Offline/MC tasks for 2006
Establish definitive KLOE data set:
• Close holes in reconstruction/DST coverage
• Reprocess various data sets
Most critical is 2004 data with bad dead-wire maps:
Due to DB problem, hits deleted on falsely declared “dead” wires (up to 4% of DC) in 645 pb-1 of reconstructed data
• Survey data quality for MC production and analysis
Produce large-scale MC samples for 2004-2005 data
KLOE MC upgrades for 2004-2005
• Map of 2004/2005 machine and trigger conditions
• New (post-2003) IR geometry
• Better parameterizations of EmC responseTime, energy resolution; cluster efficiencies
• Improved treatment of nuclear interactions/regeneration in DC wall and beam pipe
• New secondary decay generatorsKSee,ee,ee0
• Inserted background from events acquired with random trigger
• Simulation of noise correlated to K tracks
• Simulation of dE/dx measurement in DC
EmC and DC hits from random events inserted in proportion to Linst
• EmC hits require careful MC/data timescale alignment• Special treatment for “noise” hits on EmC (missing tA or tB)
Background from random triggers
– data• MC
Cluster time distributions (t0 from KS secondaries)
KS , KL crash Overall accidental levelMC/data = 1.05
KS , KL crash Overall accidental levelMC/data = 1.19
Track reconstruction efficiency higher in MC when t0 incorrect
tcl (ns)
tcl (ns)
~3% of clusters in tail (t < 0)
Sample distribution of K-correlated background hits in:– layer, distance (in wires) from reconstructed track, time
Private reconstruction of ~20 pb-1 of 2002 MC events to study how new background parameterization affects MC tracking efficiency
Simulation of noise hits for K tracks
+ (MC)+ (data)
trk+vtx as a function of t*(K)
t*(K) (ns) t*(K) (ns)
before after
• E distribution rescaled and smeared to match data• Different s-t relations effective integration gates for data/MC• Difficulties in calibrating for track inclination (space-charge effects?)
dE/dx (count/cm)
K2 sample
K2 sample
dE/dx (count/cm)
dE/dx distribution Truncated mean distribution
K2 sample
K2 sample
+ data– MC
dE/dx resolution adequate for K ID, but not e.g. Ke2/K2 separation
Simulation of DC dE/dx measurement
Monte Carlo production plans
2001-2002
450 pb-1
2004-2005
2000 pb-1
1.85G evts
8800 B80 days
8.25G evts
39000 B80 days
Averaged over entire MC sample: 0.21M evts/B80 day = 2.4 Hz0.41 s/evt (simulation + reconstruction + DST)
all, scale = 0.2KSKL, scale = 1
KK, scale = 1 radiative, scale = 5Other (1M evts/pb-1)
Total: 3.1M evts/pb-1
(about same as number of decays in data)
2001-2002 MC production Estimated time for 2004-2005 MC
Monte Carlo production status
350 pb-1 all events (2005 data) produced in 2006 for tests
• Thorough shakedown of new features in MC
• Rigorous procedural test: performance of DH system
Real production to begin next week
• all, KSKL, KK campaigns to be combined:
all_phys, L scale 1.2
• Start with 2005 data: Reprocessing not necessary for comparison
Offline resources: CPU
Nodes Type CPUsB80
“MC”
B80
“CW”
fibm14-15,17-34 P3 375 MHz 80 80 80
fibm35-44 P4+ 1.45 GHz 40 88 96
fibm45-47 (Jan ’06) P5 1.5 GHz SMT “96” 126 184
All 294 360
• KLOE CPU accounting is performed in B80 units1 “B80 CPU” = 1 P3 CPU installed in B80 serverUncertainties transferred to B80/P4+ and B80/P5 ratios
• “MC” estimates based on MC tests conducted May 2006
• “CW” estimates based on past experience
Offline CPU needs
2006 offline projects B80 days Days/214 B80
Reprocessing of 2004 data 16000 75
MC production for 2004-2005 data 39000 180
All other reprocessing (900 pb-1) 22000 100
Minimum total 55000 260
Maximum total 77000 360
9-12 months if there are no serious DH problems
Assuming: 294 B80 total (MC test, not CW)80 B80 left to users for analysis
214 B80for offline
Offline resources: Disk space
DSTs cached on nfs-mounted disks for fast analysis access
Current Final
35 TB data
10 TB MC
45 TB total
42 TB data
44 TB MC
86 TB total
DST volume*
Current DST cache capacity: 12 TB
New purchases: 21 TB FC disk + new controllerGara closed at beginning of MayOrder to be approved by Giunta next week, delivery by end of June?
~30 TB available for disk cache
*Updated to account for scan data
Offline resources: Tape library
0 200 400 600 800 1000
Final
Current
Tape library usage (TB)
raw DST
rec MC
536
955
Current capacity810 TB
Final estimate includes:• Closing of holes in
datarec/DST coverage• MC for ’04-’05 data
Library capacity:• Currently 810 TB
600 new cassettes added at start of year
• Expandable to 1400 TB(1400/3600 slots in use in new library)
Will need 145 TB of additional cassettes to finish MC production400 new cassettes (120 TB) already financed
Outlook and summary
• Start of MC production delayed to include improvements to background simulation
• MC production for 2005 data (all_phys, L scale 1.2) ready to start
• Once MC production underway, will begin reprocessing 2004 data with bad wire maps
• We have the CPU power needed to generate a definitive MC sample and reprocess as necessary on a time scale compatible with beginning of 2007
• We will probably want to expand DST disk cache
• We will need new cassettes towards the end of 2006
L dt (pb–1)
tag 100
2001 169
2002 292
2004 691
2005 1242
total 2394
Reconstruction of 2004-2005 data
0 500 1000 1500 2000
drn/drc
d3p
dk0
dkc
recon
tag 100
raw
1930
1740
1970
990
1480
1520
1480
pb–1
Runs 28700 (9 May 04) to 41902 (5 Dec 05)Updated to reflect DB work 21 Mar 06
Reconstructed KLOE data
DBV 2001 2002 2004 2005 Scan Comment
12-15 163 34Bad cut in FILFONo bias sample for FILFONo bias sample for rad
19-21 645bad
wires!
217Various significant ECL modsMinor changes to reconNo bias sample for rad
22 222 395Stable ECLOld bias sample for rad
23-24 12 502 61Stable ECL for s = m
ufo as bias sample
25 16 205Stable ECL for off-peakufo as bias sample
analyzed 163 269 645 1114 266
total 169 292 691 1242 284
trgmon luminosity in pb-1 by year and DBV
645 pb-1 to be reprocessed for sure, 278 pb-1 (617 pb-1) as time permits