    1/76

    Dubai May 2013

    Construction Management:Decision-making Tools and Processes

    CIVL 493/521 201UBC

    Konrad Siu M. Eng., M.B.A., P. Eng., FCSCEExecutive Director, Drainage Design and Construction

    City of Edmonton, Alberta, Canada

    January 2014

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    2/76

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    3/76

    Introduction

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    4/76

    H istory - 1910s

    Rat Creek Sewer Tunnel Construction in the 1910s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    5/76

    H istory - 1910s

    Rat Creek Sewer Tunnel Construction in the 1910s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    6/76

    H istory - 1920s

    Sewer Tunnel Construction in the 1920s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    7/76

    H istory - 1920s

    Sewer Tunnel Construction in the 1920s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    8/76

    H istory - 1950s

    Sewer Tunnel Construction in the 1950s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    9/76

    Tunnelling Machine 60s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    10/76

    Tunneling under the Bay Station 1970s

    H istory - 1970s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    11/76

    TBM Tunneling 1980s

    TBM 1980s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    12/76

    TBM Tunneling 2000s

    TBM 2000s

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    13/76

    Tunnelling

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    14/76

    Pipe Ramming

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    15/76

    Pipe Ramming

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    16/76

    Micro-Tunnelling

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    17/76

    Pilot Tube Micro-Tunnelling

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    18/76

    Edmontons Infrastructure

    Infrastructure arethe physical assets

    developed and usedby a municipality to

    support its socialand economic

    activities

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    19/76

    $15.11

    $12.07

    $4.28

    $1.96 $1.67$1.03

    $0.72$0.34 $0.34 $0.33 $0.14 $0.08 $0.07 $0.01

    $0.0

    $2.0

    $4.0

    $6.0

    $8.0

    $10.0

    $12.0

    $14.0

    $16.0

    $ b i l l i o n

    Total 2012 Asset Replacement Value - $38.2 billion

    Drainage ParksBuildingsRoadROW

    AffordableHousing

    TrafficControl

    WasteMgmt

    Fleet CommunityInfra.

    LibraryPoliceTechnologyEquipment

    FireRescue

    Transit Fac.& Equip.

    Replacement Value ofInfrastructure

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    20/76

    A

    B

    C

    D

    F

    VeryGood

    Good

    Fair

    Poor

    VeryPoor

    These rati ngs areappli ed to eachclassification

    StandardizedRating System

    http://www.infraguide.ca/http://www.infraguide.ca/http://www.infraguide.ca/http://www.infraguide.ca/
  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    21/76

    Value Engineering

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    22/76

    IntroductionHistory of Value Engineering

    1945

    1950

    1960

    1970

    1980

    1990

    2000

    Canada adopts V.E. Acceptance for management / strategic process

    U.S. Federal law mandates V.E.

    Japan/EPA adopts V.E.

    G.E. develops V.E.

    U.S. Navy adopts V.E.

    Adopted by:

    -U.S. Department ofDefense -U.S. Manufacturers -Europe & Australia -Military Const.

    Shortage of financial resources

    Shortage of physical resources

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    23/76

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    24/76

    Effectiveness of Value

    EngineeringProactive ValueEngineering Constructability Review

    Time

    C o s

    t

    COST TOCHANGE

    Traditional ValueEngineering

    COST SAVINGSPOTENTIAL Varies with Type

    of Project

    Concept Development Design Construction or Production

    Constructive VE Opportunity Constructive InterventionCost

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    25/76

    Value Engineering Is

    System Oriented

    Multi-disciplined Team Approach

    Life Cycle Oriented

    Function Oriented - Relates function required to the value received

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    26/76

    Value Engineering Is NOT

    Design Review

    Cheapening Process

    A Requirement Done on all Designs

    Quality Control

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    27/76

    What is Value?

    itinto putWhat wesomethingof outgetWhat we

    Value

    ResourcesBenefits

    etc.Energy,Mass,Time,Cost,etc.Appeal,y,ReliabilitQuality,

    Value

    CostFunction

    WorthCost

    Value

    Value = A ratio used for comparing alternatives that can reliably

    perform the same function

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    28/76

    Who Defines Value?

