MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail [email protected] Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur 482008, CIN-U40109MP2001SGC01 No.07-05/SG-9B-II/799 Jabalpur, dated:02.06.2016 To As per distribution list Sub: Minutes of 51 st meeting of Operation and Coordination Committee of MP. The Minutes of 51 st meeting of the Operation and Coordination Committee of MP held on 26 th April 2016 at 11.00 AM in the Banquet Hall, Shakti Bhawan, Jabalpur has been uploaded on the website of SLDC ‘www.sldcmpindia.com’ and can be downloaded. (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpur

Transcript of (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES...

Page 1: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail [email protected] Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur 482008, CIN-U40109MP2001SGC01 No.07-05/SG-9B-II/799 Jabalpur, dated:02.06.2016

To

As per distribution list

Sub: Minutes of 51st meeting of Operation and Coordination Committee of MP.

The Minutes of 51st meeting of the Operation and Coordination Committee of MP held on

26th April 2016 at 11.00 AM in the Banquet Hall, Shakti Bhawan, Jabalpur has been uploaded on

the website of SLDC ‘www.sldcmpindia.com’ and can be downloaded.

(K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpur

Page 2: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Distribution List

1. The Chief Engineer (T&C), MP Power Transmission Co. Limited, Jabalpur. Fax No- 0761-2665593, 2702710 Email- [email protected]

2. The Chief Engineer (Plg & Des), MP Power Transmission Co. Limited, Jabalpur, Fax No- 0761-2660908 Email- [email protected]

3. The Chief Engineer (Procurement.), MP Power Transmission Co. Limited, Jabalpur, .Fax No- 0761-2660908 Email – [email protected]

4. The Executive Director (O & M:Gen), MP Power Generating Company Limited, Jabalpur. Fax No- 0761-2664749, Email- [email protected], Email- [email protected]

5. The Chief Engineer (O & M:Hydel), MP Power Generating Company Limited, Jabalpur. Fax No- 0761-2664749.

6. The General Manager(PM), MPPMCL, Jabalpur Email – [email protected] [email protected]

7. The Superintending Engineer (GCC), MPPGCL, Jabalpur Email – [email protected] [email protected]

8. The General Manger (DCC-EZ), DISCOM Control Centre, MP Poorva Kshetra Vidyut Vitaran Co. Limited, Jabalpur, Fax No- 0761-2668503, Email – [email protected]

9. The Dy. General Manager (DCC –CZ), DISCOM Control Centre, MP Madhya Kshetra Vidyut Vitaran Co. Limited, Bhopal, Fax No-0755-2580611,Email- [email protected]

10. The Executive Engineer (DCC-WZ), DISCOM Control Centre, MP Paschim Kshetra Vidyut Vitaran Co. Limited, Near Polo Ground, Jail Road, Indore, Fax No- 0731-2421554, Email- [email protected]

11. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Indore, Fax No- 0731-2874515, Email – [email protected]

12. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Bhopal, Fax No- 0755-2885220, Email – [email protected]

13. The General Manger(RO), MPPMCL, In front of Bhojpur Club, E-4, Arera Colony,Bhopal, Fax No-0755-2423046, [email protected]

14. The Chief Engineer (PM&C), Narmada Hydroelectric Development Corpn. Ltd, NHDC Parisar, Shamla Hills, Bhopal – 462013., Fax No- 0755-4030130,Email – [email protected]

15. The Chief Electrical Distribution Engineer, West Central Railway (WCR), General Manager’s Office, Electrical Department, Jabalpur-482001 (MP), Fax: 0761-2627629, Email- [email protected]

16. The General Manager, Indira Sagar Power Station, NHDC Office complex, PO : Narmada Nagar, Distt : Khandwa (MP) – 450 119, Fax No- 07323-284080, Email – [email protected]

17. The General Manager, Omkareshwar Power Station, Prashsnik Bhawan, Urja Vihar, Sidhwarkut, Distt : Khandwa (MP) – 450 554, FaxNo-07280-271703, Email- [email protected]

18. The Director (Projects), BLA Power Limited, At : Niwari, PO: Khorsipan, Tah : Gadarwara, Distt ; Narsinghpur 487 551, Fax No. 07791-243667 / 243669, Email – [email protected]

19. The Sr. Vice President, Jaiprakash Power Ventures Ltd., Village Sirchopi Subpost Office-Agasod, Post Office-Bina- 470113 Distt- Sagar, Fax No. 07580-277200, Email – [email protected]

20. The Deputy General Manager, Kalpataru Satpura Transco Pvt. Ltd., Satpura Colony, Betul Road, Old

Itarsi, Distt. Hoshangabad, Email – [email protected]

21. M/s Ujaas Energy Ltd. 701, NRK Business park, Vijay Nagar Sqaure, Indore – 452010, Email id :- [email protected]

22. M/s Suzlon Global Services Ltd., 1090, Scheme no. 114, Park-2, Ring Road, Universal Hospital Row, Email- [email protected], Indore – 452010, [email protected]

Page 3: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

MINUTES OF 51ST MEETING OF OPERATION & COORDINATION COMMITTEE OF MP WAS HELD AT BANQUET HALL, SHAKTI BHAVAN, JABALPUR ON 26TH April

2016 at 11.00 AM. The 51st meeting of Operation & Coordination Committee of MP was held on 26th April 2016 at

Banquet Hall, Shakti Bhawan, Jabalpur under the Chairmanship of Shri P.A.R.Bende C.E.(SLDC) & Chairman OCC. The list of participants is enclosed at Annexure -1.0

MPPKVVCL (East Discom), being the host, welcomed all the participants by offering bouquet of flowers. Thereafter Shri S.K.Bhagwatkar, GM(DCC), MPPKVVCL, Jabalpur expressed gratitude & pleasure for conducting 51st OCCM of M.P and welcomed Shri M.C.Gupta, Managing Director, MPPKVVCL, Shri S.K.Yadav, Director (Technical), MPPKVVCL, Shri. P.A.R. Bende C.E.(SLDC) & Chairman OCC and all the participants. Then he requested Shri S.K.Yadav, Director (Technical), MPPKVVCL, Jabalpur to address on the occasion.

Shri S.K.Yadav, Director (Technical), MPPKVVCL welcomed all the officer & participants on behalf of MPPKVVCL. He deliberated that OCC is an important forum which has been formed to maintain the discipline in the State Grid. Operation & Coordination Committee constituted as per guidelines contained in MPEGC and coordinating the implementation of Load Despatch & System Operation Code to ensure that respective Generators and Distribution Companies using State Transmission System discharge their obligations under the Grid Code. The OCCM is being conducted once in every two months and deliberated on all technical & operational aspects of Load Despatch and System Operation.

He also stated that OCCM is not like other general meetings and formation of Operation &

Coordination Committee has been done for specific purpose i.e. to maintain the discipline of the Grid Code which is not the responsibility of only one company but the combined efforts of all the Power Sector Companies, intra state entities and constituents of M.P. and failure to comply Grid Code & related Regulations and lapses in this regards causes serious consequences. The decisions of the OCCM are to be complied in the interest of safe, secure and reliable operation of the grid.

Further he suggested that for OCCM a common e-mail Id should be formed and all the

correspondences shall be shared through this common e-mail ID so that each member/entity is aware of the instructions/compliances and can share the valuable information/updates in the matter. He also suggested that the most important issues should be highlighted in the MOM so that such matter is compiled within the least possible time.

Shri M.C.Gupta, Managing Director, MPPKVVCL requested all the participants to introduce themselves and thereafter he requested Shri. P.A.R. Bende C.E.(SLDC) & Chairman OCC to take-up the agenda points. ITEM NO. 1 : CONFIRMATION OF MINUTES : Minutes of 50th meeting of Operation & Coordination Committee of MP held on 27th February 2016 at Omkareshwar Hydel Power Station, Omkareshwar were forwarded to the committee members vide No. 07-05/SG-9B-II/107 dated 07.04.2016. No comments have been received to SLDC. Committee confirmed the minutes.

Minutes Of 51st OCC of MP 1

Page 4: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

ITEM NO. 2 : REVIEW OF SYSTEM OPERATION DURING THE MONTHS FEB 2016 TO MARCH 2016.

2.1 Frequency Particulars: Member Secretary informed the committee that during March 2016 the system frequency was below 49.9 Hz for 8.69% of time against 5.62% of time during Feb 2016. The system frequency was above 50.05 Hz for 21.29% of time during March 2016 against 23.89% of time during Feb 2016. The system frequency was within the IEGC range of 49.9-50.05 Hz for 70.02 % of the time during March 2016 against 70.49 % of time during Feb 2016. The average monthly frequency was 50.00 Hz during March 2016 whereas it was 50.01 Hz in the month of Feb 2016. The system frequency did not touch 49.20 Hz during the above period.

The detailed frequency particulars for the month of Feb 2016 and March 2016 are enclosed at

Annexure-2.1. The brief detail of frequency profile is given here under:

Month Average frequency

Minimum integrated frequency over an hour

Maximum integrated frequency over an hour

Instantaneous minimum frequency

Instantaneous maximum frequency

Feb 2016 50.01 Hz 49.87 Hz 50.13 Hz 49.71 Hz 50.39 Hz March 2016 50.00 Hz 49.85 Hz 50.13 Hz 49.68 Hz 50.35 Hz

Member Secretary stated that average frequency during the past two months was about 50 Hz which is a good sign for stability and security of national grid. However matter of frequency above 50.05 Hz for more than 20% time is of great concern. Maintaining frequency within the IEGC specified band is the combined responsibility of all the constituents of National Grid and MP alone cannot control the grid frequency. Being surplus state, MP has to back down generation in ISGS / SSGS for restricting under drawal at high frequencies. Shri M.C. Gupta, Managing Director, Chairman (OCCM) & other participants discussed over frequency & system related matters in depth. 2.2 Operational Matters

2.2.1 Operational Discipline : Member Secretary OCC informed the committee that System operated in terms of frequency profile for the months Feb 2016 and March 2016 is as given below for discussion by the committee :

Month % of time

Frequency Below 49.9

Hz

% of time Frequency

above 50. 05 Hz

% of time frequency within the permissible range of 49.9-

50.05 Hz

Average monthly

frequency

No. of times frequency

dipped below 49.2 Hz

Feb 2016 5.62 % 23.89 % 70.49 % 50.01 Hz 0 March 2016 8.69 % 21.29 % 70.02 % 50.00 Hz 0 2.3.1 Voltage Profile : Member Secretary OCC informed the committee that date wise voltage profile at some of the important 400 KV and 220 KV substations during the months Feb 2016 and March 2016 is enclosed at Annexure -2.3.1.

During the months Feb 2016 and March 2016, the maximum and minimum voltage as recorded at

following important 400 KV s/s in MP Grid.

Minutes Of 51st OCC of MP 2

Page 5: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Sr No

Name of 400 KV

Substation

Feb 2016 March 2016 Max. Voltage

observed Min. Voltage

observed Max. Voltage

observed Min. Voltage

observed

Voltage KV

Date Voltage

KV Date

Voltage

KV

Date Voltage

KV Date

1 Indore 420 03.02.16 400 18.02.16 413 13.03.16 397 19.03.16 2 Itarsi 419 10.02.16 394 26.02.16 417 23.03.16 396 30.03.16 3 Bina 419 17.02.16 399 04.02.16 419 13.03.16 399 15.03.16 4 Gwalior 414 21.02.16 391 16.02.16 412 13.03.16 388 02.03.16 5 Nagda 417 26.02.16 384 02.02.16 417 02.03.16 386 16.03.16 6 Satpura 423 03.02.16 400 13.02.16 424 13.03.16 406 22.03.16 7 Birsinghpur 425 01.02.16 410 03.02.16 424 13.03.16 412 02.03.16 8 ISP 427 03.02.16 410 26.02.16 426 14.03.16 404 19.03.16

Member Secretary OCC stated that the voltage profile has also improved during the course of time and the problem of low voltage has almost been eliminated in the state. Discoms have also contributed in eliminating low voltage scenario by installing capacitor banks at the load centres and improvement in voltage profile could not be achieved without the efforts made by the Discoms. The voltage remained within limits for the month of February 2016 & March 2016. 2.3.2 Status of Capacitor Banks in sub-transmission system: Member Secretary OCC informed the committee that the updated information of the status of capacitor banks in sub-transmission system as on 31st March 2016 as submitted by DISCOMs is detailed below:

2.3.3 Status of Shunt Capacitor Banks installed at various EHV Transmission Substation: Member Secretary OCC informed the committee that the updated information of the status of Installed capacitor banks (in MVAR) in EHV transmission system as on 31.03.2016 as submitted by MPPTCL is given below:

DISC

OM

Capacitor bank installed in good condition (No)

Capacitor Banks healthy but not in service due to control ckt problem

Capacitor bank installed but defective & are repairable (No)

Requirement of repair against each unit (No)

Requirement against non-repairable capacitor banks

Capacitor banks already covered under ADB T-V

Balance capacitor banks to be covered in other schemes

600 KVA

R

1200 KVA

R

1500 KVA

R

600 KVA

R

1200 KVA

R

1500 KVA

R

600 KVA

R

1200 KVA

R

1500 KVA

R

No of 100

KVAR Units

required

600 KVA

R

1200 KVA

R

600 KVA

R

1200 KVA

R

600 KVA

R

1500 KVA

R

EZ 411 163 19 - - - 30 09 0 94 0 0 0 0 0 77

CZ 5 687 666 0 0 0 0 0 0 0 0 0 0 588 0 98

WZ 620 550 298 21 11 15 31 33 89 251 8 17 - - 0 0

Minutes Of 51st OCC of MP 3

Page 6: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

As per decision taken in the meeting held at WRLDC on 18.04.2016 ATC/TTC shall be computed for

drawal areas at regional level using PSS/E software. The computation of ATC/TTC at state level could not be done accurately without modeling of capacitor bank details in PSS/E software. In view of this, it is therefore requested that the details of capacitor banks installed at various locations along with their capacity and healthiness may please be submitted in the next meeting by MPPTCL / Discoms so that the same can be modeled in PSS/E software.

MPPTCL representative agreed to furnish the above information at the earliest.

2.3.4 Status of completion of ongoing Transmission Schemes being executed by MPPTCL:

Member Secretary OCC informed the various ongoing Transmission Schemes completed during the current financial year 2015-2016 (upto March 2016) and plan for completion of various ongoing Transmission Schemes for the Year 2015-2016 is enclosed as Annexure 2.3.4(i) and 2.3.4(ii).

2.3.5 U/F and df/dt Relay Operation (i) U/F and df/dt Relay Operation: Member Secretary OCC informed the committee that Frequency did not touch 49.20 Hz or below during Feb 2016 and March 2016. There was no df/dt operation during the same period and this matter of operation of df/dt relay is monitored by CEA also.

In the earlier 48th, 49th & 50th OCC meetings of MP, SLDC requested MPPTCL to submit

the revised list of AUFLS due to allocation of group to new feeders commissioned after implementation of revised AUFLS. T&C, MPPTCL ensured to submit the same. The matter was repeatedly discussed in the above OCCM but so far the information has not been furnished. It is again requested to submit the same at the earliest.

(ii) Defective u/f, df/dt relays: Member Secretary OCC informed the committee that MPPTCL has informed that all the df/dt relays are in good/healthy working condition and where the U/F relays are not available, the numerical relays programmed for under frequency operation.

(iii) Revised df/dt Plan : Member Secretary OCC informed the committee that the revised df/dt plan has been prepared in consultation of MPPTCL and implemented by SLDC wef 20.08.2015. Chairman OCC requested MPPTCL to submit the reports of testing of df/dt relays so that it can be forwarded to WRLDC/WRPC.

Voltage Class

Capacitor bank installed as on 31.01.16(MVAR)

Capacity Added after Last OCC Meeting (MVAR)

Capacitor banks already covered under ADB T-V

Capacitor Bank Installed but defective

& are not repairable (No & MVAR)

220 KV 100.00 MVAR 0.00 100.00 MVAR All in Service 132 KV 1188.00 MVAR 17.00 1205.00 MVAR

33 KV 4336.50 MVAR 0.00 4336.50 MVAR Total 5624.50 MVAR 17.00 5641.50 MVAR

Minutes Of 51st OCC of MP 4

Page 7: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

2.4 Power Cuts / Load restrictions/Differential Load Shedding by DISCOMS & group allocation to 33 KV feeders :

(i) Member Secretary OCC informed the committee that the details of DISCOM wise Power supply given to various domestic categories during the period Feb 2016 and March 2016 is enclosed at Annexure 2.4(i).

(ii) Group Allocation to Newly Commissioned existing EHV substations :- Member Secretary OCC informed the committee that the region wise list of 33 KV feeders emanating from various newly commissioned/existing EHV substations for which groups have not been allocated is given in Annexure 2.4 (ii). The DISCOM wise details of pending group allocation to 33 KV feeders is given below :

SN DISCOM Region No of 33 KV feeders for which groups to

be allocated 01

EAST

Jabalpur 01 02 Sagar 00 03 Rewa 00 04 Total 01 05

WEST Indore 07

06 Ujjain 11 07 Total 18 08

CENTRAL Bhopal 16

09 Gwalior 06 10 Total 22

TOTAL Grand Total 41 Member secretary requested Discoms to furnish the details as per list enclosed at Annexure-2.4(ii)

in the meeting. West Discom representative informed the Committee that 3no. feeders group allocation has been done

and 15 Nos. are remaining. Representative from Central Discom informed the committee that 4 no. feeders group allocation in Bhopal region and 2 nos. in Gwalior region have been done and 16 Nos. feeders are remaining for group allocation.

East Discom representative informed the committee that the bay is charged but the feeder construction

is not complete. Thereafter Chairman OCC requested MPPTCL to submit the details of feeder allocation in revised format mentioning the date of bay charging and the date of charging of feeder. The revised format for submitting the details of feeder allocation is as below:-

LIST OF 33KV FEEDERS (For which group to be allocated)

Name of EHV Substation

Name of 33KV feeder

Date of charging of bay

Date of charging of feeder

Minutes Of 51st OCC of MP 5

Page 8: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

ITEM NO. 3 : OPERATIONAL PLANNNING:

3.1 Generating Units under planned outage and proposed maintenance programme : Member Secretary OCC informed the committee that the annual maintenance /outages of thermal generating units of MPPGCL during May ’16 to June ‘16 is as under :-

POWER STATION UNIT NO. FROM TO REASON/REMARK Amarkantak –II 4 30.04.14 Continue MPPGCL has informed that letter No.

CEA/PLG/PDM/545/2016 dated 04.03.2016 has been received from Secretary, CEA, New Delhi and ATPS units 3 & 4 approved for retirement w.e.f. 13.01.2015 and 01.05.2014, respectively. Further, informed that approval from State Govt. is still awaited.

Amarkantak –II 3 12.01.15 Continue

Satpura-IV 11 25.07.15 Continue Synchronized on 11.03.2016 Chairman OCC requested representative of MPPGCL to provide the copy of letter received from CEA

regarding retirement of ATPS units 3 & 4 to SLDC at the earliest as SLDC has to recompute the availability of MPPGCL thermal stations by removing these thermal units.

3.2 Proposed shutdown programme of Transmission lines/Transformers: Member Secretary OCC informed the committee that the proposed shutdown of transmission elements for the period 01.05.2016 to 30.06.2016 submitted by MPPTCL & NHDC is enclosed as Annexure-3.2.

3.3 Long Outages of transmission elements and protections : Member Secretary OCC informed the committee that the status submitted by MPPGCL / MPPTCL are given below :

SN Line/Transformer/Breaker/ Reactor etc under long outage

Outage date Reason Response from Utility

1 220 KV Bus bar protection scheme at SGTPS Birsinghpur

Since commissioning of 220 KV switch yard

The scheme not available

Work is completed. Service Engineer from M/s GE is required for commissioning of bus bar protection panel. Also three days shutdown of 500 MW unit is required and will be done in next AOH. MPPGCL representative confirmed the above in the meeting.

2 315 MVA , Generator Transformer of unit no. 11 of Satpura TPS

25.07.2015 GT Problem (GT caught fire, B Ph. Bushing burst)

Synchronized on dated 11.03.2016

3 100MVA(BHEL), 220/132 KV transfomer at 220 KV s/s Sarni

31.05.2015 Abnormal sound observed and Differential protection optd.

This transformer has been decommissioned wef 01.02.2016 by MPPTCL vide order no.04-02/P&D/446 dtd. 12.02.16.

4 Main Breaker of 400 KV Nagda-Rajgarh-II

23.07.15 Y-phase CT burst / BKR Problem

400 KV Rajgarh II is charged from 400 KV Main Bus-I, for ensuring connectivity with Main Bus-II. The work is in progress with work of providing Line Reactor on ISP

Minutes Of 51st OCC of MP 6

Page 9: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Bay. 400 KV Rajgarh-I is shifted in diameter of 315 MVA ICT-IV, which has facility to connect on Main Bus-I and Main Bus-II. MPPTCL representative informed in the meeting that the tentative date of commissioning is September 2016.

5 40 MVA 132/33 KV Transformer ECE make at 132 KV Lakhnadon

06.10.2015 Internal sparking in Y Ph. HV side winding.

The defect developed in transformer and matter taken up with M/s ECE for its repair. The transformer has been shifted to ECE works for repairs, on receipt of above reconditioned transformer, it will be recommissioned by June 2016 as intimated in the meeting.

6 12.5 MVA 132/33 KV HEL make X’mer at 220 KV S/s Nimrani

30.10.2015 X’mer hand tripped due to high Tan-Delta of 2 No. 132 KV bushings.

MPPTCL representative informed the committee in the meeting that the transformer has been charged on 24.04.2016.