    Good Value is definedby the owner

    Performance Quality Aesthetics

    Type of Value Religious Political Ethical Judicial Social Aesthetic

    Economic Sentimental

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    29/76

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    30/76

    Information PhaseInformation

    Phase

    Function

    Analysis

    CreativityPhase

    JudgmentPhase

    DevelopmentPhasePresentation

    Phase

    Implementation

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    31/76

    Information Phase

    Information needed from the designer andowner Design Criteria

    Site conditions Regulatory requirements Elements of the design History of the project Constraints imposed on the project Available utilities Requirements from the public Design computations Cost estimate

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    32/76

    Information Phase

    Ask Questions What is the problem we are about to

    discuss? Why do you consider this a problem? Why do you believe a solution is

    necessary?

    Ask questions of others the way youwould like questions asked of you

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    33/76

    Function Analysis

    InformationPhase

    Function

    Analysis

    CreativityPhase

    JudgmentPhase

    DevelopmentPhasePresentation

    Phase

    Implementation

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    34/76

    What is Function

    Work Performed by a project, product,element, process, or procedure

    Answers question: What does it do?

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    35/76

    Function Identification

    Active Verb:Indicates state of being;

    asserts somethingConveySupport

    Transmits

    ProtectsEnclosesHouses

    Measurable noun:Object of the verb; allowsquantitative evaluation

    WeightLoadFlowHeatLight

    People

    The more abstract the function description, the greater

    The opportunities for finding creative alternatives

    Identify using two-word description:

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    36/76

    Types of Functions

    There are two types of functions Basic Function

    The specific work or purpose the product, project,process, must complete

    Secondary Function Support function that may be needed but do not

    perform the actual work

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    37/76

    Function Analysis

    Example: Pencil

    Description Function Basic Secondary

    Pencil Make Marks

    Eraser Removes Marks

    Band Secure eraser

    Improve appearance

    Body Support lead

    Transmit force

    Accommodate grip

    Display information

    Paint Protect wood

    Improve appearance

    Lead Make Marks

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    38/76

    Function Analysis SystemTechnique (FAST)

    Expansion of Function Analysis to FASTmodel Function analysis involves asking questions

    about functions: How can we (verb/noun)?,Why do we (verb/noun)?.

    Charles Bytheway, a UNIVAC logician,organized the functions and questions into afunctional family tree in the 1960s called aFAST model (Function Analysis SystemTechnique)

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    39/76

    FAST Diagram

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    40/76

    FAST Logic

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    41/76

    SESS STAGE 1

    Major Logic PathBasicFunction

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    42/76

    Creativity Phase

    InformationPhase

    Function

    Analysis

    CreativityPhase

    JudgmentPhase

    DevelopmentPhase

    PresentationPhase

    Implementation

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    43/76

    Search for new Ideas

    Adapt What else is like this? Modify Change the meaning, size

    color, direction

    Magnify make larger, heaviermore costly

    Minify minimize, omit; lighter, lower Substitute What else could used instead? Rearrange Is there an alternative design Reverse Can it be transposed, made upside

    down? Combine Blend ideas; perform multiple functions

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    44/76

    Example Project

    Alternative Description

    1 Pond with Concrete Liner, with Pump Station

    2 Underground Concrete Tank

    3 Aboveground Steel Tanks, with Pump Station

    4 Pond without Concrete Liner, with Pump Station

    5 SuperPipe with Trenchless Options

    6Combination of SuperPipe, Trenchless Options andTanks

    7 SuperPipe and Tunneling to replace Double Barrel Sewer

    Table .1 Alternatives List

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    45/76

    Judgment Phase

    InformationPhase

    Function

    Analysis

    CreativityPhase

    JudgmentPhase

    DevelopmentPhase

    PresentationPhase

    Implementation

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    46/76

    Judgment Steps

    Determine evaluation criteria and prioritize

    Evaluation ideas Test with respect to criteria Identify advantages and disadvantages