7 3x105 MVA , 400/220 KV ICT-I at 400 KV Indore

02.08.15 Differential protection optd. and 33 KV tertiary PT burst

The transformer bank is out of circuit from 02.08.2015. 2 No. 105 MVA Units of these bank have failed. The complete bank has to be replaced with 1X315 MVA 3 Ph. Transformer. DI of 315 MVA X’mer is under process. After receipt of 315 MVA X’mer, the failed 3x105 MVA Bank will be replaced by July 2016 as intimated by MPPTCL representative in the meeting.

8 315 MVA, 400/220 kV ICT-I at 400 kV S/s Bina

15.10.15 Due to Buchholtz relay alarm.

The 315 MVA X’mer Sr. No. 6005210 is out of circuit from 15.10.2015. The Transformer has been shifted from Bina to M/s BHEL works for repairs. After repairs this X’mer will be recommissioned at 400 KV S/s, Bina by July 2016 as intimated by MPPTCL representative in the meeting.

9 3X40 MVA, 220/132 KV X’mer at 220 KV S/s, Bhopal

20.01.2016 R Phase Unit Sr. No. 6004364 of X’mer failed.

Failed R Ph. Unit of 3x40 MVA 220/132 KV X’’mer bank has been replaced and X’mer charged on 22.03.2016.

10 315 MVA, 400/220 KV ICT at 400 KV S/s, Julwaniya

05.01.2016 The ICT has been removed for installation at Bina 400 KV S/s and commissioned there at 16:49 Hrs. on dtd. 05.01.2016. MPPTCL representative informed the committee in the meeting that order for new transformer has been placed and it is expected to be commissioned by December 2016.

11. 160 MVA, 220 / 132 KV X’mer BHEL make at 220 KV S/s Ratlam

12.01.2016 BHEL make Sr. No. 6005206 X’mer failed

DI issued for replacement of failed transformer and 160 MVA X’mer received at S/s. MPPTCL representative informed the committee in the meeting that by June 2016 the new transformer will be commissioned.

Minutes Of 51st OCC of MP 7

Page 10: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

12 315 MVA, 400/220 KV X’mer II (TELK make) Main Breaker at 400 KV S/s Katni

03.11.2015 X’mer commissioned through bus coupler breaker since commissioning.

It has come to notice that the transformer-II has been connected through bus coupler breaker both side (400 KV & 220 KV) and there is no main breaker for this 315 MVA X’mer-II. MPPTCL representative informed the committee in the meeting that the work will be completed by September 2016.

13 20 MVA, 132/33 KV transformer at 132 KV Neemuch

01.03.2016 Differential Protection optd.

MPPTCL representative informed the committee in the meeting that transformer will be commissioned by June 2016.

ITEM NO. 4 : OPERATIONAL STATISTICS FOR THE MONTH OF Feb’2016 and March’2016: Member Secretary OCC informed the committee that the details of actual generation, Schedule from Central Sector demand etc. are given in the following Annexures:

Annex. 4.1 Unit wise actual Generation of MPPGCL thermal Units and station wise Generation of MPPGCL & NHDC Hydel Units.

Annex. 4.2 Power Supply Position. Annex. 4.3 Hourly Average of Availability and Demand. Annex. 4.4 Hourly average schedule Vs Drawal of DISCOMs.

ITEM NO. 5.0 : SYSTEM DISTURBANCE IN MP DURING FEB 2016 AND MARCH 2016 : Member Secretary OCC informed the committee that there was no major grid disturbance in MP during Feb 2016 and March 2016. However the Grid Disturbances and Grid Incidents in MP during these months are given in Annexure 5.0. ITEM NO. 6.0 : IMPORTANT OPERATIONAL ISSUES 6.1 STATUS OF COMPLETION OF ONGOING SCHEMES FOR COMMISSIONING OF REACTORS /

TRANSMISSION ELEMENTS:- Member Secretary OCC informed the committee that The present status regarding schedule and commissioning of reactors / transmission elements is as below:

Sr. No.

400 KV S/S Size MVAR

Implementing Agency

Expected Date of Commissioning as intimated

in the 51st OCC 1 Bus Reactor : Nagda 125 MVAR MPPTCL June 2016. 2 Bus Reactor : ISP 125 MVAR NHDC Representative from ISP

informed the committee that Price Bid for purchasing the reactor has been opened and work is likely to be completed by June 2017.

3 Line reactor at Nagda-ISP line at Nagda end

50 MVAR MPPTCL September 2016

4 Line Reactor on 400 kV Satpura –ISP line at STPS end.

50 MVAR MPPGCL MPPGCL representative informed that procurement of line reactor is under tendering stage & will be made available by February-2017.

Minutes Of 51st OCC of MP 8

Page 11: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

5 Bus Reactor at SSTPS 125 MVAR MPPGCL Work will be carried out under PSDF by March-2017 as intimated by MPPGCL.

6 Bus Reactor – I at 400 KV S/s Bhopal

80 MVAR MPPTCL 80 MVAR Bus Reactor-II has been commissioned on 27.08.15. Bus Reactor–I is commissioned on 26.03.16 at 18.59 hrs.

6.2 Commissioning of new Generating units in Madhya Pradesh and the capacity expected to be commissioned during the current year 2016-17 :- Member Secretary OCC informed the committee that the status regarding Generating units, commissioned /expected to be commissioned during the current year 2016-17 accordingly the available information is as below :

S.No Name of the Power Projects Unit no. Capacity MW Date of Commissioning

/Schedule Date 1 M/s Jhabua Power, Seoni 1 600 Commissioned on 22.03.2016 2 Moser Bear (Hindustan power) 2 600 COD on 07.04.16 3 Essar Power MP Ltd (Mahan) 2 600 June-2016 Member Secretary OCC stated that the matter was discussed in last OCCM in which SLDC has

requested MPPMCL to submit the latest status of above power plants but MPPMCL has not submitted the same.

6.3 Provision of synchronization facility at EHV sub-stations of MPPTCL:- Member Secretary OCC informed the committee that as per Grid Code, the synchronization facility should be available at all the Power Stations, 400 KV Sub-stations and 220 KV Sub-stations and 132 KV sub-stations in the path of black start. In last OCC meeting MPPTCL representative informed the committee that the procurement of synchronization trolley is under tendering stage. Further it was informed by chairman OCC that synchronization trolley at 400 KV S/s Indore is not in order and requires immediate attention for its proper functioning.

The MPPTCL representative informed the committee that the tender for 69 No. synchronization trolley

has been opened and shortly purchase order will be placed. Further he informed that by end of December 2016 the work will be completed.

6.4 System Protection Scheme (SPS) in MADHYA PRADESH:- Chairman OCC informed the committee that in the last meeting request was made by MPTCL to submit the complete details of all SPS commissioned in MP along with load shed quantum to SLDC, so that the copy of the same could be placed in Control room of SLDC and concerned substation / power station for reference and record.

The same is not furnished so far. MPPTCL is requested to submit the information at the earliest. MPPTCL representative informed that committee that detail in the above matter will be provided

shortly.

6.5 Communication problem with Hydel Power Station:- Member Secretary OCC informed the committee that there is communication, data as voice, problem between SLDC and Tons & Pench Hydel Power Stations of MPPGCL. The communication is intermittent and remained out for most of the time. Great

Minutes Of 51st OCC of MP 9

Page 12: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

difficulty is being experienced by the SLDC for contacting these HPSs for operation of the machines. This matter was raised in the OCCM in the past also. However, there is no improvement in the communication with these stations. Normally communication does not take place as & when required in order to take or stop machines at Tons & Pench HPS and quite often operation of machines gets delayed. This has adverse effect on the grid security and hence MPPGCL is requested to thoroughly the PLCC link in coordination with Communication wing of MPPTCL and help if any required, shall also be extended by the SLDC.

MPPGCL representative informed that a mobile No. 09977507928 has been provided at Pench HPS

and installation work of extending mobile facility at Tons HPS is under progress which shall be completed shortly.

Thereafter Chairman OCC requested that the PLCC communication with all Hydel Power Stations

should also be made operational RTC.

6.6 Deviation in schedule and drawal by MPPMCL:- Member Secretary OCC informed the committee that the persistent deviation is observed in schedule and drawal particularly due to uneven sale of power by MPPMCL. It would become very difficult for SLDC to keep deviation within IEGC limit at certain time block boundaries due to change in huge quantum of sale. Sometimes it causes the violation of the over drawal/ under drawal limits stipulated in the DSM regulation. The matter was brought into the notice of MPPMCL in the earlier OCC meetings also but no action has been taken by MPPMCL to streamline the drawal pattern of MP by suitably ramping the power sale / banking. It is requested that MPPMCL should take necessary action to avoid such situations and sale/purchase/banking should be planned such that suitable ramping is ensured to maintain scheduled deviation within regulatory limits.

6.7 Switching Operation of Transmission Elements without obtaining grid Code from SLDC:

Member Secretary OCC informed the committee that as per IEGC Sub -Regulation (b) of Regulation 5.6.2 “All operational instructions given by RLDC and SLDC shall have unique code which shall be recorded and maintained as specified in Central Electricity Authority (Grid Standards) Regulations, 2010.“

On dtd 10.04.2016 at 20.02 hrs during charging of 220 KV Satna- Maihar Ckt pole discrepancy was

observed resulting in tripping of various lines and transformers. On 15.04.2016 at around 09.41 hrs 220 KV Birsingpur-Rewa ckt tripped from Birsinghpur end caused tripping of transmission elements in Rewa Area. On 18.04.2016 at 06.06 hrs 132 KV B-phase CT of 220/132 KV 160 MVA transformer-I NGEF make burst at 220 KV S/S Neemuch resulting in tripping of all connected feeders. Restoration of transmission elements in above occasions had been carried out by MPPTCL S/s staff without obtaining grid code from SLDC. Such types of violations have been brought in to the notice T&C, MPPTCL in the past also. Such switching operation of transmission elements without obtaining code from SLDC/Sub-LDC is not desirable for safe and secure and smooth operation of integrated grid and also falls under violation of section 5.2 and 5.6.2 of IEGC. In case of persistence repetition of such occurrences, SLDC shall have no option but to report the same to Hon’ble commission through monthly compliance report.

Chairman OCC requested all the intra state entities to issue the suitable instruction to all concerned

officials for strict compliance of the Grid Code.

6.8 Over Loading of 220 KV OSP-Barwaha line at Omkareshwar Hydel Power Station :- Member Secretary OCC informed the committee that in 50th OCC meeting, Sr. Manager (O&M), OSP has intimated that number of trippings were occurred in past months due to overloading of the line and requested to allow to interchange the CT of 220 KV OSP –Barwaha line (500-300/1Amp) with 220 KV OSP-Barawaha (tap

Minutes Of 51st OCC of MP 10

Page 13: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Nimrani) line (800-400/1Amp. In the meeting Chairman OCC requested MPPTCL to examine the matter and report to SLDC at the earliest. The CE(T&C), MPPTCL Jabalpur has suggested to install new 200 KV CTs of 800-400/1 A in place of existing 500-300/1 A CTs of 220 KV OSP-Barwaha feeder at OSP end. Accordingly vide letter no 07-05/NCA-94/5577 dtd 19.03.2016 SLDC informed Omkareshwar HPS and requested to take necessary action in the above matter at the earliest. Representative of OSP HPS informed the committee that the replacement of CT’s of 220 KV OSP-Barawaha line with 800-400/1A shall be done after the commissioning of 6th bay at OSP by MPPTCL. Chairman OCC requested the representative of OSP the work of replacement of CT should not be linked with the construction of 6th Bay at OSP HPS and required to be completed by the OSP at the earliest and necessary steps for procurement and installation may be initiated without any delay. 6.9 Required information regarding regulatory compliance at the time of commissioning of transmission elements :- Member Secretary OCC informed the committee that while submitting request for real time code for charging of new transmission lines / transformers, the required information regarding compliance of regulatory requirements is not being furnished by the requestors. The request of SLDC Control Room staff for providing the information as a regulatory requirement, the substation staff instead of providing documents which are necessarily provided to SLDC before first charging of transmission elements, considered it as act of SLDC for delaying charging of newly constructed transmission element. The MPPTCL is requested to look into the matter and the field staff may be instructed suitably to provide the information invariably as and when desired by SLDC to process the matter for issuing the real time code for first time charging of new transmission element.

Chairman OCC stated that the submission of above mentioned information regarding charging of

new transmission lines / transformers is a regulatory requirement hence required information/documents should invariably be submitted well before charging new transmission elements.

6.10 SCHEDULING ACTIVITY BY MPPMCL ON BEHALF OF DISCOM:- Member Secretary OCC informed the committee that SLDC has taken up the issue of round the clock functioning of MPPMCL Control Room in the past OCCM also so that real time revisions of requisitions shall be made by the MPPMCL on behalf of DISCOMs which is presently done by the SLDC itself.

The MPPMCL had deputed one engineer in Shift at SLDC Jabalpur in August 2015 to understand

the scheduling procedure and preparation of requisition as per availability and demand pattern. MPPMCL engineers have acquired sufficient knowledge of requisition/scheduling over this period and doing the scheduling activities under the Balancing & Settlement Code. Now SLDC proposed that after 15 days from the date of Installation / commissioning of New SCADA (Alstom), the MPPMCL staff should start functioning from MPPMCL Control Room. Further it is a matter of pleasure to inform all the members that new SCADA (Alstom) has been recently commissioned on 18.03.2016 and it started functioning. Accordingly now MPPMCL should immediately take up real time scheduling activities on behalf of Discom. It is to mention that MP SLDC perform the scheduling activities as per the requisition of MPPMCL and DISCOMS for ISGS/SSGS/Other LTA&MTA/Bilateral agreement. However the MPPMCL engineers in shift quite often remains reluctant to make requisitions despite request of SLDC Shift in-charge to help them in this activity. Chairman OCC requested MPPMCL to immediately start functioning from MPPMCL Control Room when SLDC SCADA terminal is provided.

Representative from MPPMCL informed the committee that by end of May 2016, MPPMCL will start

independent functioning from MPPMCL independent Control Room.

Minutes Of 51st OCC of MP 11

Page 14: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

ITEM NO. 7 : REGULATORY ISSUES 7.1 Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Fourth Amendment) Regulations, 2016: Chairman OCC informed the committee that the Central Electricity Regulatory Commission vide notification dtd 06.04.2016 has made amendment(Fourth Amendment) in IEGC 2010. The new clauses have been added and gist of the same is given below :- 1. Date of Commercial Operation or 'COD' : Date of commercial operation in case of a unit of

thermal Central Generating Stations or inter-State Generating Station shall mean the date declared by the generating company after demonstrating the unit capacity corresponding to its Maximum Continuous Rating (MCR) or the Installed Capacity (IC) or Name Plate Rating on designated fuel through a successful trial run and after getting clearance from the respective RLDC or SLDC, as the case may be, and in case of the generating station as a whole, the date of commercial operation of the last unit of the generating station.

2. Trial Operation or Trial Run :- (i) Trial Run or Trial Operation in relation to a thermal Central Generating Station or inter-State

Generating Station or a unit there of shall mean successful running of the generating station or unit thereof on designated fuel at Maximum Continuous Rating or Installed Capacity or Name Plate Rating for a continuous period of 72 hours

(ii) In case of a hydro Central Generating Station or inter-state Generating Station or a unit thereof for a continuous period of 12 hours.

(iii) Trial run and Trial operation in relation to a transmission system or an element thereof shall mean successful charging of the transmission system or an element thereof for 24 hours at continuous flow of power, and communication signal from the sending end to the receiving end and with requisite metering system, telemetry and protection system in service enclosing certificate to that effect from concerned Regional Load Despatch Centre

3. Technical Minimum Schedule for operation of Central Generating Stations and Inter-

State Generating Stations: - The technical minimum for operation in respect of a unit or units of a Central Generating Station of inter-State Generating Station shall be 55% of MCR loading or installed capacity of the unit of at generating station.

(i) Compensation for degradation of Specific heat rate for low unit loading on monthly basis in

terms of energy charges. (ii) Compensation for degradation of Auxiliary Consumption for low unit loading on monthly

basis in terms of energy charges. (iii) The scheduled generation falls below the technical minimum schedule, the concerned CGS

or ISGS shall have the option to go for reserve shut down and in such cases, start-up fuel cost over and above seven (7) start / stop in a year shall be considered as additional compensation

The compensation so computed shall be borne by the entity who has caused the plant to be operated at

schedule lower than corresponding to Normative Plant Availability Factor up to technical minimum based on the compensation mechanism finalized.

Chairman OCC requested all the intra state entities should go through the above amendment which is

available in the website of CERC and act accordingly.

Minutes Of 51st OCC of MP 12

Page 15: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

ITEM NO. 8 : BLACK-START MOCK DRILL OF HYDEL POWER STATIONS : 8.1 Black Start mock drill of Hydel stations of MPPGCL and NHDC : Chairman OCC informed the committee that the black start mock drill of Tons HPS, Bargi. Pench and Gandhisagar HPS have been completed successfully on 08.10.15, 12.10.15, 06.11.15 and 06.01.2016 respectively. The second time black start mock drill of Gandhisagar HPS has been completed successfully on 04.04.2016 with extending supply to 132 KV S/s, Bherugarh (Ujjain) for Simhasta 2016. The proposed dates for black start mock drill of remaining hydel power stations is given below :-

Sl. No. Name of Power Station Date of Mock Drill

1. Indira Sagar Project 30th May 2016 2. Omkareshwar HPS 1st June 2016

In the last OCC meeting, MPPGCL has informed that the Black Start Mock Drill of Birsinghpur,

Rajghat and Madikheda HPS could not be possible due to non-auto operation of governor. MPPGCL is requested to submit the plan for readiness of these units for black start mock drill.

Now SLDC has proposed that the black start mock drill of Rajghat and Madikheda HPS shall be

planned at the earliest. Thereafter the procedure shall be prepared & furnished to the MPPGCL & concerned officials by MP SLDC.

MPPGCL representative informed the committee that Black Start Mock Drill at Madhikheda HPS

shall be conducted in July 2016 with Governor in Manual Mode. Further NHDC representative agreed for conducting Black Start Mock Drill at Indira Sagar Project and Omkareshwar HPS on above mentioned dates. ITEM NO 9: SOME IMPORTANT MATTERS REQUIRED IMMEDIATE ATTENTION:

9.1 Quarterly Review of Crisis Management Plan: Member Secretary informed the committee that the NHDC & SLDC is submitting the quarterly crisis management report to Chief Engineer (GM), CEA New Delhi under intimation to SLDC Jabalpur and WRPC Mumbai.

However despite continuous persuasion by SLDC other state utilities i.e. MPPTCL, MPPGCL and IPPs

are not submitting the report to CEA. It is requested to submit the CMP report in prescribed format for the fourth quarter of 2015-16 (Jan to March 2016) to CEA under intimation to SLDC.

9.2 Status of Physical & Cyber Security in Power Sector regarding: Chairman OCC informed the committee that the status of physical & cyber security in Power Sector for the fourth quarter (Jan to March 2016) has not been received from any of the state utilities. In the past also this report is not being furnished by any of the state utilities despite constantly pursuing the same by SLDC in OCC meetings and also through correspondence.

The state entities are requested to furnish the Status of physical & cyber security in Power Sector for

fourth quarter (Jan to March 2016) directly to the Chief Engineer (GM), CEA New Delhi under intimation to SLDC Jabalpur and WRPC Mumbai.

Minutes Of 51st OCC of MP 13

Page 16: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

ITEM NO.10: AVAILABILITY BASED TARIFF (ABT) RELATED ISSUES: 10.1 Status of AMR system installed at SLDC:

SLDC representative informed the Committee about the status of AMR data received through AMR system in the month of Mar 2016. He also informed that complete data of 492 ABT meters installed at interface points was received through AMR System and data of132 Nos meters (Monthly-83 & Partial – 49) was not received mainly due to connectivity / alignment problem of optical cable, network problem or modem not installed or due to some other problem. He also informed that SLDC is not receiving timely the missing load survey data from Indore, Ujjain & Gwalior circle offices and requested MPPTCL to issue instructions. MPPTCL stated that instructions will be issued to these circle offices. Further following points are discussed and resolved as under:-

i. SLDC representative informed that M/s Secure Meters Ltd has furnished a list of 37 Nos interface points /

meters whose data is not being read through AMR system due to different issues such as modem removed, meter defective / replaced etc. He informed that instruction were issued by the CE(T&C) office to respective SE(T&C) offices for resolving the issues, but out of 37 Nos meters only one meter of Sagar Rly Traction has be read. He further requested MPPTCL to issue the instructions for resolving the issues immediately. CE(T&C) office have assured to resolve the issues on priority basis.

ii. SLDC representative informed that for providing AMR access to the concerned SE(T&C) offices for ensuring the communication status and data downloading of the meters, M/s Secure Meters ltd. have informed that modems have been issued, but SIMs are not provided to SE(T&C) offices. MPPTCL informed that SIMs have been issued to field offices.

iii. SLDC representative informed that AMR facility is required at newly commissioned substation / Xmers / HT consumers / OACs / REGs around. 69 os. MPPTCL informed that modems & SIMs have been issued to field offices for providing AMR facility on newly commissioned substation / Xmers / HT consumers / OACs / REGs.

iv. SLDC representative apprised the Committee that M/s Secure Meters Ltd. is insisting on starting the AMC

of AMR system as Two and half year period has already passed its is difficult for them to provide the services due to financial commitment. He further informed that SLDC has requested M/s Secure Meters Ltd to resolve the issue of 37Mos interface points and provide the AMR access to SE(T&C) offices for starting the AMC. CE(T&C) has also stated that M/s Secure Meters Ltd. shall resolving these issues by May 2016 so that AMC could be started from June 2016.

10.2 Non reporting of details of newly installed meters, replaced meter & CT and change in polarity

of ABT meter installed at interface points to SLDC:

SLDC representative informed that site officials are not reporting timely the details of the newly installed meters, replaced meters, change in CT ratio of meter and polarity change in meters installed at interface points to SLDC. He further informed that this may lead to incorrect data computation of the ABT meter installed at the interface points and may affect the accuracy of MP transmission loss computation and energy accounts of Discoms. MPPTCL assured that the instructions has already been issued be issued to concerned site officials for furnishing the timely details of newly installed meters, replaced meters, change in CT ratio of meter and polarity change in meters installed at interface points to SLDC.

SLDC informed that the CE(T&C) office informs about the commissioning of new substation /

transformer to SLDC but do not furnish the details of ABT meters installed, Xmers and SLDC has to collect

Minutes Of 51st OCC of MP 14

Page 17: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

the required details from substations / field offices which is a time consuming process. He requested the CE(T&C) office to furnish the details of Xmers (Sr. No.) and ABT Meter details such as Mtr Sr. No., Meter CT & PT Ratio, Equipment CT & PT ratio, MF while intimating the commissioning details. CE(T&C) office informed that instructions will be issued to field offices for furnishing the meter details to SLDC. 10.3 Scheduling of power from Ratnagiri Gas and Power Private Ltd (RGPPL) to balance 7 Nos tapped Railway Traction Substations -

SLDC representative informed that scheduling of power from Ratnagiri Gas and Power Private Ltd

(RGPPL) to balance 7 Nos tapped Railway Traction Substations (TSS) in Madhya Pradesh has been commenced w.e.f. 00:00 Hrs of 21st March 2016 and as of now the scheduling of 200MW power is now being done for 36 Nos TSS points of Railways in MP as per the directives issued by Hon’able CERC vide order dated 05-11-2015 in petition no. 197/MP/2015 treating Railway as a deemed licensee. Further following points are discussed and resolved as under –

1. SLDC representative informed that Railway Traction Talwadia is a tapped point and tapping is done

from Interconnector-III between 132KV Cheggaon and 220KV Cheggaon substation and requested for installation of ABT meter at the TSS. CE(T&C), MPPTCL stated that Talwadia is not a tapped point and instructions will be issued for removing the tapping from Interconnector-III as it might have been done for taking some shutdown.

2. SLDC representative requested MPPTCL to apprise the Committee about the status of installation of ABT meters at 29 interface points of Railways. MPPTCL informed that Railways has deposited the meter installation charges and tendering / procurement of meters will take about 9 months time.

3. Chairman OCC stated that Railways is continuously over drawing from the grid w.e.f. 21st Mar 2016 i.e. after the scheduling of power is started on 7 Nos tapped Railways traction points. The quantum of Railway drawl is in the range of 200-300MW, also at some instances the schedule is Zero. He also stated that this over drawl by Railways has serious financial implication on the State i.e. Discoms, as Railways is an embedded licensee in the State. He further stated that Member Secretary, WRPC in the 482nd OCC meeting has made the following suggestions – • DSM liabilities of States due to tripping of RGPPL units & continue drawal by Railways, states may

transfer the DSM liabilities to Indian Railway for their further course of action. • Railway in turn should settle the DSM liabilities with RGPPL as per present PPA which envisage

RGPPL to arrange alternate supply source. • Railways should come up with an standby arrangement of power in respective states.

Chairman OCC stated that to resolve the issue of over drawl by Railways, the SLDC will take up the

matter with Hon’able MPREC. The Chief Electrical Distribution Engineer, WCR, Jabalpur informed that Railways has requested MPPMCL for purchase of power / proposal and Railways has signed agreement with M/s Jindal Power for purchase of power.

4. SLDC representative requested MPPTCL to apprise the Committee about the status of Bulk Power

Transmission Agreement (BPTA) with Railways. MPPTCL informed that draft copy of BPTA is sent to all concerned offices for comments, on receipt of their comments the BPTA will be signed with Railways.

10.4 Providing AMR facility for the ABT meters installed at MPPGCL :

SLDC representative apprised the Committee about the status of data received from MPPGCL stations

in the month of Mar 2016, Data received of 60 Meters out of 108 meters where AMR facility is provided by MPPGCL as per CE(Thermal), O/o ED(O&M:Gen), MPPGCL letter No. 426 dated 01.03.2016. He requested MPPGCL to take up the matter with M/s Secure Meters Ltd. for integrating the balance 48 Nos

Minutes Of 51st OCC of MP 15

Page 18: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

meters. MPPGCL representative asked about the list of meters not integrated with AMR system to which SLDC representative assured to send the same through email to GCC, MPPGCL.

10.5 Suspension of energy accounting of RE generators due to non- compliance of regulatory requirement:

The Chairman OCC stated that SLDC has suspended the energy accounting of 37 RE Pooling Stations of 12 No. Developers who had not provided telemetry facility upto Jan 2016, the suspension of energy accounting of the defaulting RE generators/ Developers was done in the monthly State Energy Account issued by SLDC from the month of Jan 2016. He also stated that SLDC is not indicating the energy injection of individual developers but total energy injection is shown in SEA for the purpose of energy accounting of Discoms. He further stated that three nos. of Developers has provided the telemetry data of three nos pooling stations to SLDC in the month of Feb 2016, therefore their energy accounting has been started from the month of Mar 2016 and SEA for the months of Jan & Feb 2016 have been revised.

10.6 Energy Accounting of Renewable Energy Generators (REGs) connected at 33KV as per the data recorded in ABT meter installed at the pooling station:

SLDC representative informed that it was discussed and decided in the 45th OCC meeting, that energy accounting of Renewable Energy Generators (REGs) shall be done as per the actual data recorded in ABT meters installed at the pooling station, SLDC has requested the commercial sections of Discoms to furnish the meter, modem & SIM details and % of energy purchased by MPPMCL and % of energy wheeled to Discoms for configuration at SLDC, however, Central & West Discom has furnished mostly generator wise details whereas pooling station wise details are required for energy accounting. On configuring the details of meter, modem & SIM, the data was not downloaded due unavailability of GSM service. He further clarified that in the absence of desired information from Discoms, the energy accounting of the REGs connected at 33KV pooling station could not be started.

The Chairman OCC stated that SLDC has to perform the energy accounting of RE generators on the

pooling stations for which pooling station wise meter details are required. He also advise the SLDC and Discom representative to hold the meeting at Indore with Discom officials for receiving the required details from Central and West DIscoms.

10.7 Energy Accounting of Discom embedded Open Access Customers connected at 33KV level.

SLDC representative informed that in accordance with Madhya Pradesh Electricity Balancing and Settlement Code (BSC) 2015, Discom Energy Accounting Group (DEAG) shall have to undertake the various activities such as deviation settlement, energy settlement of Discom Embedded Open Access Customers (DEOACs). In the 48th OCC meeting, it was discussed & decided that energy accounting of DEOACs shall be done by the DEAG group of Discoms. Accordingly, SLDC has provided the training and necessary inputs to Discom officials on 11th Dec 2015. He further informed that SLDC vide this office letters No. 4605 dated 05.01.2016 and 133 dated 13.04.2016 has also requested the Commercial Sections of Discoms to issue necessary instructions to Discom Energy Accounting Group (DEAG) to take over the energy accounting of DEOACs from the month of April 2016 to be done in May 2016 with parallel run for the month of Dec 2015 to March 2016.

The East & West Discoms representative have confirm their readiness in starting the energy

accounting of Discom embedded customers w.e.f. April 2016. But, Central Discom representative requested for one month time extension as their concerned person has left the job. The Chairman OCC advised that energy accounting shall be done and energy statements & accounts shall be issued by Disoms from the

Minutes Of 51st OCC of MP 16

Page 19: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

month of April 2016 to be done in May 2016, necessary inputs & help will be provided by SLDC to Central Discoms.

ITEM NO 11: SCADA/EMS RELATED ISSUES: 11.1 NON AVAILABILITY OF TELEMETRY OF IMPORTANT 132KV S/s HAVING INJECTION FROM

RENEWABLES/CAPTIVE POWER PLANTS OR HAVING INTERDISCOM FEEDERS –

It was informed by SLDC that the telemetry of new 220KV S/s, important 132KV S/s having injection from renewable generating Stations, and Captive Power Plant, is to be provided through Dongfeng RTUS installed and commissioned under MPPTCL SCADA project. Total 50 Nos. Sub Stations as mentioned in enclosed annecure-1 has already been identified and forwarded to MPPTCL for arranging integration of telemetry. Two number special meetings of MPPTCL filed officers/T&C officers have already been held at SLDC Jabalpur regarding integration issues. However, the progress is very slow. In response, MPPTCL representative informed that the work involves coordinated effort by MPPTCL SCADA team for configuration of RTUs, SLDC SCADA team for configuration in SLDC SCADA system in communication divisions in commissioning of data channel. The work regarding configuration of Dongfeng RTU, preparation of data IO list and configuration in SLDC SCADA system is almost completed and commissioning of data channel is pending for want of PLCC panels, modems etc. Accordingly, it was decided that a separate meeting with MPPTCL officers shall be held at SLDC on 2nd May 2016. 11.2 ARRANGEMENT OF TELEMETRY REQUIRED FOR KUMBH MELA AT UJJAIN:

It was informed by SLDC that, as per the Contingency plan prepared by WRLDC for grid monitoring

during Kumbh Mela nine number RTUs located at 132KV Deplapur S/s, 132KV Sanwer S/s, 132KV Ingoria, 132KV Ghosla, 132KV Dewas MSP, 132KV Makshi, 132KV Ratodiya, 132KV Bherogad, 132KV Agar were integrated with SLDC SCADA/EMS system. However, the integration is not yet completed. Several of the measure and from these stations is either not received or wrongly received. The list of telemetry discrepancy with regard to these stations is forwarded to concern offices by Sub-LDC but matter is still pending. In response, it was informed by MPPTCL officers that from same RTUs, the data in transmission SCADA system is correctly received. It was subsequently informed by SLDC that configuration in SLDC SCADA is verified by Sub-LDC as per the data IO list provided by MPPTCL SCADA team and hence problem is either due to wrong IO list or erroneous configuration of corresponding RTU port. It was further decided that the matter shall be discussed in detail in the meeting proposed at SLDC on 02-05-2016. 11.3 PRESENT STATUS OF PROCUREENT OF RTUs BY MPPGCL:-

SLDC informed that the Telemetry of Rajghat HPS is out since LAST TWO YEARS & telemetry of

Bansagar-III is out since last four months . Further, the matter of procurement of RTU for Rajghat HPS and Bansagar III HPS was discussed in detail in last fourteen OCCM meetings as well as on two number special telemetry meetings, without any conclusive result In response, MPPGCL informed that the re-tendering of RTU procurement case is done and techno-commercial bids has already been opened 14th March 2016. SLDC requested to expedite the procurement. 11.4 The arrangement of data channel for remote VDU installed at CEntrAl DISCOM Control room /laying of ADSS cable At Bhopal & Jabalpur .

It was informed by SLDC that the remote VDU from new SCADA /EMS system is successfully commissioned at East & West DISCOM Control room, GCC Jabalpur and MPPMCL CR at Jabalpur. The commissioning of remote VDU at CZ control room is pending for want of 2 mbps link. In response Central

Minutes Of 51st OCC of MP 17

Page 20: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

DISCOM officers informed that the link for commissioning of Remote VDU at Central DISCOM is under progress and shall be available shortly.

Regarding arrangement of ADSS cable between Shakti Bhawan to 220Kv S/s Jabalpur it was

informed by East DISCOM that the approval from Works section of East Discom has already been accorded and order for the same shall be placed shortly by East DISCOM.

The matter of fiber optical connectivity up to MPPMCL office at Arera colony is also discussed and

SLDC informed that the optical fiber connectivity from backup SLDC to MPPMCL office at Arera colony is required to be extended for which wide band node equipment and DC power supply is arranged under Master telecom plan of WR while ADSS cable laying is to be arranged by MPPMCL. The MPPMCL officers informed that the progress in the matter shall be informed separately.

11.5 DISCREPANCY IN TELEMETRERED VALUES RECEIVED FROM DIFFERENT EHV S/S & POWER STATIONS & UPGRADATION OF EXISTING RTUS

SLDC informed that the migration to new SCADA,EMS system is completed by SLDC. However, utilization of EMS system is not possible due to incomplete telemetry specially availability of Status parameters as availability of CB status is a prerequisite for successful functioning of EMS Hence the work regarding telemetry discrepancy is to be taken up on highest priority. SLDC further informed that during the special meeting held at SLDC on 24th August 2015, it was already agreed that the corrective action regarding STATUS telemetry which is essential for EMS functioning shall be completed by 31st October 2015, however the same is not completed. In response, MPPTCL officers requested to discuss the matter station wise, in the proposed meeting at SLDC on 2nd May 2016. 11.6 ARRANGEMENT OF NECESSARY SPACE, AIRCONDITIONING AND POWER SUPPLY, PLCC EQUIPMENTS FOR INSTALLATION OF WIDE BAND EQUIPMENTS & FOR HOT LINE PABX:-

It was informed by SLDC that under Master telecom Plan of WR and URTDSM project,

replacement of existing wideband equipments are proposed for replacement and new wideband equipments are proposed to be installed at new locations. For commissioning of these equipments, necessary space, air-conditioning and DC Power supply arrangement for all locations covered under master telecom project as well as in URTDSM project is required to be made by concern utilities. The same was requested in several OCCM meetings. However, recently while commissioning of wideband equipments by M/s Tejas, it was observed that the proper air conditioning environment is not available at 400KV Nagda & the commissioning of wideband node at 220KV Barwaha got delayed due to non- availability of space at S/s. Accordingly, it is necessary to identify and mark the space required for wideband locations so that delay in commissioning of equipments may be avoided. MPPTCL informed that NIT for Air-conditioners has already been issues. Further, MPPTCL and MPPGCL representative agreed to initiate necessary action in the matter. 11.7 Commissioning of communication channels for dual reportig of RTUs as per backup SLDC requirement:-

It was informed by SLDC that the commissioning of SCADA/EMS system at SLDC Jabalpur and backup SLDC Bhopal is completed and the additional communication channel is required to be extended to respective control center’s for testing with new SCADA/EMS system. The RTU wise progress is required to be provided by MPPTCL & MPPGCL. Further, the wideband node at SGTPS is commissioned but RTU channel for SGTPS, ATPS and Birsinghpur S/s is required to be shifted to wide band node. Similarly, after commissioning of wideband node at 400KV S/s Nagda, the PLCC channel from Nagda 400KV S/s is decommissioned while functioning of both wideband and PLCC channel is required to be ensured. MPPTCL and MPPGCL officers agreed to initiate necessary action in the matter on top most priority

Minutes Of 51st OCC of MP 18

Page 21: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

11.8 LONG OUTAGE OF RTUS, PROBLEM IN DATA and VOICE CHANNELS The long outage of telemetry of 132KV Morwa, 220KV Sagar,220KV Tikamgarh, 220KV Dewas was

discussed in detail. SLDC requested to look into these outages and expedite the restoration procedure for which concern officers agreed. 11.9 Telemetry of Railway TSS Sub Stations:-

The matter regarding arrangement of telemetry of railway TSS sub stations was discussed and it

was informed by Railway officers that the work is under progress and details progress shall be submitted within a month. SLDC requested to provide technical details of equipments arranged for telemetry before placement of order so that compatibility of proposed equipments for telemetry of railway TSS with SLDC SCADA/EMS system may be ensured. SA-1 :- Reference from MNRE regarding compilation of data for meeting renewable energy targets of 175 GW by 2020 :- Member Secretary OCC informed the committee that WRPC has requested to furnish

the following information / data for compilation which will help in taking measures how to utilize the regional

and national potential of balancing and how to distribute the effort of RE integration within Western Regional

states.

1. Data on Technical capacities of power plants such as minimum load, rate of change of generation, start up time and down time, minimum standstill time. 2. Thermal balancing potential of RE rich states today and upto 2020. 3. Theoretical hydro balancing potential of states today and upto 2020. 4. Pumped hydro projects capabilities today and upto 2020 5. Forecasting and scheduling regulations by states.

In view of the above it is requested to submit the information to this office latest by 30.04.2016 so that the compiled information could be furnish to CEA /WRPC. The matter was discussed in the meeting.

ITEM No 12 : DATE AND VENUE OF NEXT OCC MEETING :

It is proposed to hold 52nd OCC meeting of Operation and Coordination Committee of MP on 23.06.2016 at SLDC, MPPTCL, Nayagaon, Jabalpur.

***********

Minutes Of 51st OCC of MP 19

Page 22: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Minutes Of 51st OCC of MP 20

Page 23: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Minutes Of 51st OCC of MP 21

Page 24: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Minutes Of 51st OCC of MP 22

Page 25: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

S. No. Particulars

1

1.1 Maximum Frequency 50.13 HzBetween 13.00 hrs & 14.00 Hrs on 01.02.16

50.13 HzBetween 17.00 hrs & 18.00 Hrs on 23.03.16

1.2 Minimum Frequency 49.87 HzBetween 05.00 hrs & 06.00 Hrs on 23.02.16

49.85 HzBetween 03.00 hrs & 04.00 Hrs on 11.03.16

1.3 Average Frequency 50.01 Hz 50 Hz

2

2.1 Maximum Frequency 50.39 Hz AT 03.20 HRS ON 14.02.16 50.35 Hz AT 18.03 HRS ON

07.03.16

2.2 Minimum Frequency 49.71 Hz AT 22.07 HRS ON 25.02.16 49.68 Hz AT 14.33. HRS ON

18.03.163 Percentage of time when frequency was :-

%age of time when frequency was Feb-16 Mar-16

3.1 Below 48.5 Hz 0.00 0

3.2 Between 48.50 Hz and 48.8 Hz 0.00 0

3.3 Between 48.80 Hz and 49.2 Hz 0.00 0

3.4 Between 49.20 Hz and 49.5 Hz 0.00 0

3.5 Between 49.50 Hz and 49.7 Hz 0.10 0.1

3.6 Between 49.70 Hz and 49.9 Hz 5.52 8.59

3.7 Between 49.9 Hz and 50.05 Hz 70.49 70.02

3.8 Between 50.05 Hz AND 51.5 Hz 23.89 21.29

3.9 Above 51.5 Hz 0.00 0

4 No. of times frquency touched 48.80 Hz 0 0

4.1 No. of times frquency touched 48.60 Hz 0 0

4.2 No. of times frquency touched 51.0 Hz 0 0

FREQUENCY PARTICULARS

INTEGRATED OVER AN-HOUR

INSTANTANEOUS FREQUENCY

Feb-16 Mar-16

Minutes Of 51st OCC of MP 23

Page 26: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Max Min Max Min Max Min Max Min1 787 747 417 400 790 754 411 3842 787 747 417 400 790 754 411 3843 787 752 417 399 789 759 414 3944 781 744 414 394 786 750 409 3925 785 749 416 397 784 752 411 3946 781 740 416 394 789 752 410 3897 782 744 416 397 792 758 414 3968 781 748 417 400 788 759 411 3939 778 747 415 399 785 754 410 38810 786 748 419 400 790 756 410 39311 786 752 417 400 788 761 414 39412 784 745 417 399 795 755 410 38813 783 747 415 398 789 756 412 39214 786 746 416 397 787 752 410 38815 780 750 416 400 791 757 412 39416 780 750 416 400 791 757 412 39417 781 749 417 398 788 751 411 38718 781 745 414 394 784 752 409 39419 786 746 413 396 783 749 408 39120 787 746 414 395 784 755 414 39021 787 746 414 395 784 755 414 39022 785 742 416 397 788 751 413 38823 785 742 416 397 788 751 413 38824 777 751 414 399 781 761 411 39325 783 747 413 397 781 753 412 39226 788 748 416 394 791 748 417 39327 785 746 413 402 784 756 411 39228 779 747 416 400 791 761 411 39429 786 746 416 397 787 752 410 388

Max /Min 788 740 419 394 795 748 417 384

Max Min Max Min Max Min Max Min1 785 745 416 400 786 761 410 3912 778 745 414 399 785 758 417 3913 778 748 415 397 786 753 408 3864 784 751 413 402 784 758 410 3915 778 754 416 402 790 763 410 3946 784 752 417 400 792 762 412 3937 784 752 417 400 792 762 412 3938 782 747 414 400 785 758 411 3929 782 747 414 400 785 758 411 39210 781 746 417 402 795 763 413 39611 775 748 415 400 784 760 414 39412 775 748 415 400 784 760 414 39413 781 746 417 402 795 763 413 39614 787 740 416 397 789 752 415 38815 779 745 413 397 781 750 409 38616 781 745 414 399 783 752 409 38617 784 739 412 396 778 751 411 39118 781 748 415 399 783 756 410 39219 781 748 415 399 783 756 410 39220 779 744 414 399 784 754 409 38921 783 745 413 397 783 755 412 39222 780 744 411 396 779 758 408 39223 783 746 417 400 791 758 412 39424 779 746 416 400 791 763 413 39525 780 736 414 396 783 753 409 39226 774 749 410 398 776 756 406 39227 780 742 416 399 785 756 409 39228 775 740 414 398 782 753 409 39129 784 748 414 398 789 757 411 39230 777 741 411 396 779 758 407 39331 778 747 411 396 780 756 406 393

Max /Min 787 736 417 396 795 750 417 386

Nagda

Itarsi BinaDate

Itarsi Bina

Nagda

Voltage Profile During the Month of March - 2016

IndoreVoltage Profile During the Month of February- 2016

DateIndore

Minutes Of 51st OCC of MP 24

Page 27: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

I

S. No.

NAME OF THE TRANSMISSION LINE / (FINANCED BY)

ROUTE LENGTH

CIRCUIT KMS.