    Rate ideas

    Select best alternatives

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    47/76

    Develop Evaluation Criteria

    Review project value objective (sometimesidentified at the beginning of the session)

    Review owners comments during interviewsand opening presentation

    List criteria and prioritize from ownersperspective

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    48/76

    Weighted Evaluation Matrix

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    49/76

    Example to Determine Weight of Criteria

    Table 1- Evaluation Criteria A B C D E F G H I J Total Weights

    A 2A 1C 2A 1A 2A 3A 3A 1A 2A 16 19%B 2B 2D 2E 3F 2B 3B 1B 1J 8 9%C 2C 2C 2C 3C 3C 1C 2C 16 19%D 1D 1F 2D 3D 1D 2J 9 11%

    E 1E 2E 3E 1E 1E 10 12%F 2F 3F 1F 1J 10 12%G 2G 2I 1J 2 2%H 3I 1J 1 1%I 1J 5 6%J 8 9%

    85 100%A Environmental

    B Constructability 1 SAMEC Safety 2 MEDIUMD Maintainability / Operability 3 STRONGE Reliability of systemF Impact on existing infastructureG Availabiity of contractors for alternativesH AppearanceI Disruption to Traffic and other servicesJ Compatibility with WESS strategy/existing and future network

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    50/76

    Example to Rate Alternatives

    Alternative Evaluation Matrix

    Criteria Evaluation Criteria Weight Rating Score Rating Score Rating Score Rating Score Rating Score Rating Score Rating Score1 Environmental 19 4 75.3 9 169.4 6 112.9 4 75.3 8 150.6 7 131.8 7 131.82 Constructability 9 7 65.9 7 65.9 6 56.5 6 56.5 6 56.5 6 56.5 6 56.53 Safety 19 6 112.9 7 131.8 6 112.9 6 112.9 5 94.1 5 94.1 4 75.34 Maintainability / Operability 11 3 31.8 8 84.7 6 63.5 2 21.2 6 63.5 5 52.9 7 74.1

    5 Reliability of system 12 6 70.6 8 94.1 8 94.1 5 58.8 7 82.4 7 82.4 7 82.46 Impact on existing infastructure 12 8 94.1 7 82.4 7 82.4 8 94.1 8 94.1 8 94.1 8 94.17 Availabiity of contractors for alternatives 2 9 21.2 9 21.2 7 16.5 9 21.2 8 18.8 8 18.8 8 18.88 Appearance 1 4 4.7 9 10.6 5 5.9 4 4.7 8 9.4 8 9.4 8 9.49 Disruption to Traffic and other services 6 9 52.9 3 17.6 9 52.9 9 52.9 7 41.2 7 41.2 7 41.2

    10 Compat ibi li ty wi th WESSstrategy/ex isting and future network

    9 9 84.7 9 84.7 9 84.7 9 84.7 9 84.7 9 84.7 9 84.7

    Ranking Alternative Value1 13.92 12.83 8.94 8.45 7.16 6.17 5.3

    7

    61.4 58.2 69.5 66.6 66.8

    1 42 3

    8.9 7.1

    5 6

    13.9 12.8 8.49.5 5.0 5.2 8.0

    FunctionCost (Millions $)Value = Function / Cost 6.1

    11.55.3

    76.2 68.28.6 9.6

    Combination SuperPipe, Trenchless Options and TanksSuperPipe with Trenchless Options

    Underground Concrete Tank

    Pond without Concrete Liner, with Pump Station

    Function69.566.676.2

    61.4

    Aboveground Steel TankSuperPipe and Tunneling to replace Double Barrel Sewer

    Pond with Concrete Liner, with Pump Station

    66.868.258.2

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    51/76

    Development Phase

    InformationPhase

    Function

    Analysis

    CreativityPhase

    JudgmentPhase

    DevelopmentPhase

    PresentationPhase

    Implementation

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    52/76

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    53/76

    Presentation Phase

    InformationPhase

    Function

    Analysis

    CreativityPhase

    JudgmentPhase

    DevelopmentPhase

    PresentationPhase

    Implementation

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    54/76

    Presentation & Implementation

    Results General Information

    Key Issues Evaluation of alternatives Summary and alternatives VM alternatives and backup data

    Sketches* Calculations* Cost worksheet* LCC Worksheet* * Include as needed

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    55/76

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    56/76

    VE Session

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    57/76

    Risk Assessment

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    58/76

    Risk:

    The possibility of suffering loss (or harm) and the impact that loss has onthe involved party.