DATE OF COMPL- ETION

DATE OF COMMI-

SSIONING

A. 400 KV TRANSMISSION LINES

NIL 0 0Total (A) 0 0

B. 220 KV TRANSMISSION LINES

1

220KV DCDS from 220Kv S/s Daloda to proposed 180 MW Wind Energy Genration Project (wind farm)of M/s D.J. Energy Pvt. Ltd. at Bhatkheda near jaora Dist- Ratlam (2x19.875) (Contributory)

19.875 39.75 April'2015

18.04.2015 (ckt-I)/

20.04.2015 (ckt-II))

22nd ckt. Of 220 kv line Damoh - Tikamgarh line (157.7) (JICA) 157.7 157.70 May'15 28.05.2015

3

220 kv line from Gwalior(400Kv s/s PGCIL) to 220Kv S/s Gwalior II (2x2.51) (JICA) (balance I-ckt)

2.51 2.51 May'15 Comm.on May'15

4LILO of 220kv Rewa-Tons line at 220Kv S/s Sirmour(2x4.9) (PFC-II)

4.9 9.80 July'15 12.10.2015

5

220Kv DCDS line for LILO of one circuit of 220Kv DCDS Badod - Bhanpura line (presently Badod - kota/Modak line) at proposed 220/33Kv sub-station at village Nipaniya, Tahsil- Bhanpura Dist- Mandsaur fo 84.9 MW Wind Energy Genration Project of Marut Shakti Energy India Ltd. Bhopal. (Contr. work)

14.688 29.38 Jan'16 14.01.2016

6220kv S/s Lalghati(Shajapur) - 220 Kv S/s Lahori Oooling S/s of M/s INOX Wind(1x5.995) (Contrib)

5.995 6.00 Feb'16 12.02.2016

7

LILO of one Ckt of 220kv DCDS Pithampur- Rajgarh line at 220kv S/S DHAR by second circuiting of part of existing line from location no.87 upto 220 Kv S/s Dhar including Bay shifting work. (DCDS) (2x0.3)(JICA) (Distt.-Dhar)Note- 0.6cktkm. Comm.on 01.10.2014) balance work

3.3 3.3 Oct'15 17.10.2015

8

220kv DCDS line from proposed 220Kv switching Sub-station at bangrod (Ratlam) - 220 Kv Pooling S/s at Bhaisadabar (Amba) of M/s Kshema Power & Infra (2x28.4) (Contrib)

28.4 56.80 Mar'1612.03.2016

(by tapping )

9

220Kv DCSS line from 220Kv S/s Rajgarh(Dhar) to 100MW wind Energy Power Plant of M/s Cleen Wind Power (Ratlam) Pvt. Ltd. (Earlier M/s Hero Future Ltd.) at Badnawar Dist- Dhar(1x0.631)(contrib)

25.857 25.857 Mar'16 22.03.2016

10LILO of one ckt of Bina-Guna 220Kv line at Ashoknagar 220Kv S/s (2x3.794) (PFC-III)

3.79 7.588 100% 2015-16

C. 132 KV TRANSMISSION LINES

1132 kv DCDS line between Bairagarh s/s(132KV) to Runaha line (2x48.202) (JICA) 48.202 96.40 April'2015 15.04.2015

2132 kv Sitamau- Daloda DCSS line (1x34.317) (JICA) 34.317 34.32 April'2015 20.04.2015

3

132 kv DCDS Line for LILO of Ujjain- Ratadiya S/c line at 132 kv s/s at Bherugarh (2x3.842) (Ckt-I charged on 14.03.2015) Priority

3.842 3.842April'2015

(II ckt )20.04.2015

4

132Kv DCSS line from 132Kv S/s Ichhawar to 50 MW Solar Energy Power plant of M/s Waaneep Solar Pvt. Ltd. at Village Molga,Ichhawar Distt.Bhopal (1X9.5) (Contribution Work)

9.556 9.56 April'2015 25.04.2015

5

132Kv DCSS line from 220Kv S/s Badod - 2x20MW Solar PV Power project of M/s IL&FS Energy devlopement co. Ltd. at Tehsil Badod Distt. Agar (1X12.632) Contributory Work

12.632 12.63 April'2015 28.04.2015

6132 kv Shajapur- Moman Badodia DCDS line (2x25.17) (JICA) 25.17 50.34 May'15 11.05.2015

ANNEXURE - 2.3.4(i)

M.P POWER TRANSMISSION COMPANY LIMITED

TRANSMISSION WORKS COMPLETED DURING 2015-16 (UP TO 31.03.2016)

EHV TRANSMISSION LINES

Minutes Of 51st OCC of MP 25

Page 28: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

7

132kv DCDS line for Diversion of 132 kv Handiya-Nasrullaganj tap line & second circuiting of 132 kv Handiya-Nasrullaganj line and * 132 kv DCSS Tap line for proposed 132kv S/s GOPALPUR (Ckt.Km.-36.62) = (2x7.9+1x3.35+1x17.47) (GoMP) (Note- tap line completed on April 2013)

25.37 33.27May'15 June'15

25.05.2015 03.06.2015

8 132 kv Datia Interconnector (2x6.2) ( JICA ) 6.2 12.40 May'15 29.05.2015

9

132 kv DCDS Line for LILO of Ujjain- Ingoriya line at existing 132 kv s/s Ratadiya (2x1.684) (Priority)

1.684 3.37 May'15 29.05.2015

10

132Kv DCSS line from 132 Kv S/s Vijaypur - 50MW Solar PV Power project of M/s Renew Solar Energy(TN)Pvt. Ltd. at village Hulpur Distt. Sheopur (1X1.2) (Contributory Work)

1.2 1.20 May'15 07.05.2015

11

132Kv DCSS line from 132 Kv S/s Sitamau - 132Kv Pooling S/s at 40MW Solar PV Power project of M/s Focal Energy Solar India Pvt. Ltd. at village Cchoti Patlasi & Kochariakhedi, Sitamau Distt. Mandsour (1X0.43) (Contributory Work)

0.43 0.43 May'15 30.05.2015

12

132Kv DCSS line from 220kv S/s MandiDeep -M/s Proctor & Gamble MandiDeep (DIST.-Bhpoal) DCSS line (1x8.973) (Contributory)

8.973 8.973 June'15 19.06.2015

13132 kv DCDS Dewas (220KV) to Shankargarh (Dewas bypass) line (2x5.6) (JICA) 5.6 11.20 June'15 30.06.2015

14LILO of one S/C ckt of 132 KV Chhegaon - Khargone 132Kv DCDS Line at Andad(Bediya) (2x6.33) (PFC-II)

6.33 12.66 June'15 25.06.2015

15

LILO of one ckt of 132 KV Amarkantak-- Rajmilan line at 132Kv S/s Dongrital Distt- Singrauli for power supply to M/s APMDCL & Ms MPJCL (contributory)

0.141 0.28 June'15 20.06.2015

16132 kv DCSS Damoh (220Kv )-Batiyagarh line on 220Kv Towers (1x39.95) (JICA)

39.95 39.95 July'15 17.07.2015

17132 kv DCSS Sheopur-Baroda line (1x33.481) (JICA)

33.481 33.48 July'15

Completed but Part line charged on 16.06.2015

18132 kv DCSS line between 132KV Ganj Basoda to Saharwasa (1x28.927)

28.927 28.93 July'15 06.07.2015

19Stringing of 3rd conductor from Bina to Mungaoli (31.30) (ADB-III)

31.3 31.30 July'15charged on 30.12.2015

20LILO of malanpur -- Ambah 132KV line at Badagaon (Dimni)(2x2.5) PFC- 2.5 5.00 Oct'15 14.10.2015

21Malanpur -- Gohad 132KV DCSS line (1x14.55) ADB-III 14.55 14.55 Oct'15 28.10.2015

22132KV Gwalior-II Hastinapur DCSS line (JICA counter part)(1x23.276) 23.276 23.28 Oct'15 07.12.2015

23LILO of 132Kv Sironj-Maksudangarh line at 132Kv S/s Lateri (2x6.7)PFC-saving

6.7 13.40 Nov'15 09.11.2015

24132Kv Moman Badodiya- Nalkheda DCSS line (1x28.383)(PFC-II)

28.383 28.38 Nov'15 03.11.2015

25

132Kv DCSS line from 132Kv S/s Banmore for power supply of 25WVA to M/s Amba Shakhty Udyog Ltd. Banmore Dist. Gwalior.(1x0.631) (Contributory work)

0.631 0.63 Nov'15 06.11.2015

26132kv Pipariya 220kv- Bareli DCSS line (1x33.983) (JICA)

33.983 33.98 Dec'2015 02.12.2015

27132 kv DCSS Julwaniya (400kv-)-Sendhwa line (1x27.648)(JICA)

27.648 27.648 Dec'2015 03.12.2015

28132 kv DCSS line between 220KV Harda s/s and 132KV Khirkiya s/s (1x38.799) ( Part line 3.11cktkm charged on 04.12.2013) (JICA)

35.689 35.69 Dec'2015 14.12.2015

29132Kv Chapda-Sivni DCDS line (1x20.63) (Revised) (PFC-II)

20.63 20.63 Dec'2015 09.12.2015

30

132Kv DCDS line for LILO of one ckt. Of 132Kv DCDS Balaghat-Seoni line at proposed Lalbarra S/s for power supply on 33Kv to PHE Department Balaghat for Lalbarra Water supply project (2x0.725) (Contributory work)

0.725 1.45 Dec'2015 27.12.2015

31132Kv DCSS line for LILO of one ckt. Of 132Kv Bhopal- Mandideep line at Bagroda for power supply to AKVN (2x0.9) (Contributory work)

0.9 1.80 Dec'2015 27.12.2015Minutes Of 51st OCC of MP 26

Page 29: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

32LILO of 132Kv Mungaoli Traction feeder at 132Kv S/s Mungaoli (4x7.8+2x0.7)(4x7.8+1x0.7ckt.km line charged on 30.12.2015 by tapping ) (ADB-III)

8.5 31.90 Dec'2015 30.12.2015

33132 kv DCSS Line from 220Kv S/s Shujalpur - 132Kv S/s Kalapipal (1x16.428) PFC-III

16.428 16.43 Dec'2015 22.12.2015

34132 kv DCSS Chhatarpur - Laundi line (1x49.29)(JICA)

49.29 49.29 Jan'16 08.01.2016

35 LILO of one circuit of 132Kv Chhindwara - Sarni line at 132Kv S/s Umreth(2x0.5) (GoMP)

0.5 1.00 Jan'16 22.01.2016

36132 kv DCSS Line from 220Kv S/s Kotar-132Kv S/s Rampur Baghelaan line, by stringing 2nd ckt.220Kv S/s Kotar to 132Kv Prism II Line (1x7.47+ 19.3 (JICA)

26.77 26.77 Feb'16 31.03.2016

37 LILO of Badnagar 220 - Ratlam 132Kv SC line at Bilpank 132 kv S/s (2x2.82) PFC-II

2.82 5.64 Feb'16 14.02.2016

382nd Ckt.of 132 KV Rewa - Mangawan line (Dist. Rewa ) (JICA) (30.428 Cktkm comm.on 21.07.2014) balance work

2.05 2.05 Nov'15 25.11.2015

39

132Kv DCSS line from 220 kv Badnagar Sub-station to 50 MW Wind Power Plant of MK/s Orange Berchha Wind Power Ltd. at Badnagar (1x22.50) (Contributory work)

22.5 22.50 Mar'16 29.03.2016

40132Kv line from 220 kv Badnagar Sub-station to Wind Power Project of M/s Suzlan Gujrat Wind Park (1x24.37) (Contributory work)

24.37 24.37 Mar'16 29.03.2016

41 132 kv DCSS Alot-Tal line (1x19.5) (PFC-II) 19.50 20 Mar'16 31.03.2016

Minutes Of 51st OCC of MP 27

Page 30: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

II.

S. No.

NAME OF SUBSTATION / (DISTRICT) / (FINANCED BY)

No.OF X-mer &

Cap.(MVA)

EFFECTIVE CAPACITY

MVA

DATE OF COMPL-ETION

DATE OF COMMI-

SSIONING

A. 400 KV SUBSTATIONS

1 Nagda (ADDL.) (Distt. Ujjain) (JICA) 1x315 315.00 Aug'15 28.08.2015

22x80 MVAR Reactor at 400Kv S/s Bhopal (1No. 80MVAR charged on 27.08.2015) (JICA)

- - Aug'15

27.08.2015 (1No.

80MVAR charged on 27.08.2015)

3 50 MVAR Reactor at 400Kv S/s Pithampur ( ) - - Aug'15 28.08.2015

4 50 MVAR Reactor at 400Kv S/s Nagda ( ) - - Jun'15 20.06.2015

5Katni 400Kv S/s, addl. 315 MVA Transformer (JICA)

1x315 315.00 Nov'15 03.11.2015

B. 220 KV SUBSTATIONS

a. 220 KV NEW SUBSTATIONS

1Julwaniya 220/132kv S/s at 400kv s/s (Distt. Badwani) (2x160+40 MVA) (JICA)

1x160 160 Aug'1521.08.2015

(1No. Charged)

2Sirmour 220/132kv S/s (Distt. Rewa) (2x160+40 MVA) (PFC-II)

1x160 160 Oct'15 12.10.2015

3

Upgradation of Pithampur 132Kv S/s to 220/132kv 1x160MVA with 1no.220Kv X-mer bay,BC bay, 2no. 200Kv feeder bay & 1no 132KV X-mer bay (Distt.Dhar) PFC-III

1x160 160 Mar'16 15.03.2016

4 Upgradation of Ashoknagar 132Kv S/s to 220kv with 2no.220Kv feeder bay & 1x160MVA (Distt. Asahoknagar) PFC-III

1x160 160 Mar'16 30.03.2016

b. 220KV ADDITIONAL TRANSFORMERS

1Pithampur 220/132 Kv S/s, Addl. 160 MVA Transformer (Priority)

1x160 160 May'15 27.05.2015

2Bina 220/132 Kv S/s, Addl. 160 MVA Transformer (Priority)

1x160 160 Aug'15 11.08.2015

3Indore S/Z 220/132 Kv S/s, Aug. 120 to 160MVA Transformer (Priority)

0.00 40 Sept'15 30.09.2015

4Dewas 220/132 Kv S/s, Addl. 160 MVA Transformer (Priority)

1x160 160 Oct'15 07.10.2015

5Chhindwara 220/132 Kv S/s, Addl. 160 MVA Transformer (PFC-III)

1x160 160 Nov'15 05.11.2015

6Anuppur 220/132 Kv S/s, Addl. 160 MVA Transformer ( Anuppur) (GoMP)

1x160 160 Nov'15 08.11.2015

7Shivpuri 220/132 kv s/s Addl. 160 MVA X-mer (Distt.Shivpuri) JICA

1x160 160 Mar'2016 16.03.2016

C. 132 KV SUBSTATIONS

a. 132KV NEW SUBSTATIONS

1 Shankargarh 132kv s/s (Distt.Dewas) (JICA) 1x40 40 April'15

17.04.2015 (from 33Kv) &

09.07.15 (from 132Kv)

2 Budhera 132kv s/s (Distt.Tikamgarh) (JICA) 1x40 40 April'15 10.04.2015

3 Batiygarh 132kv s/s (Distt.Damoh) (JICA) 1x40 40 July'15 22.07.2015

4 Saharwasa 132kv s/s (Distt.Vidisha) PFC-II 1x40 40 Aug'15 14.08.2015

5 Nalkheda 132kv s/s (Distt.Shajapur) PFC-II 1x40 40 Aug'15

17.08.2015 (33Kv side) & 04.11.2015

(from 132Kv)

6Badagaon 132kv s/s with 1x40MVA X-mer (Distt.Morena) PFC-III

1x40 40 Oct'15 16.10.2015

7Dongari Tal 132kv s/s (Distt. Sidhi/Singroli) (contr. Work)

1x20 20 Dec'2015 01.12.2015

8 Lalbarra 132kv s/s (Distt. Balaghat)(contr. Work) 1x40 40 Dec'2015 29.12.2015

9 Bagroda 132kv s/s (Distt. Bhopal)(contr. Work) 1x40 40 Dec'2015 29.12.2015

EHV SUB - STATIONS

Minutes Of 51st OCC of MP 28

Page 31: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

10Hastinapur (New S/s) (Distt.Gwalior) (40 MVA)(JICA)

1x40 40 Dec'2015 19.12.2015

11 Sivni 132kv s/s (Distt.Indore) PFC-II 1x40 40 Dec'2015 15.12.2015

12 Lateri 132kv s/s (Distt.Vidisha) (Priority) 1x40 40 Dec'2015 31.12.2015

13Mungaoli 132kv s/s (Distt.Ashoknagar) 1x63 (ADB-III) (Dist.-Ashoknagar)

1x63 63 Dec'2015 30.12.2015

14Gohad 132kv s/s (Distt. Bhind) 1x63 MVA(ADB-III)

1x63 63 Dec'2015 03.12.2015

15Kalapipal 132kv s/s with 1 no. 132 kv feeder bay & 1x40 MVA (Distt. Sajapur ) (PFC-III)

1x40 40 Dec'2015 22.12.2015

16 Andad (Bediya)132kv s/s (Distt.Khargone) PFC -II 1x40 40 FEB'16 22.02.2016

17Umreth 132kv s/s (Distt. Chhindwara ) 1x40 MVA GoMP

1x40 40 FEB'16 20.02.2016

18Bilpank 132kv s/s with 1x40 MVA (Distt. Ratlam ) PFC-III

1x40 40 FEB'16 16.02.2016

19 Eshagarh132kv s/s (Distt. Ashoknagar) JICA 1x40 40 Mar'16 22.03.2016

20 Tal 132kv s/s (Distt. Ratlam) PFC-II 1x40 40 Mar'16 31.03.2016

Minutes Of 51st OCC of MP 29

Page 32: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

S. No.

NAME OF THE TRANSMISSION LINECKT.KMS.

Expected month of

completion

PROGRESS IN %

A. 400 KV TRANSMISSION LINES

1LILO of both Ckt of 400kv DCDS Nagda - Rajgarh line at 400kv S/S Badnawar (DCDS)(4x6.112)

24.448 - 3%

Sub Total (A) 24 0B. 220 KV TRANSMISSION LINES

1LILO of one Ckt of 220kv DCDS Bhopal - Ashta line at 220kv S/S Mugaliya chhap. (DCDS)

52 Jun-16 52%

2 2nd Ckt of 220kv Satna - Chhatarpur line (152) 160 Mar-17 8%

3LILO of one Ckt of 220kv DCDS Ashta - Dewas line at 220kv S/S Chapda (DCDS) (2x32.782)

66 - 1%

4 220Kv DCDS line from Pithampur-Depalpur line (2X31) 62 - 34%

5220Kv FCFS line for LILO of both Ckt. Of Badnagar -Ratlam D/C line at 400Kv S/s Badnawar (2x1+4x8)

34 - 4%

6 220Kv DCDS Julwaniya- Kukshi (2X58) 116 - 8%

7 220Kv DCSS Shujalpur- Narsinghgarh line (1X43.6) 44 - 5%

8 220Kv DCDS line from Gwalior(Malanpur)- Morena (2X29.25) 58.5 Dec-16 6%

9LILO of Indore 400 -Pithampur 220Kv line at Pithampur-II 220Kv S/s in Indore (1x7.38)

7.38 Jun-16 69%

11 LILO of 220kv Katni -Satna at PGCIL Satna (2x0.7) 66 - 40%C. 132 KV TRANSMISSION LINES1 132kv Birsinghpur -Shahdol DCSS line (1x48) 48 - 4%2 132kv Ichhawar -Sehore DCSS line (1x35.298) 35.298 - 15%3 132 kv DCDS Ujjain(220 kv) -Chandrawatiganj line (2x35.42) 70.84 Oct-16 79%4 132 kv DCSS Dewas-Barotha line (1x23) 23 Dec-16 60%5 132 kv DCSS Ghatabillod-Betama line (1x18) 18 Mar-17 29%6 132kv Jeerapur -Susner DCSS line (1x32) 32 - 33%7 132kv DCSS Gautampur -Depalpur line (1x19) 19 Mar-17 20%8 132kv Nagda(220kv)- Kachrod-Jaora DCSS line (1x64) 64 Mar-17 18%9 132kv DCSS Shujalpur( 220kv) -Pachhore DCSS line (1x35.5) 35.5 Mar-17 18%

10 132kv Mugaliya Chaap - Sehore DCSS line (1x24) 24 Mar-17 5%

11 132 kv DCSS line between 132Kv S/s Nasrullaganj & 220KV Itarsi s/s(1x53.209) 53.209 - 21%

12 LILO of S/C ckt of 132 KV Seoni-Lakhnadon line at 220kv S/S Seoni (2x20) 40 - 5%

13 132 kv DCSS Line from 220Kv S/s Shivpuri-132Kv Bairad (1x32.859) 32.859 Mar-17 32%14 132 kv DCSS from 220Kv S/s Datiya-132kv S/s Indergarh (1x27.1) 27.1 - 46%15 2nd ckt of Chhatarput- Khajuraho line upto location no. 73(1x8.31) 8.31 - 16%16 2nd ckt of 132Kv Chhatarpur- Khajuraho line (1x0.5+33.2) 33.7 - 23%

132 kv Ashoknagar - Eshagarh DCSS line (1x37) (Est.Sanc.-0281dtd. 17.03.2015 for Rs.1895.67)

(i) 132 kv Ashoknagar - Eshagarh DCSS line (1x18.5) (from Ashoknagar end) 18.5(ii)132 kv Ashoknagar - Eshagarh DCSS line (1x18.5) (from Eshagarh end) 18.5

ANNEXURE-2.3.4(ii)TRANSMISSION WORKS UNDER PROGRESS (AS ON 31.03.2016)

Jun-1617 46%

Minutes Of 51st OCC of MP 30

Page 33: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

18LILO of Both circuit of 132 kv DCDS Gwalior(Mahalgaon) - Dabra/Karera line at 220 KV S/s Gwalior II) (2x2x7.87)

55.09 - 39%

19 132 kv DCSS line from 132Kv S/s Kymore-132Kv S/s Barhi (1x35) 35 Mar-17 4%

20 132 kv Sirmour - Katra DCDS line (2x37.67) 75.34 - 18%21 132 kv DCSS Guna-Eshagarh line (1x72) 72 - 17%22 132 kv Sagar-Rahatgarh DCSS line (1x55) 55 Mar-17 13%23 2nd Ckt. Of 132 Kv DCSS Tikamgarh- Budhera line (32.46) 32.46 Apr-16 83%24 132 kv DCSS Datiya- Bhander line (1x23.45) 23.45 Jun-16 32%25 132 kv DCSS Khurai- Khimlasa line (1x20.937) 20.937 - 13%

262nd Ckt.of 132Kv DCSS Katangi tap line tapped to one ckt. Of 132Kv Balaghat-Seoni line (1x0.5+35.8)

36.3 Apr-16 37%

27 132 kv DCSS line from220Kv S/s Chichli - 132Kv Karapgaon (1x31.059) 31.059 - 3%28 132 kv DCSS line Mehgaon - Pratappura (1x28) 28 Jun-16 34%31 132 kv DCSS Ashoknagar - Kothiya line (1x27.5+4x2.5) 37.5 Jun-16 52%32 LILO of 132Kv Vidisha- Bairasiya line at salamatpurr (2x0.162) 0.324 Mar-17 20%33 132 kv DCDS Line Chichli - Udaypura (2x47) (On 220Kv Tower) 94 - 16%34 2nd Ckt. Of 132 Kv DCSS Gairatganj- Vidisha line (48.30) 48.3 May-16 95%35 2nd ckt of 132kv Bairagarh - Shyampur line (1x0.5+4x1.9+19) 27.1 Apr-16 88%36 132 kv DCSS line from 132Kv S/s Porsa - 132Kv S/s Ambah (1x23.059) 23.059 Feb-17 37%37 132 kv DCSS line from 132Kv S/s Lahar - 132Kv S/s Seondha (1x15.5) 15.5 Jun-16 74%38 132 kv DCSS line Datiya - Dabra (1x30) 30 Feb-17 43%39 132 kv DCSS Line from 220Kv S/s Barwaha - 132Kv S/s Kishangarh (1x57.139) 57.139 Dec-16 32%40 132Kv DCSS line from 220Kv S/s Rajgarh to 132Kv S/s Jhabua (1x50) 50 - 10%41 132 kv DCSS Panagar - Patan line (1x22.749) 22.749 - 4%

42 132Kv DCSDS line from 220Kv S/s Panagar to 132Kv S/s Katangi (2x27.96) 55.92 Sep-16 15%

43132Kv DCDS line for LILO of both circuit of 132Kv Banmore Morena/Hetampur DCDS line for 220Kv S/s Morena(2x0.616+2x3.122)

- Jan-17 -

44 132 kv DCSS Badnagar - Chhayan Line (1x31) 31 Mar-17 5%45 2nd ckt of 132kv Kukshi - Alirajpur line (1x1+36) 37 - 13%46 132 kv DCSS Dhar - Teesgaon line (1x15.35) 15.35 - 4%

47LILO of 132 kv Chhegaon - Nepanagar Line at 132Kv S/s Pandhana(1x1.895) (This line is proposed in place of Chhegaon -Pandhana Estt. Sanc.no. 0121dtd.06.08.2014)

1.895 Mar-17 20%

48 LILO of 132 kv Manawar - Kukshi Line at 132Kv S/s Singhana(2x3.1) 6.2 Mar-17 20%

49LILO of Khargone - Julwaniya DP line(132Kv) at Talakpura (2x1.1+1x0.8)(This line is proposed in place of Julwaniya- Talakpura line Rev. Estt. Sanc.no. 0245 dtd.15.01.2016 for Rs.185.40lac.)

3 - 20%

50 132 kv DCDS Beragarh - Intkhedi (2x8.7+4x1.5) 23.4 - 30%51 132 kv DCSS Udaipura - Silvani line (1x25.8) 25.8 - 13%52 132 kv DCSS Narsinghpur - Devnagar (1x23) 23 - 13%53 132 kv DCDS Narsinghpur - Karakbel line (2x23) 46 - 9%54 2nd ckt of Betul - Gudgaon line (1X57) 57 Apr-16 88%

Minutes Of 51st OCC of MP 31

Page 34: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

S.No.

NAME OF THE SUBSTATION

EFFECTIVE

CAPACITY MVA

Expected month of

completion

PROGRESS IN %

A. 400 KV SUBSTATIONS

2Bhopal (Sukhi Sewaniya) 400/220 kv s/s Addl. 315 MVA X-mer (Distt.Bhopal)

315 Mar-17 1%

3 Chhegaon 400/220 kv s/s Addl. 315 MVA X-mer (Distt.Khandwa) 315 Mar-17 9%

B. a 220 KV SUBSTATIONS

1Julwaniya 220/132kv S/s at 400kv s/s (Distt. Badwani) (2x160+40 MVA) (1No. 160MVA Charged on 21.08.2015)

320 Sep-16 79%

2Shajapur 220kv S/s (Distt. Shajapur) (2x160+40 MVA) (1x160MVA charged on 04.03.2015)

320 Sep-16 90%

3 Mugaliachhap(Bhopal) 220kv (New S/s)(1x160+40) 160 Jun-16 85%

4 Gwalior-II 220kv (New S/s)(2x160+40) (1x160 charged on31.3.2015) 160 Sep-16 90%

5 Upgradation of Chapda 132Kv S/s to 220kv with 1x160MVA (Distt. ) 160 - 2%

6 Upgradation of Depalpur 132Kv S/s to 220kv with 1x160MVA(Distt. ) 160 - 5%

7 Upgradation of Kukshi 132Kv S/s to 220kv with 1x160MVA (Distt. ) 160 - 4%

8Morena 220/132kv S/s 1x160 +1x63 MVA +2No.220Kv FB +4No.132Kv FB+6No.33Kv FB+BC +Capacitor Bank

160 Dec-16 31%

C. 132 KV SUBSTATIONS(a) NEW SUBSTATIONS1 Bairad 132kv s/s(Dist.-Shivpuri ) 40 Mar-17 13%2 Barahi 132kv s/s (Distt.Katni) 40 Mar-17 11%

3 Karapgaon 132kv s/s (Distt-Narsinghpur) 40 Mar-17 14%

Minutes Of 51st OCC of MP 32

Page 35: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

4 Rahatgarh132kv s/s (Distt.Sagar) 40 Mar-17 25%5 Indergarh 132kv s/s (Distt.Datia) 40 Mar-17 25%6 Biston 132kv s/s (Distt. ) 1x40 MVA 40 - 4%7 Agrod 132kv s/s (Distt. ) 1x40 MVA 40 - 8%8 Chhayan 132kv s/s (Distt. ) 1x40 MVA 40 Mar-17 7%9 Talakpura 132kv s/s (Distt. ) 1x40 MVA 40 - 5%

10 Devnagar 132kv s/s (Distt. Narsighpur) ) 1x40 MVA 40 - 5%

11 Khimlasa 132kv s/s (Distt. ) 1x40 MVA 40 - 3%

12 Pratappura 132kv s/s (Distt.Bhind ) 1x40 MVA 40 Jun-16 90%13 Chinaur 132kv s/s (Distt. ) 1x40 MVA 40 Dec-16 2%14 Bhander 132kv s/s (Distt. Datia) 1x63 63 Jun-16 90%15 Kothiya 132kv s/s (Distt. Guna ) 1x40 MVA 40 Jun-16 63%16 Intkhedi 132kv s/s (Distt. ) 1x63 MVA 63 - 26%17 Silvani 132kv s/s with 1x40 MVA (Distt. ) 40 - 2%

18Katangi 132kv s/s with 1 no. 132 kv feeder bay & 1x40 MVA (Distt. - Jabalpur)

40 Sep-16 43%

19Kishangarh 132kv s/s with 1 no. 132 kv feeder bay & 1x40 MVA (Distt. Dewash)

40 Dec-16 42%

Minutes Of 51st OCC of MP 33

Page 36: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Feb-16 Mar-16 Feb-16 Mar-16

Commissinary HQ 23:53 23:51 23:45 23:43

District HQ 23:56 23:55 23:40 23:45

Tehsil HQ 23:51 23:49 23:25 23:33

Rural -Mixed 23:34 23:30 22:53 22:50

Rural -DLF 23:34 23:30 23:13 23:12

Rural -Irrigation 9:57 9:58 9:43 9:36

Feb-16 Mar-16 Feb-16 Mar-16

Commissinary HQ 23:44 23:46 23:48 23:47

District HQ 23:54 23:55 23:52 23:52

Tehsil HQ 23:52 23:52 23:43 23:45

Rural -3Phase 23:44 23:37 23:20 23:16

Rural -1Phase 23:45 23:43 23:30 23:28

Total Rural 9:54 9:52 9:52 9:49

Discoms wise Average Supply Hours

PARTICULARS

PARTICULARS

West Zone MP

East Zone Central Zone

Minutes Of 51st OCC of MP 34

Page 37: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Name of EHV Substation Name of 33KV feeder Date of charging of feeder

132 KV Shahpura 33 KV PGCIL 31.03.2015

Name of EHV Substation Name of 33KV feeder Date of charging of feeder

220KV Indore (Jetpura)-II 33KV PGCIL-II feeder 24.08.2014220KV Nimrani 33KV Maral Overseas 08.06.2015

132KV Raukhedi 33KV DLF-I 01.03.201433KV DLF-II 01.03.201433KV Feeder No.1 31.12.2014

132KV Chandrawatiganj 33KV Feeder No.2 31.12.201433KV Feeder No.3 31.12.2014

Name of EHV Substation Name of 33KV feeder Date of charging of feeder

220KV Barod 33KV M&B-I&II

132KV Susner 33KV Evershine 21.05.2014132KV Maxi Sudheer Project 18.02.2015

33KV Enercon-I33KV Enercon-II33KV M&B-I33KV M&B-II

132KV Ratadia 33KV Chintaman Ganesh33KV Kachnariya33KV Lasuldiya Kelwa

132KV Sonkatch 33KV Industrial (MPAKVN)

220KV

Annexure-2.4(ii)LIST OF 33KV FEEDERS UNDER MPPKVVCL, JABALPUR

(For which group to be allocated)

132KV

132KV

UJJAIN REGION

INDORE REGION

LIST OF 33KV FEEDERS UNDER MPPKVVCL, INDORE

132KV Agar

(For which group to be allocated)

220KV

132KV

132KV Nalkheda

Minutes Of 51st OCC of MP 35

Page 38: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Annexure-2.4(ii)

Name of EHV Substation Name of 33KV feeder Date of charging of feeder

220 KV Betul 33 KV Industrial 13.06.2014220 KV Vidisha 33 KV ISanchi 30.01.2015

33 KV Barna 19.02.201433 KV Boras 19.02.2014

132 KV Khilchipur 33 KV Khajla 29.10.201433 KV Nagar Palika 09.03.201433 KV Water Works 09.03.201433 KV Jatkheda-I 07.05.201433 KV Jatkheda-II 07.05.2014

132 KV Runaha 33 KV Runaha 15.04.201533 KV Nazirabad 18.09.201533 KV Ramgarh 19.09.2015

132 KV MACT Bhopal 33 KV Bairagarh chichli-2 15.11.2014132 KV Gopalpur 33 KV AE, PHE 27.02.2015

33 KV AIIMS Hospital 29.02.201633 KV AIIMS Residence 29.02.2016

Name of EHV Substation Name of 33KV feeder Date of charging of feeder

220 KV Sagalgarh 33 KV Mangrol 30.05.2014

132 KV Morena 33 KV Bagchini 02.02.2015132 KV Datia 33 KV Karapura 17.05.2014132 KV Ron 33 KV Mangarh 21.11.2013132 KV Morar 33 KV Readymade Garment 22.08.2014132 KV Motizheel 33 KV Transport Nagar 30.05.2015

LIST OF 33KV FEEDERS UNDER MPPKVVCL,BHOPAL (For which group to be allocated)

BHOPAL REGION

132 KV Biora

220 KV

132 KV

132 KV Shyampur

132 KV Bareli

132 KV

GWALIOR REGION

220 KV

132 KV Amrawad Khurd

Minutes Of 51st OCC of MP 36

Page 39: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Minutes Of 51st OCC of MP 37

Page 40: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Minutes Of 51st OCC of MP 38

Page 41: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Minutes Of 51st OCC of MP 39

Page 42: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

A. ThermalStn. Name UNIT No. Capacity

MW February-16 March-163 120 0.00 0.004 120 0.00 0.00

PH II 240 0.00 0.005 210 146.48 155.74

PH III 210 146.48 155.74TOT 450 146.48 155.74

1 62.5 0.00 0.002 62.5 0.00 0.004 62.5 0.00 0.00

PH I 187.5 0.00 0.006 200 73.20 93.757 210 103.46 25.33

PH II 410 176.65 119.078 210 129.103 101.879 210 106.124 44.20

PH III 420 235.227 146.0610 250 139.008 146.4611 0 84.75

PH IV 250 139.008 231.20TOT 1267.5 550.89 496.34

1 210 54.369 95.522 210 83.73 116.66

PH I 420 138.10 212.183 210 19.47 113.084 210 102.34 119.60

PH II 420 121.80 232.685 500 308.70 296.88

PH III 500 308.70 296.88TOT 1340 568.60 741.74

1 600 194.16 0.002 600 160.74 73.20

PH1 600 354.90 73.20

3057.5 1620.87 1467.02AMARKANTAK POWER HOUSE-I RETIRED FROM SERVICE WEF 01.04.2009

B. HydelCapacity

MW February-16 March-16115.0 66.89 55.83172.0 67.30 47.8699.0 48.02 33.44

386.0 182.21 137.12193.0 91.11 68.56160.0 39.08 14.03107.0 26.05 9.3590.0 21.57 21.23

315.0 24.74 26.4620.0 0.00 0.0060.0 0.00 0.0030.0 2.30 2.5645.0 0.00 0.0022.5 0.00 0.0020.0 5.38 2.6660.0 13.06 0.67

1186.0 288.34 204.74915.0 173.02 123.44917.5 184.21 131.50

CapacityMW February-16 March-16

Indira Sagar Hydel Project 1000 153.370 127.070Omkareshwar Hydel Project 520 71.755 63.652

Unitwise / Stationwise Genration in MUAnn 4.1

AM

AR

KA

NTA

KSA

TPU

RA

SAN

JAY

GA

ND

HI

MPPGCL THERMAL

SSTP

S

Station NameGANDHISAGARR.P.SAGARJ.SAGARCHAMBALM.P.CHAMBALPENCHM.P.PENCHBARGITONSBIRSINGHPURB.SGR(DEOLONDH)B.SGR(SILPARA)RAJGHATM.P.RAJGHATB.SGR(JINHA)MADIKHEDATOTAL HYDELMPPGCL HydelMPSEB HYDEL Share

C. NHDC (Ex-Bus)Station Name

Minutes Of 51st OCC of MP 40

Page 43: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

S No. Source Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 TotalA.

1 Thermal 1153.43 1294.73 1139.02 1086.32 843.93 1664.96 1873.90 1613.33 1767.04 1699.19 1471.76 1319.75 16927.342 Hydel 141.33 125.30 102.47 103.87 237.87 191.06 212.00 192.60 210.46 207.53 179.04 130.09 2033.613 Total 1294.76 1420.03 1241.49 1190.19 1081.80 1856.02 2085.89 1805.93 1977.49 1906.72 1650.79 1449.84 18960.96

B.1 Indira Sagar 166.41 143.44 56.90 119.70 412.89 114.01 175.90 131.88 179.57 162.72 151.35 125.57 1940.362 Omkareshwar 75.33 74.45 36.88 75.08 200.32 59.60 78.22 60.87 81.06 75.75 71.76 63.66 952.963 MPPMCL Schedule from Central Sector of WR 1480.43 1667.87 1373.88 1455.87 1275.16 1599.69 1752.12 1714.68 1785.89 1717.76 1678.47 1815.62 19317.454 MPPMCL Schedule from Central Sector ER 28.81 34.50 23.16 40.70 19.16 31.76 36.65 37.97 36.97 26.41 37.24 33.96 387.305 Total MPPMCL Schedule from Central Sector (WR+ER) 1509.24 1702.37 1397.04 1496.57 1294.32 1631.45 1788.77 1752.65 1822.86 1744.17 1715.71 1849.58 19704.756 Deviation Energy of (WR+ER) -39.27 -34.34 -49.81 -57.83 -93.96 -98.04 -29.95 -52.77 -54.60 -43.93 -38.34 -113.91 -706.777 Schedule From DVC ER 200.99 249.67 161.97 201.83 184.65 209.01 210.32 200.72 198.03 193.07 187.98 214.09 2412.338 Schedule From Sugen 21.36 21.48 20.16 7.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 70.869 LANCO Amk 129.84 176.97 170.46 182.40 107.78 125.63 202.04 195.61 189.76 168.82 173.00 170.89 1993.20

10 SASAN 764.50 810.96 856.43 973.70 890.58 891.54 913.52 949.60 945.97 938.11 921.39 1009.76 10866.0611 ESSAR 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0012 J P Nigri 140.42 51.26 176.26 175.09 304.29 296.09 321.18 307.71 316.86 317.39 248.05 168.85 2823.4513 MB Power 0.00 18.42 9.32 29.32 35.16 65.34 105.59 128.04 129.91 128.47 119.77 108.88 878.2114 NTPC BADARPUR 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0015 Himachal Pradesh HYDAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0016 BARH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0017 Schedule from Sardar Sarovar 71.63 133.95 95.48 105.61 444.54 112.82 53.57 41.95 44.74 35.93 30.17 23.83 1194.2118 SCH to Railway from RGPPL_ebid 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 44.13 131.23 138.94 314.3019 Schedule from SEZ 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0020 Schedule from Rihand+Matatila 7.00 2.75 4.41 9.28 16.12 8.13 7.99 5.79 5.00 7.32 7.11 3.69 84.61

21 Medium Term Power Purchase from CSPDCL through PTC agaisnt PPA CSPDCCL dtd. 18.09.2012 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

22 Medium Term Power Purchase from Balco through PTC agaisnt PPA Balco dtd. 18.09.2012 Including Short term purchase against MTOA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

23 Additional Power Purchase 0.00 0.00 0.00 0.04 0.00 0.00 15.41 0.13 0.00 0.00 12.06 0.10 27.7424 Energy Exchange 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0025 Banking of Energy -259.40 -80.13 -46.66 -536.78 -611.76 -420.43 115.49 613.51 595.82 245.89 -44.58 -150.76 -579.7826 Sale of Power -145.17 -110.74 -276.27 -68.88 -166.08 -26.35 -11.98 -4.58 -43.71 -16.41 -8.30 -86.65 -965.1027 Total MP Schedule (Including Railway) 2440.42 2976.96 2568.61 2575.94 2499.61 2893.23 3721.91 4191.13 4205.25 3806.90 3493.60 3451.30 38824.8428 Total MP Drawal (Including Railway) 2401.15 2942.61 2518.79 2518.10 2405.65 2795.19 3691.96 4138.35 4150.65 3762.97 3455.26 3337.38 38118.0829 Wheeled Energy of Tawa HEG 0.00 0.00 0.00 0.01 4.47 1.77 3.47 6.65 5.54 3.25 0.84 0.00 26.0030 Wheeled Energy of Wind Farm 6.40 8.76 8.53 13.68 9.61 5.40 3.01 2.25 7.38 4.45 10.09 13.04 92.6031 Wheeled Energy of Solar Plant 15.36 16.37 13.40 9.86 10.29 13.91 14.44 12.72 14.81 14.27 14.86 16.72 167.0132 Wheeled Energy of Ascent Hydro 1.23 1.24 0.06 0.19 0.52 1.26 1.39 1.32 1.28 1.06 0.82 1.28 11.6833 POWER PURCHASE by MPPMCL from BLA Power + JP BINA (Intra State STOA) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0034 Deviation Energy of MPPGCL Thermal -1.25 -5.39 2.96 -9.37 0.49 16.87 14.06 14.41 19.06 13.49 16.08 11.19 92.6135 Sale of Power to SEZ by MPPMCL (Not Included in State Supply) -23.93 -27.17 -27.34 -29.51 -28.15 -26.82 -27.15 -24.30 -25.62 -25.53 -24.71 -26.85 -317.0836 Energy Purchased by MP from Wind Farm 95.03 145.08 145.68 248.69 197.73 114.15 69.31 60.65 69.52 50.29 109.86 140.59 1446.5737 Energy Purchased by MP from Solar Plant 56.53 48.66 53.34 42.36 44.19 59.87 64.99 54.83 63.42 69.20 74.67 84.38 716.43

38 Firm / Infirm Energy of HEG Mandideep+Hindalco+HEG Tawa +Trimula Ind. purchase by MP +Wheeled enrgy of CPP / IPP 14.24 7.32 7.00 3.61 11.79 42.96 61.71 35.37 95.02 68.43 79.59 9.73 436.77

39Purchased from ASN Biomass Katni + RDM Care Ind. Biogas Pariyat + Pragya Energy Pvt. Ltd. Biogas Richhai+ Arya Energy Kotma + Orient Green Power Limited, Gadarawara Bio-Mass+Shaliwahna (CHH+Umariya)