    Risk can be characterized in terms of its severity, where:

    Risk Concept

    58

    Severity = Likelihood of Occurrence x Magnitude of the Impact

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    59/76

    Risk Management Method

    59

    Identify Analyze

    ImplementMonitor

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    60/76

    Example of Risk Assessment Table

    Number

    Category:Planning

    Design

    Construction

    Risk FactorMitigation

    Note

    l k l

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    61/76

    Value Engineering + Risk AnalysisInformation

    Phase

    Function Analysis

    Creativity Phase

    Evaluation Phase

    DevelopmentPhase

    Presentation andImplementation

    Phase

    Nominal MethodGut Feel Index (GFI)

    AHP

    Identify RiskFactors

    RiskQuantification

    Risk Mitigation

    Life Cycle Cost

    Sensitivity Analysis

    Risk AnalysisValueEngineering

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    62/76

    Constructability

    C f Ad i l R l i hi

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    63/76

    Cause of Adversarial Relationshipsin Construction

    Poorly defined scope of project Excessive change orders Changes not properly managed Lack of communication of objectives Unrealistic project schedule Unrealistic project budget

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    64/76

    What is Constructability?

    Constructability is the optimum use ofconstruction knowledge and experience in

    planning, design, procurement and fieldoperations to achieve overall projectobjectives. CII

    Abili I fl Fi l C O P j Lif

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    65/76

    A B

    I L I T Y T O

    I N F L U E N C E C O S T

    HIGH

    LOW

    START COMPLETETIME

    START-UP

    CONSTRUCTION

    PROCUREMENT

    DESIGN

    CONCEPTUAL PLANNING

    Ability to Influence Final Cost Over Project Life

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    66/76

    Objective of Constructability Review

    Perform an in-depth analysis of the designfrom the contractors perspective.

    Answer the question: Can this project beconstructed as it is represented in the

    design?

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    67/76

    Constructability Review - 1

    The Team:

    Step 1: develops an understanding of the project, its

    constraints, design and underlying assumptions

    Step 2: becomes familiar with the plans, learns whatfeatures were existing and proposed

    Step 3: identifies potential conflicts and evaluates theproposed design in details

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    68/76

    Constructability Review - 2

    Step 4: starts developing concepts as a contractorwould build the project under the given constraints. This

    allows development of alternatives for the design and/orrecommendations for enhancement as required

    Step 5: puts together staging plan and schedule basedon various assumptions regarding achievableproductivities and methods of construction

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    69/76

    Success Factors

    Senior management's commitment to constructability and similarcommitment from all project participants.

    Formal constructability program - establish a constructability procedure for inclusion in project executionplans apply early in project planning involve construction specialist as early as possible

    Consideration of major construction methods, such asmodularization or preassembly, and sequencing of constructionactivities as part of basic design approaches to facilitate fabrication,transportation, installation , system turn over and start up.

    Success Factors

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    70/76

    Success Factors

    Encourage teamwork, creativity, newideas and new approaches.

    Emphasize total project integration, notoptimization of individual parts.

    Evaluate progress and results.

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    71/76

    Project Team

    Design engineer or

    consultant Construction

    supervisor and/ordesignate

    Planningrepresentative

    Operationsrepresentative

    Equipment/tradesrepresentative

    Estimator

    Technician Inspector Others as required

    Project Manager, and any or all of the followingpersonnel:

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    72/76

    Benefits

    Constructability works - frequently withdramatic results.

    -Better project-Lower costs-Better productivity

    -Earlier project completions-Earlier start-ups

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    73/76

    Closing

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    74/76

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    75/76

  • 8/11/2019 Konrad Decision-making Tools in Construction Management (2)

    76/76

    Thank you!Questions?