9.89 12.36 9.25 9.31 11.94 13.61 11.47 7.72 9.31 16.91 6.12 10.09 127.98

40 Deviation Energy of ISP 2.59 3.90 1.61 2.39 0.70 2.59 3.10 2.08 2.90 1.92 2.02 1.50 27.3041 Schedule Energy of BLA Power against LTOA 8.90 6.74 0.49 0.00 0.00 1.74 6.63 1.68 8.31 5.68 6.85 5.23 52.2342 Schedule Energy of JP BINA Power against LTOA 137.48 0.00 0.00 0.00 14.35 70.28 157.04 83.52 187.51 123.21 150.43 1.08 924.9043 Import from bargi Left Bank Canal Power House + ISP NVDA 0.26 0.01 0.01 0.01 0.98 1.07 1.36 2.14 2.23 2.05 1.48 1.34 12.9444 Chambal Complex Excess / less Overshare by MP -2.78 -2.60 -5.36 -9.76 -38.14 -37.03 -48.76 -48.80 -30.14 -26.57 -29.10 -17.40 -296.4645 Rajghat Hydel Power Station Excess / Less Overshare by MP -0.02 -0.02 -0.04 0.22 1.96 -0.02 0.52 2.57 3.00 0.50 -0.02 0.02 8.6846 State Supply (Ex-Power st. Bus) 4281.50 4822.95 4090.97 4214.27 4371.53 5133.25 6395.72 6376.15 6847.93 6256.30 5773.75 5255.25 63819.5847 AVERAGE DAILY (Ex-Bus) 142.72 155.58 136.37 135.94 141.02 171.11 206.31 212.54 220.90 201.82 199.09 169.52 174.3748 MINIMUM DAILY (MP Periphery) 108.61 137.66 101.80 111.57 122.01 139.30 159.47 187.82 207.84 142.92 183.89 142.57 101.8049 MAXIMUM DAILY (MP Periphery) 149.60 155.88 155.52 157.44 163.81 185.56 224.87 215.58 216.25 215.63 201.25 184.64 224.8750 State Supply (Ex-Power st. Bus):- YEAR : 2014-15 4512.41 4609.06 4315.82 4115.84 4214.10 4486.53 5436.77 6049.66 5693.67 4755.95 4798.88 4025.83 57014.5151 Year ((15-16)-(14-15))*100/Year (14-15) -5.12 4.64 -5.21 2.39 3.74 14.41 17.64 5.40 20.27 31.55 20.31 30.54 11.9452 Unshedule L/S : Year-2015-16 0.00 0.00 0.00 0.00 0.00 0.21 0.99 0.00 0.00 0.00 0.00 0.00 1.2053 Frequency Correction -5.58 -4.09 -5.30 -4.21 -1.73 5.33 1.68 1.18 2.12 1.00 0.57 1.64 -7.3854 Restricted Requirement : Year-2015-16 4275.92 4818.87 4085.68 4210.06 4369.80 5138.79 6398.39 6377.33 6850.05 6257.30 5774.32 5256.89 63813.4055 Shedule L/S : Year-2015-16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0056 Un-Restricted Requirement : Year-2015-16 4275.92 4818.87 4085.68 4210.06 4369.80 5138.79 6398.39 6377.33 6850.05 6257.30 5774.32 5256.89 63813.40

ENERGY BALANCE SHEETYear : 2015 - 16

All figures in Million Unit

M.P. Availability

Exchange with other States / Systems

Minutes Of 51st OCC of MP 41

Page 44: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

S.NO. Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Yr 15-16C.1 DEMAND MET 6141 6369 6416 6453 6093 7597 9655 10089 10728 10737 10130 9070 107372 LOAD RELIEF 0 0 0 0 0 0 0 0 0 0 0 0 03 LOAD SHEDDING 0 0 0 0 0 0 0 0 0 0 0 0 0D.1 DEMAND MET 7259 7250 7210 7303 7580 8256 9117 9153 9367 9437 8381 8280 94372 LOAD RELIEF 0 0 0 0 0 0 0 0 0 0 0 0 03 LOAD SHEDDING 0 0 0 0 0 0 0 0 0 0 0 0 0F. REGISTERED MAXIMUM 7259 7250 7210 7303 7580 8488 9823 10112 10841 10737 10130 9070 10841G. COMPUTED MAXIMUM DEMAND 7250 7247 7191 7303 7590 8488 9831 10126 10841 10737 10136 9070 10841H. UNRESTRICTED MAXIMUM DEMAND 7250 7247 7191 7303 7590 8488 9831 10126 10841 10737 10136 9070 10841I.1. Div. Head Quarters 23:46 23:44 23:45 23:43 23:46 23:45 23:47 23:51 23:49 23:46 23:48 23:47 23:462. District Head Quarters 23:50 23:49 23:48 23:50 23:50 23:48 23:48 23:54 23:52 23:50 23:52 23:52 23:503. Tahsil Head Quarters 23:39 23:33 23:25 23:33 23:39 23:35 23:36 23:44 23:44 23:42 23:43 23:45 23:384. Rural -Mixed 23:08 23:06 22:51 23:01 23:16 23:10 23:09 23:21 23:21 23:14 23:20 23:16 23:115. Rural -DLF 23:16 23:15 23:02 23:11 23:22 23:20 23:19 23:30 23:31 23:27 23:30 23:28 23:216. Rural -Irrigation 9:45 9:45 9:37 9:41 9:46 9:45 9:47 9:52 9:51 9:49 9:52 9:49 9:47J LOAD FACTOR % 81.92 89.07 78.63 77.02 76.89 82.93 86.07 85.82 83.29 76.16 78.33 74.21 80.86

S.N PARTICULARS Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Yr 15-16A. INTGRATED FREQUENCY

1 MAXIMUM 50.23 50.32 50.31 50.20 50.12 50.13 50.11 50.15 50.14 50.15 50.13 50.13 50.322 MINIMUM 49.74 49.75 49.75 49.77 49.77 49.72 49.80 49.79 49.78 49.87 49.87 49.85 49.72

B. INSTANTANEOUS FREQUENCY1 MAXIMUM 50.55 50.55 50.55 50.33 50.25 50.33 50.33 50.28 50.32 50.39 50.39 50.35 50.552 MINIMUM 49.50 49.55 49.60 49.58 49.55 49.52 49.62 49.64 49.59 49.68 49.71 49.68 49.50

C. AVG FREQUENCY 49.99 49.98 50.00 49.99 49.98 49.95 49.98 49.99 49.98 50.00 50.01 50.00 49.99D. % TIME WHEN FREQUENCY WAS

1 ABOVE 51.5 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.002 50.05 TO 51.5 Hz 24.86 19.44 25.70 19.07 14.97 10.78 16.97 21.46 17.55 22.84 23.89 21.29 19.873 49.9 TO 50.05 Hz 60.20 64.74 65.01 70.29 70.00 59.83 69.10 67.06 66.07 67.97 70.49 70.02 66.754 49.7 TO 49.9 Hz 14.35 15.10 9.09 10.43 14.72 28.74 13.79 11.33 16.19 9.10 5.52 8.59 13.095 49.5 TO 49.7 Hz 0.59 0.72 0.20 0.21 0.31 0.65 0.14 0.15 0.19 0.09 0.10 0.10 0.296 49.2 TO 49.5 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.007 48.8 TO 49.2 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.008 48.5 TO 48.8 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.009 BELOW 48.5 Hz 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ENERGY BALANCE SHEET : Demand & Sypply HoursYear : 2015 - 16

MORNING PEAK (MAX)

EVENING PEAK (MAX)

Average Power Supply per day to

FREQUENCY ANALYSIS YEAR 2015-16

Minutes Of 51st OCC of MP 42

Page 45: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

THER.Incl Aux

THER. Excl Aux

HYD. ISP OSP

Total IPPs Injecti

on

Total CPPs Injecti

on

Total CSS DVC ER Sugen Lanco Sasan Essar JP

NigriMB

Power

HP Hydel (C+P+T+K)

SSP

SCH to

Railway

SEZ Banking Sale Pur

Total MTO

Aat MP

STOA

Rihand+Matatila-Rajghat

Total SCH UN SCH TOTAL

1:00 50.03 2134 1942 172 50 30 305 258 2757 2339 236 0 211 1279 0 345 136 0 41 189 0 -203 -6 0 0 -56 10 4520 7278 4448 -73 0 7205 0 0 0 7206 7206

2:00 50.08 2109 1919 162 38 26 305 254 2703 2231 218 0 186 1278 0 345 128 0 41 189 0 -203 -16 0 0 -43 10 4366 7070 4235 -131 0 6939 0 0 0 6939 6939

3:00 50.06 2112 1922 148 38 22 305 256 2691 2175 216 0 182 1279 0 345 128 0 41 189 0 -203 -1 0 0 -41 10 4321 7012 4321 0 0 7012 0 0 0 7013 7013

4:00 50.06 2099 1910 158 76 36 306 252 2737 2149 213 0 186 1277 0 345 124 0 41 189 0 -203 -11 0 0 -40 10 4280 7017 4282 2 0 7019 0 0 0 7019 7019

5:00 50.10 2099 1910 160 154 73 307 242 2845 2158 219 0 197 1278 0 345 124 0 41 189 0 -203 -38 0 0 -61 10 4258 7104 4294 36 0 7139 0 0 0 7140 7140

6:00 50.08 2137 1944 178 275 126 309 240 3071 2255 221 0 215 1282 0 345 142 0 41 190 0 -203 -57 0 0 -58 10 4384 7455 4273 -110 0 7345 0 0 0 7345 7345

7:00 50.03 2298 2091 294 471 211 330 235 3632 2356 279 0 251 1282 0 340 170 0 41 190 0 -203 -3 0 0 3 10 4716 8347 4874 158 0 8506 0 0 0 8509 8509

8:00 50.07 2510 2284 346 546 253 391 306 4125 2445 321 0 261 1286 0 340 186 0 41 190 0 131 -2 5 0 -59 10 5157 9282 5083 -74 0 9208 0 0 0 9208 9208

9:00 50.06 2592 2359 373 579 268 409 387 4376 2459 326 0 261 1285 0 340 189 0 42 190 0 135 0 57 0 -93 10 5201 9577 5232 31 0 9608 0 0 0 9609 9609

10:00 50.07 2607 2373 314 535 253 406 475 4356 2458 327 0 261 1275 0 344 189 0 42 189 0 123 0 78 0 -112 10 5184 9540 5122 -62 0 9478 0 0 0 9478 9478

11:00 50.06 2512 2286 282 441 218 378 554 4159 2453 315 0 261 1275 0 344 187 0 42 189 0 123 0 60 0 -119 10 5140 9299 5108 -32 0 9267 0 0 0 9267 9267

12:00 50.09 2436 2217 215 231 115 355 583 3717 2429 290 0 258 1266 0 344 182 0 44 189 0 130 0 47 0 -124 10 5064 8781 4782 -281 0 8499 0 0 0 8500 8500

13:00 50.10 2403 2187 227 220 96 343 573 3646 2441 281 0 258 1260 0 332 178 0 44 187 0 131 0 61 0 -118 10 5065 8710 5152 87 0 8797 0 0 0 8797 8797

14:00 50.08 2415 2198 203 151 80 346 533 3511 2443 280 0 258 1256 0 335 184 0 44 187 0 131 0 51 0 -102 10 5077 8588 4984 -93 0 8495 0 0 0 8495 8495

15:00 50.03 2373 2159 172 135 66 345 459 3336 2440 278 0 251 1261 0 334 178 0 44 188 0 131 0 22 0 -87 10 5051 8387 5000 -51 0 8336 0 0 0 8338 8338

16:00 50.07 2348 2137 182 156 70 349 342 3237 2437 270 0 251 1262 0 335 177 0 44 188 0 131 0 12 0 -65 10 5052 8288 5027 -25 0 8264 0 0 0 8265 8265

17:00 50.07 2365 2152 268 235 100 354 196 3305 2452 288 0 258 1263 0 346 182 0 44 188 0 131 0 24 0 -55 10 5131 8436 5133 2 0 8439 0 0 0 8439 8439

18:00 50.13 2349 2137 261 211 102 342 84 3137 2463 269 0 258 1265 0 346 184 0 44 188 0 -203 0 22 0 -20 10 4826 7963 4589 -236 0 7727 0 0 0 7727 7727

19:00 50.03 2354 2142 329 219 106 331 126 3254 2408 265 0 251 1261 0 345 179 0 44 188 0 -203 -12 0 0 -42 10 4694 7948 4845 151 0 8099 0 0 0 8102 8102

20:00 50.06 2371 2158 313 206 106 324 183 3291 2413 265 0 251 1262 0 345 178 0 44 188 0 -203 -30 0 0 -43 10 4680 7971 4634 -47 0 7925 0 0 0 7926 7926

21:00 50.03 2323 2113 255 80 46 321 220 3035 2403 254 0 244 1263 0 345 170 0 44 188 0 -203 -24 0 0 -48 10 4645 7680 4511 -134 0 7546 0 0 0 7548 7548

22:00 50.13 2249 2047 203 96 48 318 253 2965 2360 229 0 233 1263 0 346 160 0 44 188 0 -203 -54 0 0 -21 10 4554 7519 4347 -207 0 7312 0 0 0 7312 7312

23:00 50.03 2248 2046 235 214 104 321 265 3185 2403 254 0 240 1269 0 345 160 0 44 188 0 -203 -9 0 0 -48 10 4655 7839 4591 -64 0 7775 0 0 0 7776 7776

24:00 50.07 2220 2020 195 88 52 315 275 2946 2386 256 0 236 1271 0 346 160 0 42 188 0 -203 -10 0 0 -51 10 4631 7576 4501 -130 0 7447 0 0 0 7447 7447

Avg. 50.07 2319 2111 235 227 109 338 315 3334 2373 265 0 238 1271 0 343 166 0 43 189 0 -64 -11 18 0 -63 10 4777 8111 4724 -53 0 8058 0 0 0 8059 8059

00 TO 06 HRS. 50.07 2115 1925 163 105 52 306 250 2801 2218 221 0 196 1279 0 345 130 0 41 189 0 -203 -21 0 0 -50 10 4355 7156 4309 -46 0 7110 0 0 0 7110 7110

06 TO 12 HRS. 50.06 2492 2268 304 467 220 378 424 4061 2433 310 0 259 1278 0 342 184 0 42 189 0 73 -1 41 0 -84 10 5077 9138 5033 -43 0 9094 0 0 0 9095 9095

12 TO 18 HRS. 50.08 2376 2162 219 185 86 346 365 3362 2446 278 0 255 1261 0 338 181 0 44 188 0 76 0 32 0 -74 10 5034 8395 4981 -53 0 8343 0 0 0 8343 8343

06TO 18 HRS. 50.07 2434 2215 261 326 153 362 394 3711 2440 294 0 257 1270 0 340 182 0 43 189 0 74 0 37 0 -79 10 5055 8767 5007 -48 0 8719 0 0 0 8719 8719

18 TO 24 HRS. 50.06 2294 2088 255 151 77 322 220 3113 2395 254 0 242 1265 0 345 168 0 44 188 0 -203 -23 0 0 -42 10 4643 7756 4571 -72 0 7684 0 0 0 7685 7685

TotAvl.

Act.Drl Deviation

Intra State STO

A

DEMAND MET

Load Shedding

REST. DEMAN

D

UNREST.

DEMAND

Hourly Average Own Generation, Schedule Drawal , Actual Drawal & Demand Month :- February 2016

FIGURES IN MW

Hrs. FREQ.

Own Generation Schedule from

Minutes Of 51st OCC of MP 43

Page 46: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

THER.Incl Aux

THER. Excl Aux

HYD. ISP OSP

Total IPPs Injecti

on

Total CPPs Injecti

on

Total CSS DVC ER Sugen Lanco Sasan Essar JP

NigriMB

Power

HP Hydel (C+P+T+K)

SSP

SCH to

Railway

SEZ Banking Sale Pur

Total MTO

Aat MP

STOA

Rihand+Matatila-Rajghat

Total SCH UN SCH TOTAL

1:00 50.01 1940 1766 117 122 75 22 233 2334 2414 272 0 228 1298 0 210 129 0 30 187 0 -203 -120 0 0 16 5 4467 6801 4403 -63 0 6737 0 0 0 6740 6740

2:00 50.04 1923 1750 99 95 58 22 212 2236 2356 266 0 204 1299 0 213 124 0 30 185 0 -203 -91 0 0 16 5 4405 6641 4254 -151 0 6490 0 0 0 6491 6491

3:00 50.05 1897 1726 86 61 43 22 209 2148 2328 263 0 196 1299 0 215 124 0 30 185 0 -203 -68 0 0 16 5 4389 6536 4315 -74 0 6462 0 0 0 6463 6463

4:00 50.03 1888 1718 86 95 50 22 204 2176 2311 264 0 189 1300 0 215 122 0 30 186 0 -203 -118 0 0 16 5 4318 6493 4233 -84 0 6409 0 0 0 6411 6411

5:00 50.03 1877 1708 92 163 79 22 202 2266 2324 259 0 177 1300 0 215 121 0 30 186 0 -203 -162 0 0 15 5 4268 6534 4227 -41 0 6493 0 0 0 6496 6496

6:00 50.04 1895 1724 133 209 99 22 212 2400 2362 260 0 194 1300 0 216 119 0 30 187 0 -203 -134 0 0 18 5 4354 6754 4296 -59 0 6696 0 0 0 6698 6698

7:00 50.05 2032 1849 239 231 106 23 220 2669 2487 340 0 251 1301 0 217 159 0 31 188 0 -203 -43 0 0 52 5 4785 7454 4738 -47 0 7407 0 0 0 7408 7408

8:00 50.05 2117 1926 258 233 108 24 312 2860 2529 379 0 258 1300 0 217 175 0 31 187 0 -203 -8 0 0 37 5 4907 7767 4813 -94 0 7673 0 0 0 7674 7674

9:00 50.03 2119 1929 267 256 123 23 407 3005 2533 343 0 255 1300 0 217 172 0 31 187 0 -203 -50 0 0 -16 5 4772 7777 4704 -68 0 7709 0 0 0 7711 7711

10:00 50.04 2083 1896 187 222 108 23 506 2941 2517 306 0 255 1299 0 217 159 0 32 180 0 -203 -34 2 0 -40 5 4693 7634 4554 -139 0 7495 0 0 0 7496 7496

11:00 50.03 1992 1812 177 203 99 23 573 2888 2473 253 0 224 1300 0 217 144 0 32 179 0 -203 -39 2 0 -66 5 4521 7409 4510 -11 0 7398 0 0 0 7400 7400

12:00 50.06 1918 1745 144 163 78 22 597 2750 2407 239 0 211 1306 0 217 129 0 32 179 0 -203 -49 0 0 -77 5 4397 7147 4102 -295 0 6852 0 0 0 6853 6853

13:00 50.06 1897 1727 131 152 73 22 592 2697 2360 242 0 211 1304 0 223 128 0 33 178 0 -203 -159 0 0 -73 5 4249 6946 4245 -4 0 6942 0 0 0 6943 6943

14:00 50.04 1893 1723 112 140 67 22 557 2622 2313 244 0 197 1308 0 223 129 0 33 183 0 -203 -121 0 0 -59 5 4251 6873 4138 -112 0 6761 0 0 0 6762 6762

15:00 50.00 1890 1720 95 129 64 22 502 2533 2282 244 0 194 1310 0 223 123 0 33 185 0 -203 -145 0 0 -49 5 4202 6735 4125 -77 0 6658 0 0 0 6661 6661

16:00 50.03 1898 1727 104 156 71 22 407 2487 2261 245 0 197 1312 0 223 123 0 33 188 0 -203 -157 0 0 -20 5 4208 6695 4121 -87 0 6608 0 0 0 6610 6610

17:00 50.05 1910 1738 162 167 78 22 277 2446 2278 246 0 197 1307 0 223 123 0 33 190 0 -203 -186 0 0 7 5 4221 6666 4291 70 0 6737 0 0 0 6738 6738

18:00 50.09 1892 1722 154 151 73 24 158 2282 2189 246 0 187 1308 0 223 123 0 34 192 0 -203 -197 0 0 35 5 4142 6424 4055 -87 0 6337 0 0 0 6338 6338

19:00 49.96 1987 1808 294 218 92 25 154 2590 2354 306 0 251 1307 0 222 153 0 34 193 0 -203 -113 0 0 40 5 4549 7140 4663 113 0 7253 0 0 0 7265 7265

20:00 50.04 2039 1855 318 273 138 26 182 2793 2476 348 0 251 1307 0 223 172 0 34 192 0 -203 -157 0 0 24 5 4672 7465 4591 -81 0 7384 0 0 0 7385 7385

21:00 50.01 2017 1835 206 209 106 26 210 2593 2485 346 0 245 1306 0 223 169 0 34 192 0 -203 -191 0 0 24 5 4633 7226 4497 -136 0 7090 0 0 0 7093 7093

22:00 50.08 2004 1823 162 173 86 26 234 2503 2457 331 0 245 1306 0 223 164 0 33 192 0 -203 -209 0 0 28 5 4571 7074 4402 -169 0 6905 0 0 0 6906 6906

23:00 50.01 1999 1819 161 227 116 25 240 2589 2473 291 0 245 1307 0 220 164 0 33 191 0 -203 -115 0 0 21 5 4631 7219 4570 -61 0 7159 0 0 0 7162 7162

24:00 50.04 1987 1808 149 166 92 22 261 2498 2463 271 0 241 1301 0 216 138 0 32 189 0 -203 -81 0 0 19 5 4591 7089 4432 -159 0 6930 0 0 0 6931 6931

Avg. 50.04 1962 1786 164 176 87 23 319 2554 2393 284 0 221 1303 0 219 141 0 32 187 0 -203 -114 0 0 -1 5 4466 7021 4387 -80 0 6941 0 0 0 6943 6943

00 TO 06 HRS. 50.03 1903 1732 102 124 67 22 212 2260 2349 264 0 198 1299 0 214 123 0 30 186 0 -203 -116 0 0 17 5 4367 6627 4288 -79 0 6548 0 0 0 6550 6550

06 TO 12 HRS. 50.04 2044 1860 212 218 104 23 436 2852 2491 310 0 242 1301 0 217 156 0 31 183 0 -203 -37 1 0 -18 5 4679 7531 4570 -109 0 7422 0 0 0 7424 7424

12 TO 18 HRS. 50.05 1897 1726 127 149 71 23 416 2511 2280 245 0 197 1308 0 223 125 0 33 186 0 -203 -161 0 0 -27 5 4212 6723 4162 -50 0 6674 0 0 0 6675 6675

06TO 18 HRS. 50.04 1970 1793 169 184 87 23 426 2682 2386 277 0 220 1305 0 220 141 0 32 185 0 -203 -99 0 0 -23 5 4445 7127 4366 -79 0 7048 0 0 0 7050 7050

18 TO 24 HRS. 50.02 2005 1825 215 211 105 25 214 2594 2451 316 0 246 1305 0 221 160 0 33 191 0 -203 -144 0 0 26 5 4608 7202 4526 -82 0 7120 0 0 0 7124 7124

TotAvl.

Act.Drl Deviation

Intra State STO

A

DEMAND MET

Load Shedding

REST. DEMAN

D

UNREST.

DEMAND

Hourly Average Own Generation, Schedule Drawal , Actual Drawal & Demand Month :- March 2016

FIGURES IN MW

Hrs. FREQ.

Own Generation Schedule from

Minutes Of 51st OCC of MP 44

Page 47: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

SCH Demand Met

O/U DRL

SCH LS

Unsch LS

Restricted

Demand

Unrestricted

DemandSCH Demand

MetO/U DRL

SCH LS

Unsch LS

Restricted

Demand

Unrestricted

DemandSCH Demand

MetO/U DRL

SCH LS

Unsch LS

Restricted

Demand

Unrestricted

DemandTotal Sch Total

Drawal

1:00 50.03 2300 2299 -1 0 0 2299 2299 2495 2517 22 0 0 2517 2517 2287 2213 -74 0 0 2214 2214 189 176

2:00 50.08 2252 2226 -26 0 0 2226 2226 2403 2382 -22 0 0 2382 2382 2242 2155 -88 0 0 2155 2155 189 176

3:00 50.06 2171 2193 22 0 0 2193 2193 2250 2310 60 0 0 2310 2310 2418 2339 -79 0 0 2340 2340 189 170

4:00 50.06 2156 2180 24 0 0 2180 2180 2259 2305 46 0 0 2305 2305 2449 2363 -87 0 0 2363 2363 189 172

5:00 50.10 2164 2185 21 0 0 2185 2185 2253 2343 90 0 0 2343 2343 2518 2437 -82 0 0 2437 2437 189 175

6:00 50.08 2239 2247 8 0 0 2248 2248 2339 2401 62 0 0 2401 2401 2616 2520 -97 0 0 2520 2520 190 176

7:00 50.03 2394 2543 149 0 0 2544 2544 2438 2684 245 0 0 2685 2685 3179 3094 -85 0 0 3095 3095 190 185

8:00 50.07 2612 2649 37 0 0 2649 2649 2811 2851 40 0 0 2851 2851 3576 3533 -43 0 0 3533 3533 190 175

9:00 50.06 2650 2670 20 0 0 2670 2670 3014 3078 64 0 0 3078 3078 3682 3680 -2 0 0 3680 3680 190 180

10:00 50.07 2650 2685 35 0 0 2685 2685 3087 3086 -1 0 0 3086 3086 3536 3529 -7 0 0 3529 3529 189 178

11:00 50.06 2650 2648 -2 0 0 2648 2648 3050 3032 -18 0 0 3032 3032 3411 3408 -3 0 0 3408 3408 189 179

12:00 50.09 2572 2521 -52 0 0 2521 2521 2882 2775 -107 0 0 2775 2775 3099 3032 -68 0 0 3032 3032 189 172

13:00 50.10 2445 2467 22 0 0 2467 2467 2670 2844 175 0 0 2844 2844 3337 3324 -13 0 0 3324 3324 187 162

14:00 50.08 2374 2350 -24 0 0 2350 2350 2710 2735 25 0 0 2735 2735 3274 3244 -29 0 0 3245 3245 187 165

15:00 50.03 2335 2327 -8 0 0 2328 2328 2640 2650 9 0 0 2650 2650 3207 3187 -20 0 0 3187 3187 188 172

16:00 50.07 2344 2327 -17 0 0 2327 2327 2640 2649 9 0 0 2650 2650 3138 3111 -26 0 0 3112 3112 188 176

17:00 50.07 2375 2335 -40 0 0 2335 2335 2665 2651 -14 0 0 2652 2652 3256 3272 16 0 0 3272 3272 188 180

18:00 50.13 2386 2391 4 0 0 2391 2391 2633 2437 -197 0 0 2437 2437 2749 2715 -34 0 0 2715 2715 188 185

19:00 50.03 2594 2669 75 0 0 2670 2670 2452 2582 131 0 0 2583 2583 2667 2660 -7 0 0 2660 2660 188 188

20:00 50.06 2633 2643 10 0 0 2643 2643 2571 2601 29 0 0 2601 2601 2508 2487 -21 0 0 2487 2487 188 194

21:00 50.03 2567 2547 -20 0 0 2548 2548 2540 2508 -31 0 0 2509 2509 2360 2299 -61 0 0 2300 2300 188 192

22:00 50.13 2499 2442 -57 0 0 2442 2442 2467 2447 -20 0 0 2447 2447 2326 2236 -90 0 0 2236 2236 188 187

23:00 50.03 2488 2457 -31 0 0 2458 2458 2621 2724 102 0 0 2724 2724 2453 2410 -43 0 0 2410 2410 188 184

24:00 50.07 2386 2383 -3 0 0 2383 2383 2619 2599 -20 0 0 2599 2599 2305 2290 -15 0 0 2290 2290 188 175

Avg. 50.07 2427 2433 6 0 0 2433 2433 2605 2633 28 0 0 2633 2633 2858 2814 -44 0 0 2814 2814 189 178

00 TO 06 HRS. 50.07 2214 2222 8 0 0 2222 2222 2333 2376 43 0 0 2376 2376 2422 2338 -84 0 0 2338 2338 189 174

06 TO 12 HRS. 50.06 2588 2619 31 0 0 2620 2620 2880 2918 37 0 0 2918 2918 3414 3379 -35 0 0 3380 3380 189 178

12 TO 18 HRS. 50.08 2376 2366 -10 0 0 2366 2366 2660 2661 1 0 0 2661 2661 3160 3142 -18 0 0 3142 3142 188 173

06TO 18 HRS. 50.07 2482 2493 10 0 0 2493 2493 2770 2789 19 0 0 2790 2790 3287 3261 -26 0 0 3261 3261 189 176

18 TO 24 HRS. 50.06 2528 2523 -5 0 0 2524 2524 2545 2577 32 0 0 2577 2577 2436 2397 -40 0 0 2397 2397 188 187

Discomwise Hourly Average Schedule Drawal , Actual Drawal &Over(+)/Under(-) DrawalMonth :- February 2016

FIGURES IN MW

Hrs. FREQ.

EZONE CZONE WZONE Railway

Minutes Of 51st OCC of MP 45

Page 48: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

SCH Demand Met

O/U DRL

SCH LS

Unsch LS

Restricted

Demand

Unrestricted

DemandSCH Demand

MetO/U DRL

SCH LS

Unsch LS

Restricted

Demand

Unrestricted

DemandSCH Demand

MetO/U DRL

SCH LS

Unsch LS

Restricted

Demand

Unrestricted

DemandTotal Sch Total

Drawal

1:00 50.01 2112 2108 -5 0 0 2108 2108 2204 2250 46 0 0 2251 2251 2264 2196 -67 0 0 2197 2197 187 184

2:00 50.04 2069 2044 -25 0 0 2044 2044 2132 2146 14 0 0 2146 2146 2198 2118 -80 0 0 2118 2118 185 182

3:00 50.05 2021 2008 -13 0 0 2008 2008 2025 2089 64 0 0 2090 2090 2235 2174 -62 0 0 2174 2174 185 191

4:00 50.03 1999 1995 -4 0 0 1996 1996 1995 2052 57 0 0 2053 2053 2244 2180 -64 0 0 2181 2181 186 182

5:00 50.03 2008 1994 -14 0 0 1995 1995 2008 2073 65 0 0 2073 2073 2307 2246 -61 0 0 2247 2247 186 181

6:00 50.04 2030 2035 6 0 0 2036 2036 2030 2118 88 0 0 2119 2119 2402 2357 -45 0 0 2358 2358 187 186

7:00 50.05 2113 2132 20 0 0 2133 2133 2121 2259 139 0 0 2260 2260 2848 2820 -28 0 0 2820 2820 188 196

8:00 50.05 2129 2120 -8 0 0 2121 2121 2269 2290 20 0 0 2290 2290 3034 3073 39 0 0 3073 3073 187 191

9:00 50.03 2117 2093 -24 0 0 2094 2094 2293 2289 -4 0 0 2290 2290 3075 3129 55 0 0 3130 3130 187 197

10:00 50.04 2116 2083 -33 0 0 2084 2084 2251 2222 -28 0 0 2223 2223 2989 2994 5 0 0 2995 2995 180 195

11:00 50.03 2130 2091 -39 0 0 2091 2091 2201 2167 -33 0 0 2168 2168 2939 2950 11 0 0 2951 2951 179 190

12:00 50.06 2110 2017 -93 0 0 2018 2018 2095 1974 -121 0 0 1974 1974 2733 2674 -59 0 0 2675 2675 179 187

13:00 50.06 2023 1977 -46 0 0 1977 1977 1934 1978 44 0 0 1979 1979 2802 2805 3 0 0 2805 2805 178 182

14:00 50.04 1966 1892 -74 0 0 1893 1893 1972 1943 -29 0 0 1944 1944 2727 2748 21 0 0 2748 2748 183 177

15:00 50.00 1937 1858 -79 0 0 1859 1859 1931 1896 -34 0 0 1897 1897 2680 2719 38 0 0 2720 2720 185 185

16:00 50.03 1928 1847 -81 0 0 1847 1847 1917 1881 -37 0 0 1881 1881 2663 2690 27 0 0 2690 2690 188 191

17:00 50.05 1916 1856 -61 0 0 1856 1856 1917 1899 -19 0 0 1899 1899 2724 2789 65 0 0 2789 2789 190 194

18:00 50.09 1933 1877 -56 0 0 1878 1878 1945 1854 -91 0 0 1854 1854 2453 2412 -41 0 0 2412 2412 192 194

19:00 49.96 2215 2315 101 0 0 2319 2319 2001 2160 158 0 0 2163 2163 2579 2577 -2 0 0 2582 2582 193 201

20:00 50.04 2381 2372 -10 0 0 2372 2372 2285 2288 3 0 0 2289 2289 2539 2517 -23 0 0 2517 2517 192 208

21:00 50.01 2341 2294 -47 0 0 2295 2295 2242 2236 -6 0 0 2237 2237 2372 2357 -16 0 0 2358 2358 192 204

22:00 50.08 2290 2220 -71 0 0 2220 2220 2196 2195 -1 0 0 2195 2195 2315 2287 -28 0 0 2288 2288 192 203

23:00 50.01 2298 2243 -55 0 0 2244 2244 2313 2371 57 0 0 2372 2372 2339 2344 5 0 0 2345 2345 191 201

24:00 50.04 2221 2187 -34 0 0 2187 2187 2331 2303 -28 0 0 2303 2303 2258 2253 -5 0 0 2253 2253 189 188

Avg. 50.04 2100 2069 -31 0 0 2070 2070 2109 2122 13 0 0 2123 2123 2572 2559 -13 0 0 2559 2559 187 191

00 TO 06 HRS. 50.03 2040 2031 -9 0 0 2031 2031 2066 2121 56 0 0 2122 2122 2275 2212 -63 0 0 2213 2213 186 184

06 TO 12 HRS. 50.04 2119 2090 -30 0 0 2090 2090 2205 2200 -5 0 0 2201 2201 2936 2940 4 0 0 2941 2941 183 192

12 TO 18 HRS. 50.05 1951 1885 -66 0 0 1885 1885 1936 1909 -28 0 0 1909 1909 2675 2694 19 0 0 2694 2694 186 187

06TO 18 HRS. 50.04 2035 1987 -48 0 0 1987 1987 2071 2054 -16 0 0 2055 2055 2805 2817 11 0 0 2817 2817 185 190

18 TO 24 HRS. 50.02 2291 2272 -19 0 0 2273 2273 2228 2259 31 0 0 2260 2260 2401 2389 -11 0 0 2390 2390 191 201

Discomwise Hourly Average Schedule Drawal , Actual Drawal &Over(+)/Under(-) DrawalMonth :- March 2016

FIGURES IN MW

Hrs. FREQ.

EZONE CZONE WZONE Railway

Minutes Of 51st OCC of MP 46

Page 49: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Annexure-5.0

System Disturbance / System Incidence :

1. System Disturbance on 12.02.2016 at 220 KV S/s Sidhi: On dated 12.02.2016 at around 18:50 Hrs. M.P system was normal and frequency of National Grid was 50.04Hz. Prior to fault 220 KV Rewa – Tons Ckt – I & II, 132 KV Rampur Bhagalen – Rewa Ckt, 132 KV Amarpatan – Jhinna Ckt were kept open for load management. Consequently complete load of complete load of Rewa and Sidhi region was fed through 220 KV Amarkantak – Sidhi Ckt and 220 KV Birsinghpur (SGTPS) – Rewa Ckt. At 18:58 Hrs. on 12.02.2016, 33 KV, ‘R’& ‘Y’- Phase pole of CB of 132/33 KV, 20 MVA GEC X’mer burst at 220 KV S/s Sidhi, resulting in 33 KV Bus Fault and tripping of 132/33 KV, 40 MVA BHEL X’mer. But there was delayed fault clearance by 132/33 KV, 20 MVA X’mer from 132 KV side as its Master Trip relay (Avana Make) did not operate, consequently fault was fed through 220/132 KV, 160 MVA X’mer and caused current unbalancing in 220/132 KV, 160 MVA X’mer at 132 KV side resulting in tripping of 132 KV incomer of 220/132 KV, 160 MVA X’mer, 132 KV Rewa - Mangawan Ckt, 132 KV Sidhi – Rewa II (Pahariya) Ckt at 220 KV S/s Sidhi. Due to the above tripping interruption occurred at 220 KV S/s Sidhi, 132 KV S/s Sidhi, 132 KV S/s Deosar, 132 KV S/s Mauganj, 132 KV S/s Katra and132 KV S/s Mangawan and there was load loss of about 172.97MW, 74MWH. There was no generation loss and System was normalized in due course of time.

2. System Disturbance on 12.02.2016 & 13.02.2016 at 220 KV S/s Sidhi & 220 KV S/s Rewa: On dated 12.02.2016 & 13.02.2016 at around 22:10 Hrs. M.P system was normal and frequency of National Grid was 49.99Hz. prior to fault 220 KV Rewa – Tons Ckt – I Tap Sirmour Ckt (tapping arrangement is temporary, 220 KV Rewa – Tons Ckt – I will be LILO at 220 Sirmour, LILO work is under process) was opened from Tons HPS end for load management hence 220 KV New S/s Sirmour was being fed through 220 KV S/s Rewa. Also, 220 KV Rewa – Tons Ckt – II, 132 KV Rampur Bhagalen – Rewa Ckt, 132 KV Amarpatan – Jhinna Ckt were kept open for load management. At 22:12 Hrs. on 12.02.2016, 220 KV Amarkantak – Sidhi Ckt tripped on transient fault from both end (indications enclosed as Annexure – III). Consequently complete load of 220 KV S/s Rewa & 220 KV Sidhi shifted on 220 KV Birsinghpur (SGTPS) – Rewa Ckt resulting in over loading and tripping of 220 KV Birsinghpur (SGTPS) – Rewa Ckt and interruption occurred at following S/s:- 220 KV S/s Rewa, 220 KV S/s Sidhi, 220 KV S/s Sirmour, 132 KV S/s Rewa, 132 KV S/s Sidhi, 132 KV S/s Deosar, 132 KV S/s Mauganj, 132 KV S/s Katra, 132 KV S/s Mangawan, 132 KV S/s Rewa II (Sagra/Paharia), 132 KV S/s Rampur Niken, 132 KV Beohari, Jhinna HPS, Silpara HPS, Devlond HPS and 220 KV Hindalco (Industary).

At around 00:23 Hrs. on 13.03.2016, 220 KV Amarkantak – Sidhi Ckt again tripped from both end on transient fault. Consequently interruption again occurred at above mentioned 15 Nos. Sub-stations. Due to the above tripping there was consumer load loss of about 301 MW, 301 MWH at 22:12 Hrs. for about 01 Hour and 326 MW, 162.8 MWH at 00:23 Hrs. on 13.02.2016 for about 30min. There was no generation loss and System was normalized in due course of time.

Minutes Of 51st OCC of MP 47

Page 50: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

3. System Disturbance on 07.03.2016 at 220 KV S/s Sidhi: On dated 07.03.2016 at around 17:05 Hrs. M.P system was normal and frequency of National Grid was 50.16Hz. prior to fault for load management & to restrict the overloading on 400/220 KV Satna ICTs, 220 KV Satna(PG) – Maihar Ckt, 220 KV Tons Rewa Ckt – I & II, 132 KV Satna – Maihar Ckt, 132 KV Satna – Kymore Ckt, 132 Rewa – Rampur Baghelan Ckt and 132 KV Chattarpur – Bijawar Ckt were kept open. At around 17:10 Hrs., 132 KV Satna – Majhgawan Ckt tripped due to R-phase Disk failure at Loc. No.103 and conductor snapping. At the same time LBB protection of 132 KV Satna – Satna Cement Ckt Mal-operated at 220 KV S/s Satna resulting in tripping of 220/132 KV, 160 MVA AREVA make X’mer from 132 KV side at 220 KV S/s Satna, 132/33 KV, 63 MVA X’mer & 40 MVA X’mer at 220 KV S/s Satna, 132 KV Satna – Panna Ckt, 132 KV Satna – Pawai Ckt, 132 KV Satna – Nagod Ckt, 132 KV Satna – Satna Cement, 132 KV Satna – Prism Cement, Interconnector – I & II. Due to the above tripping 132 KV supply failed at 220 KV S/s Satna, 132 KV S/s Majhgawan, 132 KV S/s Satna, 132 KV S/s Rampur Baghelan, 132 KV S/s Nagod, 132 KV S/s Pawai, 132 KV S/s Panna, Satna Cement and Prism Cement and there was consumer load loss of about 117 MW, for about 10 min; 19.5 MWH. At 220 KV S/s Satna & supply at 132 KV S/s Majhgawan was interrupted for about 6 Hrs., hence load loss at 132 KV S/s Majhgawan was about 11 MW for about 6 Hrs.; 66MWH. Thereafter 33 KV Back feed supply was taken at 23:10 Hrs. thus total load loss was 85.5MWH. There was no generation loss and System was normalized in due course of time.

4. System Disturbance on 18.03.2016 at 400 KV S/s Indore: On dated 18.03.2016 at around 01:15 Hrs. M.P system was normal and frequency of National Grid was 50.14Hz. At around 01:22 Hrs. 400 KV ‘R’- Phase CT of 400/220 KV, 315 MVA ICT – IV burst at 400 KV S/s Indore, resulting in 400 KV bus fault at 400 KV S/s Indore. Consequently Bus Bar protection of 400 KV Main Bus – II operated, resulting in tripping of 400/220 KV, 315 MVA ICT – IV, 400/220 KV, 315 MVA ICT – II, 400 KV Bus Tie, 400 KV Indore – Itarsi (PGCIL) – II, 400 KV Indore – ISP Ckt – II, 400 KV Indore – Indore (PGCIL) Ckt – II, 400 KV Indore – Asoj Ckt – I, 400 KV Indore – Asoj Ckt – II. Due to the above tripping there was no interruption in any are, hence there was no consumer load loss. There was no generation loss and System was normalized in due course of time.

Minutes Of 51st OCC of MP 48

Page 51: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Annexure-11.1

S.No. NAME OF SUB-STATION Telemetry Satus

1 Sirmore 220 Not Available2 Gwalior -2 220 Not Available3 Datia 220 Not Available

4 132 KV Susner Not Available5 132 KV Jaora Not Available6 132 KV Delchi(Makdone ) Not Available7 132/33 KV Ratangarh Not Available8 132 KV Kukshi Not Available9 132 KV Umariya Not Available10 132 KV Chapda Not Available11 132 KV Sailana Not Available12 132 KV Agar commissioned13 132 KV Gadarwara commissioned14 132 KV dewas BNP S/s Not Available15 132KV Sitamau Not Available16 132KV Khilchipur 17 132KV Vijaypur Not Available18 132KV Alot Not Available19 132KV Icchawar comisioned20 132KV Suasra Not Available21 132KV Gudgaon dist betul commissioned22 132 KV Mandideep Not Available23 132 KV kymore Not Available24 132 KV Rewa Not Available25 132 KV Satna Not Available26 132 KV Boregaon Not Available27 132 KV Bioara Not Available28 132 KV Ashok Nagar under progress29 132 KV Raisen Not Available30 132 KV Sagar Not Available31 132 KV Sironj Not Available32 132 KV Petlawad Not Available

33 132 KV Chanderi Not Available34 132 KV Arniakala Not Available35 132 KV Nasrullaganj Not Available36 132 KV Sonkach Not Available37 132 KV Kannod Not Available38 132KC Bercha Not Available39 132 KV Poliakalan Not Available40 132KV Momin Barodia Not Available41 132 KV Pachore Not Available

42 132KV Deplapur S/s43 132KV Sanwer S/s44 132KV Ingoria45 132KV Ghosla46 132KV Dewas MSP47 132KV Makshi48 132KV Ratodiya49 132KV Bherogad50 132 KV Agar

COmmissioned

INTERD DISCOM STATIONS

FOR KUMBH MELA

IMPORTANT 220KV Sub STATIONS

FOR RENEWABLE GENERATION INTEGRATION

LIST OF SUB STATIONS WHOS TELEMETRY IS REQUIRED AT SLDC

Minutes Of 51st OCC of MP 49

Page 52: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

SLDC STATUS FIELD STATUS

132KV BUS COUPLER CB FAULTY CLOSE33KV SUZLON-1 MW NOT COMING33KV SUZLON-2 MW NOT COMING33KV SUZLON-2 MVAR NOT COMING33KV ENERCON-1 MW NOT COMING33KV ENERCON-1 MVAR NOT COMING33KV NALKHEDA MW NOT COMING33KV NALKHEDA MVAR NOT COMING33KV DISCOM MW NOT COMING33KV DISCOM MVAR NOT COMING

NOTE:-ALL SOE DATA NEED TO BE VERIFIED.

132/33KV 63 MVA XMER-1 MW NOT COMING132/33KV 40MVA XMER-2 MW NOT COMING132/33KV 40MVA XMER-2 MVAR NOT COMING132KV BUS FREQUENCY NOT COMING33KV BUS VOLTAGE NOT COMING33KV BUS FREQUENCY NOT COMING33KV RAHGARH MVAR NOT COMING

NOTE:-CB OF ALL FEEDERS ARE FAULTYNOTE:-ALL SOE DATA NEED TO BE VERIFIED.

132KV BUS VOLTAGE 2.5132KV BUS FREQUENCY 1.4132KV GAUTAMPURA MW NOT COMING132KV GAUTAMPURA MVAR NOT COMING33KV CAPACITOR BANK-1 14.2 NOT COMING33KV CAPACITOR BANK-2 14 NOT COMING33KV BANEDIYA CB FAULTY33KV DEPALPUR CB FAULTY132KV GAUTAMPURA CB FAULTY33KV BEGANDA CB FAULTY33KV BETMA CB FAULTY

NOTE:-ALL SOE DATA NEED TO BE VERIFIED.

33KV CAP BANK-1 MVAR NOT COMING33KV CAP BANK-2 MVAR NOT COMING33KV BHOURASIA MW NOT COMING33KV BHOURASIA MVAR NOT COMING33KV DEWAS BNP-2 MW NOT COMING33KV DEWAS BNP-2 MVAR NOT COMING33KV OPEN FDR MW NOT COMING

AGAR 132KV S/s

DEPALPUR 132KV S/s

DEWAS BNP 132KV S/s

BHERUGARH 132KV S/s

Annexure-11.2

Minutes Of 51st OCC of MP 50

Page 53: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

33KV OPEN FDR MVAR NOT COMINGNOTE:-CB OF ALL FEEDERS ARE FAULTYNOTE:-ALL SOE DATA NEED TO BE VERIFIED.

GHOSLA 132KV S/s33KV CAPBANK MVAR NOT COMING

NOTE:-CB OF ALL FEEDERS ARE NOT COMINGNOTE:-ALL SOE DATA NEED TO BE VERIFIED.

INGORIA 132KV S/S132/33KV TR3 MW NOT COMING132/33KV TR3 MVAR NOT COMING

NOTE:-CB OF ALL FEEDERS ARE NOT COMINGNOTE:-ALL SOE DATA NEED TO BE VERIFIED.

MAKSI 132KV S/s

132KV RLY TRC-1 MW NOT COMING132KV RLY TRC-1 MVAR NOT COMING33KV CAPBANK MVAR NOT COMING132/33KV TR2 MW NOT COMING132/33KV TR2 MVAR NOT COMING

NOTE:-CB OF ALL FEEDERS ARE NOT COMINGNOTE:-ALL SOE DATA NEED TO BE VERIFIED.

RATADIYA 132KV S/s132KV RLY TRC-2 MW NOT COMING132KV RLY TRC-2 MVAR NOT COMING33KV PANVIHAR MW NOT COMING33KV PANVIHAR MVAR NOT COMING33KV KARTIK MW NOT COMING33KV KARTIK MVAR NOT COMING33KV CAPBANK MVAR NOT COMING

NOTE:-CB OF ALL FEEDERS ARE NOT COMINGNOTE:-ALL SOE DATA NEED TO BE VERIFIED.

SANWER 132KV S/s132/33KV TR2 MW NOT COMING132/33KV TR2 MVAR NOT COMING132/33KV TR3 MW NOT COMING132/33KV TR3 MVAR NOT COMING

NOTE:-CB OF ALL FEEDERS ARE NOT COMINGNOTE:-ALL SOE DATA NEED TO BE VERIFIED.

Minutes Of 51st OCC of MP 51

Page 54: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Annexure-11.5

1 GEN 6 GT MW/MVAR 76/4 02 GEN 7 GT MW/MVAR 152/4 03 GEN 6 GT CB FAULTY OPEN4 GEN 7 GT CB FAULTY OPEN5 220 KV TRB CB FAULTY CLOSE

1 220 KV SGTPS 3 CB TRANSIT CLOSE

1 400/220 KV TR 1 & 2 (315MVA ) OLTC N/C

1 220 KV PANAGAR CB FAULTY CLOSE

1 220 KV SIRMORE CB FAULTY CLOSE2 GEN 3 CB TRANSIT CLOSE

1 132KV BC CB FAULTY CLOSE2 132/33 TR CB OPEN CLOSE

TELEMETRY DISCRIPIENCY

1 GEN 7 MVAR N/CISP H P S

SATPURA T P S

A T P S T P S

SINGHA JI S T P S

S G T P S

GANDHISAGAR H P S

RAJGHAT H P S RTU OUT DEOLOAN HPS RTU OUT DUE TO COMM LINK PROBLEM

TONS H P S

Minutes Of 51st OCC of MP 52

Page 55: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

DATA OUT FROM LONG TIME1 SAGAR 220 KV S/S 2 MORWA 132 KV S/S3 SIDHI 220 KV S/S

LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETERSr.no. DESCRIPTION Status telemetry value at SLDC actual value at site

1 220 KV INTERCONNECTOR 1 MW/MVAR N/C 115/15

1 220 KV KOTOR CB FAULTY CLOSE

1 220/132 TR 2 CB FAULTY CLOSE2 220 KV SUKHA 1 & 2 CB FAULTY CLOSE3 220 KV JBP 1 ,2 CB FAULTY CLOSE4 133/32 KV TR 2 CB,MW/MVAR/OLTC N/A5 132 KV BARMAN 2 CB,MW/MVAR N/A6 220 KV PIPARIA CB FAULTY CLOSE

1 400/200/33 KV TERTIARY REACTOR 1 & MVAR N/A

2 220 KV PGCIL 2 CB FAULTY CLOSE

1 220 KV BUS TIE CB FAULTY CLOSE3 132 KV DIGORA MW/MVAR N/A4 220 /132 KV TR 2 MVAR N/A5 132/33 KV TR 2 MW /MVAR /CB/OLT N/A

2 220 KV REWA MW/MVAR N/C3 220 KV HINDALCO MW/MVAR N/C

1 132 KV JP NIGRI CB/MW/MVAR N/C

PROCESSES CONNECTION

REQUIRED

1 220 KV TONS PH MW /MVAR N/C 50 /5Annexure-11.5

1 132 KV KOTMA CB N/A

2220/132 KV TR 2 (160 MVA) PRI & SEC CB N/A CLOSE

3 132 KV SHAHDOL CB ,MW,MVAR N/A4 132 KV KOTMA 2 CB ,MW,MVAR N/A

1 220 KV SATPURA T P S CB /MW/MVAR N/C

1 132 KV GANJBASODA CB FAULTY2 220/132 KV TR 3 PRI CB FAULTY

1 220 /132 KV TR 1 MW/MVAR 0 60/152 220 /132 TR 1 SEC CB FAULTY CLOSE3 220 KV PGCIL 1 MW/MVAR N/C 75/104 220 /132 KV TR 2 MW/MVAR 40/10 60/15

BIRSINGHPUR 220 KV S/S

SATNA220 KV S/S

NARSINGHPUR 220 KV S/S

PROCESSES CONNECTION

BINA 400 KV S/S

SIDHI 220 KV S/S

KOTAR 220 KV S/S

DAMOH 220 KV S/S

REWA 220 KV S/S

TIKAMGRAH 220 KV S/S

PROCESSES CONNECTION

ANUPPUR 220 KV S/S

CHINDWARA 220 KV S/S

PANDURNA 220 KV S/S

BINA 220 KV S/S

Minutes Of 51st OCC of MP 53

Page 56: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

5 132 KV BUS V0LTAGE/FREQ N/C

3 132/33 kv TR 63 MVACB /MW/MVAR/OLTC

N/APROCESSES CONNECTION REQUIRED

1 132 KV BALAGHAT 1 CB FAULTY CLOSE2 132 KV PENCH 2 CB FAULTY CLOSE3 132/33 TR 1 & 2 CB FAULTY CLOSE4 132 KV I /C 1 & 2 CB FAULTY CLOSE5 132 KV MANDLA CB FAULTY CLOSE6 132 KV LAKHNADON CB FAULTY CLOSE7 132 KV BUS COUPLER CB FAULTY CLOSE

1 132 KV VFJ 1 CB FAULTY CLOSE

1 132 KV ANUPPUR 2 CB /MW/MVAR N/ACHICHLI 220 KV S/S

ALL CB DATA NOT AVIALABLE

JABALPUR220 KV S/S

SEONI 132 KV S/S

KOTMA 132 KV S/S

Minutes Of 51st OCC of MP 54

Page 57: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Annexure-11.5Telemetery Discripancies -

ParameterTelemetered /

ActualRemarks

1. Rajgarh 220 -1. 132Kv Raghogarh Cb, Mw, Mvar Nc Process connection required.2. 132Kv Maksudangarh Cb, Mw, Mvar Nc Process connection required.3. 220/132Kv Xmer-2 Cb Nc Process connection required.4. 220/132Kv Xmer-2 Cb, Mw, Mvar Nc Process connection required.5. 220Kv Main Bus-1&2 Volt Nc Process connection required.

2. Ashta 400 -1. 400Kv Bus Freq Na

3. Sabalgarh 220 -1. 132Kv Vijaypur Cb Faulty

4. Handia 220 -1. 220/132Kv Xmer-2 Mw Nc2. 220/132Kv Xmer-2, Pri Cb Faulty / Close3. 220/132Kv Xmer-2, Sec Cb Faulty / Close4. 132Kv Nasrullaganj Cb, Mw, Mvar Nc Process connection required.5. 132Kv Satwas Cb, Mw, Mvar Nc Process connection required.6. 132Kv Gopalpur Cb, Mw, Mvar Nc Process connection required.7. 132Kv Sultanpur Cb, Mw, Mvar Nc Process connection required.8. 220Kv Itarsi Cb Faulty / Close9. 220Kv Barwaha Cb Faulty / Close

5. Vidisha 220 -1. 220/132Kv Xmer-2, Sec Cb Nc Process connection required.2. 132Kv Sanchi Rly-1 Mw, Mvar Nc

6. Guna 220 -1. 132/33Kv Xmer-1 Cb Faulty / Close2. 132Kv Bus Coupler Cb Faulty

7. Gwalior 220 -1. 132Kv Bus Coupler Cb Faulty2. 132Kv Dabra Mw 13/28

8. Bhopal 400 -1. 400Kv 80Mvar Reactor Cb Nc

9. Sarni 220 -1. 220Kv Bus Transfer Cb Faulty2. 220Kv Sarni PH-1 Cb Faulty / Close3. 220Kv Betul Cb, Mw, Mvar Nc4. 220Kv Sarni PH-2 Cb, Mw, Mvar Nc5. 220 Kv Pandhurna Cb, Mw, Mvar Nc

10. Bairagarh 220 -1. 220Kv Main Bus-2 Volt Nc2. 132Kv Bhopal-2 Cb Faulty

Element

CPU database updated. Database in Alstom system to be updated.

Minutes Of 51st OCC of MP 55

Page 58: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

3. 220/132Kv Xmer-1, Sec Cb Faulty4. 220/132Kv Xmer-2, Pri Cb Nc Process connection required.5. 220/132Kv Xmer-2, Sec Cb, Mw, Mvar Nc Process connection required.6. 132/33Kv Xmer-4 Cb, Mw, Mvar Nc Process connection required.

11. Ashta 132 -1. 132/33Kv Xmer-1 Cb Open / Close2. 132Kv Interconnector-2 Cb Faulty3. 132Kv Sehore Cb Faulty

12. Itarsi 220 -1. 132/33Kv Xmer-4

13. Piparia 220 -1. 220Kv Chichli Cb Faulty / Close2. 220/132Kv Xmer-2, Pri Cb Nc Process connection required.3. 220/132Kv Xmer-2, Sec Cb, Mw, Mvar Nc Process connection required.

14. Harda 132 -1. All Cb's except Handia-1 Cb Faulty / Close

15. Mandideep 220 -1. 132Kv P&G Cb Nc Process connection required.

16. Malanpur 220 -1. 220Kv Main Bus Freq Na2. 132Kv Banmore-2 Cb Faulty / Close3. 132Kv Main Bus Volt 112 / 1304. 132/33Kv Xmer-2 Mvar Na5. 132Kv Morar Mw, Mvar Na6. 220/132Kv Xmer-2, Sec Mw, Mvar Na

17. Pichhore 132 -1. 132Kv Chanderi Cb Open / Close2. 132Kv Datia Cb Faulty / Close3. 132Kv Karera Cb Open / Close4. 132/33Kv Xmer-3 Cb Faulty / Close

18. Satpura TPS -1. Gen-6 GT Cb Faulty

Nc - Not connected, Na - Not available

Minutes Of 51st OCC of MP 56

Page 59: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

Annexure-11.5 LIST OF TELEMETRY DISCRIPIENCY AND NOT CONNECTED PARAMETERSr.no. DESCRIPTION Status telemetry value at SLDC actual value at site

1 400KV BUS-2 VOLTAGE N/C2 400KV BUS-2 FREQUENCY N/C3 220/132 TRF-2 MW N/C4 220/132 TRF-2 MVAR N/C5 220/132 TRF-2 OLTC N/C5 220/132 TRF-2 CB N/C6 220KV BUS-2 VOLTAGE N/C7 220KV BUS-2 FREQUENCY N/C

1 220/132 KV TR OLTC N/A2 132/33 KV TR OLTC N/A3 132/33 TRF-1 40MVA CB FAULTY CLOSE4 132KV NIMRANI-1 CB FAULTY CLOSE

1 220/132 TR 2 4*40 MVA MW Direction wrong Need to be reverse from field2 220/132KV TRF1 OLTC N/C3 220/132KV TRF2 OLTC N/C

1 220 KV BUS COUPLER CB FAULTY CLOSE2 220/132 KV TR 3X40MVA CB FAULTY CLOSE3 220/132 KV TR 160 MVA (SEC) CB FAULTY CLOSE4 220KV BUSCOUPLER CB FAULTY CLOSE5 132/33 KV 12.5 MVA XMER CB,MW,MVAR N/C6 132KV BUS VOLTAGE N/C7 132KV BUS FREQUENCY N/C

1 400KV BUS COUPLER CB FAULTY CLOSE3 400 KV REACTOR CB FAULTY3 400/220KV XMER OLTC N/C3 220/132KV XMER-1 OLTC N/C3 220/132KV XMER-2 OLTC N/C3 132/33KV XMER MW,MVAR,OLTC N/C

1 132 KV I/C 2 MW N/C 102 132KV BUS FREQUENCY N/C2 220/132KV TRF-1 OLTC N/C2 220/132KV TRF-2 OLTC N/C

1 132 KV KURAWAR CB FAULTY CLOSE2 220KV BUS COUPLER CB FAULTY CLOSE3 132KV CAP BANK CB FAULTY CLOSE2 132KV BUS FREQUENCY N/C

1 220/132 KV TR (160 MVA) 2 PRIMARYCB N/A CLOSE2 132 KV IFLS MW,MVAR,CB N/A3 220/132 KV TR (160 MVA) 2 SEC CB N/A CLOSE

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

CHEGAON 400 KV S/S

NEPANAGAR 220 KV S/S

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

DEWAS 220 KV S/SNOTE:- CPU FAULTY.

SHUJALPUR 220 KV S/S

JULWANIA 400 KV S/S

JULWANIA 220 KV S/S

PROCESSES CONNECTION REQUIRED

BARWAHA 220 KV S/S

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

NEEMUCH 220 KV S/S

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIEDBADOD 220 KV S/S

Minutes Of 51st OCC of MP 57

Page 60: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

4 220KV BUS 1 VOLTAGE 100 2235 220KV BUS 1 FREQUENCY 0 49.96 220KV BUS 2 VOLTAGE 100 2217 220KV BUS 2 FREQUENCY 0 49.98 132KV BUS VOLTAGE 59.9 349 132KV BUS FREQUENCY 45 49.97

1 132 KV BUS COUPLER CB FAULTY CLOSE2 132 KV GRASIM CB FAULTY CLOSE3 132 KV CAP BANK MVAR N/C4 132KV BUS FREQUENCY N/C4 132KVMAHIDPUR-2 MW,MVAR N/C

1 400/220 ICT-1 TIE CB FAULTY CLOSE2 220KV BUS-2 FREQUENCY N/C

1 132 KV SIDTUBE CB /MW/MVAR N/A2 132 KV INOX CKT (RE) CB /MW/MVAR N/A3 220KV ASTHA 1 CB FAULTY CLOSE4 220KV ASTHA 2 CB FAULTY CLOSE5 220KV BUS COUPLER CB FAULTY CLOSE6 220KV BUS 1 KV,HZ N/A7 132KV BUS 1 KV,HZ N/A8

1 220KV INDORE CB FAULTY CLOSE2 220KV BUSCOUPLER CB FAULTY CLOSE

1 220/132 TR 1 & 2 OLTC N/A2 132/33 TR OLTC N/A

1 220/132 KV TR 2 SEC CB FAULTY CLOSE2 220KV BUSTIE CB FAULTY CLOSE3 220KV BUS COUPLER CB FAULTY CLOSE4 132 KV BUS COUPLER CB FAULTY CLOSE5 132KV JHABUA CB FAULTY CLOSE6 220/132 TR 1 &2 OLTC N/A1 220KV BUS-1 FREQUENCY N/C2 220KV BUS-2 VOLTAGE N/C3 220KV BUS-2 FREQUENCY N/C6 220/132KV TRF-1 SECONDARY SIDE CB FAULTY CLOSE7 220/132KV TRF-1 SECONDARY SIDE CB FAULTY CLOSE

1 220 /132 KV TR 3 MW/MVAR N/A2 132KV KACHROD CB FAULTY CLOSE

1 220 KV MAHESHWAR 2 CB FAULTY OPEN2 220/132 TR1 OLTC N/C3 132/33 TR3 OLTC N/C4 220/132 TR3 MW,MVAR,OLTC N/C5 132KV CAP BANK MVAR N/C

PITAMPUR 220 KV S/S

NAGDA 220 KV S/S

NAGDA 400 KV S/S

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

ALL BREAKERS OF 132 SIDE ARE FAULTY EXCEPT 220/132 KV X-MAR II (HV DIDE)SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

INDORE EAST 220 KV S/S

NIMRANI 220 KV S/S

NOTE:-CB OF ALL FEEDERS ARE NOT COMING

SHAJAPUR 220 KV S/S

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIEDRAJGRAH (DHAR) 220 KV S/S

RATLAM 220 KV S/S

Minutes Of 51st OCC of MP 58

Page 61: (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpursldcmpindia.com/uploads/meeting/MINUTES OF 51st MEETING... · 2016. 6. 6. · MPPKVVCL (East Discom), being the host, welcomed

BADNAGAR 220KV S/S1 220/132KV XMER-3 MW N/C2 220/132KV XMER-3 MVAR N/C3 220/132KV XMER-3 OLTC N/C4 132/33KV TRF CB FAULTY CLOSE

NOTE:-ALL SOE DATA NEED TO BE VERIFIED.

1 220/132 TR1 & TR2 OLTC N/C2 132KV BUS-1 FREQUENCY N/C3 132KV BUS-2 FREQUENCY N/C4 132KV BUS COUPLER CB FAULTY CLOSE

1 220KV BUS FREQUENCY 100 49.992 132KV BUS COUPLER CB FAULTY3 132KV FDR-1 CB FAULTY4 132KV FDR-1 MVAR N/C5 132KV FDR-1 MW N/C5 132KV BUS VOLTAGE N/C5 132KV BUS FREQUENCY N/C

NOTE:-CB OF ALL FEEDERS ARE FAULTY

DALODA 220KV S/S

1 220KV DJ ENERGY -2 MW NOT COMING

INDORE CHAMBAL 132 KV S/S

1 132KV INDNZ-1 MW 24 -242 132KV INDNZ-1 MVAR 7 -73 132KV INDNZ-2 MW 21 -214 132KV INDNZ-2 MVAR 7 -75 13233KV TRF2 MW N/C6 13233KV TRF2 MVAR N/C7 132KV BUS FREQUENCY N/C

GANDHISAGAR HPS1 132/33KV TRF1 CB OPEN CLOSE

INDORE 400KV SS

1 400/220KV ICT-2 CB OPEN CLOSE2 220KV PITAMPUR MW N/C3 220KV PITAMPUR MVAR N/C4 220KV BUS-2 FREQUENCY N/C

OMKARESHWER HPS

1 132KV MAKSI CB OPEN CLOSE2 220KV BUS 2 FREQUENCY N/C3 132KV BUS 2 FREQUENCY N/C4 132KV BUSTIE CB FAULTY CLOSE

BHANPURA 220KV S/S

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIEDINDORE NZ (JETPURA) 220KV S/S

INDORE SZ 220KV S/S

NOTE:-CB OF ALL FEEDERS ARE NOT COMING

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

SOE DATA NOT RECEIVED CONNECTIONS FOR ALL FEDEERS HAVE TO BE VERIFIED

Minutes Of 51st OCC of MP 59